15-Section 01153 - Change Order Procedures - 08182026.pdf

PDF 148 KB Posted

Attached to
Removal and Replacement of Telemetry Cabinets for Existing SCADA System - Phased Projects
Solicitation number
ITB No.: 27-402/DL
Issued by
Palm Beach County, Florida

About this file

This is a Change Order Procedures specification document for ITB No. 27-402/DL, a phased project involving the removal and replacement of telemetry cabinets for an existing SCADA system in Florida. The project requires a licensed Florida General or Electrical Contractor to replace thirty-three (33) telemetry cabinets and provide all necessary labor, materials, equipment, and incidentals. The initial contract term is three (3) years with an option to renew for an additional one (1) year at the Authority's sole discretion. Bid security must be submitted in the form of a surety company bid bond or cashier's check in an amount not less than five percent (5%) of the total bid amount. All questions and clarifications must be submitted through Bonfire by dates specified in the bid documents, and bidders must submit responses electronically through Bonfire and confirm receipt by the specified deadline.

The specification document outlines comprehensive change order procedures governing how modifications to the contract scope, cost, and schedule will be handled throughout project execution. It establishes three types of change mechanisms: Change Orders (formal modifications to contract sum and time), Work Change Directives (authorizations to proceed pending final pricing), and Field Orders (minor clarifications without cost or time adjustments). The contractor must designate authorized personnel to accept changes and maintain detailed time-and-material documentation. All proposals for changes must be supported by substantiating data including labor, equipment, products with recommended sources and unit costs, taxes, insurance, bonds, overhead, profit, and justification for schedule impacts. The owner retains authority to prepare and execute all change orders and directives, with both parties required to sign for authorization and agreement.

View the file

Other files

File Type Posted
17-Section 01152 - Applications for Payment - 08182026.pdf PDF
32-ITB 27-402 - Section 00300 - Authority to Execute Contract.pdf PDF
16-Section 01710 - Cleaning - 08182026.pdf PDF
27-Section 160519 - Low Voltage Electrical Power Conductors and Cables.pdf PDF
21-Section 01610 - Material and Equipment - 08182026.pdf PDF
24-Section 160533 - Raceways and Boxes for Electrical Systems - 08182026.pdf PDF
22-Section 160501 - Basic Electrical Materials and Methods - 08182026.pdf PDF
2-ITB 27-402 - Section 00300 - Bid Bond.pdf PDF
3-ITB 27-402 - Section 00300 - Bid Form.pdf PDF
14-Section 01700 - Contract Closeout - 08182026.pdf PDF
19-Section 01300 - Submittals - 08182026.pdf PDF
26-Section 160502 - Miscellaneous Equipment - 08182026.pdf PDF
28-Section 160526 - Grounding and Bonding for Electrical Systems - 08182026.pdf PDF
18-Section 01200 - Project Meetings - 08182026.pdf PDF
8-Section 01014 - Construction Sequence - 08182026.pdf PDF
31-RTU-Locations Page03.jpg JPG image
13-Section 01310 - Progress Schedules - 08182026.pdf PDF
7-Section 01041 - Project Coordination - 09292026.pdf PDF
4-ITB 27-402 - Section 00300 - Project Experience Forms 1-3.pdf PDF
1-ITB 27-402 - Removal Replacement of Telemetry Cabinets.pdf PDF
29-RTU-Locations Page01REV(1).jpg JPG image
5-ITB 27-402 - Section 00300 - Trench Safety Act.pdf PDF
10-Section 01025 - Measurement and Payment - 09082026.pdf PDF
9-Section 01100 - Special Project Procedures - 09292026.pdf PDF
12-Section 01102 - Safety Health and Emergency Response Requirements - 08182026.pdf PDF
25-Section 162914 - Telemetry Cabinets - 090826docx.pdf PDF
6-Section 01005 - General Requirements - 09292026.pdf PDF
30-RTU-Locations Page02.jpg JPG image
23-Section 01740 - Warranties and Bonds - 08182026.pdf PDF
11-Section 01010 - Summary of Work - 08182026.pdf PDF
20-Section 01370 - Schedule of Values - 08182026.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITB No.: 27-402/DL Removal & Replacement of Telemetry Cabinets for 01153 -1 Existing SCADA Systems – Phased Projects

SECTION 01153

CHANGE ORDER PROCEDURES

PART 1 – GENERAL

1.01 REQUIREMENTS INCLUDED:

A. The CONTRACTOR shall promptly implement change order procedures.

1. Provide full written data required to evaluate changes.

2. Maintain detailed records of work done on a time-and-material/force account basis.

3. Provide full documentation to OWNER on request.

B. Designate in writing the member of CONTRACTOR’s organization:

1. Who is authorized to accept changes in the work.

2. Who is responsible for informing others in the CONTRACTOR’s employ of the authorization of changes in the work.

C. OWNER will designate in writing the person who is authorized to execute Change Orders and Work Change Directives (WCD).

1.02 RELATED REQUIREMENTS:

A. The Contract Documents include, but are not limited to, the following related sections:

1. Section 01152: Applications for Payment

2. Section 01310: Progress Schedules

3. Section 01370: Schedule of Values

1.03 DEFINITIONS:

A. Change Order: See General Conditions

B. Work Change Directive: See General Conditions

C. Field Order: A written order to the CONTRACTOR, signed by the

OWNER and the CONTRACTOR, which is issued to interpret/clarify the Contract Documents, order minor changes in the work and/or memorialize trade-off agreements. The work described by a Field Order is to be accomplished without change to the Contract Sum, Contract Time, and/or claims for other costs.

1.04 PRELIMINARY PROCEDURES:

A. OWNER may initiate changes by submitting a Request for Proposal (RFP) to CONTRACTOR. Request will include:

1. Detailed description of the Change, Products, and location of the change in the Project.

2. Supplementary or revised Drawings and Specifications.

Removal & Replacement of Telemetry Cabinets for 01153 -2 Existing SCADA Systems – Phased Projects

3. The projected time span for making the change, and a specific statement as to whether overtime work is, or is not, authorized.

4. A specific period of time during which the requested price will be considered valid.

5. Such request is for information only, and is not an instruction of execute the changes, nor to stop work in progress.

B. CONTRACTOR may initiate changes by submitting a written notice to OWNER containing:

1. Description of the proposed changes.

2. Statement of the reason for making the changes.

3. Statement of the effect on the Contract Sum and the Contract

Time.

4. Statement of the effect on the work of separate contractors.

5. Documentation supporting any change in Contract Sum or

Contract Time, as appropriate.

1.05 WORK CHANGE DIRECTIVE AUTHORIZATION:

A. In lieu of a Request for Proposal (RFP), OWNER may issue a Work Change Directive Authorization of CONTRACTOR to proceed with a change for subsequent inclusion in a Change Order.

B. Authorization will describe changes in the Work, both additions and deletions, with attachments of revised Contract Documents to define details of the change and will designate the method of determining any change in the Contract Sum and any change in Contract Time.

C. OWNER will sign and date the Work Change Directive Authorization as authorization for the CONTRACTOR to proceed with the changes.

D. CONTRACTOR may sign and date the Work Change Directive

Authorization to indicate agreement with the terms therein.

1.06 DOCUMENTATION OF PROPOSALS AND CLAIMS:

A. Support each quotation for a lump-sum proposal, and for each unit price which has not previously been established, with sufficient substantiating data to allow OWNER to evaluate the quotation.

B. On request, provide additional data to support time and cost computations.

1. Labor required.

2. Equipment required.

3. Products required.

a. Recommended source of purchase and unit cost.

b. Quantities required.

4. Taxes, insurance and bonds.

Removal & Replacement of Telemetry Cabinets for 01153 -3 Existing SCADA Systems – Phased Projects

5. Credit for work deleted from Contract, similarly documented.

6. Overhead and profit.

7. Justification for any change in Contract Time.

C. Support each claim for additional costs, and for work done on a time-and-material/force account basis, with documentation as required for a lump sum proposal, plus additional information.

1. Name of OWNER’s authorized agent who ordered the work, and the date of the order.

2. Dates and times work was performed, and by whom.

3. Time record, summary of hours worked, and hourly rates paid.

4. Receipts and invoices for:

a. Equipment used, listing dates and times of use.

b. Products used, listing of quantities.

c. Subcontracts

1.07 PREPARATION OF CHANGE ORDER AND FIELD ORDERS AND WORK CHANGE

DIRECTIVE (WCD):

A. OWNER will prepare each Change Order, Field Order and WCD.

B. Change Order will describe changes in the Work, both additions and deletions, with attachments of revised Contract Documents to define details of the change.

C. Change Order will provide an accounting of the adjustment in the

Contract Sum and in the Contract Time.

1.08 LUMP-SUM/FIXED PRICE CHANGE ORDER:

A. Content of Change Orders will be based on, either:

1. OWNER’s Proposal Request and CONTRACTOR’s responsive Proposal as mutually agreed between OWNER and CONTRACTOR.

2. CONTRACTOR’s Proposal for a change, as recommended by OWNER.

B. OWNER will sign and date the Change Order as authorization for the CONTRACTOR to proceed with the changes.

C. CONTRACTOR will sign and date the Change Order to indicate agreement with the terms therein.

1.09 UNIT PRICE CHANGE ORDER:

A. Content of Change Orders will be based on, either:

1. OWNER’s definition of the scope of the required changes.

2. CONTRACTOR’s Proposal for a change, as recommended by OWNER.

3. Survey of complete work.

B. The amounts of the unit prices to be:

1. Those stated in the Agreement.

2. Those mutually agreed upon between OWNER and CONTRACTOR.

Removal & Replacement of Telemetry Cabinets for 01153 -4 Existing SCADA Systems – Phased Projects

C. When quantities of each of the items affected by the Change Order can be determined prior to start of the work:

1. OWNER will sign and date the Change Order as authorization for CONTRACTOR to proceed with the changes.

2. CONTRACTOR will sign and date the Change Order to indicate agreement with the terms therein.

D. When quantities of the items cannot be determined prior to start of the work:

1. The OWNER will issue a work change directive directing

CONTRACTOR to proceed with the change on the basis of unit prices and will cite the applicable unit prices.

2. At completion of the change, OWNER will determine the cost of such work based on the unit prices and quantities used.

a. CONTRACTOR shall submit documentation to establish the number of units of each item and any claims for a change in Contract Time.

3. OWNER will sign and date the Change Order to establish the change in Contract Sum and in Contract Time.

4. OWNER and CONTRACTOR will sign and date the Change Order to indicate their agreement with terms herein.

1.10 TIME AND MATERIAL/FORCE ACCOUNT CHANGE ORDER/WORK CHANGE DIRECTIVE

AUTHORIZATION:

A. The OWNER will issue a Work Change Directive Authorization directing CONTRACTOR to proceed with the changes.

B. At completion of the change, CONTRACTOR shall submit itemized accounting and supporting data as provided in the Article “Documentation of Proposals and Claims” of this Section.

C. OWNER will determine the allowable cost of such work, as provided in General Conditions and Supplementary Conditions.

D. OWNER will sign and date the Change Order to establish the change in Contract sum and in Contract Time.

E. OWNER and CONTRACTOR will sign and date the Change Order to indicate their agreement therewith.

1.11 CORRELATION WITH CONTRACTOR’S SUBMITTALS:

A. Periodically revise Schedule of Values and Application Payment forms to record each change as a separate item of Work, and to record the adjusted Contract Sum.

B. Periodically revise the manufacturing Schedule to reflect each change in Contract Time.

1. Revise sub-schedules to show changes for other items of work affected by the changes.

Removal & Replacement of Telemetry Cabinets for 01153 -5 Existing SCADA Systems – Phased Projects

C. Upon completion of work under a Change Order, enter pertinent changes in Project Record Documents.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXECUTION (NOT USED)

END OF SECTION

File details come from the government source that posted it. Updated .