About this file

This technical specification and solicitation document outlines requirements for a construction project to renovate restrooms in the Aviation Records Building at the Mike Monroney Aeronautical Center in Oklahoma City, Oklahoma. The Federal Aviation Administration is seeking firm fixed-price proposals for base work including bringing four floors of restrooms into ADA compliance through new fixtures and finishes, with five optional additions involving wall paneling, ceiling and lighting replacement, and decorative floor logos. Proposals are due May 12, 2020. The project value is estimated between $1-4 million. A pre-proposal teleconference will be held on April 29 and a site visit arranged thereafter. The solicitation is a 100% small business set-aside for 8(a) firms under NAICS code 236220.

View the file

Other files

File Type Posted
Attachment 13 Revision 5-Questions and Answers.pdf PDF
6973GH-20-R-00087-0008.pdf PDF
Attachment 13 Revision 4-Questions and Answers.pdf PDF
6973GH-20-R-00087-0007.pdf PDF
Attachment 13 Revision 3-Questions and Answers.pdf PDF
6973GH-20-R-00087-0006.pdf PDF
6973GH-20-R-00087-0005.pdf PDF
Attachment 13 Revisions 2 -Questions and Answers.pdf PDF
Attachment A- Pictures.pdf PDF
Attachment B - Arch Drawings.pdf PDF
Attachment C- Plumbing Piping Insulation.pdf PDF
Attachment 11 - Revision 2_Past Performance Survey.doc DOC document
6973GH-20-R-00087-0004.pdf PDF
PreProposal Teleconference Attendees April 29.pdf PDF
Attachment 11 - Revised_Past Performance Survey.doc DOC document
6973GH-20-R-00087-0003.pdf PDF
Attachment 13 - Revised Questions and Answers.pdf PDF
Attachment 14 - AMP-400 Construction Safety Poster.pdf PDF
6973GH-20-R-00087-0002.pdf PDF
Attachment 15 - MMAC EOSH Policy.pdf PDF
Attachment 13 Questions and Answers.pdf PDF
6973GH-20-R-00087-0001.pdf PDF
Attachment 06 - SF25A - Payment Bond.doc DOC document
Attachment 03 - ARB_IFC Drawings.pdf PDF
Attachment 04 - Chapter_33-Construction Safety.pdf PDF
Attachment 05 - SF 25 Performance Bond.pdf PDF
Attachment 10 - Past Performance Experience Form.doc DOC document
Attachment 09 - Wage Rate Decision - General Decision No OK170049 - Construction Type - Building.pdf PDF
Attachment 11 - Past Performance Survey.doc DOC document
Attachment 07 - Contractors Release.doc DOC document
Attachment 02 - ARB_IFC_Specifications.pdf PDF
Attachment 01 - Section B - Supplies or Services-Prices.xlsx XLSX spreadsheet
6973GH-20-R-00087.pdf PDF
Attachment 08 - Operational Control Documents.pdf PDF
Attachment 12 - Client Authorization Letter.docx DOCX document
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Technical Specifications Issued for Construction

Federal Aviation Administration FIELD OFFICES AND SHEDS ARB Bldg. 22 - Restroom Renovations & Upgrades 015900 - 1

SECTION 015900 - FIELD OFFICES AND SHEDS

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes:

1. Temporary field offices and sheds.

2. Maintenance and cleaning.

3. Removal.

B. Related Requirements:

1. Section 010100 - Summary of Work: Contractor use of premises.

2. Section 015000 - Construction Facilities and Temporary Controls: Temporary electricity, temporary sanitary facilities, temporary telephone.

1. Section 016000 - Material and Equipment: Storage and protection

1.2 USE OF EXISTING FACILITIES

A. Field offices and/or storage may be located within the renovation area or at a designated location on the property. Protect all finishes and replace as necessary at completion of work.

B. Refer to Sheet A-002 for Conceptual Site Layout During Construction

PART 2 - PRODUCTS

2.1 Materials, Equipment, Furnishings: Serviceable, new or used, adequate for required purpose.

PART 3 - CONSTRUCTION

3.1 TEMPORARY FACILITIES

A. Portable or mobile buildings, or buildings constructed with floors raised above ground, securely fixed to foundations, with steps and landings at entrance doors.

B. Construction: Structurally sound, secure, weather tight enclosures for office and storage spaces.

Maintain during progress of Work; remove at completion of Work.

C. Temperature Transmission Resistance of Floors, Walls, and Ceilings: Compatible with occupancy and storage requirements.

D. Exterior Materials: Weather resistant, finished in one color acceptable to Architect/Engineer.

ARB Bldg. 22 - Restroom Renovations & Upgrades 015900 - 2

E. Interior Materials in Offices: Sheet type materials for walls and ceilings, pre-finished or painted;

resilient floors and bases.

F. Lighting for Offices: 50 ft-C at desk top height, exterior lighting at entrance doors.

G. Fire Extinguishers: Appropriate type fire extinguisher at each office and each storage area.

H. Interior Materials in Storage Sheds: As required to provide specified conditions for storage of products.

3.2 CONTRACTOR OFFICE AND FACILITIES

A. Telephone: As specified in Section 001500.

B. Furnishings in Meeting Area: Conference table and chairs to seat at least eight persons; racks and files for Contract Documents, submittals, and project record documents.

C. Other Furnishings: Contractor's option.

D. Equipment: One 10 inch outdoor weather thermometer.

3.3 STORAGE AREAS AND SHEDS

A. Size to storage requirements for products of individual Sections, allowing for access and orderly provision for maintenance and for inspection of products to requirements of Section 001600 - Material and Equipment. Fill and grade sites for temporary structures to provide drainage away from buildings.

3.4 TEMPORARY TOILET FACILITIES FOR FAA PERSONNEL USE ONLY

A. Provide a high quality toilet trailer near the south entrance to the building for FAA personnel use only. The trailer shall include one 2 stalls and 2 urinals in the male restroom plus one ADA stall furnished with a sink 2 sinks. toilet, and urinal, one Include 4 stalls and 2 sinks in the female restroom. Provide one unisex ADA restroom, each with a sink and toilet. The trailer shall be completely self-contained and is operable using a 110 volt outlet for the lights, and heat or and air conditioner. Water is supplied to portable bathroom rentals by a spigot and garden hose or a 125 200 gallon on-board fresh water holding tank. The unit shall house a 450 gallon waste holding tank. The unit shall contain flushing porcelain toilets, sinks with running hot water, vanities and mirrors, soap and paper towels, toilet paper dispenser, trash container, air conditioning, heat and ventilation, low level outdoor lighting, occupancy light indicators, dual handrails and low entry platforms. Provide all required utility hook-ups.

B. The Contractor shall provide janitorial services and supplies for the employee trailer during the construction phase when any one of the restrooms are not fully functional.

3.5 INSTALLATION

A. Install office spaces ready for occupancy 15 days after date fixed in Notice to Proceed.

ARB Bldg. 22 - Restroom Renovations & Upgrades 015900 - 3

B. Parking: To be coordinated with FAA.

3.6 MAINTENANCE AND CLEANING

A. Weekly janitorial services for offices; periodic cleaning and maintenance for office and storage areas.

B. Maintain approach walks free of mud, water, and snow.

3.7 REMOVAL OF TEMPORARY FACILITIES

A. At completion of Work remove buildings, foundations, utility services, and debris. Restore work spaces, storage, offices and site areas to original conditions

END OF SECTION 015900