LOST LAKE CAMPGROUND 013300-1
WATER SYSTEM SUBMITTAL PROCEDURES
SECTION 013300
SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section shall consist of submittal requirements.
1.2 REQUIREMENTS
A. It will be the Contractor's responsibility to submit all items with such promptness as to cause no delay in the work. Approvals must be obtained before starting work that involves the item. Contractor shall allow 10 calendar days for processing of submittals by the Government.
B. The following submittals are required following award of contract for review and approval pursuant to contract provisions:
Item Description Copies
Required
References
1. Cost breakdown schedule listing main types of work and totaling amount of contract.
1 FAR 52.232-
2. A written Safety Plan, outlining necessary measures to be taken to provide protection to the public during all construction operations.
3. Quality Control Plan 1
4. Contract Schedule – Updated on an On-going
Basis
5. As-Built Drawings. 3 paper, 1 electronic 4 See Spec.
Section
017700
6. Certification Required in Contract and Test
Results
1.3 MANUFACTURER'S LITERATURE AND SHOP DRAWINGS
A. Submit two (2) copies to the Contracting Officer for approval on the items required herein. Literature which is not marked or otherwise designated to show the exact model, size, etc., the Contractor proposed to use, will be returned by the Contracting
Officer "without action." Circle or check items on submittals. Highlighter pens may print black or not at all when copied.
LOST LAKE CAMPGROUND 013300-2
WATER SYSTEM SUBMITTAL PROCEDURES
B. Information must be adequate to determine compliance with specifications.
C. Submit three (3) copies of materials that cannot reasonably be copied on typical copy machines. One (1) copy of all submittals will be returned to the Contractor.
D. Submittals which are received from sources other than through Contractor's office will be returned by the Contracting Officer "without action."
1.4 SAMPLES
A. Submit two samples of each color, stain, style, etc. One sample of selected color, etc., will be retained. All other samples and all hardware samples will be returned.
PART 2 – PRODUCTS (NOT APPLICABLE)
PART 3 – EXECUTION (NOT APPLICABLE)
END OF SECTION