9-Section 01100 - Special Project Procedures - 09292026.pdf
PDF 153 KB Posted
- Attached to
- Removal and Replacement of Telemetry Cabinets for Existing SCADA System - Phased Projects
- Solicitation number
- ITB No.: 27-402/DL
- Issued by
- Palm Beach County, Florida
About this file
This is a Special Project Procedures specification document for a state and local contract opportunity in Florida involving the removal and replacement of telemetry cabinets for an existing Supervisory Control and Data Acquisition (SCADA) system. The project encompasses the replacement of thirty-three (33) telemetry cabinets across multiple phased projects and requires a licensed Florida General or Electrical Contractor to provide all labor, materials, equipment, and incidentals necessary for completion. The contract will operate for an initial three (3) year period with an option to renew for an additional one (1) year at the Authority's discretion. Bidders must submit responses electronically through Bonfire by specified deadlines and include bid security in the form of a surety bond or cashier's check equal to not less than five percent (5%) of the total bid amount.
The specification establishes comprehensive technical and operational requirements including mandatory onsite supervision by a competent, English-speaking representative experienced in industrial instrumentation and electrical safety; climate-controlled storage for sensitive electronics; daily reporting of installation activities; and submission of Hurricane and Severe Weather Preparedness Plans and Process Contingency and Spill Prevention Plans within fifteen (15) days of Notice to Proceed. All materials must be new, unused, and currently supported standard products from recognized manufacturers, with legacy or end-of-life components prohibited. The contractor assumes full responsibility for the work and must provide a one-year warranty from substantial completion and an extended five-year performance guarantee covering structural panel integration, terminal blocks, wiring organization, and power distributions. Emergency response requirements mandate 24/7 availability with qualified technicians responding within two (2) hours to critical system failures, with associated costs deducted from contract value if the contractor fails to meet this obligation. No Small Business Enterprise (SBE) participation requirement is specified for this solicitation.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITB No.: 27-402/DL Removal & Replacement of Telemetry Cabinets for 01100 -1 Existing SCADA Systems – Phased Projects
SECTION 01100
SPECIAL PROJECT PROCEDURES
PART 1 – GENERAL
1.01 WORKMANSHIP, MATERIAL, AND EQUIPMENT
A. When a particular control system product, programmable logic controller (PLC), human-machine interface (HMI), telemetry radio, or instrument is specified or called for, it is intended and shall be understood that the proposal tendered by the CONTRACTOR included those specific products in his bid.
B. All materials, microprocessors, surge suppressors, power supplies, terminals, and manufactured articles for incorporation into the Work shall be the new, unused, and currently supported standard products of recognized reputable MANUFACTURERS. Legacy or end-of-life electronic components will not be accepted.
1.02 RESPONSIBILITY OF CONTRACTOR
A. The CONTRACTOR shall be responsible for the entire Work determined by the Drawings, Specifications, and Contract from the date of the starting of the Work until it is accepted as evidence of approval of the Completion Certificate by the OWNER.
He shall be responsible for removals, renewals, and replacements due to electrical surges, environmental conditions, and all other causes except as otherwise provided in the Specifications.
The CONTRACTOR shall keep the Contract under his own control and it shall be his responsibility to see that the Work is properly supervised and carried on faithfully and efficiently.
B. The CONTRACTOR shall supervise the work personally or shall have a competent, English-speaking superintendent or representative— who is thoroughly experienced in industrial instrumentation, electrical safety, and SCADA deployment—on the project site at all working hours. This individual shall be clothed with full authority by the CONTRACTOR to direct the performance of the work and make arrangements for all necessary materials, specialized testing equipment, and labor without delay.
C. Renewals or repairs necessitated because of defective electronics, faulty wiring terminations, poor workmanship, or due to action of the elements or other natural causes, including electrical faults, water intrusion, or component overheating prior to final acceptance, shall be done anew in accordance with the Contract and Specifications at the expense of the
CONTRACTOR.
Removal & Replacement of Telemetry Cabinets for 01100 -2 Existing SCADA Systems – Phased Projects
D. In addition to the requirements of this section, the CONTRACTOR shall comply with the OWNER’s Pollution Prevention Plan for Construction & Contractors.
1.03 PROVISIONS FOR ENVIRONMENTAL PROTECTION AND DUST CONTROL
A. Sufficient precautions shall be taken during construction to prevent the contamination of facility systems or surface waters by electronic debris, chemical solvents, wire clippings, or backup batteries. Special precautions shall be taken to protect open conduit pathways from entering run-off water or landfill gases.
B. The CONTRACTOR shall be responsible for complying with all applicable environmental and utility permit conditions related to the site.
1.04 ONSITE STORAGE AND SENSITIVE ELECTRONICS
A. The CONTRACTOR is required to maintain special climate-controlled storage requirements for all new TELEMETRY CABINETS, PLCs, radios, and I/O modules as specified in Section 01610.
Components must be protected against dust, humidity, and temperature extremes prior to installation. All surplus material and demolished panels shall be disposed of or salvaged as directed by the OWNER.
1.05 HURRICANE AND INCLEMENT WEATHER PREPAREDNESS PLAN
A. Within fifteen (15) days of the date of Notice to Proceed, the CONTRACTOR shall submit to the OWNER a Hurricane and Severe Weather Preparedness Plan. The Plan should outline the necessary measures which the CONTRACTOR proposes to perform at no additional cost to the OWNER to secure open enclosures, protect exposed control wiring, and ensure telemetry stability in case of a severe storm warning. Such measures shall be in accordance with local and state requirements.
B. In the event of inclement weather, CONTRACTOR will, and will cause Subcontractors to protect carefully the electrical enclosures, field instruments, and sensitive hardware against damage or moisture injury. If any electronic portion of Work shall have been damaged by reason of failure to protect the panels, such hardware shall be replaced with new equipment at the expense of the CONTRACTOR.
1.06 WARRANTIES
A. Unless specified otherwise in the Contract Documents, all TELEMETRY CABINETS hardware, power supplies, and internal assemblies supplied under these Specifications shall be warrantied by the CONTRACTOR and the component MANUFACTURERS for
Removal & Replacement of Telemetry Cabinets for 01100 -3 Existing SCADA Systems – Phased Projects a period of one (1) year. The warranty period shall commence on the date of substantial completion of the entire project by the OWNER. Warranties for installed individual panels will not be accepted in piecemeal unless authorized in writing.
B. The system shall be warranted to be free from defects in workmanship, assembly, logic configuration, and materials. If any part of the control panel should fail during the warranty period, it shall be replaced and re-tested at no expense to the
OWNER.
C. The hardware MANUFACTURER’s warranty period shall run concurrently with the CONTRACTOR’s warranty or guarantee period.
No exception to this provision shall be allowed.
1.07 CONSTRUCTION CONDITIONS AND SCADA INFRASTRUCTURE
A. The CONTRACTOR shall strictly adhere to the specific requirements of the governmental unit(s), electrical codes (NEC), or safety agency(ies) having jurisdiction over the work.
Wherever there is a difference in the requirements of a jurisdictional body, the National Electrical Code, and these Specifications, the more stringent shall apply.
B. The CONTRACTOR shall be responsible for having determined to his satisfaction, prior to the submission of his bid, the nature and location of the work, the existing configuration of the control loops, the type of communication networks (fiber, radio, cellular), the status of existing field wiring, and the availability of backup power sources needed during the prosecution of the work. Any claims for extras based on field circuit discrepancies, unmapped I/O points, or network routing challenges will not be allowed.
1.08 PUBLIC NUISANCE AND NOISE (NOT USED)
1.09 SUSPENSION OF WORK DUE TO WEATHER AND ELECTRICAL HAZARDS
A. During inclement weather or high-lightning risks, all outdoor work on instrumentation loops, antenna towers, and unsealed enclosures which might be damaged or rendered unsafe shall be suspended. During suspension, panels shall be sealed weather-tight.
1.10 PERMITS Not Used
1.11 PUMPING AND RUNTIME DEACTIVATION COORDINATION
A. The CONTRACTOR shall coordinate all panel shutdowns with the facility operations group to ensure that wet well levels, leachate levels, or gas pressures are lowered prior to taking any corresponding TELEMETRY CABINETS offline.
Removal & Replacement of Telemetry Cabinets for 01100 -4 Existing SCADA Systems – Phased Projects
B. If temporary backup monitoring or emergency local manual pump tracking is needed while a TELEMETRY CABINET is disconnected, the CONTRACTOR shall deploy temporary hardwired float controls or localized controllers to prevent pump station overflows or flotation of any structures.
1.12 DAILY REPORTS
A. The CONTRACTOR shall submit daily reports of system integration and installation activities, including non-work days. The report shall include:
1. Manpower, number of technicians and electricians by craft;
2. Diagnostic and testing equipment on the project site;
3. Major equipment deliveries (TELEMETRY CABINETS, sub-panels, radios, etc.);
4. Progress tracking of specific I/O loop checks and SCADA mapping;
5. New communication, hardware, or wiring challenges encountered; and
6. Other pertinent technical info.
B. Reports shall be submitted to the OWNER within two (2) days of the respective report date, signed by the CONTRACTOR’s Project Manager.
1.13 CLEAN-UP AND DUST CONTROL IN ELECTRICAL ROOMS
A. At all times during the installation of TELEMETRY CABINETS, the CONTRACTOR shall maintain pristine cleanliness within electrical buildings and control rooms. Vacuuming (HEPA) rather than sweeping shall be used to control drywall dust, wire trimmings, and metal shavings resulting from conduit entries.
1.14 COORDINATION OF SCADA AND INTEGRATION WORK
A. Because of the critical nature of this utility infrastructure, the CONTRACTOR should expect that other network, electrical, or process expansions may occur concurrently. Landfill and station operations shall not be interrupted without authorized scheduling. The CONTRACTOR will be required to cooperate fully so as to eliminate network scheduling conflicts.
B. The CONTRACTOR shall afford the OWNER’s internal SCADA team or separate software integrators reasonable opportunity for the introduction of code modifications, PLC logic staging, and master station communications testing.
Removal & Replacement of Telemetry Cabinets for 01100 -5 Existing SCADA Systems – Phased Projects
C. If the execution of the new TELEMETRY CABINETS cutover depends upon network pathways or hardware provided by the OWNER or a separate contractor, the CONTRACTOR shall, prior to proceeding, inspect and promptly report to the OWNER in writing any apparent communication defects or missing interlocks that render the subsystem unsuitable for final loop verification.
1.15 FIVE-YEAR SPECIAL PERFORMANCE GUARANTEE
A. All structural panel integration, terminal blocks, wiring organization, and power distributions shall be guaranteed by the CONTRACTOR for a period of five (5) years from and after the date of substantial completion of the work by the OWNER.
B. If within this guarantee period, electrical faults, wire termination failures, or hardware integration errors occur which, in the opinion of the OWNER, result from inferior or defective workmanship, the CONTRACTOR shall, promptly upon receipt of notice, correct the defects and make good any associated control components disturbed in fulfilling the guarantee at no expense to the OWNER.
1.16 SLEEVES, CONDUITS, AND WALL OPENINGS
A. The CONTRACTOR shall provide all new conduit entries, core drilling through control room walls, and sealing sleeves required to route instrument cables to the new TELEMETRY CABINETS panels. All penetrations must be completely sealed with fire-rated and gas-tight materials to prevent landfill gases or moisture from entering the electrical enclosures. No structural concrete or steel cutting is permitted without written approval.
1.17 PROTECTION AGAINST ELECTRICAL SURGES AND LIGHTNING DAMAGE
A. The CONTRACTOR shall hold himself responsible for protecting the new TELEMETRY CABINETS hardware from transient voltage surges and lightning during the installation and testing phase. Panel grounding systems must be verified, connected, and tested prior to landing any critical I/O or power loops.
1.18 ELECTRICAL EMERGENCIES AND SYSTEM OUTAGES
A. The CONTRACTOR shall maintain a responsive 24/7 emergency contact number where a qualified control systems technician or industrial electrician can be reached. The CONTRACTOR is obligated to act immediately to prevent threatened process overflows, equipment damage, or personal safety risks caused by TELEMETRY CABINETS malfunctions or installation errors without waiting for special instructions.
B. If a critical TELEMETRY CABINETS error or telemetry drop occurs after working hours due to recent cutover activities, the OWNER
Removal & Replacement of Telemetry Cabinets for 01100 -6 Existing SCADA Systems – Phased Projects will notify the CONTRACTOR. The CONTRACTOR is expected to dispatch qualified personnel to institute corrective software or hardware measures within two (2) hours. If the CONTRACTOR cannot be reached or fails to arrive within two (2) hours, the OWNER reserves the right to hire emergency integrators or deploy manual operators, and all associated costs will be deducted from the contract value.
1.19 ITEMS SPECIFIED ON DRAWINGS
A. Specific TELEMETRY CABINETS interior panel layouts, power distributions, network loop topologies, and terminal block maps may be detailed on the electrical/instrumentation Drawings and not explicitly itemized in the text of the specifications. Such items shall be fully provided by the CONTRACTOR in accordance with the Drawings.
1.20 SITE RESTORATION (NOT USED)
1.21 CLAIMS FOR CONTROL SYSTEM OR FACILITY DAMAGE
A. In the event of any direct or indirect damage to existing field instruments, networking switches, fiber lines, or utility assets caused by the CONTRACTOR’s electrical work or negligence, the CONTRACTOR shall at his own expense promptly repair, recalibrate, or replace the asset to a condition equal to or better than that existing before the damage occurred.
1.22 LEACHATE AND WASTEWATER SPILL PREVENTION DURING CUTOVER
A. Within fifteen (15) days of the date of Notice to Proceed, the CONTRACTOR shall submit a Process Contingency and Spill Prevention Plan. The plan must outline how the CONTRACTOR will ensure that wastewater/leachate pump stations do not overflow while their respective TELEMETRY CABINETS control panels are unpowered, disconnected, or undergoing loop verification.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION (NOT USED)
END OF SECTION