Attachment J.08 DC BUS CAI and StartUp Chceklist.pdf
PDF 43 KB Posted
- Attached to
- Direct Current Back-Up System (DC BUS) Power Supply Federal contract opportunity
- Solicitation number
- 693KA8-20-R-00008
About this file
This document includes an attachment checklist for a Direct Current Backup System (DC BUS) power supply installation contractor acceptance inspection and startup. The Federal Aviation Administration is seeking life cycle support services for DC BUS uninterruptible power supplies through an Indefinite Delivery Indefinite Quantity contract with a potential 10-year period of performance. The checklist outlines inspection and testing requirements for equipment installation, rectifier installation and startup, control panel startup, monitoring unit installation and setup, battery startup and baseline data collection, documentation, training, spare parts, and clean-up. Contractors must meet all requirements and obtain signatures from the FAA and resident engineer to complete the acceptance inspection.
View the file
Other files for this federal contract opportunity
Show all 50
Direct Current Back-Up System (DC BUS) Power Supply has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SIR 693KA8-20-R-00008
ATTACHMENT J.8
DC Bus System Installation
Contractor Acceptance Inspection (CAI) and Startup Checklist
Location:
(City/State/Facility Type/Ident)
Inspection Date:
Startup Date:
Meets Requirements
Does Not Meet Requirements
Equipment Installation
1. DC Power System ___________ ______________
2. Batteries ___________ ______________
3. Grounding ___________ ______________
4. Power, and Control, Signal Cables ___________ ______________
5. ERMS Equipment ___________ ______________
6. DC Bus System status (through ERMS) validated with Tandem Simulation Software provided by the FAA
7. Visually inspect the physical and mechanical condition of the DC BUS System
8. Verify proper connection (tight) of all electrical connections. ___________ ______________
Rectifier Installation / Startup
1. Verify all DC wiring and AC wiring to the rectifiers for proper installation practices
2. Verify proper AC fusing at the AC panel ___________ ______________
3. Verify pre-installed alarms are being reported ___________ ______________
4. Adjust Power Plant to the proper voltage settings ___________ ______________
Control Panel Startup
1. Verify/Adjust System High Voltage Shutdown set point ___________ ______________
2. Verify High Voltage Shutdown restart operation ___________ ______________
3. Verify Low Voltage Disconnect/Reconnect set points ___________ ______________
4. Verify High Voltage alarm set point ___________ ______________
5. Verify Low Voltage alarm set point ___________ ______________
6. Verify Low Current alarm set point ___________ ______________
7. Verify alarms to their remote alarm point ___________ ______________
Monitoring Unit Installation / Setup
1. Verify all required connections have been terminated ___________ ______________
2. Program software ___________ ______________
3. Set parameters ___________ ______________
4. Checked all analog inputs for calibration ___________ ______________
5. Checked all binary input for proper operation ___________ ______________
6. Check all relay output for proper alarm trigger ___________ ______________
Overall System Startup
1. DC Power System Startup ___________ ______________
2. DC Power System Alarm Programming ___________ ______________
Contractor Acceptance Inspection (CAI) Checklist
Meets
Requirements Does Not Meet Requirements
Battery Startup / Baseline Data
1. Ensure the Battery drops are connected to the correct polarity ___________ ______________
2. Verify batteries are strapped properly ___________ ______________
3. Verify battery connections have proper torque per manufacturer’s specifications
4. Capacity Test Results ___________ ______________
5. Individual Cell Voltage Readings ___________ ______________
6. Battery Terminal Voltage Readings ___________ ______________
7. Internal Resistance Readings ___________ ______________
8. Intercell Connection Resistance Readings ___________ ______________
9. Ambient Temperature ___________ ______________
10. Temperature of the negative terminal of each cell/unit of battery ___________ ______________
11. UXTM Startup and Report (see J.9) ___________ ______________
Documentation Provided
1. Technical Product Manuals ___________ ______________
2. Maintenance Manuals ___________ ______________
3. Operation Manuals ___________ ______________
4. LRU Replacement Procedures ___________ ______________
5. Schematics __________ ______________
6. Illustrated Parts Breakdown ________ ______________
7. DC System Parameter Settings ___________ ______________
8. ERMS Documentation Provided with P1 Panel ___________ ______________
9. UXTM Documentation (see J.9) ___________ ______________
System Startup/Operations Training Conducted
1. System block diagrams ___________ ______________
2. Subsystem interface(s) ___________ ______________
3. General parameters ___________ ______________
4. Maintenance concept/responsibilities ___________ ______________
5. Verification of operational/functional checks IAW manufacturer’s instructions
6. Verification of routine preventive or corrective maintenance tasks utilizing checks/procedures established for the DC BUS System
7. System fault isolation/diagnostics ___________ ______________
8. Site diagnostics ___________ ______________
9. Remote site diagnostics ___________ ______________
10. Prevention of system security violations ___________ ______________
11. Demonstrate use of personal protection equipment ___________ ______________
Contractor Acceptance Inspection (CAI) Checklist
Meets Requirements
Does Not Meet Requirements
Spares Provided ___________ ______________ New Test Equipment Provided __________ ______________ Affected Facility As-Built Drawings Red-Lined and left onsite. __________ ______________ DC Bus System Standard Installation Drawings Provided to facility with all DC Bus System Power Terminations Identified
ERMS Installation Drawings Provided __________ ______________
Facility Cleaned ___________ ______________ Disposal Documentation Provided ___________ ______________ Copy of DC System Warranty Provided ___________ ______________ Copy of Battery Warranty Provided ___________ ______________
Comments: ___________________________________________________________________________
DC BUS Data Make: Model:
Serial #: kVA: kW:
Software Version:______________ Firmware Version:___________________
Battery Data Make: Model:
# of Strings: Jars/string: Cells/Jar: Float/Cell:
SIGNATURES: (Indicate initial acceptance of the DC Bus System by the FAA if all requirements are met.)
SSC Representative Resident Engineer (RE)
Name______________________Phone___________ Name_______________Phone_______
Contractor Representative
Name______________________Phone___________
| DC Bus System Installation |
| DC Bus System Installation |