TI Maintenance Work Plan Development Process Flowchart_3-19-21.pdf

PDF 180 KB Posted

Attached to
Tactical Infrastructure (TI) Maintenance for Big Bend Sector and El Paso Sector in Texas
Solicitation number
70B01C21R00000007
Issued by

About this file

This document outlines the process flowchart for developing Tactical Infrastructure (TI) maintenance work plans for the Big Bend Sector and El Paso Sector in Texas. Over a 90 day period, the process involves the Contracting Officer's Representative and Alternate COR gathering work plan requirements, conducting site visits with the contractor and Border Patrol stations to develop work descriptions. The Contractor then finalizes the maintenance work plan, develops cost estimates, and enters the plan into the Work Management System. The COR/ACOR reviews and finalizes the plan, validates activities and costs, prioritizes work, and submits the plan for approval up the chain of command. Once approved, the COR activates the maintenance work plan in the WMS to begin execution.

View the file

Other files

File Type Posted
Copy of Contractor Unit Pricing Sheet 04262021.xlsx XLSX spreadsheet
70B01C21R00000007 IT Maintenance Contractor Questions From Amendment 2 04072021 (revised).docx DOCX document
70B01C21R00000007 IT Maintenance Contractor Questions From Amendment 2 04072021.docx DOCX document
ATTACHMENT 4 - Notional Work Plan 04072021.xlsx XLSX spreadsheet
Contractor Unit Pricing Sheet 04072021.xlsx XLSX spreadsheet
ATTACHMENT 7 Work Order Form.xlsx XLSX spreadsheet
ATTACHMENT 4 -- Notional Work Plan 3-29-21.xlsx XLSX spreadsheet
ATTACHMENT 1 -- SOW EPT BBT North TI Maintenance IDIQ Rev 03292021.pdf PDF
70B01C21R00000007 ATTACHMENT 9 PM Checklist.pdf PDF
ATTACHMENT 2 -- Line Item Summary EPT BBN 3-28-21.xlsx XLSX spreadsheet
70B01C21R00000007 IT Maintenance Contractor Questions Resp 03292021.pdf PDF
RFP 70B01C21R00000007 Amendment A0002 SF30.pdf PDF
ATTACHMENT 5 -- PAST PERFORMANCE INFORMATION SURVEY 3-29-21.docx DOCX document
ATTACHMENT 8 Estimate Form 70B01C21R00000007 3-29-21.xlsx XLSX spreadsheet
Site Visit Attendees.docx DOCX document
Meeting Location for Day 1 of the site vists.pdf PDF
70B01C21R00000007 Amendment 1.pdf PDF
Site Visit Signup El Paso and Big Bend Sector.xlsx XLSX spreadsheet
Attachment 6 Wage Determination DBA Presidio Hwy.pdf PDF
Attachment 1 SOW EPT BBT North TI Maintenance IDIQ 12012020.docx DOCX document
Attachment 4a TI Design Standards_v1_Chapter 1_Sept 2012.pdf PDF
Attachment 4 Boat Ramp Design Standards.pdf PDF
Attachment 6 Wage Determination DBA El Paso Hwy.pdf PDF
Attachment 3 Inventory Asset List 12-08-2020 (003).pdf PDF
Attachment 4 Boat Ramp Detail.pdf PDF
CUS1449 - Commercial Items (SF1449).pdf PDF
Attachment 4 Submittal 01 Engineering Letter and Shop Drawings.pdf PDF
Attachment 4 TI Design Standards_v1_Chapter 3_Sept 2012.pdf PDF
RFP 70B01C21R00000007 Line Item Summary 01212021.xlsx XLSX spreadsheet
RFP 70B01C21R00000007 continuation pages.pdf PDF
Attachment 5 Notional Work Plan.xlsx XLSX spreadsheet
Attachment 4 TI Design Standards_v1_Sept 2012 - Roads Section.pdf PDF
Attachment 6 Wage Determination DBA Presidio Bldg.pdf PDF
Attachment 2 Contractor Unit Pricing Sheet final.xlsx XLSX spreadsheet
Attachment 6 Wage Determination SCA El Paso.pdf PDF
Attachment 4 TI Standards v2_Wall-Fence-Gates Drawing Updates_080618 (003).pdf PDF
Attachment 6 Wage Determination DBA El Paso Bldg.pdf PDF
Attachment 4 TI Design Standards_v1_Chapter 2_Sept 2012.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TI Maintenance Work Plan Development Process

Step 3: CTR Finalizes CWP Day 61 - 62: CTR finalizes CWP (hardcopy)

• Submits to COR for review and approval

Step 1: COR/ACOR Gathers Work Plan Requirements

Day 1 - 45: 90 Day CWP Requirements Identified by CTR, BP, and COR

• CTR sends requirements to COR

• BP sends requirements to TI

Coordinator Day 45: All requirements are due

• Prior to next work plan

Day 46: COR and TI Coordinator:

• Review identified requirements , WMS and backlog

• Plan site visit to discuss identified requirements with respective BP stations and CTR

Day 47 - 53: COR Conducts site visit/tailgate meeting with contractor and develops brief work descriptions, Work Order or SOW (as required)

Step 5: CTR Develops Cost Estimate and Enters CWP in WMS Day 68 - 76:

• CTR develops cost estimates for Work

Orders/CWP, submits to COR review/ acceptance (outside of WMS)

• CTR submits CWP to COR/ACOR via WMS

Cost Estimate

Approved?

Yes

No

GO TO

Work Plan Execution

Process

Step 2: COR/ACOR Sends WP Requirements to CTR

Day 54 - 58:

• COR directs CTR to develop CWP

(hard copy) Using Work Orders

• CTR submits CWP to COR for review

Day 58 - 60: COR makes edits to proposed CWP (hardcopy) and submits back to CTR

CWP

Step 6: COR/ACOR Reviews CWP Day 77 - 81:

• Validates all CWP activities

• Reviews cost

• Revises Work Orders/CWP (as necessary)

• Prioritizes work activities

60 days 7 days 23 days

Step 7: COR/ACOR Finalizes CWP in WMS Day 82 - 89:

• COR submits CWP to Director in WMS

• Director validates CWP, adds funds, and submits to OBP

• OBP validates prioritized requirements and submits to BC

• Director marks CWP “Reviewed” and submits to COR Day 90: COR activates CWP in WMS

Step 4: COR/ACOR Meets w/CTR and Routes Final CWP to ENG/ENV/RE

Day 63 - 67:

• COR/ACOR holds discussions to:

- Outline requirements and expectations

- Ensure mutual understanding

• COR submits final CWP (hard copy) to ENG/ENV/RE for review