QA Log 1 11.23.26.pdf
PDF 110 KB Posted
- Attached to
- Mike Monroney Aeronautical Center (MMAC) Industrial Waste Water Treatment Plant Upgrades
- Solicitation number
- 6973GH-27-R-00005
About this file
This document is a Questions and Answers log for a Federal Aviation Administration (FAA) Solicitation for Information (SIR) regarding the design and construction of a new Industrial Wastewater Treatment Plant (IWTP) and related infrastructure at Will Rogers International Airport in Oklahoma City. The document addresses 89 submitted questions and RFIs from potential bidders, with responses clarifying project requirements, specifications, and contractual obligations.
Key project details include six bid options: Base (new IWTP building and infrastructure), Option 1 (demolition of existing IWTP), Option 2 (new lift station), Option 4 (forcemain replacement), Option 5 (window/canopy work), and Option 6 (upgraded flooring/wall tile finishes). The FAA retains discretion to award any combination of options at initial award. Critical requirements addressed include: proposal guarantees calculated on base plus all options with a $3M cap (Amendment 0004); proposal submission to andre.casiano@faa.gov with individual emails not exceeding 15 Megabytes (Amendment 0004); all work must be completed within 730 calendar days with phased sequencing outlined on drawing C-001; staging and laydown areas to be determined post-award; and all controls and monitoring systems to utilize Johnson Controls International (JCI) Metasys platform integrated with existing MMAC systems. The contractor is responsible for securing all required City and State permits, establishing project milestones, coordinating with Will Rogers International Airport for crane operations and vehicle access via the Commercial Vehicle Inspection gate, maintaining existing facility operations during construction, and providing detailed price breakdowns by option. Key technical clarifications address geotechnical conditions (Terracon report included in Attachment 1a), wastewater design flow rates and effluent limits (Specification 46 07 53), asbestos survey results (no asbestos or lead identified; PCB survey not conducted), and chemicals to be provided by FAA with testing on FAA influent. Relevant experience requirements mandate three Prior Project Experience Information (PPEI) forms including industrial process wastewater treatment experience exceeding $2M and two multi-discipline construction projects exceeding $5M; teaming partner PPEI forms count toward minimum standards.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
No. Reference Sheet Question Answer
1 SIR L.2
Please reconcile conflicting proposal submission email addresses: L.2(c) identifies andre.casiano@faa.gov, while L.2(f) lists andre.casiano@us.af.mil. Confirm the only authorized submission address and receipt/size-limit procedure.
Amendment 0003 was issued on November 16th which corrected SIR Section L.2(f) to list andre.casiano@faa.gov as the proposal submission email.
Additionally Amendment 0004 revised Section L.2(f) to identify that individual emails should not exceed 15 Megabytes
2 SIR Section L Please provide Amendment incorporating all site-visit answers, revised plans/specifications and an updated proposal due date if significant clarifications are issued after November 4.
All Q&A Logs will be posted to SAM.gov as they become finalized
3 SIR Section B
Confirm whether award of each option is strictly at initial award, and whether Option 1 demolition of existing IWTP may be awarded without Option 2 or 4; clarify interdependence and required temporary works included in Base.
a. The FAA's decision to award of any the bid options is strictly at initial award.
b. The FAA may decide to award Bid Option 1 and not to award Bid Options 2 or 4.
c. If the FAA elects not to award Bid Option 1, the existing IWTP building will remain in place, the forecemain will tie into the new IWTP building regardless of whether this option is taken or not.
4 SIR p.26
For the 20% proposal guarantee, confirm whether calculation includes Base plus all six options or only the evaluated combination FAA elects to award, and any cap.
The proposal guarantee calculation must include the base plus all options. The cap for the proposal guarantee is $3M.
Amendment 0004 revised Clause 3.4.1-1
8 SIR Section J
Please provide Attachment 1a, IFC Specifications Volume I revised September 29, 2026, missing from the supplied package, including all Division 01, commissioning and general requirements.
Attachment 1a, IFC Specifications Volume I revised September 29, 2026 was posted with the intial SIR posting and is labeled "Attachment 1a FAA MMAC IWTP_Specifications_IFC Volume I Rev 2026 09 29" under the Attachments section of the SAM.gov posting.
9 31 20 00 S-001 Please provide complete Terracon geotechnical report 03255131 with boring logs, location plan, groundwater records, bearing values, settlement, corrosivity and earthwork recommendations.
Complete Terracon geotechnical report is included in Attachment 1a IFC Specifications Volume I revised September 29, 2026 which is located under attachments in the SAM.gov posting
10 31 20 00 C-001 Confirm seasonal and perched groundwater levels and whether excavation support/dewatering discharge, permits, pumping treatment and disposal are contractor responsibility.
Refer to Geotechnical Report.
11 31 20 00 CG101
Confirm limits of unsuitable/contaminated soil removal, undercut depths, haul/disposal criteria and owner-directed unit prices for unforeseen material.
Refer to General Notes on CD101-CD103
12 31 20 00 C-001 Provide survey/CAD utility base map and all subsurface utility engineering records; clarify allocation of risk for unknown private utilities and conflicting line locations.
Survey and CAD files to be provided to the awarded Contractor.
All Questions/RFI's Submitted
13 01 50 00 C-001
Identify approved staging, laydown and trailer footprint, permitted stockpile height, temporary fencing, haul routes, crane access, traffic flagging and restoration extents.
Staging, laydown, trailer footprint, and temporary fencing will be discussed and determined after award. After award, the contractor will need to submit a plan for review and FAA approval for what materials they want to stockpile and at what height they are requesting and location(s). Crane access is the same as the haul route. All crane use will require a crane permit and coordination with the Will Rogers International Airport. Traffic flagging will be the resposibility of the contractor. Restoration extents include all areas impacted by the demolition or construction of the project. No storage is permitted within 20' feet of the perimeter fence. A hauling route map will be posted in an upcoming amendment
14 C-001
Confirm limits of excavation near operational buildings/pipelines and required engineered shoring/monitoring, vibration thresholds and owner review/approval time.
Limits will not be confirmed as it is up to each bidder to determine as part of their means and methods to execute the work. Excavation Preotection Plan (31 23 16) to be reviewed by the Owner. Review and approval will be similar to other construction submittals see Specification 013000 1.4.F
15 02 41 16 CD101-CD103
Provide current ACM/lead/PCB and process residue testing, manifests, disposal classifications, and accepted cleaning/decontamination standards for existing IWTP and lift stations.
There was no asbestos or lead identified during the surveys.
The asbestos survey reports will be posted to SAM.gov (Files: Asbestos Survey 186-IWT & Asbestos Survey 190-CLS).
Lead Based Paint Readings for Building 186 will be posted to Sam.gov (File: Lead Based Paint Readings 186-IWT XRF) A survey for PCBs was not conducted. Refer to C-001 for cleaning / decontamination requirements.
16 02 41 16 CD102
Clarify ownership and full quantities of sludge, chemical inventory, residual wastewater and grit requiring treatment, transport and permitted disposal before demolition.
Refer to Drawing C-001.
17 C-001 Confirm whether soils/concrete removed from existing trench must be handled as special waste in all cases and identify sampling, landfill approval, tipping fees and owner acceptance.
Refer to Drawing CD101, general note #6
18 CG101
Identify applicable OPDES/SWPPP requirements, disturbance acreage, permit holder, inspection/reporting frequency, and discharge sampling/treatment responsibilities.
Refer to Specification 015723 Storm Water Pollution Prevention; as well as, instructions for required permits.
19 46 07 53 P-series Provide the guaranteed peak, average and minimum design flow rates and influent wastewater quality basis, including pH, ORP, metals, FOG, solids and temperature/design excursions.
Performance and design criteria are provided with Specification 46 07 53, paragraph 2.1.C.
20 46 07 53 P-series Identify mandatory process equipment package vendor(s), acceptable equals and whether pilot/treatability tests or new process design validation are required.
Refer to Paragraph 2.1.A and any subsequent paragraphs.
21 46 07 53 P-series Provide basis-of-design process narrative, P&IDs, equipment schedule, instrument list and vendor responsibility matrix for packaged vs field installed elements.
Refer to D-series drawings.
22 46 07 53 P-series Clarify who provides chemicals and seed/sludge/media for commissioning, quantities, storage, safety training and first-fill costs.
Chemicals to be provided by FAA. Testing will be provided on the FAA influent, per Specification 46 07 53, 3.3.C.2.
23 46 07 53 P-series Define process performance acceptance criteria, effluent limits, sampling duration, consecutive operating days, failure/retest protocol and third-party laboratory responsibility.
Refer to Specification 46 07 53, Part 3.
24 46 07 53 P-series Define manufacturer onsite representative days, operator training hours, manuals, spare parts/consumables, warranties and remote response obligations.
Refer to Specification 46 07 53, Part 3.
25 46 07 53 P-series Confirm whether all tanks/pumps/filter presses/chemical feed/skids are contractor furnished or any equipment is government-furnished; provide delivery and factory acceptance requirements.
Refer to Specification 46 07 53
26 P-series Provide design data for available industrial wastewater flow during tie-in and any emergency storage/bypass, including maximum allowable plant outage and 24/7 monitoring requirement.
Refer to Drawing C-001
27 P-series Specify temporary bypass treatment quality, redundant pumps/power, secondary containment, alarms and permitted discharge arrangements during each cutover.
Refer to Drawing C-001
28 C-001 Provide actual horizontal/vertical forcemain lengths, pipe diameters/classes, trench section, depth range and locations of restrained joints, vaults and connection points for Option 4.
Refer to Drawing CD102 and CS102
29 C-001 Clarify separation of trench demolition, new forcemain, excavation, special disposal and bypass/temporary tie-ins between Base and Option 4.
Refer to Drawing C-001 - Phase A notes.
30 C-001 Confirm forcemain shutdown windows, exact maximum outage duration, notification/approval workflow and whether north/south segments may be worked sequentially without delay.
Information and direction is provided on Drawing C-001
31 C-001 Provide wet-well sizes/depths, pump duty points, control panel details, power utility conditions, force-main interfaces, bypass sequencing and demolition extent for Option 2.
Refer to the bid documents.
32 CD103
Confirm existing LS#2 active/inactive status, full demolition footprint and whether abandoned piping/electrical must be removed to property boundary or capped at indicated points.
LS#2 is not currently active but does exist. Demolition would be limited to definition indicated on Drawings CD103, C-001, and Specification 01 03 00
33 C-001
Provide recent lift station pump run-hours, wet well level/flow trends, operational redundancy and emergency overflow restrictions.
This information is unneccessary for the purpose of bidding this project.
34 03 30 00 S-101/S-102 Confirm all underground tank/vault water-retaining concrete testing, waterstop/waterproofing type, hydrostatic tightness testing and repair/retest obligations.
Not applicable, there are no underground concrete tanks/vaults as part of this project.
35 S-111 Provide definitive ICC 500 / IBC storm shelter occupancy, design wind/impact criteria, testing/inspection, label and specialty door/louver requirements.
Refer to Drawing G-004
36 S-001 Confirm engineered foundation design is final and no delegated redesign of foundations or slab to accommodate equipment loads is required of contractor.
Based on note Drawing S-101, the footings and piers are preliminary for bidding only. Final sizes for construction, by EOR, will be issued after selection and approval of PEMB. Refer to Specification 46 07 53, 1.3, E in relation to changes.
37 23 controls M-700 to M-704 Confirm HVAC BAS platform, JCI integration scope, licensing and whether sole-source BAS programming is owner/JCI furnished or paid by contractor.
All controls shall be by Johnson Controls International (JCI). JCI's Metasys, web-based "extended architecture" series of controls shall be provided and monitored from the Central Control and Monitoring System (CCMS) located in the Base Maintenance Building 015- BMB via the MMAC fiber-optic backbone.
MMAC utilizes the Metasys Direct Digital Controls to monitor, control, and maintain the MMAC's heating, cooling, and ventilation through hardware and software. JCI is the only responsible source to make modifications to the Metasys licensed software.
All new meters (water, gas, and electric) shall be monitored through JCI Metasys control system and be FAA compatible.
The Contractor is to provide all controls, hardware, and programming for a fully functional controls system that interfaces with the MMAC controls system. Contractor is responsible for scheduling, coordinating, and interfacing the controls with the work of other trades.
38 23 M-101 Clarify space ventilation/odor control classification, corrosion-resistant materials, chemical exhaust requirements and whether process vendor supplies ventilation controls.
Refer to Drawing M-701.
39 26 E-601/E-602 Provide confirmed incoming service capacity, utility transformer ownership, available fault current, outage approvals and new electrical service/15kV work responsibility.
Refer to Drawing E-601 and E-602.
40 26 E-112/E-113 Confirm emergency power/generator and UPS requirements for process continuity, equipment controls, storm shelter and lift stations; indicate any government furnished power.
Refer to Div 27 specifications.
41 26/46 E-113 / P-series Provide I/O point list, process PLC/SCADA architecture, HMI licensing, historian, cybersecurity acceptance and communications interface to existing FAA networks.
Refer to Div 27 specifications.
42 26 E-113 Clarify equipment vendor vs electrical subcontractor responsibilities for control wiring, VFDs, panel certifications, programming, loop checks and integrated functional tests.
This is to be determined by the Contractor and the equipment vendor.
44 C-001
Clarify whether completion of Phase C / demolition is required before substantial/final completion, and whether government operation begins before final acceptance.
Government operation could begin prior to final acceptance if Option 1 is selected. "See AMS Clause 3.2.2.3-52 Use and Possession Before the Project is Complete" included in the
SIR
45 C-001
Identify operational training completion requirements and plant operators furnished for startup/shakedown, with shift coverage and duration.
Refer to Sepcification 46 07 53, Drawing C-001 and other Div 01 specifications for guidance and requirements.
46 SIR p.1
Provide required interim milestone dates for building completion, beneficial use, continuous operation, lift station/forcemain completion, demolition and final acceptance within 730 days.
The contractor is responsible for establishing milestones for the items noted. All work must be complete and final acceptance established within 730 calendar days.
47 C-001
Confirm the allowed sequencing of Base, Options 1-4 and whether 730 days includes all awarded options, long-lead procurement, storm shelter and final performance testing.
Phased construction sequencing is outlined on C-001, if a bid option isn't taken they will bypass that step in the sequencing.
48 A-612
Confirm Option 5 window/canopy framing, structural reinforcement, waterproofing, finishes and whether Base includes wall/roof infill ready for option installation.
Base not to include any details associated with Option 5 work.
49 9 I-111 / I-600
Confirm Option 6 flooring/wall tile deductions vs additive quantities and whether base FRP and sealed concrete are to be deducted in pricing.
Refer to Attachment 1a IFC Specifications Volume I revised September 29, 2026 which is posted to SAM.gov, Section 01 03 00. Quantities to be determined by the contractor based off the contract documents. The FRP and sealed concrete are to be included in the base price. The upgrade to ceramic wall tile and chemical resistant epoxy flooring is an additive from the base price.
50 03 30 00 S-101
Provide consolidated responsibility matrix separating owner special inspections from contractor QC/testing (compaction, concrete, welding, coatings, piping and startup).
Refer to Specification 01 40 00
51 49 CFR 15/1520 G-001
Identify SSI-approved document transmission/storage and subcontractor need-to-know process;
clarify whether any documents must be redacted before vendor quotations.
Subcontractors and suppliers are in the "need to know" catagory and the documents can be shared with them without redaction for the purpose of bidding the project.
52 Attachment 10
Specify whether full-time safety representative, separate QC personnel, confined-space rescue plan and 24-hour monitoring staffing are mandated by FAA for this project.
Requirements are in attachment 10 Chapter 33 Construction Safety and contract documents.
The FAA does not mandate a full-time safety representative, separate QC personnel, or 24 hour monitoring staff. Requirements for a confined space rescue plan will be determined when applying for confined-space entry permits. Amendment 0004 incoporates revisions "Attachment 10 Chapter 33 Construction Safety Rev 11.23.26"
53 C-001 Please provide applicable industrial wastewater discharge permit, design effluent limits, operating permit transfer requirements and agency witness/approval durations.
Refer to Specification 46 07 53
54 Amend 0001
Identify required domestic content/country of origin documentation for process skids, controls, piping, steel and specialty equipment; advise procedure for unavailable domestic products.
Refer to the full text AMS Clause 3.6.4-3 Buy American Act - Construction Materials in Amendment 0001 which incorporated the clause into the SIR
55 SIR pp.1, 65
Confirm whether six-option bid must show detailed work-package cost breakdown by option and whether a separate schedule/cash-flow plan is required for each.
SIR Section L .3(e)(4) "Price Breakdown: Contractor Format, Identifying Major Components of work and overhead rates/profit rate" has been revised in Amendment 0004 to "Price Breakdown: Contractor Format, Identifying Major Components of work and overhead rates/profit rate for the base bid and each individual option"
56 C-001
List all construction permits, ODEQ approvals and City of OKC inspections required, identifying permit holder, fees and agency review durations.
FAA does not determine permits required by City and State agencies. Bidders must contact the entities for permit and inspection information. The project has been submitted to City of Oklahoma City, reference BLDC-2026-07545.
Reference AMS Clause 3.2.2.3-47 Permits and Responsibilities contained in the SIR
Please identify the designated construction truck route for deliveries, equipment, and hauling operations to and from the project site. Include the approved entrance/exit gates and any applicable vehicle restrictions.
Amendment 0004 has incorporated "Attachment 12 MMAC Delivery Truck Route Roads" Refer to Question #64
58 Note 3 C-701
Note 3 on Sheet C-701 states to provide conduit from LS Control panels to building footprint. Please define the requirement as to where this conduit it be installed? I.E. within 5’of existing building, stubbed up on exterior wall of building, brought into the inside of the exterior wall of existing building.
Note 3 refers to Sheet C-702. Refer to C-702 "Lift Station Process Control System Notes" Section 2.
Is there a size requirement for the Telecom Handhole shown on T-101 & A4/T-501 Refer to Div 27 specifications.
Is Johnson Controls responsible for bidding on the access control system and PA system for this project? If so, please confirm the required manufacturer/brand for the access control system and the required manufacturer/brand for the PA system.
The new IWTP building won't have card readers or cameras but will have security door contacts on all exterior doors. Refer to Spec Section 08 71 00 Door Hardware, Section 08 76 00 Door Hardware Schedule, Section 28 10 00 Access Control, and 27 51 16 Public Address Systems.
Can you confirm that there are no existing slabs on-site that are post tension? Historical plans have be posted to SAM.gov, these plans are for Informational Purposes Only. Contractors must field verify existing conditions
Where is the laydown yard and staging for Conex boxes for this project? Laydown yard and staging areas will be discussed and determined after award.
If space permits it's likely the adjacent parking lot area could be utilized as a laydown yard/conex staging area
Where could the GC install a job trailer? Laydown yard and staging areas will be discussed and determined after award.
If space permits it's likely the adjacent parking lot area could be utilized as a laydown yard/conex staging area
From a badging point of view, when deliveries like concrete, dumpster swapping and port-a-john cleaning happen, how do those vendors get in and out of the facility without a badge? Do those type of vendors need to be escorted in and out of the facility?
These types of deliveries must come through the Commercial Vehicale Inspection gate off of SW 74th west of S. MacArthur Blvd to sign-in and be allowed access. Badged individuals from the GC will need to give the guards their badge number and provide escort on the center.
There is a note that reads “CONTRACTOR TO ENSURE EXISTING BUILDING REMAINS
FUNCTIONAL DURING CONSTRUCTION, INCLUDING THE DEMOLITION OF THE WALL
SEPARATING THE OLD SPACE FROM THE NEW”. If it is implied that we are to ensure that the existing building remains functional, then we will require all service records on that building for the past 10 years so that we know what to expect from a maintenance standpoint.
Intent of the note is to ensure construction activities do not prevent the existing facility from maintaining current operations by the FAA. The Contractor is not required to operate and maintain the existing facility, the FAA will maintain and operate.
Guage of seamless aluminum panel on monument sign. Refer to Specification 10 14 00
What permits are required for this project?
a. What are the costs for these and who is responsible for paying for these fees?
See Response to Question #56, Refer to Div 01 specifications and AMS Clause 3.2.2.3-47 Permits and Responsibilities
Who is inspecting this project?
a. If third party inspections are required, is the GC able to utilize the testing lab of their choice?
b. Who is to pay for all testing?
Refer to Specification 01 40 00
Is weekend work acceptable for specific related items? Refer to Specification 01 01 00
Can bypass pumping be ran above ground?
a. Specifically, regarding road and access crossing?
Yes, as long as the Contractor coordinates with FAA per the Div01 specifications.
74 Trench Demolition, 5.4 Pg. C-001
Is sand blasting an acceptable means of cleaning the equipment/piping? No
75 Phase A1-Trench Demolition, 5.5 Pg. C-001
Where is the ELWTP Cyanide Waste Holding Tank located? Tank is located within the existing IWTP footprint.
76 Phase A1-Trench Demolition, 5.5 Pg. C-001
What is the capacity of the ELWTP Cyanide Waste Holding Tank and how often is it emptied? 500 gallons, frequency is use dependent.
77 Phase A1-Trench Demolition, 7 Pg. C-001
Is ALL concrete that is to be demolished and surplus soil to be disposed at a special waste at an ODEQ approved nonhazardous industrial waste landfill? If not, please be specific on exactly what is to be disposed at this location.
Refer to Drawing CD101, general note #6
Where do we set up the containment area to clean equipment/piping that is to be demo’d? Within the staging area. The location to be determined with the contractor after award.
What are the flow rates on all of the lift stations? Refer to Drawing C-601.
Where can the residual waste from cleaning be disposed of? Refer to C-001
Who is responsible for the disposal of this residual waste? Refer to C-001
Regarding chemicals needed to successfully commission the IWWTP, is the contractor required to use a specific brand?
a. i.e. Does the FAA have a current contract with a chemical supplier that would then take over providing chemical to the new plant?
b. If so, is the contractor required to utilize this company's chemical when proving the treatment process is operating as designed?
The current plant is being served by ChemTreat of Oklahoma City and we expect this to remain the same when the new plant comes on-line.
During Lift station outages if Option 1 is awarded, is the contractor or government responsible for temporarily handling industrial waste from affected buildings during the outage to the new wastewater treatment plant?
a. If contractor requirement, will the government limit building waste to just during normal business hours or is the contractor responsible for diverting waste constantly (i.e. 24 hour responsibility)?
If Option 1 is awarded, that scope of work would not start until to the completion and commissioning of the new IWTP and therefore industrial waste would be routed to the new facility while demolition of the existing is executed.
Referencing Bid Option 4, the force main will be out of service while the lines are replaced. Is the contractor or government responsible for temporarily handling industrial waste from affected buildings during the outage to the new wastewater treatment plant?
a. If contractor requirement, will the government limit building waste to just during normal business hours or is the contractor responsible for diverting waste constantly (i.e. 24 hour responsibility)?
Refer to Drawing C-001
According to Section L.3.(1) Factor 1 (Relevant Experience), the offeror is required to submit 3 PPEI forms, including two (2) multi-discipline construction projects >$5M and one (1) wastewater treatment project >$2M.
a. Please confirm the FAA is specifically looking for industrial / process wastewater treatment experience, not sanitary waste / sewage treatment.
b. Will FAA relax the dollar value threshold for the wastewater project to $500,000?
c. The SIR states, “If an offeror is proposing under Teaming Agreement, each Teaming Partner must have a minimum of one (1) PPEI form towards the required three (3) PPEI forms.” Please clarify the intent of this statement. Does this mean that one of the offeror’s three PPEI’s can be furnished by a designated teaming partner; or is the offeror still required to furnish three PPEIs on their own?
A) Industrial process wastewater treatment experience B) No C) If proposing under a teaming agreement, each teaming partner's PPEI will count toward the minimum acceptability standards under Factor 1
Can PVC pipe be used on underground sanitary sewer piping and above ground vent piping? (We were unable to find a material call out in the specifications.)
Refer to Specification 22 13 16
Are as-built drawings available for the existing Industrial Wastewater Treatment Plant building scheduled for demolition, specifically drawings showing the existing foundation, footings, and below-grade construction? If available, please provide these drawings.
Historical Plans are being provided for Informational Purposes Only in a forthcoming amendment, Contractors must verify existing conditions