LOST LAKE CAMPGROUND AND TRAILHEAD
INDEX OF SPECIFICATIONS
DIVISION 01 - GENERAL REQUIREMENTS
Section 011100 - Summary of Work Section 011419 – Use of Site Section 012200 – Definition of Bid Items Section 013223 – Survey and Layout Design Section 013300 – Submittal Procedures Section 014000 – Quality Requirements Section 015020 – Construction Signing & Fencing Section 016400 – Government Furnished Materials Section 017419 – Construction Waste Management and Disposal Section 017700 – Closeout Procedures
DIVISION 02 – EXISTING CONDITIONS
Section 024113 - Selective Site Demolition Section 024114 – Handpump Removal Section 024116 – Structure Demolition
DIVISION 03 - CONCRETE
Section 033000 – Cast-In-Place Concrete Section 034113 – Precast Concrete Planks for Boat Ramp Section 034500A – Pre-cast Concrete Toilet and Vault Buildings Section 034500B – Installation Checklist
DIVISION 05 – METALS
Section 051200 – Structural Steel
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
Section 061290 – Treated Timber Steps, Border and Edger
DIVISION 09 – PAINTING
Section 099113 – Painting and Staining
DIVISION 10 – SPECIALITIES
Section 101410 – Site Identification or Entrance Sign
Section 101450 - Signs
DIVISION 12 – FURNISHINGS
Section 129300 – Miscellaneous Site Furnishing
DIVISION 31 – EARTHWORK
Section 311100 – Clearing and Grubbing Section 311413 – Obliteration of Abandoned Roadways Section 312316 – Structural Excavation, Backfill and Compaction Section 312413 – Road and Spur Excavation and Embankment Section 312510 – Temporary Erosion and Sedimentation Controls Section 312523 – Rock Barriers and Relocation Section 313519 – Geosynthetic Slope Reinforcement Section 313700 – Rock Rip-Rap Stone Retaining Wall
DIVISION 32 – EXTERIOR IMPROVEMENTS
Section 321123 – Aggregate Base Course Section 321540 – Crusher Fines Surfacing with Soil Solidifier Additive Section 321713 – Rubber Wheelstop Section 323100 - Gates Section 329219_A – Seeding Section 329219_B – General Seed Mixtures for Paonia Ranger District
DIVISION 33 – UTILITIES
Section 331214 - Handpumps Section 332900 – Well Abandonment Section 333100 – Sanitary Sewerage Section 334213 – Culverts
LOST LAKE CAMPGROUND AND TRAILHEAD 011100-1
SUMMARY OF WORK
SECTION 011100
SUMMARY OF WORK
PART 1 – GENERAL
1.1 SUMMARY
A. Work for this project consists of furnishing labor and equipment for the reconstruction of the Lost Lake Campground, Lost Lake Day Use Area and Trailhead and the
Beckwith Horse Trailhead. Items of work in the base bid include (but not limited to) are: Clearing, grubbing, and stump removal; Obliteration of roadways and relocation of barrier rocks; Construction staking and quality control; Construction Closure Signs;
Constructing the aggregate surfaced Beckwith Horse Trailhead with relocation of an existing cattleguard; Constructing main campground roads, spurs, and trails associated with units in the base bid (1- 14) - Crushed Aggregate with Plasticity Index
= 8 (+/- 4), crusher fines surfacing with Plasticity Index = 8 (+/- 4);
Replacing/installing drainage ditches; Host unit improvements; Fee station with bulletin board; Relocation of a government furnished fee tube, Installing government furnished entrance sign panels on contractor installed posts, Directional signage with posts, Reconstruction of all camp units and construction of new camp units including crusher fine surfaced use pads, timber borders, steps, unit number posts, and site furnishings; Concrete dumpster pad; and Coordination and installation of Government furnished items: including fire rings with concrete footings; expanded metal tables with drive-in anchors; rubber wheelstops; plastic number posts with symbol/sign plates; some on-site rock for barrier rocks or retaining walls. Crushed Aggregate will be obtained from a Government, Forest Service owned pit as a Government Furnished item. The Forest Service will pay Gunnison County for crushing and the Contractor to haul to the Lost Lake project site. Aggregate will be stockpiled at the existing Lodge –
Trailhead parking area. The Government furnishes and the Contractor installs one gate with concrete footings. Work also includes a new handpump well at the Trailhead site with concrete slab. Install one host sewage holding tank at Lost Lake CG Host Site.
Note: For both Tables and Fire Rings: Contractor to furnish concrete for footings. For fire rings, contractor to furnish aggregate for raised fire surface.
B. Optional Bid Items include (but not limited to) are: Clearing, grubbing and stump removal, Obliteration of roadways and relocation of barrier rocks, Constructing, furnishing and installation of new roads and parking areas, a Day Use Picnic Area with expanded metal tables and fire rings, Resurfacing a Trailhead Parking Area, Replacing/installing culverts and ditches, New construction of a 5 unit Horse Trailer
Campground with spurs, crusher fine surfaced use pads, timber borders, directional signage with posts, horse hitch rails, unit number posts with numbered symbol plaque, Concrete dumpster pad; Abandonment of an existing handpump well in the Lost Lake
Campground and Coordination and installation of government furnished items:
including fire rings with anchor pins, expanded metal tables with drive-in anchors, and rubber wheelstops. Other Optional Bid Items include (but are not limited to):
LOST LAKE CAMPGROUND AND TRAILHEAD 011100-2
Government furnished and stockpiled Class 6 Crushed Aggregate Plasticity Index = 8;
Construction of the remaining Beckwith Horse Trailhead including directional signing with posts, a tubular steel bulletin board, and horse hitch rails; Installing a concrete plank boat launch ramp with aggregate base in the Lost Lake Slough Reservoir and lastly furnishing seed mix and seeding. The Government furnishes and the Contractor installs a second gate; contractor installed entrance sign and fee station; all unit number posts Contractor installed with number symbol plaque; and installation of two new Contractor furnished double concrete vault toilets in the campground and trailhead area.
Note: For both Tables and Fire Rings: Contractor to furnish concrete for footings. For fire rings, contractor to furnish aggregate for raised fire surface.
1.2 LOCATION
A. This project is located approximately 12 miles west of the town of Crested Butte, Colorado, 20 miles east from Paonia, Colorado and 49 miles from Delta, Colorado on the Paonia Ranger District of the Grand Mesa, Uncompahgre and Gunnison National
Forest. The site is located at the end of National Forest System Road No.706, approximately 2 miles south of Gunnison County Road # 12, Kebler Pass Road
(Section 4, T. 14S., R. 88W., 6 th
P.M.) The campground lies adjacent to the Lost Lake
Slough reservoir, which provides excellent fishing and small craft boating activities.
1.3 GENERAL SITE CONDITIONS AND WEATHER
A. The altitude of the project is approximately 9,623 feet above mean sea level. The construction site experiences snowfall and rain and extremely cold temperatures, with snow on the ground typically from October through mid -June.
B. In-depth soil surveys have not been performed. The Contractor should expect to encounter rock during excavation and grubbing operations. Blasting of rocks will not be permitted unless approved by the Contracting Officer.
C. In-depth water table surveys have not been performed; however, if water is encountered during excavation, the Contractor shall perform adequate dewatering to keep the excavation free from water and dispose of the water without damage to property.
1.4 STAGING AREA AND SAFETY
A. The staging and landing areas are shown on the drawings in the proposed west side trailhead parking and turn-around areas and as approved on site by the Contracting
Officer. The Lost Lake Campground will be closed to the public during construction.
Contractor shall provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Contractor shall minimize disturbance of all undisturbed areas outside of project work. Vegetation, meadows and forested areas outside of roadwork, drainage or Construction Limits
LOST LAKE CAMPGROUND AND TRAILHEAD 011100-3
determined by the Contracting Officer shall be protected from equipment impacts or other disturbances.
1.5 MEALS AND LODGING
A. Meals and lodging are commercially available in the towns of Crested Butte, Paonia and Delta, Colorado within 12 to 50 miles of the construction site.
B. A work camp will be allowed at the construction site with prior approval of the
Contracting Officer and the Paonia Ranger District. Other campgrounds in the area are operated by a concessionaire and payment of fees would be required.
1.6 SITE CLEANUP AND DISPOSAL
A. The Contractor shall dispose of all waste off National Forest Lands in accordance with
Section 017419, Construction Waste Management and Disposal.
1.7 CONSTRUCTION SEQUENCE
A. Construction shall begin in September 2009.
B. The project shall be completed within the time frame established by the terms of this contract and according to the approved Schedule of Work.
C. Depending on conditions, normal fire restrictions may apply to activities associated with this project.
1.8 COOPERATION BETWEEN CONTRACTORS
A. The Government reserves the right to contract for or perform other additional work on or near the work covered by this contract.
1.9 STORAGE
A. The Contractor shall be responsible for protection of all equipment and supplies intended for use in the project. The Contractor shall pay all costs related to such protection. Refer to Section 011419, Use of Site.
1.10 FIELD VERIFICATION
A. Field verify all new and existing conditions affecting the work of this contract before ordering products.
1.11 PERMITS
A. Special permits required by County, State, or Federal laws or regulations shall be obtained by the Contractor.
LOST LAKE CAMPGROUND AND TRAILHEAD 011100-4
PART 2 – PRODUCTS – (NOT APPLICABLE)
PART 3 – EXECUTION – (NOT APPLICABLE)
END OF SECTION
LOST LAKE CAMPGROUND AND TRAILHEAD 011419-1
USE OF SITE
SECTION 011419
USE OF SITE
PART 1 - GENERAL
1.1 SUMMARY
A. Applies to Government facilities at the worksite available for use by the Contractor.
This section also requires maintaining National Forest System Road No. 706 in an acceptable, existing condition and preserving the existing road drainage structures, road shoulders and ditches, and limiting construction traffic to the existing road surface so no damage or impacts occur to adjacent wet areas, forest or vegetation and private summer homes and roads along the road.
1.2 SANITARY FACILITIES
A. Contractor shall provide sanitary facilities for use by Contractor’s personnel as per
OSHA regulations.
1.3 DRINKING WATER
A. Contractor shall provide drinking water for use by Contractor’s personnel as per
OSHA regulations.
1.4 TELEPHONE
A. The Contractor will be responsible for providing any telephone service deemed necessary for the duration of the contract.
1.5 ELECTRICAL SERVICE
A. There is no electrical service at this site.
1.6 STORAGE AREA
A. Storage for Contractor's materials and equipment, if required, may be at the project area or staging/landing areas where approved by the Contracting Officer.
Staging/Landing areas are as shown on the drawings. The Government shall not be responsible for Contractor's materials or equipment stored on Government property.
1.7 WORK CAMPITES
A. Authorization from the Paonia Ranger District and the Contracting Officer must be obtained prior to use of any National Forest lands by the Contractor in the Lost Lake
Campground for camping of Contractor personnel during construction. Campground dumpsters shall not be used for construction material. Contractor shall haul all construction trash off-site for disposal.
LOST LAKE CAMPGROUND AND TRAILHEAD 011419-2
USE OF SITE
The nearest approved landfills are located at:
Gunnison County Landfill, 45800 US Highway 50, Gunnison, CO. 81230. Phone:
(970) 641-5522. FAX: (970) 641-8120.
Delta County, Adobe Buttes Landfill, 1221 Trap Club Road, Eckert, CO. Phone:
(970) 835-7999.
B. Contractor shall maintain a clean work site to prevent any potential conflicts with wildlife in the area.
1.8 MAINTAINING THE CONDITION OF NATIONAL FOREST SYSTEM ROAD
NO. 706
A. The contractor is required to maintain National Forest System Road No. 706 in an acceptable, existing condition and preserving the existing road drainage structures, road shoulders and ditches, and limiting construction traffic to the existing road surface so no damage or impacts occur to adjacent wet areas, forest or vegetation along the road.
B. Unless otherwise approved by the Contracting Officer, construction traffic shall be confined to the roadway and turn-out limits of National Forest System Road No. 706 to avoid damage to roadway out-of-limits forest areas and to protect private property, road surfaces, shoulders or stream/wet areas. The contractor shall be responsible for repairing any damage to the road that occurs from construction traffic.
PART 2 – PRODUCTS (NOT APPLICABLE)
PART 3 – EXECUTION (NOT APPLICABLE)
LOST LAKE CAMPGROUND AND TRAILHEAD 012200-1
DEFINITION OF BID ITEMS
SECTION 012200
DEFINITION OF BID ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general; what is and what is not included in a bid item; the limits or cut-off points where one bid item ends and another begins; and method of measurements and basis of payment for work items listed in the Base Bid
Item Schedule and Optional Bid Item Schedule.
B. Work:
1. Furnishing all labor, materials, equipment, and other incidentals necessary to successfully complete the project or any portion of it, and carrying out all duties and obligations imposed by the contract on the Contractor.
2. For each individual item listed here and in the Schedule of Items, payment shall be full compensation for all work related to the particular item in accordance with these specifications, as shown on the drawings, and as staked in the field.
3. Measurement and payment for contract work shall be made only for and under those pay items included in the Schedule of Items. All other work and materials shall be considered incidental or as included in the payment for items shown.
1.2 DETERMINATION OF QUANTITIES
A. The contractor shall perform, or cause to be performed, all measurement of quantities of materials incorporated into the work processes that are to be measured under the provisions of the contract.
B. Quantity Measurements:
1. The Contractor shall make all measurements for computation of quantities for all work items except those specified for payment by Lump Sum Quantity
(LSQ).
2. The contractor shall compute the quantities for periodic progress payments; the
Contracting Officer shall compute the quantities for the final payment based on measurements taken by the Contractor.
3. All Contractor measurements are subject to verification.
4. The Contractor shall submit all field notes, calculation sheets, and other data used to determine quantities.
5. The Contractor shall certify in writing as to the accuracy of the measurements and computations submitted.
C. The following measurements and calculations are used to determine contract quantities.
1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement
LOST LAKE CAMPGROUND AND TRAILHEAD 012200-2
unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.
2. The average end area method shall be used to compute volumes of excavation or embankment. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three dimensional methods.
3. Structures shall be measured according to neat lines shown on the drawings or as altered by the Contracting Officer, in writing, to fit field conditions.
4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, and under drains, measurements shall be made parallel to the base or foundation upon which the structures are placed. Pipes shall be measured along center of invert.
5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.
6. For standard manufactured items—such as fence, wire, plates, rolled shapes, pipe conduits—identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions.
Unless controlled by tolerances in cited specifications, manufacturer’s tolerances shall be accepted.
1.3 UNITS OF MEASUREMENT
A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:
B. Acre: 43,560 square feet. Make longitudinal and transverse measurements for all computations horizontally. Do not make deductions from the area computation for individual exclusions having an area of 500 square feet or less.
C. Cubic Yard: A measurement computed by one of the following methods:
1. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.
2. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.
3. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.
Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.
D. Each: One complete unit, which may consist of one or more parts.
E. Linear Foot: Linear feet measured horizontally.
F. Lump Sum: Do not measure directly. The bid amount is complete payment for all work described in the contract and necessary to complete the work for that item.
LOST LAKE CAMPGROUND AND TRAILHEAD 012200-3
G. Square Yard: 9 square feet. Longitudinal and transverse measurements for area computations will be made horizontally. Do not make deductions from the area computation for individual fixtures having an area of 9 square feet or less.
H. Ton: 2000 pounds. No adjustment in contract price will be made for variations in quantity due to differences in the specific gravity or moisture content. Use net certified scale weights, or weights based on certified volumes.
I. Where tolerances are shown in the contract, they are intended to define reasonably close conformity. Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed roadway sections and to balance earthwork. Such adjustments shall not be considered as “Changes.”
PART 2 - METHOD OF MEASUREMENT
2.1 GENERAL
A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:
B. ACTUAL QUANTITIES (AQ)
1. These estimated quantities are determined from actual measurements of completed work.
C. LUMP SUM QUANTITIES (LSQ)
1. These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall be measured complete and in-place.
PART 3 – DEFINITION OF BID ITEMS
3.1 SCHEDULE OF ITEMS
A. The project Schedule of Items includes several sections to organize the bid items into
Base Bid Items and Optional Bid Items. Contractor shall provide item pricing for all items listed in the Schedule of Items. Contract award will be made for all Base Bid
Items. Those items listed as Optional Bid Items will be awarded based on available project funding. The Optional Bid Items are not listed in priority order and may be awarded in any combination of individual items.
3.2 DESCRIPTION OF BASE BID LABOR AND EQUIPMENT ITEMS
A. Bid Item No. 1 – Mobilization
1. This bid item consists of all preparatory work and operations necessary for the movement of personnel, equipment, and incidentals to the project site, and for
LOST LAKE CAMPGROUND AND TRAILHEAD 012200-4
all other work and operations that must be performed or that cause costs to be incurred prior to beginning work on the various items on the project site.
2. Payment shall be made at the contract lump-sum price.
3. Progress payment shall be made as follows:
a. When 5 percent or more of the original contract amount is earned from other pay items, 50 percent of the amount for mobilization, or 5 percent or the original contract amount, whichever is less, shall be paid.
b. When 10 percent or more of the original contract amount is earned from other pay items, 100 percent of the amount for mobilization, or 10 percent of the original contract amount, whichever is less, shall be paid.
c. Upon completion of all work on the project, any unpaid amount for mobilization shall be paid.
d. The total of all payments, including bonding, shall not exceed the original contract amount for this item.
B. Bid Item No. 2 – Quality Control
1. This item consists of all quality control and quantity measurements and all quality control testing as required in the specifications.
2. Payment shall be made at the contract lump-sum price.
C. Bid Item No. 3 – Construction Surveying and Staking
1. This bid item consists of all survey work and construction staking necessary to adequately control the work and set horizontal and vertical alignments.
2. Payment shall be made at the contract lump-sum price.
D. Bid Item No. 4 – Construction Signing
1. This work includes construction closure signing along County Road 12 and
National Forest System Road No. 706 and maintaining barricade(s) at the campground entrances to close the site to the public. Additional temporary fencing barricades for public closure at the staging/landing area adjacent to the campground entrance are considered incidental to this item.
2. Payment shall be made at the contract lump-sum price.
E. Bid Item No. 5 – Temporary Erosion & Sedimentation Control
1. This item consists of furnishing, installing and maintaining temporary erosion and sedimentation controls for the duration of the contract to ensure that storm water drainage passes through a filter system before being discharged.
2. Payment shall be made at the contract lump-sum price.
F. Bid Item No. 6 – As-Built Drawings
1. This item includes all materials, equipment, labor and incidentals required to produce all required electronic and hard copy as-built deliverables.
2. Payment shall be made at the contract lump-sum price.
G. Bid Item No. 7 –Excavation and Embankment - Campground
1. This bid item includes excavation and fill placement for Lost Lake Campground
Road reconstruction, entrance turn-around, boat parking areas, and all Base Bid
LOST LAKE CAMPGROUND AND TRAILHEAD 012200-5
units including spurs or pull-thrus, unit use pads, tent pads, and campground unit trails as shown on the drawings and as described in the specifications. Site grading is incidental to this item. It shall be measured as a design quantity
(DQ). Excavation and embankment for Optional Bid Items is included in those items.
2. Payment shall be made at the contract unit price per cubic yard. Payment is for excavation; embankment is considered incidental to this pay item.
H. Bid Item No. 8 –Excavation and Embankment – Beckwith Horse Trailhead
1. This bid item includes excavation and fill placement for Beckwith Horse
Trailhead area, entrance road reconstruction and trailhead as shown on the drawings and as described in the specifications. Site grading is incidental to this item. It shall be measured as a design quantity (DQ). Excavation and embankment for Optional Bid Items is included in those items.
2. Payment shall be made at the contract unit price per cubic yard. Payment is for excavation; embankment is considered incidental to this pay item.
I. Bid Item No. 9 – Borrow Fill - Beckwith Horse Trailhead
1. This bid item includes furnishing, hauling, placing and compacting borrow material for the Beckwith Horse Trailhead area, entrance road and trailhead as shown on the drawings and as described in the specifications.
2. Payment shall be made at the contract unit price per cubic yard.
J. Bid Item No. 10 – Crushed Aggregate Base, CDOT Class 6 gradation plus Plasticity
Index of 8, Compaction B, 6” Thick, for Campground Roads
1. This bid item includes hauling, placing and compacting Government Furnished aggregate base complete in place as shown on drawings and as described in the specifications. Site grading is incidental to this item. Aggregate of the same size not used in this application shall be incidental to another pay item.
2. Payment shall be made at the contract unit price per cubic yard.
K. Bid Item No. 11 – Crushed Aggregate Base, CDOT Class 6 gradation plus Plasticity
Index of 8, Compaction B, 6” Thick, for Beckwith Horse Trailhead
1. This bid item includes hauling, placing and compacting Government Furnished aggregate base complete in place as shown on drawings and as described in the specifications. Material included here is for all Beckwith Horse Trailhead area parking, entrance road and trailhead reconstruction. Aggregate of the same size not used in this application shall be incidental to another pay item.
2. Payment shall be made at the contract unit price per cubic yard.
L. Bid Item No. 12A – Construction of Single Camping Spurs with Crushed Aggregate
Base, CDOT Class 6 gradation plus Plasticity Index of 8, Compaction B, 6” Thick
1. This bid item includes hauling, placing and compacting Government Furnished aggregate base complete in place as shown on drawings and as described in the specifications for construction of Campground Units # 3, 4, 6, 12 and 13. Site excavation and embankment, grading and installation of Government Furnished wheelstops is incidental to this item. Material included here is for all Lost Lake
LOST LAKE CAMPGROUND AND TRAILHEAD 012200-6
Campground single spur reconstruction. Aggregate of the same size not used in this application shall be incidental to another pay item.
2. Payment shall be made at the contract lump-sum price per each.
M. Bid Item No. 12B – Construction of Double Camping Spurs with Crushed Aggregate
Base, CDOT Class 6 gradation plus Plasticity Index of 8, Compaction B, 6” Thick
1. This bid item includes hauling, placing and compacting Government Furnished aggregate base complete in place as shown on drawings and as described in the specifications for construction of Campground Units # 1- Host, 2, 11 and 14.
Site excavation and embankment, grading and installation of Government
Furnished wheelstops is incidental to this item. Material included here is for all
Lost Lake Campground double spur reconstruction. Aggregate of the same size not used in this application shall be incidental to another pay item.
2. Payment shall be made at the contract lump-sum price per each.
N. Bid Item No. 12C – Construction of Camping Pull-Thru or Turn-outs with Crushed
Aggregate Base, CDOT Class 6 gradation plus Plasticity Index of 8, Compaction B, 6” Thick
1. This bid item includes hauling, placing and compacting Government Furnished aggregate base complete in place as shown on drawings and as described in the specifications for construction of Campground Units # 5, 7, 8, 9 and 10. Site excavation and embankment, grading and installation are incidental to this item.
Material included here is for all Lost Lake Campground pull-thru or turn-out reconstruction. Aggregate of the same size not used in this application shall be incidental to another pay item.
2. Payment shall be made at the contract lump-sum price per each.
O. Bid Items No. 13A – Single Use Pad, Tent Pad and Trails with Crusher Fines
Surfacing with Soil Solidifier, 4” Thick, Plasticity Index = 8 (+/- 4)
1. This bid item includes furnishing, hauling, placing and compacting Government
Furnished crusher fines surfacing complete in place as shown on drawings and as described in the specifications for construction of Campground Units # 3, 4, 5, 6, 7, 8, 10, 12 and 13. Work also includes application of a Contracting
Officer approved soil solidifier to harden the surfaces, furnishing and installing timber borders and Government Furnished unit markers, fire rings and 8 foot tables. Site excavation and embankment, grading and installation are incidental to this item. Aggregate of the same size not used in this application shall be incidental to another pay item.
2. Payment shall be made at the contract lump-sum price per each.
P. Bid Items No. 13B – Double Use Pad with 10 ft. table, Tent Pads and Trails with
Crusher Fines Surfacing with Soil Solidifier, 4” Thick, Plasticity Index = 8 (+/- 4)
1. This bid item includes furnishing, hauling, placing and compacting Government
Furnished crusher fines surfacing complete in place as shown on drawings and as described in the specifications for construction of Campground Units # 1-
Host and 2. Work also includes application of a Contracting Officer approved soil solidifier to harden the surfaces, furnishing and installing timber borders
LOST LAKE CAMPGROUND AND TRAILHEAD 012200-7
and Government Furnished unit markers, fire rings and 10 Foot table. Site excavation and embankment, grading and installation are incidental to this item.
Aggregate of the same size not used in this application shall be incidental to another pay item.
2. Payment shall be made at the contract lump-sum price per each.
Q. Bid Items No. 13C – Double Use Pad with two 8 foot tables, Tent Pads and Trails with Crusher Fines Surfacing with Soil Solidifier, 4” Thick, Plasticity Index = 8 (+/-
4)
1. This bid item includes furnishing, hauling, placing and compacting Government
Furnished crusher fines surfacing complete in place as shown on drawings and as described in the specifications for construction of Campground Units # 9, 11 and 14. Work also includes application of a Contracting Officer approved soil solidifier to harden the surfaces, furnishing and installing timber borders and
Government Furnished unit markers, fire rings and 8 foot tables. Site excavation and embankment, grading and installation is incidental to this item.
Aggregate of the same size not used in this application shall be incidental to another pay item.
2. Payment shall be made at the contract lump-sum price per each.
R. Bid Item No. 14 – 2” Minus Washed Stone at 4” Depth Plasticity Index = +/- 4 for
Boat Launch Trail and Ramp – Lost Lake Slough
1. This bid item includes hauling, placing and compacting Government Furnished
2 inch minus washed stone surfacing for a boat ramp trail or ramp complete in place as shown on drawings and as described in the specifications. Work also includes application of a soil solidifier to harden the surface as approved by the
Contracting Officer. Aggregate of the same size not used in these applications shall be incidental to another pay item.
2. Payment shall be made at the contract unit price per cubic yard.
S. Bid Item No. 15 – Obliteration of Abandoned Roadways, Spurs and Use Areas
1. This bid item includes obliteration of abandoned campground roads, spurs, unit pads and use areas as shown on the drawings and as approved by the
Contracting Officer.
2. Work includes obliteration, ripping, plowing, and scarifying to promote restoration of abandoned roadways, spurs, and unit pads as shown on the drawings.
3. Payment shall be made at the contract lump-sum price.
T. Bid Item No. 16 – Barrier Rock Relocation
1. This bid item includes relocation of existing on-site barrier rocks or suitable excavated rock to new barrier rock locations as shown on the drawings and as approved by the Contracting Officer.
2. Work includes excavation, hauling, stockpiling, placement, backfilling and compaction as shown on the drawings and described in the specifications.
3. Payment shall be made at the contract lump-sum price.
LOST LAKE CAMPGROUND AND TRAILHEAD 012200-8
U. Bid Item No. 17 – Barrier Rocks for Host Holding Tank – 3 Foot Diameter Size
1. This bid item includes relocation of existing on-site barrier rocks or suitable excavated rock to new barrier rock locations at the Host Unit Holding Tank as shown on the drawings and as approved by the Contracting Officer.
2. Work includes excavation, hauling, stockpiling, placement, backfilling and compaction as shown on the drawings and described in the specifications.
3. Payment shall be made at the contract lump-sum price.
V. Bid Items No. 18 – Clearing and Grubbing, Individual Tree, Stump and Slash
Removal – Campground and Entrance Turn-around
1. These bid items includes clearing, grubbing, trimming, removing and disposing of trees, slash and stumps within the new construction areas on the site.
Designated stumps and slash are to be disposed of by methods described in the specifications and as approved on the ground by the Contracting Officer.
2. Payment shall be made at the contract lump-sum price.
W. Bid Items No. 19 – Clearing and Grubbing, Individual Tree, Stump and Slash
Removal – Beckwith Horse Trailhead
1. These bid items includes clearing, grubbing, trimming, removing and disposing of trees, slash and stumps within the new Beckwith Horse Trailhead area.
Designated stumps and slash are to be disposed of by methods described in the specifications and as approved on the ground by the Contracting Officer.
2. Payment shall be made at the contract lump-sum price.
X. Bid Item No.20 – Metal Gate, 25 Foot, Installation at Campground Entrance
1. This bid item includes installation of a Government Furnished metal gate at the campground entrance as shown on the drawings, described in the specifications and at location as approved by the Contracting Officer. Work includes excavation, backfill, concrete footings, assembly and final grading.
2. Payment shall be made at the contract lump sum price.
Y. Bid Item No. 21 – Culvert, 18” Diameter, Galvanized With End Sections -
Campground Entrance Turn-around
1. This bid item includes supplying and installing the 18” diameter corrugated metal pipe culvert as shown on the drawing and as described in the specifications. Work shall include excavation, bedding, backfilling, and constructing a drainage outlet from the culverts where required.
2. Payment shall be made at the contract unit price per linear foot.
Z. Bid Item No.22 – Metal Fee Tube Re-location and Installation
1. This bid item includes installation of a Government Furnished metal fee tube at the campground fee station as shown on the drawings, described in the specifications and as approved by the Contracting Officer. Work includes excavation, backfill, concrete footer, and final grading.
2. Payment shall be made at the contract lump sum price.
LOST LAKE CAMPGROUND AND TRAILHEAD 012200-9
AA. Bid Item No. 23 – Cattleguard Re-location and Installation – Beckwith Horse
Trailhead and Forest Development Road # 706
1. This bid item includes relocation and re-installation of a Government Furnished cattleguard at the entrance to the Beckwith Horse Trailhead and re-located on
National Forest System Road No. 706 as shown on the drawings, described in the specifications and as approved by the Contracting Officer. Work includes excavation, backfill, concrete foundation, and final grading.
2. Payment shall be made at the contract lump sum price.
BB. Bid Item No. 24 – Double Concrete Dumpster Pad
1. This bid item includes furnishing and installing an 8” thick double-sized (unless contractor wants to double the amount of fiber in the pour) fiber reinforced concrete dumpster pad as shown on the drawings and as described in the specifications. Work includes excavation, aggregate base and final grading.
2. Payment shall be made at the contract lump-sum price.
CC. Bid Item No. 25 – Timber Steps Campground Units
1. This bid item includes installation of pressure treated timber steps or stairs in the campground as shown on the drawings or staked in the field and as described in the specifications. Work shall include site clearing, excavation, installation of timbers, sleepers, rebar pins, landings, final site grading and cleanup.
2. Payment shall be made at the contract lump-sum price.
DD. Bid Item No. 26 – Site Identification Sign, Installation with Posts and Hardware
1. This bid item includes installation of Government Furnished Sign Panel, Plaque and Shield on pressure treated timber timbers as shown on the drawings, described in the specifications and staked as approved by the Contracting
Officer. Work shall include site clearing, excavation, backfill, installation of timbers, hardware, final site grading and cleanup.
2. Payment shall be made at the contract lump-sum price.
EE. Bid Item No. 27 – Host Site Sewage Holding Tank – Lost Lake Campground
1. This bid item includes supplying and installing all components of the host waste system including the host hook-up, piping, holding tank and water level indicator. Work shall include unclassified excavation, bedding, backfill, final site grading and cleanup.
2. Payment shall be made at the contract lump-sum price.
3.3 DESCRIPTION OF OPTIONAL BID ITEMS – (LOST LAKE CAMPGROUND
AND TRAILHEAD AREA)
The following are optional bid items and will only be included in the contract if funds are available and determined in the best interest of the Government.
A. Optional Bid Item No. 1 – Handpump
1. This optional bid item includes supplying and installing a handpump on a new well as shown on the drawings and as described in the specifications. Work
LOST LAKE CAMPGROUND AND TRAILHEAD 012200-10
includes installation of above ground and below ground components and includes a flange cover and matching concrete pad surface to crusher fine trail surfaces on all sides. Work items also include excavation, aggregate base, concrete, backfill, and final grading.
2. Payment shall be made at the contract lump-sum price.
B. Optional Bid Item No. 2 – Complete Construction of the Entrance Road, Day Use
Area Parking with Picnic Pads, Trailhead Parking Area, Turn-around, Horse Trailer
Campsites with Spurs and Handpump Well Abandonment in Lost Lake Campground
1. This bid item includes complete construction of the west side facilities including: Site excavation and embankment for roads, parking, spurs and use pads; furnishing, hauling, placing and compacting borrow material for roads, parking, spurs and use pads; placing and compacting Government Furnished aggregate CDOT Class 6 Plasticity Index = 8, Compaction B, 6” Thick base complete in place as shown on drawings and as described in the specifications including Government Furnished wheelstops which are incidental to this item;
placing and compacting Government Furnished crusher fines surfacing complete in place as shown on drawings and as described in the specifications for construction of Horse Trailer Campsites Units # 1 thru 5 and two picnic use pads. Work also includes application of a Contracting Officer approved soil solidifier to harden the surfaces, furnishing and installing timber borders and
Government Furnished metal gate on entrance road, unit markers, fire rings and
8 foot tables; barrier rock relocation and installation; clearing, grubbing, trimming, removing and disposing of trees, slash and stumps with disposal by methods described in the specifications and as approved on the ground by the
Contracting Officer; obliteration, demolition and disposal of septic tanks, hydrant, piping, valves, wiring and posts; supplying and installing the 18” diameter corrugated metal pipe culvert as shown on the drawing and as described in the specifications. Work shall include excavation, bedding, backfilling, and constructing a drainage outlet from the culverts where required;
furnishing and installing an 8” thick double-sized (unless contractor wants to double the amount of fiber in the pour) fiber reinforced concrete dumpster pad as shown on the drawings and as described in the specifications. Work includes excavation, aggregate base and final grading; furnishing and installing a double tubular steel information kiosk; and fabricating and installing tubular steel horse hitch rails in concrete footings as shown on the drawings and described in the specifications.
2. Work also includes demolition, removal and abandonment with the State of
Colorado of the existing handpump well in the Lost Lake Campground.
3. Payment shall be made at the contract lump-sum price.
C. Optional Bid Item No. 3 –Additional Facilities – Beckwith Horse Trailhead
1. This bid item includes furnishing and installing: A single tubular steel information kiosk, traffic or directional signs and posts with panels, and tubular steel horse hitch rails in concrete footings as shown on the drawings and as described in the specifications. Site grading, excavation and embankment, backfill and concrete are incidental to this item.
LOST LAKE CAMPGROUND AND TRAILHEAD 012200-11
2. Payment shall be made at the contract lump-sum price.
D. Optional Bid Item No. 4 – Traffic and Directional Signs and Posts for Campground, Entrance Road and Turn-Around
1. This bid item includes furnishing and installing: signs and posts with panels as shown on the drawings and described in the specifications for the Campground, entrance road and turnaround. Excavation, backfill and hardware are incidental to this item.
2. Payment shall be made at the contract lump-sum price.
E. Optional Bid Item No. 5 – Traffic and Directional Signs and Posts for Day Use, Trailhead Parking and Horse Trailer Campsites
1. This bid item includes furnishing and installing: signs and posts with panels as shown on the drawings and described in the specifications for the Day Use
Area, Trailhead parking, Turnarounds and Horse trailer campsites. Excavation backfill and hardware are incidental to this item.
2. Payment shall be made at the contract lump-sum price.
F. Optional Bid Item No. 6 – Fee Station Three Panel Kiosk for Campground Entrance
1. This bid item includes furnishing and installing: A triple panel tubular steel information kiosk in concrete footings as shown on the drawings and as described in the specifications. The Panels are Government Furnished. Site grading is incidental to this item. Aggregate, excavation, backfill, concrete and hardware are considered incidental to this item.
2. Payment shall be made at the contract lump-sum price.
G. Optional Bid Item No. 7 – Pre-cast Concrete Plank Boat Ramp with 3” Minus Washed
Stone Base and Shoulders
1. This bid item includes construction of a pre-cast concrete plank boat ramp including survey and layout, excavation and embankment, supply and installation of concrete planks with metal cable or hardware anchors, perimeter backfill with 3” minus washed stone, and final grading.
2. Polyfiber geotextile fabic and placement of washed stone base are considered incidental to this item. 3” Minus Washed Stone is Government Furnished.
Contractor hauls,places and compacts washed stone.
3. Payment shall be made at the contract lump-sum price.
H. Optional Bid Item No. 8 - Seeding
1. This bid item includes furnishing, spreading and placing native seed by methods as described in the specifications. This is for the restoration of areas over abandoned roads, spurs campsite areas and other facilities or construction areas to be obliterated and removed.
2. Payment shall be made at the contract lump-sum price.
I. Bid Items No. 9 – Clearing and Grubbing Individual Tree, Stump and Slash Removal–
Connector Trail from Beckwith Horse Trailhead to Horse Trailer Campsites including
Excavation and Embankment
LOST LAKE CAMPGROUND AND TRAILHEAD 012200-12
1. These bid items includes clearing, grubbing, trimming, removing and disposing of trees, slash and stumps including trail construction by methods described in the specifications and on the ground as approved by the Contracting Officer.
Site grading including excavation and embankment is considered incidental to the construction of the new 4 ft. width trail alignment.
2. Payment shall be made at the contract lump-sum price.
J. Optional Bid Item No. 10 – Double Concrete Vault SST Toilet Installation Lost Lake
Campground including Demolition of the Existing Concrete Block Vault Toilet, Rock
Retaining Wall with Geotextile and Concrete Toilet Entry Apron
1. This optional bid item includes furnishing and installing a double unit vault toilet with service room as shown on the drawings and as described in the specifications. Construct a rock retaining wall with geotextile underlayerment and concrete entry apron slab as shown on the drawings, described in the specifications and at location approved by the Contracting Officer. Site
Grading, excavation and embankment, backfill and drainage are considered incidental to this item. Coordinate delivery and follow all manufacturer installation instructions.
2. Work includes removing, demolishing and disposing of the existing Concrete
Vault Toilet with concrete slab as shown on the drawings and described in the specifications. Backfill is considered incidental to this item.
3. Work includes furnishing and installing rock riprap retaining wall for excavated slope at the rear of the new toilet. Work includes hauling rock from off-site sources, on-site excavation as required, and placement as shown on the drawings. Poly fiber geotextile fabric and aggregate base are considered incidental to this item.
4. This bid item includes furnishing and installing a 6” thick fiber reinforced concrete entry slab adjacent to the new toilet as shown on the drawings and as described in the specifications. Work includes excavation, aggregate base, final grading and thickened edge on one side with campground loop road.
5. Payment shall be made at the contract lump-sum price.
K. Optional Bid Item No. 11– Double Concrete Vault SST Toilet Installation Lost Lake
Day Use Trailhead Area including Concrete Toilet Entry Apron
1. This optional bid item includes furnishing and installing a double unit vault toilet with service room as shown on the drawings and as described in the specifications. Locate and construct a concrete entry apron slab as shown on the drawings, described in the specifications and at location approved by the
Contracting Officer.
Site Grading, excavation and embankment, backfill and drainage are considered incidental to this item. Coordinate delivery and follow all manufacturer installation instructions.
2. This bid item includes furnishing and installing a 6” thick fiber reinforced concrete entry slab adjacent to the new toilet as shown on the drawings and as described in the specifications. Work includes excavation, aggregate base, final grading and thickened edge on one side with campground loop road.
3. Payment shall be made at the contract lump-sum price.
LOST LAKE CAMPGROUND AND TRAILHEAD 012200-13
LOST LAKE CAMPGROUND AND TRAILHEAD 013223 - 1
SURVEY AND LAYOUT DESIGN
SECTION 013223
SURVEY AND LAYOUT DESIGN
PART 1 – GENERAL
1.1 SUMMARY OF WORK
A. This work shall consist of the construction staking of the project by the methods specified herein, or another acceptable coordinate geometry method. The items to be surveyed and staked include roadways, spurs, camp units, toilets, dumpster pads, trails and other related site work shown on the drawings, from coordinates and control points shown on the drawings. The work includes furnishing all labor, equipment, instruments, stakes, materials, transportation, and other incidentals necessary to complete the construction staking in accordance with these specifications and acceptable engineering practice. The work shall also include setting grade-finishing stakes and/or red and blue tops for surfacing and concrete forming.
B. Construction staking shall be accomplished under the direction of a Registered
Professional Engineer or Land Surveyor. The Professional Engineer or Land Surveyor will be closely associated and familiar with the construction staking and periodic visits to the project site are required.
C. Measurement shall be lump-sum for surveying and staking the project through all phases of construction.
PART 2 – PRODUCTS
2.1 STAKES
A. Identification stakes and hubs shall be of sufficient length and width (nominal size of
1”x2”x18”) to provide a solid set in the ground and to provide space for marking above ground when applicable. Other dimensions and materials may be used, such as steel reinforcing bars, wire flagging and markers, and metal pins, if approved in writing by the Contracting Officer (CO). The top 2 inches of all slope, guard, reference, clearing, and structure stakes shall be painted or marked with plastic flagging.
2.2 SURVEY NOTE PAPER AND BOOKS
A. Paper for survey notes shall be moisture-resistant paper. Notes shall be contained in books with covers that will protect the contents and retain the pages in numerical sequence during field use. Field notebooks or note paper shall be furnished by the contractor. All notes shall become the property of the Government.
B. Upon completion of a portion of any staking involving grading, a cut sheet shall be prepared showing, at a minimum, point number or station, offset (if any) stake
LOST LAKE CAMPGROUND AND TRAILHEAD 013223 - 2
elevation, proposed grade and cut or fill. The Contractor shall submit one (1) copy of the cut sheets to the Contracting Officer in addition to any copies required by the
Contractor's work crews.
C. At the conclusion of construction, a set of construction drawings reflecting the actual locations and elevations of all contract features, as constructed, shall be submitted to the Contracting Officer.
2.3 GOVERNMENT-FURNISHED DOCUMENTS
A. The Contractor shall be furnished electronic and/or hardcopy drawings, location and coordinates of control points.
PART 3 - EXECUTION (SURVEY REQUIREMENTS)
3.1 SURVEY NOTES
A. The Contracting Officer shall approve format for submitted slope stake notes. A sample format will be supplied upon request from the Contractor.
B. Manually recorded survey notes shall be printed in characters at least 0.15 inches height and shall be legible at a distance of 2.5 feet. Errors shall be deleted by lining out.