This is a Scope of Work document for Bid No. 26-407/DL prepared by the Solid Waste Authority of Palm Beach County, Florida, detailing the removal and replacement of telemetry cabinets for an existing SCADA (Supervisory, Control, and Data Acquisition) system. The project encompasses the replacement of thirty-three (33) telemetry cabinets through a series of phased projects and requires a licensed Florida General or Electrical Contractor to furnish all labor, materials, equipment, tools, and incidentals. The scope of work includes demolition and safe removal of existing cabinets and associated infrastructure, furnishing and installing new NEMA-rated telemetry cabinets equipped with programmable logic controllers (PLCs), power supplies, surge protection, network switches, and control peripherals, rerouting and terminating existing and new field wiring, and provision of temporary control systems during cutover to ensure continuous operations. Substantial completion requires successful installation and visual inspection of all new cabinets, telemetry connection and communication verification with the central SCADA system, submittal of project record drawings, and completion of all operational items. Final acceptance requires completion of all punch list items, delivery of operations and maintenance manuals, PLC program code files, as-built drawings, and owner approval of final invoicing. The contract has an initial term of three (3) years with an option to renew for an additional one (1) year at the authority's discretion.

Each bid submittal must include bid security in the form of a surety company bid bond or cashier's check in an amount of not less than five percent (5%) of the total bid amount. All questions and clarifications must be submitted through Bonfire by the specified deadline, with the authority responding through written addenda as needed. Bidders must submit responses electronically through Bonfire and confirm receipt to ensure valid submission; responses submitted by other means will not be considered. Materials specifications require NEMA-rated enclosures appropriate for environmental conditions, MTW stranded copper wiring with minimum gauges as specified, and all components must comply with approved component lists in the technical specifications. Installation requirements include secure mounting using stainless steel hardware, proper conduit entry to maintain NEMA ratings with bottom entry preferred for outdoor panels, and proper signal shielding grounded at the panel end. Field testing and commissioning must include point-to-point wiring verification, functional testing of all control logic and sequences, and SCADA telemetry validation to ensure accurate data mapping to the central HMI graphics interface. No Small Business Enterprise (SBE) participation requirement is specified for this solicitation.

View the file

Other files

File Type Posted
15-Section 01153 - Change Order Procedures - 08182026.pdf PDF
17-Section 01152 - Applications for Payment - 08182026.pdf PDF
32-ITB 27-402 - Section 00300 - Authority to Execute Contract.pdf PDF
16-Section 01710 - Cleaning - 08182026.pdf PDF
27-Section 160519 - Low Voltage Electrical Power Conductors and Cables.pdf PDF
21-Section 01610 - Material and Equipment - 08182026.pdf PDF
24-Section 160533 - Raceways and Boxes for Electrical Systems - 08182026.pdf PDF
22-Section 160501 - Basic Electrical Materials and Methods - 08182026.pdf PDF
2-ITB 27-402 - Section 00300 - Bid Bond.pdf PDF
3-ITB 27-402 - Section 00300 - Bid Form.pdf PDF
14-Section 01700 - Contract Closeout - 08182026.pdf PDF
19-Section 01300 - Submittals - 08182026.pdf PDF
26-Section 160502 - Miscellaneous Equipment - 08182026.pdf PDF
28-Section 160526 - Grounding and Bonding for Electrical Systems - 08182026.pdf PDF
18-Section 01200 - Project Meetings - 08182026.pdf PDF
8-Section 01014 - Construction Sequence - 08182026.pdf PDF
31-RTU-Locations Page03.jpg JPG image
13-Section 01310 - Progress Schedules - 08182026.pdf PDF
7-Section 01041 - Project Coordination - 09292026.pdf PDF
4-ITB 27-402 - Section 00300 - Project Experience Forms 1-3.pdf PDF
1-ITB 27-402 - Removal Replacement of Telemetry Cabinets.pdf PDF
29-RTU-Locations Page01REV(1).jpg JPG image
5-ITB 27-402 - Section 00300 - Trench Safety Act.pdf PDF
10-Section 01025 - Measurement and Payment - 09082026.pdf PDF
9-Section 01100 - Special Project Procedures - 09292026.pdf PDF
12-Section 01102 - Safety Health and Emergency Response Requirements - 08182026.pdf PDF
25-Section 162914 - Telemetry Cabinets - 090826docx.pdf PDF
6-Section 01005 - General Requirements - 09292026.pdf PDF
30-RTU-Locations Page02.jpg JPG image
23-Section 01740 - Warranties and Bonds - 08182026.pdf PDF
20-Section 01370 - Schedule of Values - 08182026.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid No.: 26-407/DL 01010 - 1 Removal & Replacement of Telemetry Cabinets for Existing SCADA System – Phased Projects

SECTION 01010

SUMMARY OF WORK

PART 1 – GENERAL

1.01 LOCATION OF WORK

A. All of the work of this Contract is located in the right-of-way or on property owned by Solid Waste Authority of Palm Beach County, Florida, generally located in Central Palm Beach County, Florida.

1.02 SCOPE OF WORK

A. The CONTRACTOR shall furnish all labor, materials, equipment, tools, and incidentals required to replace, integrate, and commission Telemetry Cabinets at the designated locations as shown on the Drawings and specified herein.

B. The work includes, but is not necessarily limited to, the following:

1. Demolition and safe removal of existing Telemetry Cabinets, associated conduits, legacy wiring, and obsolete instrumentation.

2. Furnishing, installing, and anchoring new NEMA-rated Telemetry Cabinets equipped with new Programmable Logic Controllers (PLCs), power supplies, surge protection, network switches, and control peripherals.

3. Rerouting, terminating, and labeling existing and new field wiring (analog, digital, and communication loops) to the new

TELEMETRY CABINETS.

4. Provision of temporary control, telemetry, or bypass systems during the cutover window to ensure continuous monitoring and prevent disruption to critical Authority operations.

1.03 SUBSTANTIAL COMPLETION

A. The following items are required to be completed to achieve Substantial Completion:

1. Successful installation and visual inspection of all new

TELEMETRY CABINETS.

2. Successful telemetry connection and communication verification with the central SCADA system.

3. Submittal of Project Record Drawings.

Bid No.: 26-407/DL 01010 - 2

Existing SCADA System – Phased Projects

4. Completion of all operational items indicated on the Drawings.

1.04 FINAL ACCEPTANCE

A. The following items are required to be completed to achieve Final Acceptance:

1. Completion and OWNER’s approval of all punch list items (including panel labeling, wire management, and site cleanup).

2. Delivery and acceptance of final approved Operations & Maintenance (O&M) manuals, finalized PLC program code files, and as-built drawings.

3. OWNER’s recommendation of CONTRACTOR’s proposal for a final change order, if applicable.

4. OWNER’s recommendation of CONTRACTOR’s request for final payment and OWNER’s acceptance of final invoice.

1.05 WORK SEQUENCE

A. Perform work to ensure completion of the work in the contract time. Completion dates of the various stages shall be in accordance with the approved construction schedule submitted by the CONTRACTOR.

1.06 CONSTRUCTION AREAS

A. CONTRACTOR shall limit his use of the construction areas for work and for storage, to allow for:

1. Work by other contractors.

2. OWNER use.

B. Coordinate use of work site and access to electrical/control rooms with the OWNER.

C. Assume full responsibility for the protection and safekeeping of Products under this Contract, stored on the site.

D. Move any stored Products under CONTRACTOR’s control which interfere with operations of the OWNER or other CONTRACTOR.

E. Obtain and pay for the use of additional storage or work areas needed for operations.

F. CONTRACTOR shall at all times conduct his operations to ensure the least inconvenience to facility operations, utility communications, and the general public.

Bid No.: 26-407/DL 01010 - 3

Existing SCADA System – Phased Projects

1.07 PLANS AND SPECIFICATIONS

A. Specifications

1. The Technical Specifications consists of three (3) parts:

General, Products, and Execution. The General Section contains General Requirements which govern the work. Products and Execution modify and supplement these by detailed requirements of the work and shall always govern whenever there appears to be a conflict.

B. Intent

1. All work called for in the Specifications applicable to this Contract, but not shown on the Plans in their present form, or vice versa, shall be of like effect as if shown or mentioned in both. Work not specified in either the Plans or in the Specifications but involved in carrying out their intent or in the complete and proper execution of the work, is required and shall be performed by the CONTRACTOR as though it were specifically delineated or described.

2. The apparent silence of the Specifications as to any detail, or the apparent omission from them of a detailed description concerning any work to be done and materials to be furnished, shall be regarded as meaning that only the best general industrial automation and electrical practice is to prevail and that only material and workmanship of the best quality is to be used, and interpretation of these Specifications shall be made upon that basis.

3. The inclusion of the General Requirements (or work specified elsewhere) in the General part of the Specifications is only for the convenience of the CONTRACTOR and shall not be interpreted as a complete list of related Specification Sections.

PART 2 – PRODUCTS

2.01 MATERIALS

A. All control panels shall be enclosed in NEMA-rated enclosures suitable for their environmental location (e.g., NEMA 4X stainless steel or non-metallic for corrosive/outdoor environments; NEMA 12 for indoor climate-controlled spaces) as specified in the panel schedules.

B. Internal components, including PLCs, power supplies, terminal blocks, circuit breakers, and surge protection devices (SPDs), shall strictly comply with the approved components list in the Instrumentation and Electrical divisions of the Technical Specifications.

Bid No.: 26-407/DL 01010 - 4

Existing SCADA System – Phased Projects

C. All control wiring shall be MTW stranded copper, minimum 16 AWG for control circuits and 18 AWG for analog signal loops, clearly numbered using heat-shrink or wrap-around printed wire markers at both ends.

2.02 PRODUCTS - GENERAL

A. Assembly and Certification: All new Telemetry Cabinets shall be completely assembled, wired, and tested prior to shipment to the site.

B. Programming and Software: All industrial software, firmware, and logic configuration protocols applied to the PLCs shall match the standard software platform currently utilized by the OWNER to ensure full compatibility.

PART 3 – EXECUTION

3.01 INSTALLATION

A. New TELEMETRY CABINETS shall be mounted securely to walls, floors, or structural framing structures using stainless steel hardware as indicated on the standard mounting details.

B. Conduit entry locations shall maintain the NEMA rating of the enclosure. Bottom entry is preferred for outdoor panels to prevent moisture ingress.

C. All signal shielding shall be properly grounded at the panel end only, unless otherwise specified by the device manufacturer.

3.02 FIELD TESTING AND COMMISSIONING

A. Point-to-Point Verification: The CONTRACTOR shall perform comprehensive point-to-point wiring validation from the field device to the PLC I/O modules.

B. Functional Testing: Conduct complete operational logic testing of all control interlocks, alarms, failures, and automatic sequences.

C. SCADA Telemetry Testing: Validate that all data points, configurations, and alarm tags map accurately to the central SCADA HMI graphics interface.

END OF SECTION