This document includes technical specifications for testing direct current backup systems (DC BUS) and associated batteries as part of a federal contract opportunity. The Federal Aviation Administration is seeking life cycle support services for DC BUS power supplies to provide uninterruptible power to critical air traffic equipment. Offerors must comply with submission instructions by March 10, 2020. Questions are due by this date as well, with answers to be posted by March 18th. Proposals are due March 27th. The contract will have a two-year base period and four two-year option periods, for a potential ten-year term. The specifications describe required tests for DC BUS units, batteries, system operation, and load performance. Test procedures, equipment, recording parameters, and pass/fail criteria are defined.

View the file

Other files for this federal contract opportunity

Other files attached to Direct Current Back-Up System (DC BUS) Power Supply, newest first.
File Type Posted
Section L _Instructions Conditions and Notices to Offerors_AMEND 00004.pdf PDF
SF 30 _ Amend 00004.pdf PDF
Section M _Eval Factors For Award_Amend 00004.pdf PDF
Section L _Instructions Conditions and Notices to Offerors_AMEND 00003.pdf PDF
FAA Response to Questions Requests for Clarifications_Amend 00003.pdf PDF
Section L_Instructions Conditions and Notices to Offerors_Amend 00002.pdf PDF
SF 33_Amend 00001 and 00002.pdf PDF
Attach J.01 DC BUS Specification_Amend 00002.pdf PDF
Section B.4_Price Schedule_Amend 00002.xlsx XLSX spreadsheet
Section F_Deliveries or Performances_Amend 00002.pdf PDF
Attach J.02 CDRLs and DIDs _Amend 00002.pdf PDF
FAA Responses to Questions Requests for Clarifications_ Amend 00002.pdf PDF
Section M_Evaluation Factors For Award_Amend 00002.pdf PDF
DC BUS Section L _ Information for ConsiderationAffecting Offeror Proposal Submission_AMENDMENT 00001.pdf PDF
Attachment J.04 SOP FAA Field Site Requests.pdf PDF
Attachment J.09 DC BUS UXTM CAI Checklist.pdf PDF
Attachment J.03 DC BUS Frequently Used Acronyms.pdf PDF
Section B.4_Price Schedule.xlsx XLSX spreadsheet
Attachment J.10 DC BUS Grounding Requirements.pdf PDF
DC BUS Section L _ Information for ConsiderationAffecting Offeror Proposal Submission.pdf PDF
Attachment J.18 DC BUS CDLS Cumulative Warrantied Orders.xlsx XLSX spreadsheet
Attachment J.16 DC BUS CDLS Quarterly Tracking Trending and Cost.xlsx XLSX spreadsheet
Attachment J.29 FAA Form 3900-17.pdf PDF
Section J _ List of Attachments .pdf PDF
Attachment J.14 CDLS User Guide.pdf PDF
Attachment J.27 Business Declaration.docx DOCX document
Attachment J.20 DC BUS CDLS Depot Inventory.xlsx XLSX spreadsheet
Attachment J.25 DC BUS Equipment Characteristics - L.3.xls XLS spreadsheet
Attachment J.17 DC BUS CDLS Quarterly Depot Shipments.xlsx XLSX spreadsheet
Attachment J.05 FAA-STD-028C.pdf PDF
Section M _ Evaluation Factors for Award.pdf PDF
Section G _ Contract Admin Data.pdf PDF
Attachment J.02 CDRLs and DIDs.pdf PDF
Attachment J.28 FAA Order 4600.27C.pdf PDF
Attachment J.01 DC BUS Specification.pdf PDF
Attachment J.12 PreConstruction Conference Agenda and Checklist.pdf PDF
Section F _ Deliveries or Performances.pdf PDF
Section D _ Packaging Marking.pdf PDF
Section I _ Contract Clauses.pdf PDF
Section C _ Statement of Work.pdf PDF
Attachment J.11 Excavation and Handling of Contaminated Material.pdf PDF
Attachment J.30 FAA Order 6950.27A.pdf PDF
Attachment J.23 Module Performance - L.1.doc DOC document
Section E _ Inspection Acceptance.pdf PDF
Attachment J.21 Project Schedule Example Waco TX.pdf PDF
Attachment J.19 DC BUS CDLS Cumulative Spare Orders Depot Receipts.xlsx XLSX spreadsheet
Section H _ Special Contract Requirements.pdf PDF
Attachment J.07 FAA Form 3900-20_Pre-Construction and Maintenance Checklist.pdf PDF
Attachment J.24 DC BUS Module Performance - L.2.xls XLS spreadsheet
Attachment J.22 DC BUS Past Performance Questionnaire.doc DOC document
Show all 50

Direct Current Back-Up System (DC BUS) Power Supply has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

9/23/19

ATTACHMENT J.6 DC BUS INSTALLATION TEST

The DC BUS installation contractor shall perform all DC BUS system tests, including batteries, and disconnecting devices as needed to certify the proper operation of the system as a whole.

1. DC BUS start-up must be completed before beginning system test. See Section J, Attachment J.1 Paragraph 3.1.

2. The DC Bus installation Contractor shall provide all testing and monitoring equipment required to conduct site test.

3. The Installing Contractor shall provide electricians for site test, as needed.

4. Load banks and load bank cables as required for site testing shall be provided and operated by the Installing Contractor.

1.0 DC BUS Test

1.1 DC BUS Unit

a. DC BUS Data

1) Make: Model:

2) Serial #: kVA: kW:

b. Battery Data

1) Make: Model:

2) # of Strings: Jars/string: Cells/Jar: Float/Cell:

1.2 Heat Run.

Operate the entire system continuously for four (4) hours at full load. Record: rectifier output voltage, current; Inverter output voltage, current and frequency at one hour time intervals to verify stability of the DC BUS output. Also monitor and record the room temperature throughout the heat run. After 4-hours, perform an infrared scan of DC BUS module, DC BUS input and output breaker(s), and DC BUS battery connections. During the Heat Run verify that all operating controls, alarms, meters and mimic lights are functioning properly.

1.3 Steady-State Test

1. Connect the multi-functional Power Quality Meter (PQM) to the input of the DC BUS to be tested.

2. Record the input voltage, current, power, Power Factor, and Total Harmonic Distortion

(THD) (voltage and current distortion). Record, on the data sheets, the input voltage and current readings from the PQM recorder and from the DC BUS display panel at the following load levels:

a) 100% load.

b) 50% load.

c) No load (0% load).

3. Connect the PQM recorder to the 24 volt DC bus, output of the rectifier(s).

4. Record DC bus output voltage, current, power. Record, output voltage and current readings from the PQM recorder and from the DC BUS display panel at the following load levels:

a) 100% load.

b) 50% load.

c) No load (0% load).

1.4 Transient Load Tests

1. Connect the PQM waveform recorder to the 24 volt DC bus, output of the rectifier(s).

2. Recovery shall meet or exceed the vendor’s declared recovery time and steady state value.

SIR 693KA8-20-R-00008

ATTACHMENT J.6 DC BUS INSTALLATION TEST

3. Record the following load step transients with the waveform recorder:

a) 0% - 50% - 0%.

b) 0% - 100% - 0%.

2.0 System Battery Test: The objective of this test is to verify the compatibility of the batteries with the associated DC BUS and to verify the full load operation of each unit for the reserve time specified.

1. Prior to the start of the test, the battery shall be floated at the required voltage for the time specified by the battery vendor. Measure and record the resistance of all inter-cell and inter-tier connections using a micro-ohmmeter.

2. DC BUS is tested using Installation Contractor supplied loads and load bank(s). The 100% linear load is distributed as follows: One inverter connected without a load, second inverter output load at 800 Watts; remaining load is 24 volt DC from distribution panel.

3. After successfully battery load test, recharge batteries of system to 95% capacity, after which time perform full load test or service test as specified by the FAA using the appropriate procedure located in Attachment J.1, Section 3.2.

4. Close DC BUS AC input circuit breaker. Upon successful completion of the battery tests and after the batteries have a chance to reach their normal charge and temperature, take a full set of cell voltage readings.

5. After completion of discharge testing, torque connections varying by more than ±10% of average voltage.

6. Compare the battery discharge test data with the battery manufactures battery charts. Note any differences.

3.0 Complete battery data and checklist, Sheets 1 and 2, found in Appendix 1 to Section J, Attachment J.6.

APPENDIX TO ATTACHMENT J.6 DC BUS INSTALLATION TEST

Note & Record All battery Manufacturer Data on Battery Load Test Data Sheet (next tab)

Check for Cell Cracks or Electrolyte Leakage on Flooded Cells.

Check for Corrosion & Post Seal Integrity.

Check integrity of Battery Racks.

Check and Record Ambient Temperature and Ventilation.

Obtain initial Cell Corder data of battery string(s).

Measure and record total battery system (string) voltage.

Measure and record individual cell voltages.

Perform Internal Cell Resistance and Intercell Resistance Tests.

Provide hard copy of Cell Corder data.

Disconnect battery string to be tested using installed disconnect device or by disconnecting the negative cable connection and insulating.

Connect Load Bank to Battery Quick Disconnect

Initiate Load (Capacity) Test for 4 hours of testing, at the Battery

Manufacturer's recommended Load to 1.75 VPC. For battery designs with loads exceeding the 4-hour test value, a 6-hour test must be performed.

Record discharge data on Battery Load Test Data Sheet Record measured capacity (in %) on Battery Load Test Data Sheet

After at least 12-hours of recharge, initiate off-line recharge of tested string.

Upon completion of charge, place string back on-line. Record any battery problems in "Notes" section of Battery Load Test Data Sheet.

Battery Load Test and Baseline ok See Comments ok See Comments ok See Comments ok See Comments ok See Comments ok See Comments ok See Comments ok See Comments ok See Comments ok See Comments ok See Comments ok See Comments ok See Comments ok See Comments ok See Comments ok See Comments ok See Comments ok See Comments

ATTACHMENT J.6 APPENDIX 1 - DC BUS INSTALLATION TEST

Customer :

Site :

City: State:

Contact: On Site Date:

Battery Manufacturer Battery Model Battery AH Battery String Site Reserve Time

Installers 1).

2).

3).

4).

SERIAL

AS

RECEIVED

CELL

VOLTAGE

(OPEN

CIRCUIT)

CELL

VOLTAGE

UNDER

LOAD

(START

OF TEST)

CELL

VOLTAGE

AFTER

RECHARGE

CELL TEMP.

(NEG. POST

OF CELL)

BATTERY ON DISCHARGE (MINUTES)

CELL

NO. 0

10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170 180 190 200 210 220 230 240

Cell 1

Pa ge

Y es o r N o

Cell 2 Cell 3 Cell 4 Cell 5 Cell 6 Cell 7 Cell 8 Cell 9

Cell 10 Cell 11 Cell 12

C on tin ue d N ex t

Total Batt Voltage

Amb. Temp

Test Amps

% Capacity (Tested)

NOTES:

ATTACHMENT J.6 APPENDIX 1 - DC BUS INSTALLATION TEST

SERIAL

AS

RECEIVED

CELL

VOLTAGE

(OPEN

CIRCUIT)

CELL

VOLTAGE

UNDER

LOAD

(START

OF TEST)

CELL

VOLTAGE

AFTER

RECHARGE

CELL TEMP.

(NEG. POST

OF CELL)

BATTERY ON DISCHARGE (MINUTES)

CELL

NO. __

Cell __

Pa ge

Y es o r N o

Cell __ Cell __ Cell __ Cell __ Cell __ Cell __ Cell __ Cell __ Cell __ Cell __ Cell __

C on tin ue d N ex t

Total Batt Voltage

Amb. Temp

Test Amps

% Capacity (Tested)

NOTES:

Attachment J.6
Battery Test Appendix 1 Attachment J.6
Attachment J.6 Appendix 1