ATTACHMENT 4 -- Notional Work Plan 3-29-21.xlsx

XLSX spreadsheet 49 KB Posted

Attached to
Tactical Infrastructure (TI) Maintenance for Big Bend Sector and El Paso Sector in Texas
Solicitation number
70B01C21R00000007
Issued by

About this file

This document contains a notional work plan and related federal contract opportunity. The notional work plan outlines various maintenance, repair, and improvement tasks required for tactical infrastructure assets in the Big Bend and El Paso Sectors in Texas. The tasks are grouped into categories including roads and bridges, fence and gates, vegetation control, debris removal, border lighting and electrical, drainage and grate systems. The federal contract opportunity is a solicitation seeking contractor services to perform the tactical infrastructure maintenance tasks outlined in the attached statement of work for assets located in the Big Bend and El Paso Sectors. The solicitation is issued by the Department of Homeland Security Customs and Border Protection. Offerors are instructed to fill out an attached site visit form if attending the site visit and email it by March 11, 2021.

View the file

Other files

File Type Posted
Copy of Contractor Unit Pricing Sheet 04262021.xlsx XLSX spreadsheet
70B01C21R00000007 IT Maintenance Contractor Questions From Amendment 2 04072021 (revised).docx DOCX document
70B01C21R00000007 IT Maintenance Contractor Questions From Amendment 2 04072021.docx DOCX document
ATTACHMENT 4 - Notional Work Plan 04072021.xlsx XLSX spreadsheet
Contractor Unit Pricing Sheet 04072021.xlsx XLSX spreadsheet
ATTACHMENT 7 Work Order Form.xlsx XLSX spreadsheet
ATTACHMENT 1 -- SOW EPT BBT North TI Maintenance IDIQ Rev 03292021.pdf PDF
70B01C21R00000007 ATTACHMENT 9 PM Checklist.pdf PDF
TI Maintenance Work Plan Development Process Flowchart_3-19-21.pdf PDF
ATTACHMENT 2 -- Line Item Summary EPT BBN 3-28-21.xlsx XLSX spreadsheet
70B01C21R00000007 IT Maintenance Contractor Questions Resp 03292021.pdf PDF
RFP 70B01C21R00000007 Amendment A0002 SF30.pdf PDF
ATTACHMENT 5 -- PAST PERFORMANCE INFORMATION SURVEY 3-29-21.docx DOCX document
ATTACHMENT 8 Estimate Form 70B01C21R00000007 3-29-21.xlsx XLSX spreadsheet
Site Visit Attendees.docx DOCX document
Meeting Location for Day 1 of the site vists.pdf PDF
70B01C21R00000007 Amendment 1.pdf PDF
Site Visit Signup El Paso and Big Bend Sector.xlsx XLSX spreadsheet
Attachment 6 Wage Determination DBA Presidio Hwy.pdf PDF
Attachment 1 SOW EPT BBT North TI Maintenance IDIQ 12012020.docx DOCX document
Attachment 4a TI Design Standards_v1_Chapter 1_Sept 2012.pdf PDF
Attachment 4 Boat Ramp Design Standards.pdf PDF
Attachment 6 Wage Determination DBA El Paso Hwy.pdf PDF
Attachment 3 Inventory Asset List 12-08-2020 (003).pdf PDF
Attachment 4 Boat Ramp Detail.pdf PDF
CUS1449 - Commercial Items (SF1449).pdf PDF
Attachment 4 Submittal 01 Engineering Letter and Shop Drawings.pdf PDF
Attachment 4 TI Design Standards_v1_Chapter 3_Sept 2012.pdf PDF
RFP 70B01C21R00000007 Line Item Summary 01212021.xlsx XLSX spreadsheet
RFP 70B01C21R00000007 continuation pages.pdf PDF
Attachment 5 Notional Work Plan.xlsx XLSX spreadsheet
Attachment 4 TI Design Standards_v1_Sept 2012 - Roads Section.pdf PDF
Attachment 6 Wage Determination DBA Presidio Bldg.pdf PDF
Attachment 2 Contractor Unit Pricing Sheet final.xlsx XLSX spreadsheet
Attachment 6 Wage Determination SCA El Paso.pdf PDF
Attachment 4 TI Standards v2_Wall-Fence-Gates Drawing Updates_080618 (003).pdf PDF
Attachment 6 Wage Determination DBA El Paso Bldg.pdf PDF
Attachment 4 TI Design Standards_v1_Chapter 2_Sept 2012.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions

Purpose of this effort is to evaluate vendors technical ability to determine proper equipment, materials and labor resources and amount of time to complete a task order
Steps :
1Use Your Estimate Form to complete the YELLOW highlighed sections of the Work Estimate Form (Attachment 8) for each Notional Work Plan task identified within each tab.
a) Labor resources
b) Equipment Resources
c) Material Resource Quantity
d) Mobilization
e) Other Cost: ex. NM tax
2Under Work Description just fill out TI Asset Description and Work category: ex.- R&B, V&D, etc.
3All Yellow Highlighted Columns should be completely filled out under the Estimate Forms (Attachment 8): Item, UoM, and Qty
4PDF all completed estimate forms and lock so they can only be viewed and not edited

F&G

Notional Work Plan; Use Work Order Form to complete cost
Task #Task DescriptionAsset ObjcetiveWork CategoryLocationSectorOccurrances
1Gate Inspections: Perform inspection and maintenance of 119 manual gates on a monthly basis. Inspections shall be completed three times: July, August and September. Maintenance includes cleaning out the tracks and moving parts with air, greasing, lubricating, testKeep all gates fully operationalF&GTXEl Paso3

2 Perform inspection and maintenance of 10 gates once a week (for 90 day POP): 4 gates at Santa Teresa, 1 gate at Ft Hancock,1 gate at County Lakes Road, 1 Gate at Camp 8 and 3 atomated gates. Maintenance includes cleaning out tracks and moving parts with air and lubrication if Keep all gates fully operational F&G TX El Paso 9

Urgent fence breach repairs; estimated quantity is 225 for 3 Months. Work will be requested by the Government and completed 7 days a week. All work will occur in Texas with 10 mile segement. For this exercise figure the following: 4 beaches 3' X 3' full replacement of mesh style fecning in accordance with Ti standards and 6 breaches 2' x 2' full replacement of mesh style fecning in accordance with TI standards. Close all opennings and meet CBP standards F&G TX El Paso 1

R&B

Task #Task DescriptionAsset ObjcetiveWork CategoryLocationSectorOccurrances
1BSI 235-240: Re-shape and compact the V-Ditch next to Illumination at Columbus POE using motor grader, roller, Water trucks and/or additional equipment as necessary. "Its a 1/2 mile between BSI markers."Conditions for this effort are as existing during the site visit. Ditch must be constructed to accommodate existing culvert system.Keep water conveyances fully operationalR&BNMEl Paso1

2 Maintenance Blading of Border Fence Road: East side of the Columbus POE (BSI 241) to Arena Access Road (BSI 265). Contractor will complete maintenance blading (smoothing) on roadways to include, as applicable, gathering road base material off side of road, replacement and compaction of road base back on driving surface, blading to remove wash boarding, and blading to remove erosion or washouts. Contractor will provide notification when roadways that are found to require additional work to restore above and beyond the efforts described above. Requires written COR approval. "Its a 1/2 mile between BSI markers." Keep road surfaces free from washboarding, erosions and potholes R&B NM El Paso 1

3 Maintenance Blading of 2.2 miles of Bosque Rd near BSI 46-50, .4 miles of Lopez Road, near BSI #53 and .9 miles of County Lakes Rd near BSI #79. QTY: 3.7 miles. Contractor will complete maintenance blading (smoothing) on roadways to include, gathering road base material off side of road, watering, and compacting. "Its a 1/2 mile between BSI markers." Keep road surfaces free from washboarding, erosions and potholes R&B TX El Paso 1

4 Santa Teresa: Additional road base between Gate 4 and Landfill (East of the POE) and between Gate 1 and end of pedestrian fence (West of the POE); Process and compact upper 3" of loose sand on this 6.0 mile road. Prepare the area to be plated with 3" of road base. 1) Use the motor grader, water trucks and roller to process and compact existing material. 2) Prepare the area to receive road base 14' wide by 3" thick. Keep road surfaces free from washboarding, erosions and potholes R&B TX El Paso 1

L&E

Task #Task DescriptionAsset ObjcetiveWork CategoryLocationSectorOccurrances
1During the work plan period, it is estimated that forty five (45) light fixtures will be found not working. Subcontractor to make repairs to the 45 fixtures, estimated to require replacement of lamp, ballast, or fuse.Maintain all fixtures to stay fully operationalL&ENMEl Paso0

2 Work Element Description: Columbus POE: Repair circuit LP 45-50 which appears to be a blowout due to moisture and compromised conductor jacketing. Estimate is based on replacing four conductors between junction boxes at Light Poles 23 and 27. Includes Maintain all fixtures to stay fully operational L&E NM El Paso 1

3 Transfer switch for the controls of the mechanical grates at K1-B. Add manual transfer switch for the controls of the mechanical grates at K1-B to allow for use of a back-up generator for power if needed. Install in one 30A circuit. Maintain all fixtures to stay fully operational L&E NM El Paso 1

4 Megger Test Columbus POE Lighting Circuits – Isolate individual cables by removing mechanical connections/terminations. Based on original construction plans, Subcontractor estimates a maximum of 301 circuits/903 individual conductors for testing. Findings will likely be less than 903 as home runs do not break at every light pole/j-box. Subcontractor reduced the estimated quantity by 1/3. The ground cable will not be tested. Subcontractor shall not be responsible for any damage caused to the electrical infrastructure during the test performance due to existing deteriorated condition. Note that the Megger test will test the insulation integrity of individual conductors but will not identify a fault location. A report of findings will be provided to the Government at the test conclusion (test results, determination of pass/fail for each conductor, visual deficiencies in wiring or connectors). Excludes repair/replacement of any items except connectors that cannot be re-used. Maintain all fixtures to stay fully operational L&E NM El Paso 1

5 Columbus POE: Maintenance on Illumination Fixtures; 107 poles: a. Clean-out the nests/birds in the pole's mast arm, as necessary; b. Secure steel mesh covers over the open holes of all arms using self tapping screws to prevent future access from the birds. c. Open and clean all the fixtures. Maintain all fixtures to stay fully operational L&E NM El Paso 1

Urgent Allowance Item. During the work plan period, it is estimated that ten (10) light fixtures will be found not working, to be completed under one (1) urgent service call. Repair bulbs / ballasts / etc. (10 lights) Maintain all fixtures to stay fully operational L&E NM El Paso 1

V&D

Task #Task DescriptionAsset ObjcetiveWork CategoryLocationSectorOccurrances
1Vegetation Removal from BSI #46 to BSI #78/79. North and South sides of Fence. 25% remaining for CWP #14. Vegetation Control from BSI 46 to BSI 79: A. North side of the TI: Cut/mulch all vegetation from the TI to the top of the adjacent canal wall or to a width of ten feet, whichever is closer. B. South side of the TI: Cut/mulch all vegetation from the TI to the top of the levee road. C. Use an ATV for work east of BSI 60. Use Government provided incinerator. use weed eaters to mulch material and leave in place. *** Any accumulation will be loaded and hauled offsite. Option - debris(Tumble weeds) can be burned in an Incinerator and may result in a small amount of cost savings. Assume 300 Cu yds of silt and debris/mile to be hualed off to an approved local landfill. "Its a 1/2 mile between BSI markers."Maintain clear site of view for BP agentsV&DTXEl Paso1

2 BSI 89 to BSI 93: Remove vegetation on the south side of the TI to include tumbleweeds and with the use of an incinerator. *** estimate includes additional insurance premium for Gov't incinerator. "Its a 1/2 mile between BSI markers." Maintain clear site of view for BP agents V&D TX El Paso 1

3 Remove Vegetation and Debris from Catch Dams at BSI 231-232. "Its a 1/2 mile between BSI markers." maintain proper function V&D NM El Paso 1

4 Clean catch dams on V-Ditch, BSI 265-266: Clean silt, soil and vegetation from catch dams. Move and re-set catch dams as needed. Add additional 200 tons Rip Rap to prevent blowouts and erosion. "Its a 1/2 mile between BSI markers." maintain proper function V&D NM El Paso 1

5 Remove silt accumulation and vegetation at the TI between BSI 31 - 46. Clean sand out of TI (north and south) Footing and remove vegetation West of Zaragoza POE, QTY 9.5 miles: Gather, load, haul and dispose of debris/silt/sand. There are some areas where silt and debris has accumulated on the north side of the TI where it will be necessary to use a wheelbarrow to remove this material. Use pedestrian access gates. North side material to be blown over to the south side for hand work removal. Notes: Mostly Hand Work. Use of a mini excavator and the incinerator will be needed. The incinerator can be staged by the Zaragoza POE. Assume 300 Cu yds of silt and debris/mile to be hualed off to an approved local landfill. "Its a 1/2 mile between BSI markers." maintain proper function V&D TX El Paso 1

D&G

Task #Task DescriptionAsset ObjcetiveWork CategoryLocationSectorOccurrances
1NM BSI 235 - 240: Columbus POE West Lighting: Remove Sedimment from inside 5 box culverts and from the culvert aprons. Construct a swale from BSI 235 to 240 and tie to invert elevation to each culvert. "Its a 1/2 mile between BSI markers."Hual off all excess matrials to an approved landfill.maintain free flow of water through drainage structureD&GNMEl Paso1

2 Monthly maintenance of K1B grates to include cleaning, regreasingof stems, cleaning & regreasing of actuators and cleaning of gate guides. Power to acuate the grates by means of government furnished generator. maintain free flow of water through drainage structure D&G TX El Paso 3