23-Section 01740 - Warranties and Bonds - 08182026.pdf
PDF 136 KB Posted
- Attached to
- Removal and Replacement of Telemetry Cabinets for Existing SCADA System - Phased Projects
- Solicitation number
- ITB No.: 27-402/DL
- Issued by
- Palm Beach County, Florida
About this file
Summary
This is a Warranties and Bonds specification section for ITB No. 27-402/DL, addressing the removal and replacement of telemetry cabinets for an existing SCADA system in Florida through a series of phased projects. The contract requires a licensed Florida General or Electrical Contractor to replace thirty-three (33) telemetry cabinets and provide all associated labor, materials, equipment, and incidentals. The initial contract term is three (3) years with an option for renewal for an additional one (1) year at the Authority's discretion. The specification establishes comprehensive warranty and bonding requirements including manufacturer's standard product warranties, special project-specific warranties covering control panel fabrication and integrated systems, and Performance, Payment, and Maintenance/Warranty Bonds equal to 100% of the panel fabrication contract value. All warranty and bond documents must be submitted in a bound 8.5" x 11" format with a tabbed index within ten (10) days following successful Factory Acceptance Testing but prior to final shipment and payment application.
The specification mandates a two-year systemic integration warranty from the date of Substantial Completion covering the entire assembled telemetry cabinets, with all critical electronic components carrying full manufacturer's warranties registered to the Owner. The Contractor must provide warranty extensions if storage or testing consumes any portion of the manufacturer's standard warranty period. Warranty claim response protocols require acknowledgment within twenty-four (24) hours of notification and qualified technician availability within forty-eight (48) hours for critical control system faults. When critical components are replaced during the warranty period, the warranty for that specific item is reinstated for an additional one (1) year from commissioning. Environmental protection during storage at 0°C to 50°C with non-condensing humidity and space heater energization for outdoor-rated enclosures are required to maintain hardware warranty validity. Bid security in the form of a surety bond or cashier's check equal to at least five percent (5%) of the total bid amount is required, with electronic submission through Bonfire by the specified date and time.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ITB No.: 27-402/DL Removal & Replacement of Telemetry Cabinets for 01740 -1 Existing SCADA Systems – Phased Projects
SECTION 01740
WARRANTIES AND BONDS
PART 1 - GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
B. Related Sections include but are not limited to:
1. Section 01300 – Submittals (Shop Drawings, Product Data, and Samples).
2. Section 160501 – Basic Electrical Materials and Methods.
3. Section 162914 – Telemetry Cabinets.
1.02 SUMMARY
A. This Section includes administrative and procedural requirements for warranties and bonds required for the manufacture, assembly, testing, and delivery of Telemetry Cabinets, including:
1. Manufacturer’s standard product warranties.
2. Special project-specific warranties covering control panel fabrication, internal components, wiring, and integration.
3. Performance, Payment, and Maintenance/Warranty Bonds.
1.03 DEFINITIONS
A. Standard Product Warranty: Preprinted written warranty published by individual component manufacturers (e.g., PLCs, power supplies, terminal blocks, network switches) for its standard commercial products.
B. Special Panel Warranty: A written warranty required by the Contract Documents to extend the duration of coverage or provide explicit performance remedies specifically for the assembled Telemetry Cabinets as an integrated system.
C. Correction Period: The period after Substantial Completion during which the Contractor must remedy, at no cost to the Owner, any defects in materials, assembly, or factory workmanship.
1.04 SUBMITTAL REQUIREMENTS
A. Form of Submittals:
1. Bind warranty and bond documents in an 8.5" x 11" format within a heavy-duty, 3-ring binder with a cleanable plastic cover.
2. Provide a clear label on the cover and spine titled "WARRANTIES AND BONDS – Telemetry Cabinet ", indicating the Project Name, Contract Number, and the Contractor/Integrator's corporate contact details.
Removal & Replacement of Telemetry Cabinets for 01740 -2 Existing SCADA Systems – Phased Projects
3. Organize with tabbed index sheets keyed to a Table of Contents matching the Project Manual's section sequence.
B. Content Profiles: Provide a dedicated contact registry sheet for each panel subcomponent (e.g., PLC processor, I/O modules, surge suppressors, radio/modems, UPS systems) listing:
1. Component manufacturer name, physical address, and technical support hotline.
2. Specific model numbers, hardware revisions, and serial numbers.
3. Warranty commencement dates and duration.
4. Step-by-step procedures to follow in the event of hardware failure.
C. Time of Submittal:
1. Submit draft copies of all required warranties and bonds to the Engineer for review alongside the initial Telemetry Cabinets shop drawings.
2. Submit finalized, executed, and notarized original documents within ten (10) days following successful Factory Acceptance Testing (FAT), but prior to final shipment to the project site or application for final payment.
PART 2 - PRODUCTS
2.01 PERFORMANCE AND MAINTENANCE BONDS
A. Performance and Payment Bonds: The Contractor shall execute and maintain Performance and Payment Bonds in an amount equal to 100% of the panel fabrication contract value, ensuring faithful execution of the manufacturing schedule and system delivery.
B. Maintenance / Warranty Bond:
1. Provide a Maintenance Bond securing the correction of any component defects, firmware issues, or assembly failures for the entirety of the specified warranty period.
2. The bond shall be issued by a surety company authorized to do business in the state where the project is located and acceptable to the Owner.
2.02 WARRANTY OBLIGATIONS & TIMESCALES
A. Systemic Integration Warranty: The Panel Fabricator/Contractor shall warrant the entire assembled Telemetry Cabinets including enclosure, internal wiring, thermal management, power distribution, and terminal terminations—to be free from defects in materials and craftsmanship for a period of two (2) years from the date of Substantial Completion.
B. Component-Level Warranties: 1. Ensure all critical electronic components (e.g., Programable Logic Controllers, Managed Network
Removal & Replacement of Telemetry Cabinets for 01740 -3 Existing SCADA Systems – Phased Projects
Switches, and Power Supplies) carry their full manufacturer's warranty directly registered to the Owner.
1. If storage or extended factory testing consumes any portion of a manufacturer's standard warranty, the Contractor shall purchase warranty extensions to ensure the Owner receives the full benefit of the term starting at the project's formal handover.
PART 3 - EXECUTION
3.01 PRE-CONSTRUCTION AND STORAGE PROTECTION
A. If manufactured Telemetry Cabinets are stored at the factory, fabricator's facility, or job site prior to field deployment, they must be housed in a climate-controlled environment conforming strictly to the environmental tolerances of the internal electronic components (typically 0°C to 50°C, non-condensing humidity).
B. Space heaters installed within outdoor-rated enclosures must be energized immediately upon field placement to prevent condensation from invalidating the hardware warranties.
3.02 WARRANTY RESTATEMENTS & FIELD REMEDIES
A. Related Damage Coverage: In correcting a Telemetry Cabinets failure, the Contractor is fully responsible for removing, replacing, or repairing any adjacent work or components that were damaged either by the failure itself or as a necessary consequence of accessing the failed hardware.
B. Warranty Reinstatement: When a critical component (such as a primary CPU or power supply module) fails and is replaced or completely rebuilt during the warranty period, the warranty for that specific item shall be reinstated for an additional one (1) year period starting from the date the replacement item is commissioned and verified online.
C. Response Protocol: The Contractor must acknowledge any warranty claim on the Telemetry Cabinets within twenty-four (24) hours of formal notification and provide a qualified technician or field engineer on-site (or via authenticated secure remote access) within forty-eight (48) hours to diagnose and remediate critical control system faults.
3.03 CERTIFICATION OF COMPLETION
A. The Contractor, Panel Fabricator, and any designated technical co-signers must execute the final warranty documents, certifying that the panel assemblies comply exactly with the approved engineering schematics and functional design specifications before final closeout will be granted.
END OF SECTION