TI Maintenance Work Plan Development Process Flowchart_3-19-21.pdf
PDF 180 KB Posted
- Attached to
- Tactical Infrastructure (TI) Maintenance for Big Bend Sector and El Paso Sector in Texas
- Solicitation number
- 70B01C21R00000007
About this file
This document outlines the process flowchart for developing Tactical Infrastructure (TI) maintenance work plans for the Big Bend Sector and El Paso Sector in Texas. Over a 90 day period, the process involves the Contracting Officer's Representative and Alternate COR gathering work plan requirements, conducting site visits with the contractor and Border Patrol stations to develop work descriptions. The Contractor then finalizes the maintenance work plan, develops cost estimates, and enters the plan into the Work Management System. The COR/ACOR reviews and finalizes the plan, validates activities and costs, prioritizes work, and submits the plan for approval up the chain of command. Once approved, the COR activates the maintenance work plan in the WMS to begin execution.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TI Maintenance Work Plan Development Process
Step 3: CTR Finalizes CWP Day 61 - 62: CTR finalizes CWP (hardcopy)
• Submits to COR for review and approval
Step 1: COR/ACOR Gathers Work Plan Requirements
Day 1 - 45: 90 Day CWP Requirements Identified by CTR, BP, and COR
• CTR sends requirements to COR
• BP sends requirements to TI
Coordinator Day 45: All requirements are due
• Prior to next work plan
Day 46: COR and TI Coordinator:
• Review identified requirements , WMS and backlog
• Plan site visit to discuss identified requirements with respective BP stations and CTR
Day 47 - 53: COR Conducts site visit/tailgate meeting with contractor and develops brief work descriptions, Work Order or SOW (as required)
Step 5: CTR Develops Cost Estimate and Enters CWP in WMS Day 68 - 76:
• CTR develops cost estimates for Work
Orders/CWP, submits to COR review/ acceptance (outside of WMS)
• CTR submits CWP to COR/ACOR via WMS
Cost Estimate
Approved?
Yes
No
GO TO
Work Plan Execution
Process
Step 2: COR/ACOR Sends WP Requirements to CTR
Day 54 - 58:
• COR directs CTR to develop CWP
(hard copy) Using Work Orders
• CTR submits CWP to COR for review
Day 58 - 60: COR makes edits to proposed CWP (hardcopy) and submits back to CTR
CWP
Step 6: COR/ACOR Reviews CWP Day 77 - 81:
• Validates all CWP activities
• Reviews cost
• Revises Work Orders/CWP (as necessary)
• Prioritizes work activities
60 days 7 days 23 days
Step 7: COR/ACOR Finalizes CWP in WMS Day 82 - 89:
• COR submits CWP to Director in WMS
• Director validates CWP, adds funds, and submits to OBP
• OBP validates prioritized requirements and submits to BC
• Director marks CWP “Reviewed” and submits to COR Day 90: COR activates CWP in WMS
Step 4: COR/ACOR Meets w/CTR and Routes Final CWP to ENG/ENV/RE
Day 63 - 67:
• COR/ACOR holds discussions to:
- Outline requirements and expectations
- Ensure mutual understanding
• COR submits final CWP (hard copy) to ENG/ENV/RE for review
Slide Number 1