Attachment J.21 Project Schedule Example Waco TX.pdf
PDF 2 MB Posted
- Attached to
- Direct Current Back-Up System (DC BUS) Power Supply Federal contract opportunity
- Solicitation number
- 693KA8-20-R-00008
About this file
This solicitation requests proposals for life cycle in-service support of direct current back-up system (DC BUS) uninterruptible power supplies. The Federal Aviation Administration (FAA) requires DC BUS equipment to provide conditioned, uninterruptible electrical power to support critical National Air Space communication and electronic equipment. The anticipated contract is an Indefinite Delivery Indefinite Quantity contract with a base period of two years and four two-year options, for a potential period of performance of ten years. Proposals are due by 2:00pm EST on March 27, 2020. Questions are due by 2:00pm EST on March 10, 2020, and the FAA will post responses by 5:00pm EST on March 18, 2020. The contract type is anticipated to be IDIQ with a single award, though the FAA reserves the right to make multiple awards or no award.
View the file
Other files for this federal contract opportunity
Show all 50
Direct Current Back-Up System (DC BUS) Power Supply has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ID Task Name Duration Start Finish
2 Pre Con Meeting 1 hr 10/3/17 10/3/17
3 Arrive at site stage tools 1 hr 10/3/17 10/3/17
4 Delivery of materials/equipment
3 hrs 10/3/17 10/3/17
5 Stack batteries 1 hr 10/3/17 10/3/17
6 Anchor DC Bus 1 hr 10/3/17 10/3/17
7 DC Bus AC Input Tasks 4 days 10/3/17 10/6/17
8 Run PCU conduit 1 day 10/3/17 10/3/17
9 Run inverter conduit 1 day 10/4/17 10/4/17
10 Run PCU wire from dc bus
1 day 10/5/17 10/5/17
11 Run inverter wire from DC bus
1 day 10/6/17 10/6/17
12 TERMINATE PCU AND
INVERTER CIRCUITS IN AC
PANEL**FULL SCHEDULED
OUTAGE 1**
4 hrs 10/10/17 @
10/10/17 @1200
13 Turn up and Test DC Bus 4 hrs 10/10/17 10/10/17
14 DC Bus Familiarization Overview to SSC
0 days 10/11/17 10/11/17
15 Battery Installation 6 days 10/3/17 10/12/17
16 Turn up UXTM 1 day 10/11/17 10/11/17
17 New Battery Resistive load test
6 hrs 10/11/17 10/11/17
18 UXTM Familiarization Overview to SSC
0 days 10/12/17 10/12/17
19 New DC Distribution Tasks 6 days 10/5/17 10/13/17
20 Modify wire way 1 day 10/5/17 10/5/17
21 Run new cables 1 day 10/10/17 10/10/17
22 Terminate cables at DC Bus
2 days 10/11/17 10/13/17
23 ERMS INSTALLATION
TASKS
4 days 10/5/17 10/11/17
24 Mount ERMS 3 hrs 10/5/17 10/5/17
25 Run inveter input to ERM4 days 10/5/17 10/12/17
26 Run circuit to DC Bus 1 day 10/10/17 10/10/17
27 Run output circuit to FTI 1 day 10/10/17 10/10/17
28 Test and turn up ERMS 2 hrs 10/13/17 10/13/17
29 DC Bus Inverter Output Circuits
3 days 10/10/17 10/12/17
30 Run conduit to
FTI/NAVCOM
1 day 10/10/17 10/10/17
31 Run circuit fm DC Bus to
FTI/NAVCOM
1 day 10/11/17 10/11/17
32 Test inverter output circuits
1 hr 10/12/17 10/12/17
33 DC BUS & UXTM
FAMILIZARIZATION
34 CUT OVER TO NEW DC
BUS**FULL SCHEDULED
OUTAGE 2**
1 day 10/13/17 @0700
10/13/17 @1700
35 Wire Radios to DC Bus term strip in Radio Racks **PART OF FULL
SCHEDULED OUTAGE
2**
5 hrs 10/13/17 10/13/17
36 Transfer FTI/TELCO to new DC Bus**PART OF
FULL SCHEDULED
OUTAGE 2**
2 hrs 10/13/17 10/13/17
37 FAA to De energize old
DC BUS **PART OF
FULL SCHEDULED
OUTAGE 2**
1 hr 10/13/17 10/13/17
38 Remove Old DC Bus Circuit in AC Panel
**PART OF FULL
SCHEDULED OUTAGE
2**
2 hrs 10/13/17 10/13/17
39 VERIFY ERMS RMLS
REPORTING
0.5 days 10/13/17 10/13/17
40 Remove Old DC Bus 1 day 10/16/17 10/16/17
41 Remove old batteries 1 day 10/16/17 10/16/17
42 CAI Project Complete 0 days 10/16/17 10/16/17
10/11
10/12
10/16
T W T F S S M T W T F S S M T Oct 8, '17 Oct 15, '17
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration‐only
Manual Summary Rollup
Manual Summary
Start‐only
Finish‐only
Deadline
Progress
Waco, TX (ACT) RCAG DC BUS PROJECT
Waco, TX (ACT) RCAG DC BUS PROJECT
RED TASK NAME INDICATES
INCREASED RISK FOR
OUTAGE
Attachment J.21 Project Schedule Example Waco TX
SIR 693KA8-20-R-00008