Amendment 0003.pdf

PDF 93 KB Posted

Attached to
General Construction Multiple Award IDIQ Federal contract opportunity
Solicitation number
6973GH-23-R-00020
Issued by
Department of Transportation Federal Aviation Administration Franchise Acquisition Services

View the file

Other files for this federal contract opportunity

Other files attached to General Construction Multiple Award IDIQ, newest first.
File Type Posted
Amendment 0004.pdf PDF
Questions and Answers 16-37.pdf PDF
Addendum 2 specifications.pdf PDF
18. Schedule B Task Requirement, Revision 1 dated 3-23-23.xlsx XLSX spreadsheet
Attachment 26 21-017375 Addendum 1.pdf PDF
List of Attendees for Site Visit.pdf PDF
Attachment 25 AMP400 OC Construction contractors combined.pdf PDF
Attachment 24 EOSH documents.pdf PDF
Questions and Answers 5 through 15.pdf PDF
Amendment 0002 with attachments.pdf PDF
Amendment 0001.pdf PDF
6. WD_2.10.23.pdf PDF
20. 21-017375 CAI B50 - Specifications for Bid.pdf PDF
13. SOW Appendix F EXCAVATION PERMIT v1.pdf PDF
11. SOW Appendix D Installed Equipment Data sheet.pdf PDF
3. Contractor's Release.pdf PDF
1. Specification 01010, Statement of Work.pdf PDF
8. SOW Appendix A Submittal form.pdf PDF
22.. Past Performance Information Form.doc DOC document
15. Division 27 Communications.pdf PDF
10. SOW Appendix C AMKFM-224001 Division 27 Revision 16.pdf PDF
14. Division 26 Elecrical Requirements.pdf PDF
4. SF25 Performance Bond.pdf PDF
6973GH-23-R-00020 3-1-23.pdf PDF
21. Client Auth. Letter.pdf PDF
19. 21-017375 CAI B50 - All Drawings for Bid.pdf PDF
2. Chapter_33_Construction_Safety.pdf PDF
12. SOW Appendix E Construction waste management.pdf PDF
17. 21-017375 Task Requirement SOW.pdf PDF
7. Specification Table of Contents 01.10.2023.pdf PDF
18. Schedule B Task Requirement.pdf PDF
9. SOW Appendix B Substitution form.pdf PDF
23. Past Performance Survey.doc DOC document
16. Division 28 Electronic Safety and Security.pdf PDF
5. SF25A Payment Bond.pdf PDF
Show all 35

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

5. PROJECT NO. (If applicable)2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.NO.

PAGE OF PAGES

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6)

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

CODE

9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

Items 8 and 15, and returning is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required.)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(x) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO THE AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14.

E. IMPORTANT: Contractor is not, is required to sign this document and return

ORDER NO. IN ITEM 10A.

1 3

0003 03/02/2023

AAQ-731 FAC. & AVIATION SAFETY ACQ

FAA AERONAUTICAL CENTER

PO BOX 25082

BLDG 014-AHQ, ROOM 233A

AAQ0731-AFN

OKLAHOMA CITY OK 73125

AAQ-811 FAC. & AVIATION SAFETY ACQ

FAA AERONAUTICAL CENTER

PO BOX 25082

MPB ROOM 380

AAQ811-AFN

OKLAHOMA CITY OK 73125

x

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

separate letter or telegram which includes a reference to the solicitation and amendment number. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By ___________ 1 x x

6973GH-23-R-00020

1 copies to the issuing office.

03/02/2023

(x)

The purpose of this amendment is to provide Addendum 1 to the Seed Project, 21-017375, Specifications and Drawings, add Attachment 24, Environmental, Occupational Safety and

Health Policy, add Attachment 25, AMP400-ENV-OC-2.4.3-CC, List of Attendees for the Site

Visit held on March 14, 2023, and Questions and Answers 5 through 15.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. CONTRACT AUTHORITY 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Cynthia L. Cooper

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

6973GH-23-R-00020/0003

FIRST: Addendum 1 to the Seed Project, 21-017375, Specifications and Drawings is hereby added to the SIR as Attachment 26 and detailed as follows:

Description:

1. Refer Drawing Sheet AS1, Renovation Site Plan

Keynote J.

a. Clarification: Contractor must provide new

Garlock sleeves, waterstop collars, and Garlock

Link-Seal pipe seals, or approved equal, at foundation wall. Contractor must repair existing waterproofing membrane at foundation wall so that wall and penetrations are waterproof.

b. Sheet E5 indicates 4 separate electrical conduit penetrations.

c. Sheet M1 indicates 2 separate refrigerant piping penetrations.

2. Refer Drawing Sheet A6, change sheet total to read “8 of 24” in lieu of that shown.

3. Refer Drawing Sheet A7, A/A7 Longitudinal

Section, at note “NEW WALL-MOUNTED CURTAIN

TRACK”, delete note referring to Detail E/A10.

4. Refer Specification Section 08 71 00 – Door

Hardware, Part 4.1, Hardware Set #1, delete reference to doors being 20-minute fire rated.

5. The following specification section is attached, and hereby made a part of the project.

a. Section 12 22 00 – Curtain and Tracks, 4 pages

7. 21-017375 Drawing Sheets A3, A5, A9, & E5 are replaced with the attached.

SECOND: Attachment 24, Environmental, Occupational Safety and Health Policy is hereby added to the SIR.

THIRD: Attachment 25, AMP400-ENV-OC-2.4.3-CC is hereby added to the SIR.

FOURTH: The List of Attendees for the Site Visit are provided for all potential offerors.

FIFTH: Questions and Answers 5 through 15 are provided for all potential offerors.

Continued ...

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

3 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

6973GH-23-R-00020/0003

SIXTH: The closing date for the SIR is hereby extended as follows:

From: March 24, 2023, 5:00 p.m. CT

To: March 28, 2023, 12:00 noon, CT