Amendment 0004.pdf
PDF 92 KB Posted
- Attached to
- General Construction Multiple Award IDIQ Federal contract opportunity
- Solicitation number
- 6973GH-23-R-00020
View the file
Other files for this federal contract opportunity
Show all 35
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO.
PAGE OF PAGES
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6)
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
CODE
9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
Items 8 and 15, and returning is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required.)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14.
E. IMPORTANT: Contractor is not, is required to sign this document and return
ORDER NO. IN ITEM 10A.
1 3
0004 03/02/2023
AAQ-731 FAC. & AVIATION SAFETY ACQ
FAA AERONAUTICAL CENTER
PO BOX 25082
BLDG 014-AHQ, ROOM 233A
AAQ0731-AFN
OKLAHOMA CITY OK 73125
AAQ-811 FAC. & AVIATION SAFETY ACQ
FAA AERONAUTICAL CENTER
PO BOX 25082
MPB ROOM 380
AAQ811-AFN
OKLAHOMA CITY OK 73125
x
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By ___________ 1 x x
6973GH-23-R-00020
1 copies to the issuing office.
03/02/2023
(x)
The purpose of this amendment is to provide Addendum 2 to the Seed Project, 21-017375, Specifications and Drawings, incorporate Attachment 18, Schedule B Task Requirement, Revision 1, provide Questions and Answers 16 through 37, extend the due date for Past
Performance Surveys and extend the closing date of the SIR.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. CONTRACT AUTHORITY 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Cynthia L. Cooper
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
6973GH-23-R-00020/0004
FIRST: Addendum 2 to the Seed Project, 21-017375, Specifications and Drawings is hereby added to the SIR as Attachment 27 and detailed as follows:
1. Refer Sheet G1, Architectural Product
Requirements, Division 09 – Finishes, Paint.
Delete reference to paint systems on Drawings.
Provide system in attached Specification Section
09 91 23.
2. The following Specification sections are attached to this document and are made a part of the project.
00 00 01 SPECIFICATION LIST, REVISED
01 40 00 QUALITY REQUIREMENTS
02 41 19 SELECTIVE DEMOLITION
03 10 00 CONCRETE FORMING, ACCESSORIES, AND
SEALANTS
03 20 00 CONCRETE REINFORCING
03 30 00 CAST-IN-PLACE CONCRETE
03 35 00 CONCRETE FINISHING
09 51 13 ACOUSTICAL PANEL CEILINGS
09 65 13 RESILIENT BASE AND ACCESSORIES
09 65 19 RESILIENT TILE FLOORING
09 68 13 TILE CARPETING
09 91 23 INTERIOR PAINTING
31 05 13 SOIL MATERIALS
31 05 16 AGGREGATES
31 22 13 ROUGH GRADING
31 22 16 FINE GRADING
31 23 16 EXCAVATING
31 13 16.13 TRENCHING
31 23 23.13 GENERAL BACKFILLING
32 13 13 PORTLAND CEMENT CONCRETE PAVING
32 92 13 GENERAL SITE SODDING
SECOND: Attachment 18, Schedule B Task
Requirement, included in the Original SIR is hereby replaced with Attachment 18, Schedule B
Task Requirement, Revision 1, dated 3-23-23.
THIRD: Questions and Answers 16 through 37 are provided for all potential offerors.
FOURTH: The due date for Past Performance
Surveys is extended as follows:
From: March 23, 2023, 5:00 p.m. CT
To: March 31, 2023, 12:00 noon, CT
Continued ...
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
3 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
6973GH-23-R-00020/0004
FIFTH: The closing date for the SIR is hereby extended as follows:
From: March 28, 2023, 12:00 noon, CT
To: March 31, 2023, 12:00 noon, CT