832674621 Site Survey Notes.docx

DOCX document 24 KB Posted

Attached to
DISA Global COLUMBUS FURNITURE Upgrade
Solicitation number
832674621
Issued by

About this file

This is a site survey notes document from a contractor walk-through conducted at the DISA Global Columbus Facility for a furniture system installation and upgrade project. The survey was attended by key personnel including Mike Reid, Steve Hein (J9 Facilities Representative), Bryan Brannam (J9 Safety Representative), a Site Lead, IT Subject Matter Expert, and four contractor teams. The document details critical logistics and design decisions established during the facility inspection, including the plan to terminate electrical and IT cables above the ceiling grid, the establishment of loading dock areas for product delivery and furniture removal, and the decision to upgrade temporary wall egress from one door to two doors to meet emergency egress requirements while removing card entry restrictions as specified by J9 representatives. A pending decision remains regarding whether old cables will be abandoned in place or recovered and disposed of by DG432.

The survey also documented the temporary seating and equipment relocation strategy. Five civilians will be relocated to an internal non-Global J9 space with existing desks and pre-installed cable infrastructure, while contractors will occupy seats within the SCIF. For IT equipment removal, approximately 300 units including monitors, keyboards, mice, KVMs, Thin Clients, SIPR and NIPR computers, and associated cables must be removed, stored, and potentially relocated. A critical pending decision involves determining whether onsite employees or DG432 will execute the IT equipment removal and storage operations. If DG432 is tasked with this responsibility, they are authorized to additionally set up temporary civilian workstations and handle old cable recovery and disposal. The overall engagement was characterized as highly positive with strong coordination between contractor teams and J9 facility and safety representatives.

View the file

Other files

File Type Posted
HC102826R0053 AMD 05.pdf PDF
Attachment 1 Performance Work Statement 26 Aug.docx DOCX document
832674621 Columbus furniture upgrade QA Full listing 26 Aug.docx DOCX document
HC102826R0053 AMD 04.pdf PDF
832674621 Columbus furniture upgrade QA Full listing 25 Aug.docx DOCX document
Attachement 3 _EPL revised 18 AUG.xlsx XLSX spreadsheet
Attachment 1 Performance Work Statement 18 Aug.docx DOCX document
HC102826R0053 AMD 03.pdf PDF
832674621 Columbus furniture upgrade QA Full listing 18 Aug.docx DOCX document
HC102826R0053 Conformed copy.docx DOCX document
Attachement 3 _EPL revised 13 AUG.xlsx XLSX spreadsheet
HC102826R0053 AMD 02.pdf PDF
832674621 Columbus furniture upgrade QA Full listing 13 Aug v2.docx DOCX document
Attachment 1 Performance Work Statement.docx DOCX document
Attachement 3 _EPL.xlsx XLSX spreadsheet
Attachment 6a_Pre-Proposal Site Visit Instructions31JUL.docx DOCX document
HC102826R0053 AMD 01.pdf PDF
Attachment 6c_DSCC Map to Bldg.pdf PDF
Attachment 5b_Plans and Specifications (Attachment A on PWS).pdf PDF
Attachement 3 _EPL.xlsx XLSX spreadsheet
HC102826R0053 Furniture upgrade.pdf PDF
Attachment 6b_VAR info.pdf PDF
Attachment 6a_Pre-Proposal Site Visit Instructions.docx DOCX document
Attachment 5d_Plans and Specifications (Attachment C WS4 on PWS.pdf PDF
Attachment 5c_Plans and Specifications(Attachment B WS14 on PWS).pdf PDF
Attachment 5a_Plans and Specifications.pdf PDF
Attachment 4_Provisions Clauses.docx DOCX document
Attachment 2_QASP_Columbus Furniture.docx DOCX document
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Event Details

Purpose
Contractor walk-through for furniture system installation
Key Personnel
Mike Reid, Steve Hein (J9 Facilities Representative), Bryan Brannam (J9 Safety Representative), Site Lead, IT SME, four (4) Contractor Teams
Location
DISA Global Columbus Facility

Walk-Through Observations & Logistics

Topic
Discussion / Action Taken
Project Scope
Reviewed requirements for furniture removal, relocation, and installation.
Electrical & IT
Determined that electrical and IT cables will be terminated above the ceiling grid. Confirmed that new IT cables will be pulled from the communications closet and verified all cable specifications on the new furniture system.
Logistics & Disposal
Walked the loading dock area to plan product delivery and removal of furniture. Established locations for metal recycling and a 20ft trash container.
Safety & Egress
Reviewed the temporary wall location. Upgraded the design from one door to two doors to support emergency egress and removed the card entry requirement for these doors as specified by J9 representatives.
Pending Decision
It remains to be determined whether the old cables will be abandoned in place above the ceiling grid or if DG432 will recover and dispose of them.

Contractor Q&A & Coordination

Phase
Details
Conference Room Q&A
Held a post-walk-through session for contractor questions. Notably, two of the four teams present had previously provided information during market research.
J9 Integration
Steve Hein (J9 Facilities) and Bryan Brannam (J9 Safety) participated in both the walk-through and Q&A. They provided crucial guidance on facility limitations, ensuring synchronization between the contractors and J9 requirements.
Conclusion
Contractors were successfully escorted out after the Q&A. The overall engagement was highly positive.

Temporary Seating Courses of Action (COAs)

Personnel Group
Relocation Plan
Status / Notes / Setup
Civilians (5)
Moving internally to a non-Global J9 space equipped with existing desks and pre-installed Green/Red cables.
Approved. Exceptional support was provided by Steve Hein to secure this space. Workstation setup can be completed by onsite personnel; however, if DG432 is present to support the equipment storage, they can also perform the setup in this temporary location.
Contractors
Moving to occupy seats within the SCIF.
Approved. The Site Lead and Global Contract Lead confirmed all mission requirements can be accomplished with this arrangement.

IT Equipment Removal Plan

Task
Details
Equipment Scope
Approximately 300 monitors, keyboards, mice with, KVMs, Thin Clients, SIPR and NIPR computers, USB cables, and power cables.
Objective
Clear the project area of all IT equipment so the existing furniture can be disassembled and removed.
Storage Strategy
A concrete plan for the storage location and packing method was established.
Pending Decision
It remains undetermined whether onsite employees will execute the IT removal/storage or if DG432 will deploy a team to complete IT equipment removal and storage (similar to the DG Hill furniture project). Note: If DG432 deploys to complete IT equipment removal and storage, they are also authorized to set up the temporary civilian workstations and may handle the old cable recovery/disposal.

File details come from the government source that posted it. Updated .