70B01C21R00000007 ATTACHMENT 9 PM Checklist.pdf

PDF 95 KB Posted

Attached to
Tactical Infrastructure (TI) Maintenance for Big Bend Sector and El Paso Sector in Texas
Solicitation number
70B01C21R00000007
Issued by

About this file

This document contains a preventative maintenance checklist and statement of work for a federal contract solicitation. The solicitation is seeking contractor services to perform maintenance, repair, and improvement work for Tactical Infrastructure assets in the Big Bend and El Paso Sectors in Texas. Required services include work on roads and bridges, fences and gates, vegetation control, debris removal, border lighting and electrical systems, drainage and grate systems, and tunnel remediation. The maintenance checklist outlines monthly, quarterly, and annual preventative maintenance tasks for gates and related components. Interested offerors are instructed to submit a site visit form by March 11, 2021 if attending an optional site visit. The solicitation is designated for the Department of Homeland Security Customs and Border Protection.

View the file

Other files

File Type Posted
Copy of Contractor Unit Pricing Sheet 04262021.xlsx XLSX spreadsheet
70B01C21R00000007 IT Maintenance Contractor Questions From Amendment 2 04072021 (revised).docx DOCX document
70B01C21R00000007 IT Maintenance Contractor Questions From Amendment 2 04072021.docx DOCX document
ATTACHMENT 4 - Notional Work Plan 04072021.xlsx XLSX spreadsheet
Contractor Unit Pricing Sheet 04072021.xlsx XLSX spreadsheet
ATTACHMENT 7 Work Order Form.xlsx XLSX spreadsheet
ATTACHMENT 4 -- Notional Work Plan 3-29-21.xlsx XLSX spreadsheet
ATTACHMENT 1 -- SOW EPT BBT North TI Maintenance IDIQ Rev 03292021.pdf PDF
TI Maintenance Work Plan Development Process Flowchart_3-19-21.pdf PDF
ATTACHMENT 2 -- Line Item Summary EPT BBN 3-28-21.xlsx XLSX spreadsheet
70B01C21R00000007 IT Maintenance Contractor Questions Resp 03292021.pdf PDF
RFP 70B01C21R00000007 Amendment A0002 SF30.pdf PDF
ATTACHMENT 5 -- PAST PERFORMANCE INFORMATION SURVEY 3-29-21.docx DOCX document
ATTACHMENT 8 Estimate Form 70B01C21R00000007 3-29-21.xlsx XLSX spreadsheet
Site Visit Attendees.docx DOCX document
Meeting Location for Day 1 of the site vists.pdf PDF
70B01C21R00000007 Amendment 1.pdf PDF
Site Visit Signup El Paso and Big Bend Sector.xlsx XLSX spreadsheet
Attachment 6 Wage Determination DBA Presidio Hwy.pdf PDF
Attachment 1 SOW EPT BBT North TI Maintenance IDIQ 12012020.docx DOCX document
Attachment 4a TI Design Standards_v1_Chapter 1_Sept 2012.pdf PDF
Attachment 4 Boat Ramp Design Standards.pdf PDF
Attachment 6 Wage Determination DBA El Paso Hwy.pdf PDF
Attachment 3 Inventory Asset List 12-08-2020 (003).pdf PDF
Attachment 4 Boat Ramp Detail.pdf PDF
CUS1449 - Commercial Items (SF1449).pdf PDF
Attachment 4 Submittal 01 Engineering Letter and Shop Drawings.pdf PDF
Attachment 4 TI Design Standards_v1_Chapter 3_Sept 2012.pdf PDF
RFP 70B01C21R00000007 Line Item Summary 01212021.xlsx XLSX spreadsheet
RFP 70B01C21R00000007 continuation pages.pdf PDF
Attachment 5 Notional Work Plan.xlsx XLSX spreadsheet
Attachment 4 TI Design Standards_v1_Sept 2012 - Roads Section.pdf PDF
Attachment 6 Wage Determination DBA Presidio Bldg.pdf PDF
Attachment 2 Contractor Unit Pricing Sheet final.xlsx XLSX spreadsheet
Attachment 6 Wage Determination SCA El Paso.pdf PDF
Attachment 4 TI Standards v2_Wall-Fence-Gates Drawing Updates_080618 (003).pdf PDF
Attachment 6 Wage Determination DBA El Paso Bldg.pdf PDF
Attachment 4 TI Design Standards_v1_Chapter 2_Sept 2012.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Gate: XX_XX Preventative

Maintenance Checklist

Date: Required

CID Component Inspection Maintenance Maintenance Component Notes 1 Concrete Slab and Pier Caps 1 month 1 month Clear top of concrete 2 Guide Rail 1 month 1 month Clean guide rail 3 Impact Beam 1 month 1 month Cleanout drainage holes

4 Filler Fence 1 month 1 month Remove debris 5 Gate Panels 1 month 1 month Remove debris from mesh/pickets 6 Emergency Light 1 month 3 months Clean plastic, check batteries/lamps 7 Magnetic Lock 1 month 3 months Clean magnets/steel 8 Operator 1 month 3 months Tighten hardware if loose 9 Photo-Eyes 1 month 3 months Clean lenses, check alignment

10 Flood Lights 1 month 3 months Clean plastic/reflectors, replace lamps if burned out 11 Trolley Beam 1 month 3 months Remove debris from beam 12 Cross Members 1 month 3 months Remove debris 13 Trolleys 1 month 3 months Check trolley suspension rod pins 14 Winch 1 month 3 months Exercise winch 15 Chain 1 month 6 months Remove debris, tighten if sagging, lubricate if necessary 16 Key Pads 1 month 6 months Clean keys of dirt/dust 17 Signage 1 month 6 months Clean signs of dirt/dust 18 Surrounding Area 1 month 6 months Clear area and grade terrain 19 Baseplates, Nuts, Bolts 3 months N/A (As required) 20 Columns 3 months N/A (As required) 21 Electrical Conduits 3 months N/A (As required) 22 Battery Box 3 months N/A Remove debris / replace wiring as necessary 23 Gate Operator Alarm 3 months 3 months Activate alarm through photo-eye obstruction, re-set to silence 24 System locks 3 months 6 months Exercise locks 25 Share lock 3 months 6 months Clean system /grease chain 26 Batteries 3 months 12 months Change Batteries if necessary 27 Operator Sprockets 6 months 6 months Check screws, tighten if necessary 28 Bird Spikes 6 months 6 months Remove debris 29 Inspect VegControl on Foot Print Area 1 month 1 month Clear up any tall grass or vines growing around gate.

30 TI Area for TI Work 1 month 1 month Examine surrounding area for work needed ( i.e. sink holes, breaches).

31 Rat Repellent 1 month 1 month Replace rat repellent.

32 Rodent Damage 1 month 1 month Inspect for any Rodent Damage, i.e. chewed wires, urine.

33 Inspect for Insects 1 month 1 month Inspect for insects, i.e. ants, bees etc. Eliminate in a environmentally safe manner.

34 Gate Status N/A N/A Is Gate Operational? Yes or No 35 Additional Comments N/A N/A

Frequency

Work Performed By:____________________________________ _____________________________________________________

File details come from the government source that posted it. Updated .