14-Section 01700 - Contract Closeout - 08182026.pdf

PDF 116 KB Posted

Attached to
Removal and Replacement of Telemetry Cabinets for Existing SCADA System - Phased Projects
Solicitation number
ITB No.: 27-402/DL
Issued by
Palm Beach County, Florida

About this file

This is a Contract Closeout section (Section 01700) for Bid No. 26-407/DL, a phased project in Florida for the removal and replacement of thirty-three (33) telemetry cabinets for an existing SCADA (Supervisory, Control, And Data Acquisition) system. The contract will be awarded to a licensed Florida General or Electrical Contractor and involves a three-year initial period with an option for one additional year renewal at the Authority's discretion. The work requires the contractor to provide all labor, materials, equipment, and incidentals necessary for cabinet replacement and system integration. The contract closeout procedures specify requirements for Substantial Completion, including submission of Factory Acceptance Testing (FAT) records, preliminary Operation and Maintenance (O&M) manuals, As-Built electrical schematics, and delivery of all telemetry cabinets to the designated site. Final Completion requires submission of a 100 percent completion Application for Payment, Engineer's inspection punch list with sign-offs, final Project Record Documents, finalized O&M manuals, spare parts and special tools, and manufacturer warranties with certificates of compliance and registered software licenses.

The file establishes detailed requirements for project record documentation, including As-Built drawings marked with red erasable pencil and converted to AutoCAD .dwg and PDF formats, and comprehensive O&M manuals in heavy-duty three-ring binders with electronic PDF equivalents. Spare parts and special tools must be delivered in original manufacturer packaging, including a minimum of five percent (or two units minimum) of each I/O module type, ten percent of each fuse amperage rating, two spare interposing relays with bases, and one spare 24 VDC power supply module. The manufacturer provides a one-year warranty from Substantial Completion covering defects in materials, wiring, assembly, and workmanship, with all software and firmware licenses registered to the Owner. The Engineer will conduct a maximum of two final closeout inspections; costs for additional inspections due to uncorrected deficiencies will be deducted from the contractor's final contract payment.

View the file

Other files

File Type Posted
15-Section 01153 - Change Order Procedures - 08182026.pdf PDF
17-Section 01152 - Applications for Payment - 08182026.pdf PDF
32-ITB 27-402 - Section 00300 - Authority to Execute Contract.pdf PDF
16-Section 01710 - Cleaning - 08182026.pdf PDF
27-Section 160519 - Low Voltage Electrical Power Conductors and Cables.pdf PDF
21-Section 01610 - Material and Equipment - 08182026.pdf PDF
24-Section 160533 - Raceways and Boxes for Electrical Systems - 08182026.pdf PDF
22-Section 160501 - Basic Electrical Materials and Methods - 08182026.pdf PDF
2-ITB 27-402 - Section 00300 - Bid Bond.pdf PDF
3-ITB 27-402 - Section 00300 - Bid Form.pdf PDF
19-Section 01300 - Submittals - 08182026.pdf PDF
26-Section 160502 - Miscellaneous Equipment - 08182026.pdf PDF
28-Section 160526 - Grounding and Bonding for Electrical Systems - 08182026.pdf PDF
18-Section 01200 - Project Meetings - 08182026.pdf PDF
8-Section 01014 - Construction Sequence - 08182026.pdf PDF
31-RTU-Locations Page03.jpg JPG image
13-Section 01310 - Progress Schedules - 08182026.pdf PDF
7-Section 01041 - Project Coordination - 09292026.pdf PDF
4-ITB 27-402 - Section 00300 - Project Experience Forms 1-3.pdf PDF
1-ITB 27-402 - Removal Replacement of Telemetry Cabinets.pdf PDF
29-RTU-Locations Page01REV(1).jpg JPG image
5-ITB 27-402 - Section 00300 - Trench Safety Act.pdf PDF
10-Section 01025 - Measurement and Payment - 09082026.pdf PDF
9-Section 01100 - Special Project Procedures - 09292026.pdf PDF
12-Section 01102 - Safety Health and Emergency Response Requirements - 08182026.pdf PDF
25-Section 162914 - Telemetry Cabinets - 090826docx.pdf PDF
6-Section 01005 - General Requirements - 09292026.pdf PDF
30-RTU-Locations Page02.jpg JPG image
23-Section 01740 - Warranties and Bonds - 08182026.pdf PDF
11-Section 01010 - Summary of Work - 08182026.pdf PDF
20-Section 01370 - Schedule of Values - 08182026.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid No.: 26-407/DL 01700 - 1 Removal & Replacement of Telemetry Cabinets for Existing SCADA Systems – Phased Projects

SECTION 01700

CONTRACT CLOSEOUT

PART 1 – GENERAL

1.1 SUMMARY

A. This Section specifies administrative and procedural requirements for the contract closeout of manufactured Telemetry Cabinets, including but not limited to:

1. Substantial Completion and Final Inspection procedures.

2. Submittal of Factory Acceptance Testing (FAT) records and certifications.

3. Project Record Documents (As-Built drawings and electrical schematics).

4. Operation and Maintenance (O&M) manuals.

5. Warranties, manufacturer certificates, and software licensing.

6. Spare parts and maintenance materials inventory turnover.

1.2 SUBSTANTIAL COMPLETION

A. Before requesting inspection for certification of Substantial Completion, the Manufacturer/Contractor shall complete the following and list known exceptions in the request:

1. Submit certified Factory Acceptance Testing (FAT) reports verifying that all Telemetry Cabinets have been built, wired, powered, and loop-tested in accordance with contract specifications.

2. Deliver preliminary draft copy of Operation and Maintenance (O&M) Manuals for Engineer review.

3. Submit provisional As-Built Electrical Schematics showing any point-to-point wiring modifications made during shop assembly and testing.

4. Deliver all primary Telemetry Cabinets hardware to the designated delivery site, matching approved shipping and packaging protocols.

1.3 FINAL COMPLETION & FINAL PAYMENT

A. Before requesting final inspection for certification of Final Completion and release of final payment/retainage, complete the following:

1. Submit a final Application for Payment showing 100% completion of all physical deliverables.

2. Submit a copy of the Engineer’s Substantial Completion inspection punch list, with each item signed off, dated, and certified as complete or otherwise resolved.

Bid No.: 26-407/DL 01700 - 2

Existing SCADA Systems – Phased Projects

3. Deliver final, approved Project Record Documents (incorporating all redlines from testing and field verification).

4. Deliver final O&M Manuals, specialized spare parts, and special tools as specified.

5. Provide signed manufacturer warranties, certificates of compliance, and registered firmware/software licenses for the Telemetry Cabinets.

PART 2 – PRODUCTS

2.1 PROJECT RECORD DOCUMENTS (AS-BUILTS)

A. Record Drawings: Maintain one clean, undamaged set of contract drawings, approved shop drawings, and manufacturer panel layouts at the manufacturing facility.

1. Mark up drawings using a red erasable pencil to record actual deviations from the original design.

2. Give precise attention to internal control panel wiring, terminal block assignments, PLC/RTU I/O card mapping, power distribution circuitry, and communication cable routing.

3. Provide a cross-reference on corresponding logic diagrams and schematic schedules where terminal points have been altered.

4. Convert redline markups into final electronic format (AutoCAD .dwg and high-resolution compiled PDF) and deliver on physical media or secure project portal.

2.2 OPERATION AND MAINTENANCE (O&M) MANUALS

A. Organization: Assemble O&M data into matching, heavy-duty, 3-ring, vinyl-covered binders. Clearly label the front and spine of each binder with the project name, panel designations, and "Operation and Maintenance Manual." Provide an electronic PDF equivalent featuring a fully interactive, bookmarked digital table of contents.

B. Content Requirements: Manuals must include:

1. System Description: Functional narrative of the Telemetry Cabinets operation, power distribution networks, ups system (if applicable), and communication topology (e.g., Modbus, DNP3, Ethernet/IP).

2. Bill of Materials (BOM): Comprehensive parts list identifying the manufacturer, exact model number, electrical rating, and quantities for every component (RTU controllers, I/O modules, power supplies, circuit breakers, relays, surge protect devices, and terminal blocks).

3. Manufacturer Literature: Original technical data sheets, installation sheets, and calibration guides for all sub-components.

Bid No.: 26-407/DL 01700 - 3

Existing SCADA Systems – Phased Projects

4. Configuration Files: Prints and digital files of RTU configuration parameters, IP address allocations, and I/O point mapping tables.

2.3 WARRANTIES AND LICENSING

A. Submittal: Compile and bind all product warranties and software/firmware licenses in a dedicated section of the final documentation.

B. Warranty Terms: Provide manufacturer's standard warranty backed by the Contractor’s comprehensive warranty, guaranteeing panels against defects in materials, internal wiring, assembly, and workmanship for a period of one (1) year from the date of Substantial Completion.

C. Software/Firmware Ownership: Deliver all RTU programming software licenses, configuration utility access keys, and hardware firmware certificates registered directly to the Owner.

PART 3 – EXECUTION

3.1 FINAL CLEANING AND SHOP TOUCH-UP

A. Prior to final packaging and crate shipment, the panels must undergo thorough detailing:

1. Internal Cleaning: Vacuum out all dust, wire clippings, insulation shavings, and debris from the panel interior, wire ducts, and DIN rails.

2. External Cleaning: Wipe down interior components and exterior enclosure surfaces to eliminate smudges, fingerprints, oils, and grease marks.

3. Finish Touch-Up: Inspect painted or powder-coated surfaces for scratches, chips, or abrasions. Repair marred finishes using matching, original manufacturer-supplied touch-up paint to eliminate visible defects.

3.2 SPARE PARTS AND SPECIAL TOOLS TURNOVER

A. Inventory Delivery: Deliver specified spare parts and tools in original, unopened manufacturer packaging. Each item must be clearly tagged with its associated panel name, functional description, part number, and matching contract specification reference.

B. Minimum Spare Parts Package:

1. Five percent (5%) or a minimum of two (2) of each type of I/O module (Discrete Input, Discrete Output, Analog Input, Analog Output).

2. Ten percent (10%) spare fuses of each amperage rating utilized in the panels.

3. Two (2) spare interposing relays and matching bases of each type used.

Bid No.: 26-407/DL 01700 - 4

Existing SCADA Systems – Phased Projects

4. One (1) spare power supply module ($24\text{ VDC}$).

C. Transmittal Receipt: Hand over materials to the Owner’s authorized warehouse or plant personnel and secure a signed, itemized inventory transmittal receipt to be submitted with the final closeout package.

3.3 CLOSEOUT INSPECTIONS

A. Initial Deficiency Review: The Engineer will conduct an initial closeout inspection to review panel construction against shop drawings and check for structural or wiring discrepancies. A punch list of deficiencies will be provided to the Contractor.

B. Reinspection Protocol: The Engineer will conduct a maximum of two (2) final inspections: one to identify punch list elements, and a second to verify that corrections have been fully completed. Should subsequent inspections be required due to uncorrected deficiencies, the cost of the Engineer’s additional time and expenses will be deducted directly from the Contractor’s final contract progress payment.

END OF SECTION

File details come from the government source that posted it. Updated .