A07 ATTACHMENT 0084 TE 10.2 Bridge Operating Procedures (SOP).pdf

PDF 16 KB Posted

Attached to
Base Operations Support Services on the Rock Island Arsenal, Rock Island, Illinois
Solicitation number
W52P1J-21-R-5001
Issued by

About this file

This document contains standard operating procedures for bridge operations and maintenance at the Rock Island Arsenal in Rock Island, Illinois. The procedures outline the normal steps for opening and closing the swing span bridge, providing alternate electrical power from Lock and Dam #15, and locking and unlocking the swing span.

The related federal contract opportunity is a solicitation for base operations support services at the Rock Island Arsenal, including grounds maintenance, pavement clearance, facility maintenance for both vertical and horizontal structures, pest management operations, hydroelectric plant operations and maintenance, bridges operation and maintenance, and unscheduled services. The proposed contract would be for one base year and four option years, with a potential six month option to extend services.

View the file

Other files

File Type Posted
Amendment 0008.pdf PDF
A07 Pricing Matrix RIA Base Ops Rev L 16 Feb 2021.xlsx XLSX spreadsheet
A07 Amendment 00006.pdf PDF
Amendment 00007.pdf PDF
A07 A RIA Overarching (OA) PWS BASEOPS_20210210.pdf PDF
A07 Pricing Matrix RIA Base Ops Rev K 11 Feb 2021.xlsx XLSX spreadsheet
A07 Amendment 00005.pdf PDF
Pricing Matrix RIA Base OpsRev J 08 Feb 2021.xlsx XLSX spreadsheet
A07 Att 4 Facility Maintenance Vertical JV_20210208.pdf PDF
A07 Amendment 0004.pdf PDF
A07 TE 4.21 Cranes and Crane Rails_20210208.pdf PDF
Amendment 0003.pdf PDF
A07 DB WAGE DETERMINATION BUILDING revised 21 January 2021.pdf PDF
A07 DB WAGE DETERMINATION Heavy Highway revised 01 January 2021.pdf PDF
A07 DB WAGE DETERMINATION Heavy revised 15 January 2021.pdf PDF
A07 Att 6 Facility Maint Horizontal JV_IGSA Rev 20210121.pdf PDF
A07-Amendment 0002.pdf PDF
A07 CONFORMED COPY WITH ALL AMENDMENTS.pdf PDF
A07 Att 10 Bridge Operations and Maintenance JV_Final 2020121.pdf PDF
A07 PWS OA and All Attachments 20210126.pdf PDF
A07 ATTACHMENT 0007 Pricing Matrix 11 January 2020.xlsx XLSX spreadsheet
A07 ATTACHMENT 0009 Past Performance Questionnaire 12 Jan 2021.docx DOCX document
A RIA Overarching (OA) PWS 12 January 2021.pdf PDF
A07 TE 5.10 Family Housing Inventory Items rev.xlsx XLSX spreadsheet
CBA 2018-2023 .pdf PDF
AMENDMENT 0001.pdf PDF
A07 ATTACHMENT 0074 TE 7.20 Stormwater Observation Report.pdf PDF
A07 ATTACHMENT 0012 TE 1.2 Estimated Workload Data DETAIL rev.xlsx XLSX spreadsheet
A07 ATTACHMENT 0005 TE List.docx DOCX document
A07 ATTACHMENT 0027 TE 4.6 Overhead Doors.xlsx XLSX spreadsheet
A07 ATTACHMENT 0072 TE 7.18 Flood Pump Information.pdf PDF
A07 ATTACHMENT 0080 TE 9.1 Elect Distrib Sytm Mjr Components HydroPlant.xlsx XLSX spreadsheet
A07 ATTACHMENT 0013 TE 1.2 Estimated Workload Data Summary.pdf PDF
A07 ATTACHMENT 0054 TE 6.1 Outage Log.xlsx XLSX spreadsheet
A01 ATTACHMENT 0001 PWS Att 2 Grounds Maintenance.pdf PDF
A07 ATTACHMENT 0081 TE 9.2 SCADA Reporting Elements.pdf PDF
A07 ATTACHMENT 0028 TE 4.7 List of Air Compressors.xlsx XLSX spreadsheet
A07 ATTACHMENT 0038 TE 4.17 Mass Notification Systems.xlsx XLSX spreadsheet
A07 ATTACHMENT 0037 TE 4.16 Fire Suppression Systems.xlsx XLSX spreadsheet
A07 ATTACHMENT 0014 TE 1.4 RIA Spill Prevention Contingency and Countermeasure Plan 2017.pdf PDF
A07 ATTACHMENT 0057 TE 6.4 Sign Replacement Requirements.pdf PDF
A07 ATTACHMENT 0039 TE 4.18 Playground Equipment.pdf PDF
A07 ATTACHMENT 0017 TE 1.7 Government Furnished Facilities 20200807.pdf PDF
A07 ATTACHMENT 0031 TE 4.10 Grease Trap.xlsx XLSX spreadsheet
A07 ATTACHMENT 0041 TE 4.20 Meter Reading Form.xlsx XLSX spreadsheet
A07 ATTACHMENT 0063 TE 7.1 Major Components of Water System.pdf PDF
A01 ATTACHMENT 0001 PWS RIA Overarching (OA) PWS.pdf PDF
A07 ATTACHMENT 0067 TE 7.10 Water Distribution Valves.pdf PDF
A07 ATTACHMENT 0050 TE 5.6 Recreational Areas and Playgrounds AFH.pdf PDF
A07 ATTACHMENT 0042 TE 4.21 Cranes and Crane Rails.pdf PDF
Show 40 more

Latest 50 of 109 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TE 10.2 Bridge Operating Procedures (SOP)

TE 10.2 Bridge Operating Procedures (SOP) 1

SOP: SWING SPAN BRIDGE OPERATION

SECTION 1 - PROCEDURES FOR OPENING AND CLOSING OF SWING

SPAN

Normal steps involved in opening and closing of swing span (sometimes called turning of the bridge).

1. Turn on advanced warning lights 5 minutes prior to a turn.

2. Turn on "Bridge Open" lights.

3. Sound air whistle.

4. Monitor camera system throughout following procedures.

5. Stop and clear all traffic to include pedestrians.

6. Close all vehicle and pedestrian gates and barriers.

7. Operate Interlocking Controls.

a. Disengage rail-locks.

b. Lower bridge ends.

c. Operate control levers to turn swing span.

8. Align opened bridge.

9. Allow vessel to pass.

10. Close bridge.

11. Align bridge in closed position.

12. Raise bridge ends.

13. Engage rail-locks

14. Open all vehicle and pedestrian gates and barriers.

15. Resume bridge traffic.

16. Turn off "Bridge Open" and advance warning lights.

TE 10.2 Bridge Operating Procedures (SOP) 2

SECTION 2 - PROVIDE ALTERNATE ELECTRICAL POWER FROM LOCK

AND DAM #15

1. Coordinate with on duty personnel from Lock 15 for any operation that requires switching to auxiliary power. Only one operation (Lock gate/valve or Bridge) can be accommodated at a time while both operations are on the emergency generator.

2. Operator must ensure that any power draw is turned OFF or disconnected before switching to emergency power.

3. Place the transfer switch handle in the control tower attic in the middle (neutral, open) position.

4. Inside the breaker panel box marked (SB), on the inside east wall of the bridge workshop, verify that the emergency power switch #1 is in the OFF position.

5. Connect the emergency power cable stored in the workshop area beneath the bridge swing span from the outlet on the outside of the shop wall to the one on the bridge structure.

6. Inside the breaker panel box marked (SB), on the inside east wall of the bridge workshop, place the emergency power switch #1 in the ON position.

7. Place the transfer switch handle located in the operating tower attic in the DOWN (emergency power) position. Front cover is marked.

8. Perform normal turning procedures, except swing span can only be turned 90 degrees and back (Due to cable length).

9. Reconnect to main power supply when it is restored by reversing the procedure.

SECTION 3 - LOCKING AND UNLOCKING SWING SPAN

Normal steps involved in locking and unlocking swing span bridge.

1. Locking:

a. Place locking devices onto lifting mechanisms. This is done on both ends of the swing span (designated J-1 and J-2).

b. Attach railroad-interlocking locks to each rail at both ends of swing span (8 total).

TE 10.2 Bridge Operating Procedures (SOP) 3

c. Unhook all roadway and sidewalk gate control arms and lock the gates in open position.

2. Unlocking:

a. Remove and store locking devices used on lifting mechanism.

b. Remove and store locking bars used on railroad interlocking.

c. Connect all roadway and sidewalk gate control arms to motors and unlock

File details come from the government source that posted it. Updated .