This is a Quality Assurance document for a Defense Information Systems Agency (DISA) furniture upgrade solicitation (832674621) at the Columbus facility. The document provides quality assurance requirements and acceptance criteria for the successful vendor performing furniture removal, procurement, and installation work. The contractor must remove all existing furniture as designated on construction drawings, purchase new furniture, and install it with reconnection to the existing electrical grid and cable network, all completed per the proposed concept plans (Attachment A - Furniture Layout). The solicitation includes a base bid with an optional add to include carpeting of the project area and receipt of 85 office chairs.

The solicitation underwent five amendments between July 31, 2026, and August 26, 2026, with the final proposal due date of August 26, 2026, at 2:00 PM CDT. Amendments revised FAR 52.212-2 clauses, adjusted office chair quantities in the Performance Work Statement and Pricing and Equipment List, clarified site visit instructions, updated Q&A documents, and extended the proposal deadline. The file references a conformed copy of the complete RFP containing all amendments, construction drawings, furniture layout plans, equipment pricing lists, pre-proposal site visit instructions, and questions and answers documentation as supporting attachments.

View the file

Other files

File Type Posted
HC102826R0053 AMD 05.pdf PDF
Attachment 1 Performance Work Statement 26 Aug.docx DOCX document
832674621 Columbus furniture upgrade QA Full listing 25 Aug.docx DOCX document
HC102826R0053 AMD 04.pdf PDF
HC102826R0053 AMD 03.pdf PDF
HC102826R0053 Conformed copy.docx DOCX document
Attachment 1 Performance Work Statement 18 Aug.docx DOCX document
Attachement 3 _EPL revised 18 AUG.xlsx XLSX spreadsheet
832674621 Columbus furniture upgrade QA Full listing 18 Aug.docx DOCX document
832674621 Site Survey Notes.docx DOCX document
Attachement 3 _EPL revised 13 AUG.xlsx XLSX spreadsheet
Attachment 1 Performance Work Statement.docx DOCX document
832674621 Columbus furniture upgrade QA Full listing 13 Aug v2.docx DOCX document
HC102826R0053 AMD 02.pdf PDF
HC102826R0053 AMD 01.pdf PDF
Attachement 3 _EPL.xlsx XLSX spreadsheet
Attachment 6a_Pre-Proposal Site Visit Instructions31JUL.docx DOCX document
Attachment 5b_Plans and Specifications (Attachment A on PWS).pdf PDF
Attachment 5c_Plans and Specifications(Attachment B WS14 on PWS).pdf PDF
Attachment 5d_Plans and Specifications (Attachment C WS4 on PWS.pdf PDF
Attachment 2_QASP_Columbus Furniture.docx DOCX document
Attachment 5a_Plans and Specifications.pdf PDF
Attachment 6a_Pre-Proposal Site Visit Instructions.docx DOCX document
Attachment 4_Provisions Clauses.docx DOCX document
Attachment 6b_VAR info.pdf PDF
HC102826R0053 Furniture upgrade.pdf PDF
Attachment 6c_DSCC Map to Bldg.pdf PDF
Attachement 3 _EPL.xlsx XLSX spreadsheet
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

We kindly request clarification on the following items:

1. Governing Document – Attachment B (WS-14) vs. Attachment 5a Please clarify which document shall govern in the event of any discrepancy or conflict between Attachment B (WS-14) and Attachment 5a regarding furniture configuration, design intent, and installation requirements.

FURNITURE SYSTEM MUST BE ONE CONITUOUS UNIT

The contractor needs to determine how to connect the furniture consoles so that there is a circular watch desk and supporting straight desk configuration that becomes one system with one entry point for the watch desk.

2. Monitor Arm Configuration Requirement Please confirm the required monitor arm configuration for the workstation systems.

The solicitation identifies a requirement for 312 total monitor arms, while the WS-14 documentation references a four-monitor configuration.

Please clarify whether the requirement is:

· One (1) four-monitor arm system per workstation;

· Four (4) individual single-monitor arms per workstation; or

· Another configuration intended by the Government.

A CONFIGURATION THAT WILL SUPPORT 4 MONITORS IN A 60 INCH SPACE

It is up to the contractor to figure out if that means 4 monitor arms or two-way arms or another configuration that meets the requirement of 4 monitors that can be raised and lowered at each workstation.

3. Classified / Non-Classified Network Separation Requirement The WS-14 documentation references a 36-inch separation requirement between classified and non-classified networks.

Please confirm whether this requirement applies to the complete workstation layout shown on drawing I-100.

Additionally, please provide guidance on how this requirement should be coordinated with the workstation spacing and console arrangement shown on the I-100 layout.

4. Basis of Design – Battle Captain Consoles and Additional Furniture Components The provided WS-14 documentation appears to provide detailed information primarily for the 68 straight spanner consoles.

Please provide clarification regarding the Basis of Design or required specifications for the following additional components:

· 10 Battle Captain bridge consoles;

· Utility cabinets; and

· Storage console.

CONSOLES THAT WILL SUPPORT BATTLE CAPTAIN AND STORAGE REQUIREMENTS.

The consoles may have removable slidable or rollable cabinets. It is up to the contractor to figure it out with the best furniture system that will meet the specified requirements.

Please confirm whether specific manufacturer/model references are required for these components or whether equivalent products meeting the required functional, dimensional, and performance requirements will be acceptable.

Your clarification on these items will assist GovCrest in preparing a complete, accurate, and compliant proposal.

No specific manufacturer/model references are not required but the specifications for the furniture system found in Attachment 5c must be addressed.

Q&A from 8/6/26

Can you advise if client would be willing to separate the consoles scope from the IT work and carpet laying option.

The Project is one effort with several components. Furniture installation is already separated in the contract vehicle from IT work and Carpet laying. Each have separate CLINs. The entire project must be completed at the conclusion of the 60 day period.

IT work and carpet work are not core competencies of Console manufactures. In this instance we would be disqualified for not committing to a couple of your Clins.

The contractor can work with subs to complete each element of the contract. If a contractor is unable to find subs for whatever element resulting in an incomplete project of required elements then YES, that would disqualify them from the contract award. The contractor could choose to submit a bid excluding optional elements.

Q&A from 8/12/26

1. Question deadline. Attachment 6a (revised 31 July 2026) states questions are due Wednesday, 12 August 2026. Section 6a, paragraph 1.2 as embedded in the RFP body states 19 August 2026. Please confirm the operative date.

Q&A was due on the 12th, the proposals are due on the 19th. The old 6a attachment will be removed when all Q&A are posted and site survey result info as another RFP amendment

1. Offers deadline: Please confirm whether the operative date for submission of offers remains August 19, 2026, 2:00 PM CDT.

Yes, it remains August 19, 2026, 2:00 PM CDT

1. Site visit record. Attachment 6a, paragraph 1.2 provides that a record of the site visit will be distributed to all contractors as an amendment. Please confirm when that record will be issued, and whether it will include photographs of conditions above the ceiling grid and along the proposed temporary wall line. Will a second site visit be offered, and if so, will the proposal due date be adjusted?

This document is the record of the site visit that will be distributed to all contractors. No. There are no photographs authorized from the site visit. No contractors determined to view conditions above the ceiling grid at the time of the walk thru. Resources were made available. Additional tabletop discussion occurred after the walk thru until all questions from contractors were exhausted.

1. Raised floor platform scope. Sheets I-500, I-501 and I-502 of Attachment 5a depict a 12-inch raised access floor platform, ABA-compliant ramps and handrails. No CLIN in Section B and no PWS paragraph appears to reference these items. Please confirm whether they are within the priced scope of CLIN 0003, and if so, under which CLIN the raised floor system, ramps and handrails are to be priced.

The raised floor was removed from the project.

1. Layout configuration. PWS 5.3.2 requires 68 linear workstations with 10 in a circular orientation consistent with drawing I-501 (Attachment 5a). Attachment 5b, labeled "Attachment A on PWS," depicts a square configuration. Please confirm which layout governs.

Attachment A provides the specifications for each workstation. Yes. The center is circular

1. Order of precedence among attachments. PWS 5.8 establishes precedence of the PWS over attachments but does not rank the attachments against one another. Attachment 5a and Attachment 5c (WS-14) conflict on work surface dimensions, storage configuration, power distribution method and monitor arm configuration. Please confirm which attachment governs where they differ.

5A focuses on the center consoles and 5C the linear consoles. The specification outlined in the PWS hold true for both 5A and 5C

1. Monitor arms, CLIN 0004. PWS 6.2.1.2 describes gas-spring arms each supporting one 24-inch monitor with 12 inches of vertical adjustment. Attachment 5c specifies a single arm holding four monitors. If a proposed console system integrates monitor arms into the workstation, should CLIN 0004 be priced separately at 312 units, or carried within CLIN 0003 and shown at no separate charge?

The specifications outlined in the PWS hold true for both 5A and 5C

1. Temporary wall, CLIN 0008. Please confirm: (a) construction type — demountable partition or conventional stud and gypsum; (b) height — to finished ceiling or full deck to deck; (c) required sound attenuation rating and test standard; and (d) unit of measure, as CLIN 0008 shows a quantity of 120 while PWS 6.2.1.7 describes 120 linear feet.

Please see specifications outlined in the PWS. Card reader has been removed. Construction types may vary. Sound Attenuation Definition: Required if classified discussions will occur; involves adding sound-deadening materials.

1. Fire protection at the temporary wall. If the wall extends above the ceiling grid to structure, relocation or addition of sprinkler heads under NFPA 13 may be required. No CLIN or PWS paragraph addresses fire protection work. Please confirm whether sprinkler modification, permitting and inspection are within contractor scope.

No Construction is authorized for this project.

1. Access control, CLIN 0008. Please confirm whether the card reader and intrusion detection components are government-furnished or contractor-supplied, whether integration to an existing access control system is required, and who performs credentialing and system enrollment.

Removed.

1. Quantity reconciliation. Please confirm the governing quantities where documents differ:

(a) existing workstations to be removed — PWS 5.2 states 77, PWS 6.1.1.1 states 69;

(b) office chairs — CLIN 0010 and Attachment 3 state 82, PWS 6.5.1 as amended by Amendment 01 states 85;

(c) electrical connections — CLIN 0007 and the EPL Summary tab state 82, the EPL Materials tab states 85;

(d) CAT6 cable — CLIN 0006 states 24,000 feet, while the PWS drop counts at 150 feet each total approximately 24,600 feet.

a. Some cubes will be relocated vs removed

b. 85

c. 85 (some connections may already exist for relocated furniture)

d. Approximately 24000 feet. (some cables could be reused for relocated and installed furniture)

1. Attachment 5d. Attachment 5d (WS-4) specifies two 7'-0" x 7'-0" workstations for rooms 1307 and 1309. No CLIN references these units. Please confirm whether they are within scope and under which CLIN they are to be priced.

No Office furniture will be replaced

1. Pricing template administration. FAR 52.212-2 as replaced by Amendment 01 directs pricing submission on "Attachment 2," while the EPL is posted as Attachment 3. Additionally, CLIN numbers on the EPL Materials tab (0009 lockers, 0010 chairs, 0011 carpet, 0012 whiteboards) do not match the Section B schedule (0009 carpet, 0010 chairs, 0011 whiteboards, 0012 lockers). Please confirm the correct pricing template and CLIN alignment.

Will be corrected on amended RFP

· 2 doors for egress

· Is that a J9 ask or taken from input from the contractors? J9. They also nix the card reader requirement so that will bring down the cost of the wall. I think it is a wash.

· Is it required or suggested? The cheapest route for the temp wall is the way to go as long as we are compliant.

They said required for egress.

· Removal of old cabling

· Is local J9 IT not part of this?

· Would think they would play in the removal.

Does not need to be removed. It is up to J9. Asking the contractors to remove it will add $$ to the contract.

· Abandon in place is not ideal for any future work that may need to be done in the facility We can add that to the contract if you would like. We can also have DG432 remove it or ask J9.

· From the Q&A session

· Do you have a list of the questions that the contractors brought up? Would be interested to see what was discussed in that forum The KO has the list of questions so far. We are still in the Q&A phase. I can get you what we have so far.

· Any concerns with the 60-day timeline of the project? No concerns from contractors or J9.

· Any concerns with the furniture configuration from the vendor teams? No concerns with the configuration.

· Temporary seats

· How many SCIF seats are we using for the contractors? Six

· Temp J9 seats for CIVs

· Is that 5 seats or 5 civilians at 24x7 support? Yes

· Any issues traversing the project space while the vendor is installing the new furniture? No issues. We will put a walk line like they have here at Hill for the HaC Furniture project.

· We need to make sure it is clear with the vendor that only Mike Reid, Jeremy Rose, or DITCO can adjust what the contractors are doing. Yes.

· If staff are walking through that space I want to avoid a situation where someone tries to provide guidance to the vendor who isn’t permitted to do so. They will be limited to the walk line/path

· Storage/IT inventory

· Would like to hear more on this. A lot if not all of the equipment is NOT DISA Global funded – want to make sure we stay organized on where things move for accountability. Concur. Work in Progress.

· Do we risk the machines falling off the domain? Yes

· This could be problematic when going to return to the space. Agreed. Defer to DG432

· I don’t see any specifications other than a couple of notes on drawings for carpet, glass marker boards, lockers, even the furniture systems which is the main part of this project. Can that be provided? Please see PWS Attachment #1 for more details.

· Attachment 5A shows raised flooring but I am being told by my furniture rep that there will not be raised flooring. Please confirm if there is raised flooring? Correct. No Raised Flooring

· Attachment 3 EPL (pricing sheet) does not show or breakout general conditions for this project. Do you want us to add that to each line item or can we modify the pricing sheet to account for this cost? This is NOT a construction document. The contracting office can provide information for overall rules, rights, and responsibilities.

· Is there a laydown area where we can store material while work is progressing? If the contractor is to provide storage containers where can those be placed? The project area will be vacated and is a secure area so you can store your carts, tools, materials there. You will provide a schedule of activities so you will know what needs to move where and when.

· Please provide the site visit sign in sheet. You will be required to badge in and out of the secured space.

· Is a bid bond required? No

· Do we need to provide performance and payment bonds for this project? No

· Do we need to include taxes in our pricing or will this be a tax exempt project and the government will provide a tax-exempt certificate? You will be evaluated on the over bid price. This is a LPTA contract vehicle.

· Note 5 on sheet I-101 states - OPTIONAL BID ITEM #1. LOCKERS OR STORAGE CABINETS FOR PERSONAL EFFECTS - CONFIRM WITH DISA GLOBAL POC. – Who is the point of contact? Can more information be provided on the lockers. Can you provide a spec for the lockers? Please see PWS for specs.

· General note 4 indicates carpet will remain where new consols are to be installed and note 5 indicates to remove and install new carpet where the raised flooring will be installed which is around 1500 sf or less of carpet depending on how this is taken off. On the bid sheet it indicates 15,000 sf of carpet. Please confirm what carpet needs to be replaced and whereas the plans do not show carpet removal or install. As stated previously, NO raised flooring. Carpet specs on found on the PWS paragraph 6.4

· The plans do not call out the glass white boards but is noted as 4 ea on the excel pricing form. Is this the correct qty? what size is wanted? Are these electronic? Please provide a spec for this product. Specs for Glass White Boards are found in the PWS paragraph 6.6

· Please clarify what the “Ladders” are? Please see PWS 6.2.1.3

· Please provide a photo of the electrical panels that will be used and confirm there is adequate power available for the newly designed furniture and equipment. Photo not available. Walk thru provided information for electrical panels. Power is available.

· Please provide a power drawing with one line design. I will consult with the Architect

· Please confirm this is not a design build contract. All Design is to be provided by the government. This is NOT a construction project. This is NOT a design build contract. This is an LPTA Furniture Project

1. Material scope changes issued after the close of questions: Questions closed 12 August; Amendment 0002 issued 13 August. That amendment removed the raised floor system, removed the card reader requirement, established that no construction is authorized, confirmed that the Attachment 5d workstations are not in scope, revised quantities, and established the four-monitor configuration within a 60-inch space. These changes materially affect the technical solution and its pricing, and offerors have had no opportunity to submit follow-on questions. We further note that the question regarding the 36-inch classified/non-classified network separation requirement and its coordination with the layout shown on drawing I-100 was published without a response.

All issues were discussed in the walk thru.

0. 5A workstation specs are to be used. There are NO cube (5D) workstations to be installed. 5A workstation specifications are included in the packet and are in scope.

0. There have been no revisions in quantities of workstations 78 as noted in PWS 6.2.1.1

0. 4x monitor configuration is noted in the PWS 6.2.1.2

0. 36 inch separation was discussed in the walk thru. Con tractors were encouraged to attend the walk thru. In the event the contractor was unable to attend the walk thru, Q&A was provided with responses and follow up questions.

0. This discussion Q&A is an opportunity to submit follow on questions.

1. Deliverables required for technical acceptability: Subfactor 1.1 requires color and finish samples and 3D renderings as a condition of technical acceptability. These are produced by the furniture manufacturer and cannot be developed until the design basis is stable, which occurred with the issuance of Amendment 0002 on 13 August.

1. Upon award. The contractor will provide coordinate with stakeholders to provide the above.

Amend04 Questions

Can you give me some clarification on the white noise? A white noise generator is required during the 60 day project execution. Where do you want it installed? This does not need to be installed. Will it be temporary or permanent? I may be temporary. How much area will it need to cover? 120 ft wall length.

Can you clarify CLIN 0007 Electrical Boxes? Electrical boxes mounted to the floor that provide power to the workstations. Each outlet constitutes one circuit. It is possible that four outlet boxes could be used. If there is another method to bring electrical connections to workstations that meets the operational requirements and meets electrical code requirements, please provide details in your submittal. 6.2.1.5 Electrical Connections. Connect no more than four workstations to each electrical circuit sup-porting the project area. Workstations will be tested upon completion of electrical connection. What are these? I don’t see information in the Performance of Work to indicate what is included for this cost? The requirement is in 6.2.1.5. How you achieve that will be part of your submittal.

· For the new Cat 6 cables being installed to the new system furniture, is there existing cable trays in the ceiling for the new cabling to be installed in?

NO

· If cable trays are to be installed, does there need to be a separation maintained between the SIPR and NIPR new cabling?

Must meet current code requirements. Yes there needs to be separation.

· Are we to provide and install new CAT 6 patch panels to allow for the termination of the new cabling? Existing patch panels will be utilized

· Is there room in the existing racks to accept the new patch panels?

Yes What is the purpose of the temp wall? We will need to do work (replacing carpet) in this area and this will inhibit the work.

The temp wall divides J9 Space from J357 space. We will carpet up to the temp wall and most probably the temp wall will stay there. I put it in the PWS to install a temp wall. I did not put in the PWS to remove it. That is something that can be done later or never.