Questions and Answers_Amendment0004_Nov25.docx
DOCX document 124 KB Posted
- Attached to
- Amendment 0008- Environmental Remediation Support Services Federal contract opportunity
- Solicitation number
- 692M15-19-R-00005
About this file
This is a screening information request (SIR) for environmental remediation support services at the William J. Hughes Technical Center located at Atlantic City International Airport in Pomona, New Jersey. The Federal Aviation Administration (FAA) seeks to award an indefinite delivery/indefinite quantity contract with a ten-year period of performance to perform operations and maintenance, remedial action construction, and Geographic Information Systems/Global Positioning System tasks. Key requirements include treatment plant operations, groundwater remediation systems maintenance, and data repository management. The North American Industry Classification System code is 562910 and the size standard is 750 employees. Interested parties should submit any questions to the contracting officers by the dates provided in Section L of the SIR. Proposals are due according to the schedule in Section L. The FAA will award one contract as a best value procurement.
View the file
Other files for this federal contract opportunity
Show all 39
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question#
| Solicitation Reference |
| Discussion |
| Question |
| FAA Response |
1) RFP Section L – Instructions, Conditions, and Notices to Bidders, 3.2.4-1 Type of Contract (Apr 1996)-Page 60/82.
2) RFP Section I – Contract Clauses, 3.2.4-4 FIXED- PRICE CONTRACTS WITH ECONOMIC PRICE ADJUSTMENT-LABOR AND MATERIAL (APR 1996)- Page 22/62;
3) File B-001-CLIN Structure-Pricing Schedule.xlsx Clause 3.2.4-1 states the FAA contemplates award of a hybrid contract to include time and materials and fixed price line items resulting from this Screening Information Request. The RFP incorporates the following contract clause by reference: 3.2.4-4 FIXED-PRICE CONTRACTS WITH ECONOMIC PRICE ADJUSTMENT-LABOR AND MATERIAL (APR 1996) but B-001-CLIN_Structure-Pricing_Schedule only references FFP CLINs.
| To which FFP CLINs on B-001- CLIN_Structure- Pricing_Schedule.xlsx does clause 3.2.4-4 apply? |
| Clause 3.2.4.4 applies to fixed price CLINS 1,3,4 and 5. |
| C-001_Statement of Work; Site Visit – Issued Thumb- Drives |
| The Statement of Work lists Appendices A thru J on page 3 of 56, which were not provided with the RFP. The thumb drive provided on the site visit does not contain |
Appendices A, B, C, D, E, F, I or J.
| How are offerors to gain access to Appendices A, B, C, D, E, F, I and J? |
| Please see attachments “ERSS Thumbdrive Appendices File List_Amendment0004” and “ERSS Thumbdrive FAA Superfund Repository File List_Amendment0004”, which provides specifics regarding what was included on each thumb drive, including the referenced Appendices. |
| RFP 629M15-19-R-00005 and C-001_Statement of Work |
| In order to accurately estimate costs and any escalation associated with costs requires an expected contract start date. |
| What is the expected Contract Start Date? |
| For bidding purposes, the Offerors should assume a full performance start date of April 1, 2021, with a transition period prior to that performance start date. This does not commit the Government to a performance start date of April 1, 2021. |
| 1) C-001_Statement of Work; Section 2.3.1.6. Site System Maintenance General Maintenance 2) B-001- CLIN Structure-Pricing Schedule; Worksheet Tab B- 001 CLIN 0003; SUBTASKS 5 & 6 |
| B-001-CLIN Structure-Pricing Schedule; Worksheet Tab B- 001 CLIN 0003; SUBTASKS 5 & 6 both refer to SOW Section |
2.3.1.6 and both include Other Direct Costs on rows 27 and 29, respectively.
Please clarify which specific paragraphs of SOW section
2.3.1.6 should be estimated as part of/belonging to SUBTASK 5?
SUBTASK 5 pricing should include the following items identified in SOW Section 2.3.1.6 Site System Maintenance: Subsection "General Maintenance" and the following Subsections of Subsection "General Maintenance," "Maintenance Supplies and Spare Parts", "Preventative Maintenance", "Corrective Maintenance", and "Other Direct Costs". The following items from SOW Section 2.3.1.6 Site System Maintenance, which are Subsections of Subsection “General Maintenance,” should be included in SUBTASK 1 pricing: "Housekeeping", "Trash Removal", "Grass, Weed, and Brush Cutting Services", and "Snow Removal Services".
1) C-001_Statement of Work; Section 2.3.1
2.3.1. Scope of Work by Remediation System 2) B- 001-CLIN Structure-Pricing Schedule; Worksheet Tab B-001 CLIN 0003 - All SUBTASKs SUBTASK 1 / SOW Section 2.3.1 includes subsections 2.3.1.3, 2.3.1.4, 2.3.1.5 and 2.3.1.6 (but not 2.3.1.2) which all Separate SUBTASKS.
So that offerors don't duplicate any costs in the SOWs subsections under Section 2.3.1, will the FAA provide the specific paragraph and/or sections for each of the subsections 2.3.1.3, 2.3.1.4,
2.3.1.5 and 2.3.1.6 which don't apply to SUBTASK 1?
Sections are to be priced to the following subtasks:
· SOW Section 2.3.1.3 -> SUBTASK 2
· SOW Section 2.3.1.4 -> SUBTASK 11
· SOW Section 2.3.1.5 -> SUBTASK 11
· SOW Section 2.3.1.6 -> SUBTASK 5 pricing should include the following items identified in SOW Section 2.3.1.6 Site System Maintenance: Subsection "General Maintenance" and the following Subsections of Subsection "General Maintenance," "Maintenance Supplies and Spare Parts", "Preventative Maintenance", "Corrective Maintenance", and "Other Direct Costs". The following items from SOW Section 2.3.1.6 Site System Maintenance, which are Subsections of Subsection “General Maintenance,” should be included in SUBTASK 1 pricing: "Housekeeping", "Trash Removal", "Grass, Weed, and Brush Cutting Services", and "Snow Removal Services".
Environmental Remediation Support Services (ERSS) Contract Solicitation 692M15-19-00005 Amendment 00004 Comment/Response Matrix
| Comment # |
| Solicitation Reference |
| Discussion |
| Question/Comment |
| FAA Response |
| 1) C-001_Statement of Work; Section 3.0 Environmental Requirements 2) B-001-CLIN Structure-Pricing Schedule; Worksheet B-001 CLIN 0003, SUBTASK 4. |
| SOW Section 3 Environmental Requirements provides many requirements the contractor must meet including compliance with regulations, data standards, permits, Hazardous/Non-Hazardous Waste Management, Off-site Disposal of Materials/Waste ("The OMC must remove and dispose of off-site, at an approved disposal facility, all unacceptable and rejected chemicals or carbon."), Fuel and Chemical Spill and Radiological Equipment permitting. The requirements referred to, however, do not include |
| Will the FAA please provide all of the specific work load, copies of all environmental permits at the site and their associated fees, and all available data to allow offerors to estimate the "Other Direct Costs" associated with SUBTASK 4 OR |
| The ERSS Contractor is to perform the required work in compliance with all federal, state, and local laws. Generally, cost of permits are usually needed under CLIN 001 (Remedial Action Construction) and will be identified in the task SOW. The ERSS Contractor may have costs associated with personnel maintaining required certifications and continuing education costs; these are priced under SUBTASK 4. |
| specifics with regards to the regulations, permits, quantities of Hazardous/Non-Hazardous Waste Management, Off-site Disposal of Materials/Waste, Fuel and Chemical Spills standards referred to. Without specific workload, copies of all permits and their associated fees, number of hazardous/Non-Hazardous incidents, volumes of all waste streams, removal requirements, etc.....it is not possible to accurately estimate the cost for SUBTASK 4. |
| consider changing SUBTASK 4 to a "FAA Provided Quantity and Cost" SUBTASK a using an NTE value for SUBTASK 4 similar to SUBTASK 6? |
| 1) C-001_Statement of Work and Site Visit - Issued files |
| There is no workload history or data which clearly describes the requirements for any of the "Subcontractors" categories under CLIN III's SUBTASKs 1, 2, 4, 5, 7A, 10A or 11 from which to base a cost estimate on. In order to accurately estimate the amount of any subcontracts required for the FFP CLINs, specific workload requirements are needed. |
| Please provide specific quantifiable Subcontracting work load data. |
| Subcontractor workload is based upon the balance of tasks that the Offeror determines will be performed and completed by the Offeror’s subcontractors. The SIR does not require subcontractors. If an Offeror chooses to have subcontractors perform workload requirements under the SOW/SIR, that workload data would be determined by each Offeror, and would need to be included in that Offer’s proposal. |
| 1) C-001_Statement of Work |
| Throughout the SOW, the term "Operations Plan" is referred to but there's no information or Appendix with this information. |
| Please provide the referenced Operations Plan. |
| The Operations Plan referred to in the SOW is a Contractor-based document developed by the Offeror based upon their corporate format. . |
| 1) C-001_Statement of Work; 2) File B-001-CLIN Structure-Pricing Schedule.xlsx, Worksheet B001 CLIN 0003 |
| A review of the O&M requirements indicates no specific maintenance requirements or the Locations of Equipment, Equipment Lists, Equipment Identifiers (make/model/size/In-service dates). |
| Please provide the specific maintenance requirements for each specific piece of equipment. |
| ERSS Preventative Maintenance Program was provided via Appendix F to Offerors on a thumb drive mailed on August 31, 2020, after the site visit. |
Solicitation No. 692M15-19-R-00005, Amendment #2 dated 23Jun20 and file B-001-CLIN Structure- Pricing Schedule.xlsx
| The solicitation's Section B.1 indicates this is a Contract for Services. Item #22 on Amendment #2 states "Plant operators and other staff such as non-construction or field drilling operations staff are non-prevailing wage. Prevailing rate/Davis-Bacon rates apply to only “new” construction task orders." It is not clear if prevailing rates apply to the Pricing Deliverable's B-001-CLIN Structure-Pricing Schedule.xlsx FP/FFP requirements including the Environmental Technicians or Operators. |
| Will the FAA confirm all the Labor Category positions listed in attachment "B-001-CLIN Structure-Pricing Schedule" are FLSA - Exempt and as such not subject to the Service Contract Act (SCA). |
Otherwise, iaw FAR 22.1007 - please provide the applicable SCA?
Prevailing rates are applicable to new construction activities, generally under CLIN 001 (Remedial Action Construction). A wage determination was provided as attachment I-001 to the SIR. The Davis Bacon Act applies to all construction projects over $2,000.00. The SCA does not apply to the labor categories included in B-001 CLIN Structure Pricing Sheet.
| Comment # |
| Solicitation Reference |
| Discussion |
| Question/Comment |
| FAA Response |
| Invitation to Public Dropbox folder email dated 26Aug20 from Lori Mclaughlin. |
| The Dropbox folder email included 107 items (just files, no folders or directories). Of the 107 items, 89 items had the same file name of files already provided on the site visit – issued thumb drives; 18 files were new. |
| Will the FAA issue a formal amendment incorporating all the files included on the 26Aug20 email and clarify with of the 89 files previously included on the site visit - issued thumb drives, if any, are to be deleted or kept as the official version of the files? |
| Please do not rely on the drop box for any documents related to this SIR. The storage limitations of the drop box did not support the size of all the documents related to the SIR. The FAA provided the two thumb drives to Offerors that include the documents related to the SIR. Offerors are to rely on the thumb drive handed out at the site visit and the thumb drive that was mailed on August 31, 2020 to each Offeror after the site visit. |
Please see attachments “ERSS Thumbdrive Appendices File List_Amendment0004” and “ERSS Thumbdrive FAA Superfund Repository File List_Amendment0004”. These documents provide a list of all documents provided on each thumb drive.
| Internal Email regarding 27Aug20-dated email from Lori McLaughlin, CO regarding flash drive being sent to one person from each company via fed ex. |
| IAW the subject email, a notice was posted on beta.SAM.gov referencing an Amendment #3 with new Due Dates for Questions and undefinitized due date for proposals as "after all questions are submitted". A flash drive with Appendices was received on posted internally on 01Sep20 |
| Will the FAA formalize an amendment clarifying what was specifically included on the flash drive(s) sent separately after the site visit or are offerors to view the information as unofficial only? |
| Please see attachments “ERSS Thumbdrive Appendices File List_Amendment0004” and “ERSS Thumbdrive FAA Superfund Repository File List_Amendment0004”. These documents provide a list of all documents provided on each thumb drive. |
| C-001_Statement of Work Section 3.4 |
| Section 3.4 states the OMC must remove and dispose of off site wastes at approved disposal facilities. |
| Please provide FAA approved disposal facilities for the expected wastes so that transportation and disposal fees can be priced. |
| Section 121(d )(3) of the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) applies to any CERCLA response action involving the off-site transfer of any hazardous substance, pollutant or contaminant (CERCLA wastes). The ERSS Contractor provides information/data on the subject waste for offsite disposal action to FAA; FAA forwards the collective information to the USEPA Region 2 Off-Site Contact for verification and/or approval of the waste disposal action. For bidding purposes, the Offeror should use "EPA” approved facilities in lieu of "FAA" approved facilities. |
| C-001_Statement of Work Section 2.3.1.5 |
| Section 2.3.1.5 states the cost per change out must include reactivation. |
| Please clarify if the spent carbon that must be reactivated is currently a hazardous waste and if so, please provide the applicable waste codes. |
| The spent carbon analysis have been found to be non-hazardous. |
| C-001_Statement of Work Section 2.3.1.5 |
| Section 2.3.1.5 states the carbon must be virgin. |
| Please clarify if the virgin carbon is coal or coconut based carbon. |
| Virgin carbon is coconut based. |
| C-001_Statement of Work Section 2.3.1.5 |
| Section 2.3.1.5 states the cost per change out must include cost for removal. |
| Please confirm that confined space entry is not required to remove spent carbon from the vessels. |
| Confined space entry is not required to remove spent carbon from the vessels. |
| Comment # |
| Solicitation Reference |
| Discussion |
| Question/Comment |
| FAA Response |
| C-001_Statement of Work Section 2.3.1.5 |
| Section 2.3.1.5 states the cost per change out must include cost for removal. |
| Please clarify the carbon vessel filling procedure and whether slurry filling is acceptable. |
| Removal and replacement of carbon in a slurry is acceptable. ACTIVATED CARBON VESSEL FILLING PROCEDURE |
1. Close the spent carbon discharge valve located at the bottom of the adsorber.
2. Place approximately 1,500 gallons of utility water in the adsorber to protect the underdrain from the impact of the replacement carbon.
3. Position the bulk trailer with the replacement carbon near the adsorber to be transferred.
4. Fill the bulk trailer with approximately 5,000 gallons of utility water.
5. Connect a temporary carbon/water transfer line (flexible hose with quick connect fittings) between the bulk trailer and the adsorber's carbon fill line.
6. Position the remaining valves on the adsorber to be filled as indicated on Exhibit VI.
7. Connect a temporary compressed air line to the bulk trailer and regulate the compressed air at 150 scfm and 18 psig.
Once this has been completed, the valves on the bulk trailer will be opened starting the transfer.
| C-001_Statement of Work Section 3.4 |
| Section 3.4 states the OMC must remove and dispose of off site wastes at approved disposal facilities. |
| Please state whether the sludge from the filter press is currently a hazardous waste. |
| Historically, the laboratory analysis of the filter cake from the CTP filter press have been 'non-hazardous'. |
| C-001_Statement of Work Section 3.4 |
| Section 3.4 states the OMC must remove and dispose of off site wastes at approved disposal facilities. |
| If the sludge from the filter press is currently a hazardous waste, please provide the applicable waste codes, water content and other applicable waste characteristics so that transportation and disposal can be priced. |
| Historically, the laboratory analysis of the filter cake from the CTP filter press have been 'non-hazardous'. |
| C-001_Statement of Work Section 2.3.1.3. Overall Site System Management, Use of Subcontractors: Page 15/56 AND 8.3 Government Provided Workspaces Page 42/56 |
| SOW section 8.3 state O&M personnel and site management are provided workspaces in Building 380 at Area D (Jet Fuel Farm) and section 2.3.1.3 includes a reference to providing trailer housekeeping service. |
| Please provide with trailer(s) in SOW section 2.3.1.3 requires housekeeping services including the physical attributes of the trailer (location, make/model, size, # of windows, types of flooring, any special considerations, etc...). |
| A floor plan of Building 380, which provides all the information necessary to estimate trailer housekeeping services, was hand-delivered to all Offeror's during the site visit. |
| Comment # |
| Solicitation Reference |
| Discussion |
| Question/Comment |
| FAA Response |
| L-001a_Sample Task Order |
| Identify the AREA 20A extraction, injection and monitoring well locations. |
| Please provide the location of the new AREA 20A extraction, injection and monitoring well locations as it pertains to site preparation scope and cost (does the area need clearing and/or grubbing wooded area locations) and geotechnical investigation needs. |
| For bidding purposes relative to site preparation, assume that the ground where the wells will be installed is cleared, level, and with no access issues. |
| L-001a_Sample Task Order |
| Geotechnical report or well logs for existing wells at the site may be used to identify typical soil conditions relative to new wells and the new Carbon Treatment Building |
foundation.
| Please provide a geotechnical report or well logs for existing wells at the site. |
| For bidding purposes, the Offeror should assume sandy soil, 115 pcf. |
| L-001a_Sample Task Order |
| Per Sheet C1, Note: ASSUME THAT THIS CONTRACT BOUNDARY WILL BEGIN AT THE BUILDING WALL. ASSUME UNDERGROUND PIPING UP TO THE BUILDING WALL IS |
EXISTING OR WILL BE PROVIDED BY OTHERS.
Please the utilities, piping, or site restoration needed - requirements outside the building.
For bidding purposes, assume that any work outside of the building wall is not part of this bid task. Assume all utilities and piping will be in place at the time of building construction.
| L-001a_Sample Task Order |
| Per Sheet C1, Note: ASSUME THAT THIS CONTRACT BOUNDARY WILL BEGIN AT THE BUILDING WALL. ASSUME UNDERGROUND PIPING UP TO THE BUILDING WALL IS EXISTING OR WILL BE PROVIDED BY OTHERS. |
| Are the site grading and erosion control plans to be included in the scope of work, or are these efforts provided by others? |
| These items are not part of this SOW. |
| L-001a_Sample Task Order |
| Per Sheet C1, Note: ASSUME THAT THIS CONTRACT BOUNDARY WILL BEGIN AT THE BUILDING WALL. ASSUME UNDERGROUND PIPING UP TO THE BUILDING WALL IS EXISTING OR WILL BE PROVIDED BY OTHERS. |
| Please clarify if the Contractor will be responsible for piping and electrical connections to/from the extraction/injection wells and the treatment system building. |
| Piping and electrical connections between the extraction/injection wells and the treatment building are not part of this SOW. |
| L-001a_Sample Task Order |
| Per Sheet C1, Note: ASSUME THAT THIS CONTRACT BOUNDARY WILL BEGIN AT THE BUILDING WALL. ASSUME UNDERGROUND PIPING UP TO THE BUILDING WALL IS EXISTING OR WILL BE PROVIDED BY OTHERS. |
| Is there a designated lay-down area for equipment and supplies? If so, where is it located OR where can offeror set one up? |
| For bidding purposes, assume that a clear, level laydown area, immediately adjacent to the construction area, is available for use by the ERSS Contractor. |
| L-001a_Sample Task Order |
| Sheet M1, P&ID |
| Are all instruments in the treatment building local read only or do they require 4- 20ma output for remote access? |
| For bidding purposes, assume that all instruments are local read only. |
| L-001a_Sample Task Order |
| Sheet M2, Well Details |
| Please provide the specifications, make/model numbers for the extraction well pumps. |
| Please note that per Detail 1 on Drawing M2, the submersible pump is not part of this SOW. |
| Comment # |
| Solicitation Reference |
| Discussion |
| Question/Comment |
| FAA Response |
| L-001a_Sample Task Order |
| Sheet M2, Well Details |
| Please provide operating system details if the pressure transducers in the extraction/injection wells connect to a plc for control of the well pumps. |
| Please note that per Detail 1 on Drawing M2, the pressure transducer is not part of this SOW. |
| C-001_Statement of Work Section 2.3.1.3 Utilities, Use of Sub-Contractor |
| Provide Bldg. 380 HVAC an annual service agreement for maintenance and service of HVAC components |
| Please prove the make model and size of the HVAC systems and the components requiring annual service. |
| The CTP has two (2) Carrier HVAC units (model number 50VQL300BDN601C2) with a Honeywell controller (model XL500), sensors and switches. |
| C-001_Statement of Work Section 2.3.1.3 Utilities, Use of Sub-Contractor |
| Provide certified fire alarm and extinguisher inspections |
| Please prove the make, model, and location of fire alarm systems and types, quantity and location of the fire extinguisher requiring inspections and the frequency of these inspections. |
| The fire alarm system is a FCI Fire Control System - 7200 Series. There are forty-four (44) fire extinguishers in the CTP and remedial support buildings. |
The fire alarm system requires annual inspection by a New Jersey certified inspector. The fire extinguishers are inspected monthly by the ERSS Contractor and annually by a New Jersey certified inspector.
| C-001_Statement of Work Section 2.3.1.3 Utilities, Use of Sub-Contractor |
| Provide service agreement for maintenance and service of photocopier. |
| Please prove the make, model, and quantity of photocopiers routine service in bldg. 380. |
| ERSS Contractor to furnish photocopier according to SOW Section 2.3.1.3. |
| RFP Section L.4.6 |
| RFP Section L.4.6 makes reference to prime contractor submittal letter and subcontractor commitment letters, and transmittal letters. However, there is no further guidance on where these items are to be included in the proposal submittal or any requirements. |
| Please clarify where these items go within the proposal submittal and if there are any further requirements/instructions. |
| Conformed_SIR_Amendment0004 Section L.4.6 is updated to omit reference to subcontractor commitment letters and transmittal letters. The prime contractor submittal (cover) letter must be included in Annex #1- Executive Summary. |
| RFP Section L.4.6 |
| RFP Section L.4.6 states that Times New Roman 10pt font is to be used. Section L.5.7.3 states that files must not be locked. Attachment B-001 Clin Structure Pricing Schedule.xlsx file provided by the government does not conform to the font requirements and is locked/Password protected. |
| Please confirm that bidders will not be penalized for not meeting the requirements of the two sections mentioned for this file. |
| The SIR requirement that proposals must be formatted using Times New Roman 10 pt. normal font (no reduction permitted) does not apply to Attachment B-001 CLIN Structure Pricing Schedule. |
| RFP Section L.5.6 |
| RFP Section L.5.6 indicates that “Item F must be in narrative form.” |
| What is “Item F”? |
The paragraphs below this sentence includes only items a through e.
The final SIR version had an error in the lettered list in Section L.5.6; "Quality of Service" should have been identified as item "a" to start the list. The lettering should be as follows:
a. Quality of Service
b. Timeliness of Performance
c. Customer Satisfaction
d. Business Relations/Integrity/Effective Management
e. Ability to Manage Cost/Control Cost
f. Environmental Violations/Enforcement Actions
See Conformed_SIR_Amendment00004.
| Comment # |
| Solicitation Reference |
| Discussion |
| Question/Comment |
| FAA Response |
RFP Section L.5.7.3.b
Can the FAA provide the basis for the 10 contract periods listed in RFP Section L.5.7.3.b.?
Are the periods based on date of award or are they based on the FAA fiscal year?
Please provide assumed start date.
The ERSS Contract will have ten (10) 1-year contract periods. The start of the contract base period will begin on date of award. Each subsequent option period (if exercised) will start on the year anniversary of the contract award.
For bidding purposes, the Offerors should assume a full performance start date of April 1, 2021, with a transition period prior to that performance start date. This does not commit the Government to a performance start date of April 1, 2021.
L001 – Sample Task Order
| Is it the intention of the FAA to award L001 – Sample Task Order? |
| FAA intends to construct a more permanent solution to house the granular activated carbon treatment train, based upon the availability of funding, at a future date TBD. For bidding purposes, the Offeror should assume an award during the first quarter of calendar year 2021. |
L001 – Sample Task Order
| What is the assumed start date for L001 – Sample Task Order? |
| For bidding purposes, the Offeror should assume that the start date for the Sample Task Order is expected to be in the first quarter of calendar year 2021. |
CLINs 0003-0005
How does the FAA intend to award task orders for CLINs 0003-0005 of the ID/IQ?
Will the contractor submit proposals or will the FAA award the yearly prices provided under this solicitation?
The FAA will award CLINs 0003-0005 using the yearly prices provided by the awarded Offeror using the B-001 Pricing Schedule.
CLINs 0003-0005
Can offerors include a narrative for CLINs 0003-0005 in their proposal and if so, what are the page limitations and where should this be included?
Section L.5.7.4 describes the information required in the Price Proposal Narrative. In accordance with SIR Section L.4.5 there is no page limitation for the Price Proposal Volume.
Scope of Work, Section 1.5.1
Is the operation and subsequent decommissioning of the TCH system at Area D the responsibility of the contractor (Scope of Work, Section 1.5.1)?
Will there be LTM requirements once decommissioned?
The TCH remedial action contractor is responsible for the TCH system up to the point that the effluent enters the CTP and associated treatment components (e.g., Building 293 - CATOX Building and Building 294B Manifold Building).
The TCH remedial action contractor is responsible for decommissioning of the TCH system. LTM requirements will be evaluated upon the completion of the TCH remedial action. Please see Section 1.5.1 of the Conformed SOW.
Scope of Work Section 2.3.1.1
| Scope of Work Section 2.3.1.1 indicates Area 41 is currently offline, does the Government plan to put it back online? |
| Area 41 is currently offline due to operational challenges. The FAA is evaluating how the system can be modified or altered to improve performance. It is the FAA’s intention that Area 41 will be put back online. |
| Comment # |
| Solicitation Reference |
| Discussion |
| Question/Comment |
| FAA Response |
Scope of Work Section 2.3.1.3 and Section 7.1
| Is the Project Hydrogeologist an on-site position? Scope of Work Section 2.3.1.3 indicates that it is a full-time on-site position, but Section 7.1 does not indicate that this position is on-site. |
| The Project Hydrogeologist is a full-time, on-site position, which has been retitled as “Project Geologist/Hydrogeologist” and clarified in Section 7.1 of the Conformed SOW that is included in Amendment 00004. |
Scope of Work Section 2.3.1.3 and Section 7.1
Is the GIS/GPS System Administrator an on-site position?
Scope of Work Section 2.3.1.3 does not indicate that it is, but Section 7.1 indicates “The GIS/GPS System Administrator is an on-site, supervisory position…” GIS/GPS System Administrator is an on-site position, supervisory position.
Scope of Work, Section 1.5.22
Is Area B suspected as being impacted with PFOA/PFAS contamination (Scope of Work, Section 1.5.22)?
If PFOA/PFAS has not been investigated at Area B, will this investigation be required/requested and be the responsibility of the contractor under this contract?
Environmental Investigations (including PFAS, et al) are performed by the Environmental Architect/Engineer (A/E).
Scope of Work, Section 1.1
Can the Government please provide the existing Sampling and Analysis Plans (SAP), Operation Strategy Plan (Op Plan), and Staffing Plan for the AOCs as indicated in the Scope of Work, Section 1.1? We understand that the O&M Manuals were provided previously as
GFI.
FAA will not provide existing SAP, Op Plan or Staffing plan as those documents are proprietary to the current contractor.
| Comment # |
| Solicitation Reference |
| Discussion |
| Question/Comment |
| FAA Response |
Scope of Work, Section 10
| Can the Government please provide the current Transition In and Transition Out Plans (Scope of Work, Section 10)? |
| FAA will not provide current Transition In and Transition Out Plans as those document are proprietary to the current contractor. |
Scope of Work
Will the contractor be responsible for preparing a Five-Year Review during the
POP?
No. The Five-Year Review will be prepared for the FAA by the Environmental A/E. The ERSS Contractor will provide operational data and remedial construction information in support of the Five- Year Review.
Scope of Work, Section 2.6 Scope of Work, Section 2.3.1.5 Section 2.3.1.6, Appendix F
Can the government please provide a list of the corrective maintenance/surge unscheduled repairs for the past 5 years of operations (i.e., transducer, pump, etc.) as described in Scope of Work, Section 2.6?
We understand the Government has supplied frequency of treatment process chemical usage (Scope of Work, Section 2.3.1.5) and will provide an example of the preventive maintenance schedule (Section 2.3.1.6, Appendix F).
FAA has estimated $200K for a yearly budget for corrective maintenance/SURGE unscheduled repairs based upon a ten-year history of the project. In the event additional repairs are warranted, FAA will evaluate and modify the contract as needed.
Scope of Work
| What is the required response time for auto-dialer calls and emergency alarms? |
| Auto-dialer calls should be acknowledged by the operator with the remote access laptop (aka the "football") within 15-minutes. |
Emergency Alarms will require immediate acknowledgement and personnel to respond on-site within 60-minutes. This requirement was added as Section 2.3.1.1-ss and 2.3.1.2-ee to the Conformed SOW that is included in Amendment 00004.
Scope of Work
| Is there a minimum uptime required for operations of the CTP and Area 20A systems that is tied to regulatory requirements or payment milestones? |
| The CTP and Area 20A systems are expected to run 24 hours, 7 days per week as much as possible, with the exception of reasonable downtime associated with repairs, maintenance, electrical shutdowns, etc. to meet regulatory requirements of optimal system operation. Payment milestones are made based upon the ERSS Contractor's performance and response towards meeting those goals. This requirement was added as Section 2.3.1-1-tt and 2.3.1.2-ff to the Conformed SOW that is included in Amendment0004. |
| Comment # |
| Solicitation Reference |
| Discussion |
| Question/Comment |
| FAA Response |
Scope of Work, Section 7.2
Scope of Work, Section 7.2 lists the positions of Project Environmental Engineer, Project Geotechnical Engineer, and Site Hydrogeologist. These positions are not listed in the B-001 Labor Category List.
Which of the provided Labor Categories should bidders use for these positions?
The referenced positions have been retitled for clarity purposes and added to the Pricing Schedule - WJHTC Labor tab. See Conformed Attachment B-001 “CLIN Structure - Pricing Schedule” that is included in Amendment 00004.
Sample Task
| Sample Task – The sample task requires labor categories not present in B-001 WJHTC Labor Tab. Is it acceptable to propose additional labor categories in the sample task? |
| Attachment B-001 WJHTC Labor Tab was meant to encompass the labor categories necessary for CLINS 0002 and 0006. The work being proposed under the Sample Task would fall under CLIN 0001, and is not bound to the labor categories on the WJHTC Labor Tab. Further, after the start of performance, the FAA has the right to add labor categories deemed necessary in accordance with SIR Section B.3.1. |
Sample Task
| Sample Task - Is the FAA expecting the Contractor to take responsibility for the design of the Area 20A Carbon Treatment System given the Performance Requirements (Section 11371, Part 1.4.1) and Checkout Requirements (Section 11371, Part 3.7) for mercury and PFAS? |
| The information provided regarding the carbon and vessels within the specifications should be the minimum necessary to meet the treatment requirements. The bidder may propose an alternate design, or comment on the existing design, as a means of demonstrating their understanding of the treatment components and project requirements. |
Sample Task
| Sample Task - What is existing condition of soil to be removed for building footers and foundations? |
| For bidding purposes, assume that the soils in the building footprint are not known to be impacted from contaminants of concern. |
| Comment # |
| Solicitation Reference |
| Discussion |
| Question/Comment |
| FAA Response |
Sample Task
Sample Task - What is the pressure of the influent water to the treatment building? Is the influent water pressure sufficient to meet the piping test requirements in Specification Section 02713, Part 3.2.1. Note, there is a discrepancy between the test pressure specified in Section 02713, Part 3.2.1 and Section 11371, Part 3.5.
For bidding purposes, assume pressure testing will be conducted at 100 psig. Assume that the influent water pressure to the building will meet the 100 psig requirement.
Sample Task
| Sample Task - What is the pressure drop across each bag filter unit (with new 5 micron bags inserted) and GAC filter vessel (filled with 12 x 40 carbon media)? |
| For bidding purposes, assume that all piping and components are sized for the appropriate pressure drop. In any case, the bidders may assume that the pressure drop across the bag filter unit with new 5 micron bags is 5 psig maximum and the pressure drop across each GAC filter with a new charge of carbon is 10 psig maximum. |
Sample Task
| Sample Task - What is the grade change from the Area 20A Carbon Treatment Building to the injection gallery? |
| Please note that no work outside of the Treatment Building is required. If necessary, assume all grades are flat. |
Sample Task
| Sample Task - Are pressure relief valves required on the Multibag Filter housings? |
| No pressure relief valves are required on the bag filter units. |
Sample Task
| Sample Task - Is Contractor required to pull wire from the power supply to EP-1? If so, where is switch gear located relative to EP-1? |
| Pulling wires from the outside service to EP-1 is not part of this bid task. |
Sample Task
| Sample Task - Is Lightning Protection System (per Section 16740) required under this contract? It is not shown on the Drawings. |
| Refer to note 2 on Drawing E1 for the lightning protection system requirements. |
| Comment # |
| Solicitation Reference |
| Discussion |
| Question/Comment |
| FAA Response |
CLIN III - SOW Section 7.2
| CLIN III – Is the Project Geologist referenced in CLIN III pricing equivalent to the Non- Key Personnel Site Hydrogeologist Position described in section 7.2 of the SOW (Other Personnel? |
| The SOW and Pricing Schedule have updated labor category designations to provide clarity. The labor categories referenced in this comment are not equivalent. The Project Geologist/Hydrogeologist (Key Personnel) position has more responsibility and authority than the Geologist/Hydrogeologist (non-Key Personnel) position. |
See Conformed Attachment B-001 “CLIN Structure - Pricing Schedule” and Conformed SOW included in Amendment 00004.
CLIN III - SOW Section 7.2
CLIN III – Section 7.2 of the SOW (Other Personnel defines the Project Geotechical Engineer and Project Engineer labor categories, however these positions are not shown on CLIN III.
Where shall the bidder provide rates for these proposed non-key personnel?
Project Geotechnical Engineer and Project Engineer labor categories have been retitled as “Geotechnical Engineer” and “Environmental Engineer” and added to the revised B-001-CLIN Pricing Schedule on the WJHTC Labor tab. See Conformed Attachment B-001 “CLIN Structure - Pricing Schedule” that is included in Amendment 00004.
CLIN III - SOW 2.3.1.5.1
| Is the operation of the organoclay included in the SOW? If yes, where should the costs be included? (SOW 2.3.1.5.1) |
| Operation and maintenance costs of the organoclay filters will be covered under Subtask 1 of Attachment B-001 “CLIN Structure - Pricing Schedule” (System Operation - SOW Section 2.3.1.5.1). Please see Section 2.3.1.5.1 of Conformed SOW that is included in Amendment 00004. Direct costs related to organoclay media change out will be included under the SURGE CLIN. |
CLIN III - SOW 2.3.1.1
Is the operation of the SVE included in the SOW? If yes, where should the costs be included?
(SOW 2.3.1.1)
Operational costs related to the SVE will be covered under the Subtask 1 of Attachment B-001 “CLIN Structure - Pricing Schedule” (System Operation - SOW Section 2.3.1.1). Maintenance related to the SVE will be covered under the SURGE CLIN.
CLIN III - SOW 2.3.1.2 and 2.3.1.3
Is the operation of the CATOX included in the SOW? (SOW
2.3.1.2 and 2.3.1.3) Operational costs related to the CATOX will be covered under the Subtask 1 of Attachment B-001 “CLIN Structure - Pricing Schedule” (System Operation - SOW Section 2.3.1.1). Maintenance related to the CATOX will be covered under the SURGE CLIN.
CLIN III - SOW 1.5.1 and 3.5
| Is free-phase product recovery included in the SOW? If yes, where should the costs be included? (SOW 1.5.1 and 3.5) |
| Area D product recovery equipment has been removed from the site and has been replaced with product recovery infrastructure associated with the TCH project. Costs associated with product disposal not covered under the TCH project will be handled under the SURGE CLIN. |
CLIN III - SOW 2.3.1.5.1
| How much sludge is generated per year? (SOW 2.3.1.5.1) |
| Historically, approximately twelve (12) 1-cubic yard boxes of non- hazardous sludge was removed from the CTP each year. |
| Comment # |
| Solicitation Reference |
| Discussion |
| Question/Comment |
| FAA Response |
CLIN III - SOW Section 2.3.1.5
| Please provide the most recent profile/waste characterization analysis for GAC, organoclay and sludge. (SOW Section 2.3.1.5) |
| For bidding purposes, the Offeror should assume the GAC, organoclay and sludge is all non-hazardous. |
CLIN III - SOW 9.2
| Please provide a more detailed scope of work and frequency for the injection well survey and redevelopment. (SOW 9.2) |
| Injection Well surveys are conducted annually. Redevelopment is based upon the results of those surveys. Costs for redevelopment will be covered under the SURGE CLIN. |
CLIN III - SOW 2.3.1.1 and 2.3.1.2
| What is the frequency for breakthrough testing in the GAC? (SOW 2.3.1.1 and 2.3.1.2) |
| GAC breakthrough testing is performed using the monthly sample data. |
CLIN III - SOW 2.3.1.1
| Please provide the historical rate of dosing for coagulant and flocculent dosage and concentration. The O&M manual does not detail dosing. (SOW 2.3.1.1) |
| Due to recent modifications to the CTP treatment system, coagulant and flocculant are not currently used. Therefore, the Offeror should not include pricing for this task. Please see updated language in Section 2.3.1.5.1 in Conformed SOW that is included in Amendment0004. |
CLIN III - SOW 2.3.1.1 and 2.3.1.2
| Please provide the operating limits, target water levels, and performance criteria for all systems. The O&M manual does not detail the limits. (SOW 2.3.1.1 and 2.3.1.2) |
| The Offeror must ensure system discharges meet the discharge criteria and the groundwater extraction system maintains effective hydraulic control to manage groundwater contaminant plumes by any and all means necessary, subject to individual Offeror's recommendations. |
CLIN III - SOW 2.3.1.1
The CTP O&M manual describes components which were not discussed during the site visit.
What components are still online? (SOW 2.3.1.1) Within the CTP, the flocculator/clarifier has been bypassed, the greensand filters have been removed, and Final Transfer Tank T3 has been removed.
CLIN III - SOW 2.3.1.1 and 2.3.1.2
| Please provide the scope of work and frequency for the below activities. Will these activities be covered under SURGE? (SOW 2.3.1.1 and 2.3.1.2) |
| See Responses to Questions 76-84. |
| Comment # |
| Solicitation Reference |
| Discussion |
| Question/Comment |
| FAA Response |
| a. Topographic and geophysical |
| These activities are included in CLIN 001 (Remedial Action Construction) projects; requirements are identified in the individual project scope of work or will be performed under a contract modification to CLIN 003. |
| b. Soil and rock borings, sampling, testing and other geotechnical analysis. |
| These activities are included in CLIN 001 (Remedial Action Construction) projects; requirements are identified in the individual project scope of work or will be performed under a contract modification to CLIN 003. |
| c. Drilling, installation and development of extraction, injection, monitoring, and observation wells. |
| These activities are generally included in CLIN 001 (Remedial Action Construction) projects; requirements are identified in the individual project scope of work or will be performed under a contract modification to CLIN 003. |
| d. Hydrogeological testing. |
| These activities are generally included in CLIN 001 (Remedial Action Construction) projects; requirements are identified in the individual project scope of work or will be performed under a contract modification to CLIN 003. |
| e. Multi-media sampling and sample management for chemical and geotechnical characteristics. |
| These activities are generally included in CLIN 001 (Remedial Action Construction) projects; requirements are identified in the individual project scope of work or will be performed under a contract modification to CLIN 003. |
| f. Work area and perimeter air monitoring, sampling, and related analysis. |
| These activities are generally included in CLIN 001 (Remedial Action Construction) projects; requirements are identified in the individual project scope of work or will be performed under a contract modification to CLIN 003. |
| g. Multi-media chemical analysis for a wide variety of compounds including nitroaromatic compounds and other energetic materials. |
| These activities are generally included in CLIN 001 (Remedial Action Construction) projects; requirements are identified in the individual project scope of work or will be performed under a contract modification to CLIN 003. |
| h. Installation of support facilities (i.e., site project offices, decontamination facilities, roads, utilities, and fence lines). |
| These activities are generally included in CLIN 001 (Remedial Action Construction) projects; requirements are identified in the individual project scope of work or will be performed under a contract modification to CLIN 003. |
| Comment # |
| Solicitation Reference |
| Discussion |
| Question/Comment |
| FAA Response |
| i. Updates to the As-Built Drawings/Plans and Operation and Maintenance Manual when modifications or alterations are made to any of the systems or appurtenances |
| These activities are generally included in CLIN 001 (Remedial Action Construction) projects; requirements are identified in the individual project scope of work or will be performed under a contract modification to CLIN 003. |
CLIN III - SOW 2.3.1.2 and 2.3.1.3
Please provide the scope of work for the CTP heating, ventilation, and air conditioning (HVAC) annual service agreement for maintenance and service of HVAC components. (SOW
2.3.1.2 and 2.3.1.3) The HVAC system in the CTP consists of two (2) Carrier HVAC Units (model number 50VQL300BDN601C2) with a Honeywell controller (model XL500), sensors and switches. The Offeror is required to contract an annual service agreement for maintenance and service with a Carrier certified company.
CLIN III - SOW 2.3.1.2 and 2.3.1.3
| Please provide the scope of work for the regular certified fire alarm and fire extinguisher inspections. Where are these systems and fire extinguishers located? (SOW 2.3.1.2 and 2.3.1.3) |
| The fire alarm system is a FCI Fire Control System - 7200 Series. There are forty-four (44) fire extinguishers in the CTP and remedial support buildings. |
The fire alarm system requires annual inspection by a New Jersey certified inspector. The fire extinguishers are inspected monthly by the ERSS Contractor and annually by a New Jersey certified inspector.
CLIN III - SOW 2.3.1.4
| Does the WQIP parameters need to be collected by a NJDEP-certified sampler using NJ certified water quality instruments? (SOW 2.3.1.4) |
| The individual sampler does not need to be NJDEP certified; |
The ERSS Contractor must utilize New Jersey certified/calibrated WQIP instruments. Please see updated Section 2.3.1.4 in Conformed SOW that is included in Amendment 0004.
CLIN III - SOW 2.3.1.4
| What percentage of samples need to be validated? (SOW 2.3.1.4) |
| 25% of all data generated through field activities, sampling, and final laboratory analysis must be reduced, verified, and validated employing a "Tiered" approach before results are released. |
Sample Task
| Please provide a grading plan f |
| For bidding purposes, assume the ground on which the building will be constructed is cleared and level. |
Sample Task
Please provide the detail on how the treatment system will be connected to the existing extraction system. No details were provided on how site water will be connected to the system for checkout and final testing. (11371, 3.7 and 02713, 3.2.2) For bidding purposes, assume all influent and effluent water piping will be in place at the time of building construction. Assume that the influent water pressure to the building will meet the required hydrostatic testing requirements.
| Comment # |
| Solicitation Reference |
| Discussion |
| Question/Comment |
| FAA Response |
Sample Task
| Are duplicate or equipment blanks required for checkout testing? |
| For bidding purposes, assume that no duplicate or equipment blanks are not required for checkout testing. |
Sample Task
The specifications call for: “Provide a treatment system including two (2) bag filter assemblies and eight (8) fully (manually) backwashable granular activated carbon (GAC) absorber units.” The drawings do not appear to show any piping or connections for backwashing the GAC units. How will water be provided for these units, do we need plan appropriate connections and assume availability of the required water flow and pressure from the fire hydrant located adjacent to the building?
For bidding purposes, assume that ports for countercurrent backwash flow will need to be provided. Assume that backwash water will be provided from an outside source and that backwash water will be discharged to an auxiliary tank. Neither the backwash, water piping, or auxiliary tank are part of this bid task.
Sample Task
There are references to wiring for Fire Alarm systems, junction boxes, recovery couplings, etc. If required, please provide Fire Alarm panel specifications.
For bidding purposes, assume that any Fire Alarm components will not be part of this bid task.
Sample Task
| Has there been any pilot testing to assure that the specified carbon will meet the regulatory limits for the Performance Testing part of the specification? |
| The information provided regarding the carbon and vessels within specification should be the minimum necessary to meet the treatment requirements. The bidder may propose an alternate design or comment on the existing design as a means of demonstrating their understanding of the treatment components and project requirements. |
| Comment # |
| Solicitation Reference |
| Discussion |
| Question/Comment |
| FAA Response |
Past Performance Information Sheet
Questions d) Business Relations/Integrity/ Effective Management, e) Ability to Manage Cost/Control Cost, and f) Environmental Violations/Enforcement Actions ask the offeror to describe various aspects of work on “previous contracts.”
Please confirm that the response provided for each of those questions should be limited to the contracts proposed under Phase I, Factor II, Corporate Experience and not previous or other contracts performed.
Responses under Factor V are limited to the contracts proposed under Phase I, Factor II Corporate Experience.
SIR
| Please define the years/months associated with Years 1 through 10 for the Price Submittal (i.e., CLINs III, IV, & V). Please confirm the start date on which Contractors should base their bids. |
| For bidding purposes, the Offerors should assume a full performance start date of April 1, 2021, with a transition period prior to that performance start date. This does not commit the Government to a performance start date of April 1, 2021. |
| SOW Section 2.3.1.5.1, Treatment Process and Chemicals |
| For purposes of O&M costing, should Contractors assume any costs for the changeout of the organoclay filters (SOW Section 2.3.1.5.1, Treatment Process and Chemicals)? |
| Costs related to organoclay changeouts will be included under the SURGE CLIN. |
| SOW Section 2.3.1.5.1, Treatment Process and Chemicals |
| For the purposes of O&M costing, under which subtask should the costs for polymer be included (SOW Section 2.3.1.5.1, Treatment Process and Chemicals)? |
| Costs for polymer will be included under the SURGE CLIN. |
| Comment # |
| Solicitation Reference |
| Discussion |
| Question/Comment |
| FAA Response |
SOW Section 2.3.1.4, Discharge Monitoring and Reporting
If Contractors are able to provide data validation and/or report preparation services in house (SOW Section 2.3.1.4, Discharge Monitoring and Reporting), should these hours/costs be included in the O&M cost estimate for Subtask 11 as an ODC cost?
If the contractor has the ability to perform data validation and report preparation services in house, those costs are O&M related and should be included on the Pricing Schedule (CLIN 0003) under Subtask 11 as an ODC cost.
Factor IV – Key Personnel and SOW Section C.7.1
Under Factor IV – Key Personnel, the RFP states “Offerors must submit resumes for each of the Key Personnel Positions listed in the SOW Section C.7.1.
Resumes are limited to two (2) pages each and must demonstrate the proposed key personnel’s experience relevant to the SIR requirements as referenced in the SOW.” Would the FAA allow additional information to be provided or is it strictly limited to the resumes?
See SIR Section L.5.5 for the requirements of and information that must be included in Offeror’s response to Factor IV. Resumes are limited to two (2) pages each and no additional pages are permitted. This page limitation does not include the Letter of Intent, as applicable, referenced in SIR Section L.5.5.
Factor V – Past Performance, Under Factor V – Past Performance, the RFP states “The Offeror must submit a Past Performance Information Sheet (Attachment L-003) for each of the contracts proposed under Phase I, Factor II, Corporate Experience. The Offeror is limited to only submitting Past Performance for the proposed Corporate Experience contracts.” Would the FAA allow additional information to be provided or is it strictly limited to the past performance information sheets?
See SIR Section L.5.6 for the requirements of and information that must be included in Offeror’s response to Factor V.