LOST LAKE CAMPGROUND 011100-1
WATER SYSTEM SUMMARY OF WORK
SECTION 011100
SUMMARY OF WORK
PART 1 – GENERAL
1.1 SUMMARY
A. Work for this project consists of the partial design and complete construction of a new potable water system. Work includes but is not limited to: Partial demolition of existing waterlines, valves, and tanks; Installation of new waterlines, valves, drains, and water hydrants; transportation and installation of a Government furnished water treatment building; Provide and install associated plumbing, fittings, chlorinator, solar power source (including panels, poles, and supports), lighting, control panels, switches and other miscellaneous items within the building; Design and construction of a new solar powered potable water supply utilizing an existing well including solar panels, submersible pump, pitless adapter, wiring, tank level controls, underground storage tank, control panels and other miscellaneous items required for a complete and working system as described in these specifications and shown on the drawings.
1.2 LOCATION
A. This project is located approximately 12 miles west of the town of Crested Butte, Colorado, 20 miles east from Paonia, Colorado and 49 miles from Delta, Colorado on the Paonia Ranger District of the Grand Mesa, Uncompahgre and Gunnison National
Forest. The site is located at the end of National Forest System Road No.706, approximately 2 miles south of Gunnison County Road # 12, Kebler Pass Road
(Section 4, T. 14S., R. 88W., 6 th
P.M.) The campground lies adjacent to the Lost Lake
Slough reservoir, which provides excellent fishing and small craft boating activities.
1.3 GENERAL SITE CONDITIONS AND WEATHER
A. The altitude of the project is approximately 9,623 feet above mean sea level. The construction site experiences snowfall and rain and extremely cold temperatures, with snow on the ground typically from October through mid -June.
B. Electric power is not available at the site.
C. In-depth soil surveys have not been performed. The Contractor should expect to encounter rock during excavation and grubbing operations. Blasting of rocks will not be permitted unless approved by the Contracting Officer.
D. In-depth water table surveys have not been performed; however, if water is encountered during excavation, the Contractor shall perform adequate dewatering to keep the excavation free from water and dispose of the water without damage to property.
1.4 STAGING AREA AND SAFETY
LOST LAKE CAMPGROUND 011100-2
A. The staging and landing areas will be as approved on site by the Contracting Officer.
The Lost Lake Campground will be closed to the public during construction.
Contractor shall provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Contractor shall minimize disturbance of all undisturbed areas outside of project work. Vegetation, meadows and forested areas outside of roadwork, drainage or Construction Limits determined by the Contracting Officer shall be protected from equipment impacts or other disturbances.
1.5 MEALS AND LODGING
A. Meals and lodging are commercially available in the towns of Crested Butte, Paonia and Delta, Colorado within 12 to 50 miles of the construction site.
B. A work camp will be allowed at the construction site with prior approval of the
Contracting Officer and the Paonia Ranger District. Other campgrounds in the area are operated by a concessionaire and payment of fees would be required.
1.6 SITE CLEANUP AND DISPOSAL
A. The Contractor shall dispose of all waste off National Forest Lands in accordance with
Section 017419, Construction Waste Management and Disposal.
1.7 CONSTRUCTION SEQUENCE
A. Construction shall begin in September 2009.
B. The project shall be completed within the time frame established by the terms of this contract and according to the approved Schedule of Work.
C. Depending on conditions, normal fire restrictions may apply to activities associated with this project.
1.8 COOPERATION BETWEEN CONTRACTORS
A. The Government reserves the right to contract for or perform other additional work on or near the work covered by this contract.
1.9 STORAGE
A. The Contractor shall be responsible for protection of all equipment and supplies intended for use in the project. The Contractor shall pay all costs related to such protection. Refer to Section 011419, Use of Site.
1.10 FIELD VERIFICATION
A. Field verify all new and existing dimensions affecting the work of this contract before ordering products.
LOST LAKE CAMPGROUND 011100-3
1.11 PERMITS
A. Special permits required by County, State, or Federal laws or regulations shall be obtained by the Contractor.
PART 2 – PRODUCTS – (NOT APPLICABLE)
PART 3 – EXECUTION – (NOT APPLICABLE)
END OF SECTION