This document contains a federal contract solicitation and related work order form. The solicitation seeks contractor services to perform maintenance, repair, and improvement of Tactical Infrastructure assets in the Big Bend and El Paso Sectors in Texas. Asset categories include roads and bridges, fence and gates, vegetation control, debris removal, border lighting and electrical, drainage and grate systems, and tunnel remediation. Interested offerors are to complete and submit the attached site visit form by March 11, 2021 via email. The work order form provides a template for work activity reports, detailing asset descriptions, locations, work standards, estimated and actual costs, and sign-off sections for prime and subcontractor representatives.

View the file

Other files

File Type Posted
Copy of Contractor Unit Pricing Sheet 04262021.xlsx XLSX spreadsheet
70B01C21R00000007 IT Maintenance Contractor Questions From Amendment 2 04072021 (revised).docx DOCX document
70B01C21R00000007 IT Maintenance Contractor Questions From Amendment 2 04072021.docx DOCX document
ATTACHMENT 4 - Notional Work Plan 04072021.xlsx XLSX spreadsheet
Contractor Unit Pricing Sheet 04072021.xlsx XLSX spreadsheet
ATTACHMENT 4 -- Notional Work Plan 3-29-21.xlsx XLSX spreadsheet
ATTACHMENT 1 -- SOW EPT BBT North TI Maintenance IDIQ Rev 03292021.pdf PDF
70B01C21R00000007 ATTACHMENT 9 PM Checklist.pdf PDF
TI Maintenance Work Plan Development Process Flowchart_3-19-21.pdf PDF
ATTACHMENT 2 -- Line Item Summary EPT BBN 3-28-21.xlsx XLSX spreadsheet
70B01C21R00000007 IT Maintenance Contractor Questions Resp 03292021.pdf PDF
RFP 70B01C21R00000007 Amendment A0002 SF30.pdf PDF
ATTACHMENT 5 -- PAST PERFORMANCE INFORMATION SURVEY 3-29-21.docx DOCX document
ATTACHMENT 8 Estimate Form 70B01C21R00000007 3-29-21.xlsx XLSX spreadsheet
Site Visit Attendees.docx DOCX document
Meeting Location for Day 1 of the site vists.pdf PDF
70B01C21R00000007 Amendment 1.pdf PDF
Site Visit Signup El Paso and Big Bend Sector.xlsx XLSX spreadsheet
Attachment 6 Wage Determination DBA Presidio Hwy.pdf PDF
Attachment 1 SOW EPT BBT North TI Maintenance IDIQ 12012020.docx DOCX document
Attachment 4a TI Design Standards_v1_Chapter 1_Sept 2012.pdf PDF
Attachment 4 Boat Ramp Design Standards.pdf PDF
Attachment 6 Wage Determination DBA El Paso Hwy.pdf PDF
Attachment 3 Inventory Asset List 12-08-2020 (003).pdf PDF
Attachment 4 Boat Ramp Detail.pdf PDF
CUS1449 - Commercial Items (SF1449).pdf PDF
Attachment 4 Submittal 01 Engineering Letter and Shop Drawings.pdf PDF
Attachment 4 TI Design Standards_v1_Chapter 3_Sept 2012.pdf PDF
RFP 70B01C21R00000007 Line Item Summary 01212021.xlsx XLSX spreadsheet
RFP 70B01C21R00000007 continuation pages.pdf PDF
Attachment 5 Notional Work Plan.xlsx XLSX spreadsheet
Attachment 4 TI Design Standards_v1_Sept 2012 - Roads Section.pdf PDF
Attachment 6 Wage Determination DBA Presidio Bldg.pdf PDF
Attachment 2 Contractor Unit Pricing Sheet final.xlsx XLSX spreadsheet
Attachment 6 Wage Determination SCA El Paso.pdf PDF
Attachment 4 TI Standards v2_Wall-Fence-Gates Drawing Updates_080618 (003).pdf PDF
Attachment 6 Wage Determination DBA El Paso Bldg.pdf PDF
Attachment 4 TI Design Standards_v1_Chapter 2_Sept 2012.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Inspection Report Form

Work Activity (WA) Number:Date(s):REV:0
WORK DESCRIPTION
TI Asset Description:Work Category:

Work Category Sub Type:

Asset Objective(s):Damage Extent:
Work Category:Location:
Work Classification:Sector:
Work Subdivisions:GPS:BEGN:
W:ENDN:

W:

Prime Lead Contact:Name:Ph:Email:
SUB Lead Contact:Name:Ph:Email:
GOV Lead Contact:Name:Ph:Email:
WORK PERFORMANCE
Inspection:Frequency:
Scope of Work:

Work Standards/ QC Metrics:

Work Duration:Days: ##WAR STATUS:Initial
ACCESS
Access Issues (including any expiration dates):Access Stakeholder(s):
Stakeholder Type:
ENVIRONMENTAL
Applicable
Environmental Regulations and Sources (_):Applicable Environmental BMPs:BMP’s reviewed and implemented?Yes
Survey by Biologist if required?No
COST
Est. Labor Costs:Act. Labor Costs:Other Notes/Photos
Est. Travel Costs:Act. Travel Costs:Other Notes/Photos

Nearest CBP facility: xxx Avg. travel time to TI asset: #.# HRS Work Classification: [routine/urgent]

POC:

Est. Equip CostsAct. Equip Costs
Est. Material Costs:Act. Material Costs:
Est. Mobilization:Act. Mobilization:
Est. Other Costs:Act. Other Costs:
Est. Total Costs:Act. Total Costs:
Prime Representative:Date:
Name, SignatureDD/MM/YYYY
Subcontractor:Date:
Name, SignatureDD/MM/YYYY
Photographs:
Before:

After:

&"Times New Roman,Bold"&24Work Activity Report

&"Times New Roman,Regular"&10 Contract # xxxxx &"Times New Roman,Regular"&10Page &P of &N &"Times New Roman,Regular"&10Revised: 04/04/2019