A.15.01.03.07 Annex G delivery matrix.xlsx
XLSX spreadsheet 10 KB Posted
- Attached to
- Spangdahlem Total Maintenance
- Solicitation number
- HQC01026QE016
- Issued by
-
Defense Commissary Agency
About this file
This is a Delivery Matrix that establishes the timeline and Performance Work Statement (PWS) references for all deliverables required under the Spangdahlem Total Maintenance contract. The matrix organizes deliverables into three categories: those due within 30 days of contract start, recurring monthly and quarterly submissions, and time-sensitive or as-needed items. Initial deliverables due within 30 days include a 100% inventory verification of all equipment and refrigerant gases with corresponding checklists, an annual PM schedule, initial Quality Control Plan (QCP), emergency call number notification, and base access requests. The contractor must also establish PM services with a monthly schedule commencing the first workday of each month and submit PM findings by the 7th of the following month. Quarterly inventory updates are due by the last week of each quarter, while annually a refrigeration leak report must be submitted by January 30th. For unscheduled maintenance work orders, the contractor is required to submit a requested proposal per work order within 14 days of request and complete the work within 45 days of notice to proceed. Recurring administrative deliverables tied to invoice submission include monthly summaries of work performed and summaries of remaining funds. Base access request renewals must be submitted 60 days prior to expiration, and Quality Control Plan updates are due within 7 days of any changes. All deliverables must be logged and tracked in DeCA's Service Order Management System (SOMS) per the PWS requirements.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Delivery Matrix | |||
| Deliverable | Due | PWS reference | |
| Start of contract | |||
| 100% inventory verification | 30 days after contract start | 3.1.1.1 | |
| PM Schedule (annual) | 30 days after contract start | 3.1.1/3.1.1.2 | |
| PM Checklists, blank, for all items | 30 days after contract start | 3.1.1.2 | |
| Base Access request (initial) | 30 days after contract start | 4.5.2.1 | |
| Emergency call number | 30 days after contract start | 3.3.1 | |
| QCP, initial | 30 days after contract start | 5.1 | |
| Monthly | |||
| Summary of work preformed | with invoice * | 4.4.3.2 | |
| Summary of funds remaining | with invoice * | 4.4.3.2 | |
| PM findings | by 7th of following month | 3.1.3 | |
| PM services schedule | 1st work day of month | 3.1.1.2 | |
| Quarterly | |||
| Inventory update | last week of the quarter | 3.1.1.1.2 | |
| Annually | |||
| Refrigeration leak report | 30th of January | 4.7.2 | |
| As required | |||
| Requested proposal per WO (SOMS) | 14 days from Request | 3.2.1 | |
| Completed WO (SOMS) | 45 days from Notice | 3.2.3 | |
| base access request (renewal) | 60 days prior to expiration | 4.5.2.1 | |
| QCP, update | 7 days after change | 5.1 | |
| * if the contractor submits an invoice |