017419_constr_waste_management_disposal.pdf

PDF 14 KB Posted

Attached to
RECOVERY - Lost Lake Campground - Grand Mesa, Uncompahgre and Gunnison NFs
Solicitation number
AG-82B1-S-09-0057
Issued by

About this file

docs

View the file

Other files

File Type Posted
331111-Water_Supply_Design_Construction.pdf PDF
311000_Clearing_Grubbing_REV Amd 2.doc DOC document
WS Demo - Aframe tank 1.JPG JPG image
033000_Cast-in-place_concrete.pdf PDF
U9_WELL-DETAILS.pdf PDF
Optional Bid Item 12 Amend 2.doc DOC document
WS Demo - culvert.JPG JPG image
U1-UTIL-PLAN.pdf PDF
U4_UTILITY-DETAILS.pdf PDF
Revised Schedule of Items Amend 2.xls XLS spreadsheet
312316_Struct_Excavation_Backfill.pdf PDF
LOST_LAKE_CG_WS_SPEC_INDEX.pdf PDF
U6_TREATMENT-BLDG-PLAN.pdf PDF
017700_closeout_procedures.pdf PDF
WS Demo - Aframe tank 2.JPG JPG image
013300_submittal_procedures.pdf PDF
331219-Water-hydrant.pdf PDF
011100_summary_of_work.pdf PDF
016400_government_furnished_mats.pdf PDF
T1_TITLE_SHEET.pdf PDF
011100_summary_of_work_REV09_03_09.pdf PDF
311100_Clearing_Grubbing.pdf PDF
T1_TITLE_SHEET-SIGNATURES.pdf PDF
WS Demo - Spring and piping.JPG JPG image
U8_TYP_SPUR_UTIL_DET.pdf PDF
011419_use_of_site.pdf PDF
331116-Water-distribution.pdf PDF
U7_TREATMENT-BLDG-PLUMBING.pdf PDF
U5-HYDRANT-DETAILS.pdf PDF
U2-UTIL-PLAN-PROFILE.pdf PDF
SF 30 AMEND 2.PDF PDF
332110_Water_Supply_Wells.pdf PDF
312317_Trenching_Utilities.pdf PDF
012200_definition_bid_items_REV09_03_09.pdf PDF
100perc_FINAL_Lost_Lake_CG_Spec_Index_REV09_03_09.pdf PDF
012200_definition_bid_items.pdf PDF
wage determination.txt TXT text file
024113_selective_site_demolition.pdf PDF
U3-UTIL-PLAN-PROFILE.pdf PDF
Amendment 001 to Solicitation AG.doc DOC document
Amendment 001 —
AG-82B1-S-09-0057.pdf PDF
sf 1442.pdf PDF
lost-lake-dwgs.pdf PDF
sf24_f.pdf PDF
lost-lake-specs.pdf PDF
wage determination.txt TXT text file
Show all 47

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LOST LAKE CAMPGROUND 017419-1

WATER SYSTEM CONSTRUCTION WASTE MANAGEMENT

AND DISPOSAL

SECTION 017419

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

PART 1 - GENERAL

1.1 SUMMARY

A. The work of this section includes clean up and disposal of waste and hazardous waste materials generated or encountered as a result of the work of this contract.

1.2 CLEAN UP

A. The Contractor shall keep the work site free from accumulation of waste materials and rubbish resulting from the work.

B. Before final acceptance of the project by the Government, the Contractor shall remove from Government land and properly dispose of all waste materials and rubbish resulting from this work.

C. If work is stopped or delayed for an extended period of time, the Contractor shall clean up the site as determined by the Contracting Officer.

1.3 DISPOSAL

A. Bear-proof Dumpsters and Garbage Containers:

1. This area is a heavily populated with black bears. All trash or garbage containers including dumpsters shall be secured and made bear-proof for the duration of contract work.

B. Excavated material:

1. Excavated material that is excess to needs and reasonably free of muck, roots, and debris shall be disposed of on site as approved by the Contracting Officer.

C. Debris, Trash and Garbage:

1. Brush, wood, packaging and other trash shall be hauled to a State-approved sanitary landfill. The nearest landfill is the Adobe Buttes Landfill, 1221 Trap

Club Road, Phone (970) 835-7999, The landfill is located approximately 45 miles from Lost Lake just west of Eckert, Colorado. The landfill is operated by the Delta County Solid Waste Manager. Contact the manager for fees, hours and load requirements. There is a trailer transfer station located at: North Fork

Transfer Station, 36577 K50 Road, Hotchkiss, Colorado. A second landfill option is: Gunnison County Landfill, 45800 US Highway 50, Gunnison, CO.

81230, Phone (970) 641-5522 or FAX (970) 641-8120.

D. Unusable Excavated Material:

LOST LAKE CAMPGROUND 017419-2

WATER SYSTEM CONSTRUCTION WASTE MANAGEMENT

AND DISPOSAL

1. Unusable Excavated Material (such as muck and roots) shall be hauled off of government land.

E. Washing waste material into waterways will not be permitted.

1.4 HAZARDOUS WASTE MATERIALS

A. Storage, Transportation, and Disposal:

1. The Contractor shall remove, within forty-eight (48) hours, all waste materials from the site in compliance with applicable waste requirements.

2. The Contractor shall be responsible for determining whether any of the waste materials are hazardous waste according to the regulations defined in 40 CFR

Part 261, "Identification and Listing of Hazardous Waste." This includes solid waste and wastewater generated from the project.

3. Containers used for shipping and disposal shall be appropriate for the type of waste material and shall comply with all governing regulations.

4. Hazardous waste shipments must be accompanied by the "Uniform Hazardous

Waste Manifest." The Contractor shall obtain and prepare all manifests. The pick-up manifest will be reviewed and given to the Contracting Officer for signature by an appropriate Government official. Completed copies of all manifests shall be furnished to the Contracting Officer and shall be submitted in such a manner as to comply with the timeliness prescribed by the State and

Environmental Protection Agency regulations.

5. The Contractor shall arrange to have hazardous waste collected and transported to an EPA-approved treatment, storage, and disposal facility (TSD). The

Contractor shall obtain from the TSD, an EPA I.D. number. The disposal facility selected must not have any currently outstanding permit violations that are relevant to the prevention of releases to the environment or involve an active or historic release.

PART 2 – PRODUCTS (NOT APPLICABLE)

PART 3 – EXECUTION (NOT APPLICABLE)

END OF SECTION