LOST LAKE CAMPGROUND 024113-1
WATER SYSTEM SELECTIVE SITE DEMOLITION
SECTION 024113
SELECTIVE SITE DEMOLITION
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Contractor shall remove and dispose of the existing above ground piping, culvert pipe, spring collection system, wood “A” frame structure and water tank located immediately adjacent to the new potable water storage tank.
1.2 DEFINITIONS
A. Remove: Remove and legally dispose of items except those indicated to be reinstalled, salvaged, or to remain the Government's property as directed by the
Contracting Officer. Dispose of demolished material at an approved landfill off government lands.
B. Existing to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by the Contracting Officer, items may be removed to a suitable, protected storage location during selective demolition and then cleaned and reinstalled in their original locations.
C. Abandon: Remove items indicated that are visible above ground
1.3 MATERIALS OWNERSHIP
A. Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain the Government's property, demolished materials shall become the
Contractor's property and shall be removed from the site and disposed of in accordance with Section 017419.
1.4 PROJECT CONDITIONS
A. The Contractor will demolish the existing identified water system facilities in Lost
Lake Campground prior to the beginning of contract work.
PART 2 – PRODUCTS – (Not Applicable)
PART 3 - EXECUTION
3.1 GENERAL
A. Excavation and backfill shall be specified in Section 312316
LOST LAKE CAMPGROUND 024113-2
WATER SYSTEM SELECTIVE SITE DEMOLITION
B. Excessive settlement or other evidence of improper backfill shall be corrected by reopening the excavation to the depth required for proper refilling and compaction.
3.2 EXAMINATION
A. Inventory and record the condition of items to be removed and reinstalled and items to be removed and salvaged.
3.3 ITEMS TO BE ABANDONED
A. Abandoned waterlines shall remain in place underground after removing the above ground portions of lines. Where excavation occurred, the natural drainage pattern shall be restored or maintained or both.
3.4 DISPOSAL
A. General: Promptly dispose of demolished materials. Do not allow demolished materials to accumulate on-site.
B. Burning: Do not burn demolished materials.
C. Disposal of debris shall comply with Section 017419 – Construction Waste
Management and Disposal.
END OF SECTION