The document is an Air Force Form 3052 Construction Cost Estimate Breakdown template for Solicitation # FA252125B0009, designed to provide a detailed cost breakdown for a construction project at Ascension Auxiliary Airfield. The template requires contractors to itemize costs across multiple construction categories including general requirements, sitework, concrete, metals, doors and windows, finishes, mechanical, and electrical work, with specific columns for material costs, labor costs, manhours, and other direct costs.

The form includes comprehensive instructions for completing each column, emphasizing the need for detailed, verifiable cost data and supporting documentation. Contractors are expected to provide unit costs, quantities, labor rates, and total costs for each line item, with the ultimate goal of developing a transparent and analyzable cost estimate for the government. The template also requires contractors to potentially disclose overhead rates, profit rates, and bonding costs, and grants the contracting officer the right to examine supporting documentation to verify the submitted cost and pricing data.

View the file

Other files

File Type Posted
FA252125B0009 SF1409.pdf PDF
24. Geology Study-Investigation (1997) (Ref Only).pdf PDF
23. YXTK 13-1806 RPR FDR 5 Design Analysis (Section 5) (Ref Only)).pdf PDF
22. Government Response to Contractor Submitted Questions.pdf PDF
FA252125B0009 A004.pdf PDF
FA252125B0009 A003.pdf PDF
FA252125B0009 A002.pdf PDF
Solicitation Amendment FA252125B00090001 SF 30.pdf PDF
16. Enivronmental Final Governing Standards Ascension Island.pdf PDF
14. YXTK 13-1806 DWG E-409 (RevA).pdf PDF
4. Contractor HAZMAT Usage Worksheet.xlsx XLSX spreadsheet
3. YXTK 13-1806 Recovered Materials Determination Form (Green Procurement).pdf PDF
19. Ascension Island PSD.pdf PDF
18. Catherine Point PSD (Services Distribution).pdf PDF
17. Installation Facility Standards Ascension Auxiliary Airfield.pdf PDF
13. YXTK 13-1806 (FY23 Historical Contractor Question-Govt Responses).pdf PDF
2. YXTK 13-1806 Specifications.pdf PDF
1. YXTK 13-1806 DWG.pdf PDF
21. Facility 800 Photos.pdf PDF
10. QA Template.docx DOCX document
7. Contractor Travel Request Form.pdf PDF
FA252125B0009 (YXTK 13-1806 RPR Electrical Dist Sys (Feeder 5)) IFB.pdf PDF
20. Fiber Wall Mount Dist Cabinets Photos.pdf PDF
15. Concrete Mix Design (Local Aggregate).pdf PDF
12. MH 42 Photos.pdf PDF
11. Site Visit Procedures.pdf PDF
5. Record of EqmtMat List Template (OM Database).xlsx XLSX spreadsheet
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AF3052 CLIN 001

CONSTRUCTION COST ESTIMATE BREAKDOWNSolicitation # FA252125B0009
CONTRACTORADDRESS

CONTRACT FOR PROPOSED TOTAL CONTRACT PRICE

PURCHASE REQUEST FORMPROJECT NUMBERWORK LOCATION
YXTK 13-1806 RPR FEEDER 5ASCENSION AUXILIARY AIRFIELD
MATERIAL COSTLABOR COST
UNITOTHER
LINEITEMOFQUANTITYMANHOURSAVERAGETOTALDIRECTLINE
NO.MEASUREUNITTOTALMANDAYSRATECOSTSTOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

1General requirements0.000.000.00
Administrative requirements0.000.00
EXAMPLE: Project Manager?????
Temporary facilities and controls0.000.00
Execution requirements0.000.00
Facility operations0.000.00
2Sitework0.00
Site preparation0.00
3Concrete00.00
Formwork0.000.00
EXAMPLE: Isolated Beam Side Forms????????
Concrete reinforcing0.000.00
Cast in place concrete0.00
4Metals0.000.00
Basic metal materials and methods0.000.00
Structural framing0.000.00
Metal restoration and cleaning0.00
6Wood and plastics0.00
Basic wood and plastic materials and methods0.000.00
Subtotals for Col 5, 8, 9 and 100.000.000.000.00
CECC FORM 3052PAGE 1
INSTRUCTIONS FOR COMPLETING CECC FORM 3052
Col (Column) 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient
detail to permit itemizing of all direct costs.
Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples--square yards--SY, cubic yards--
CY, square feet--SF, linear feet--LF, board feet--BF, each--EA, pound--LB).
Col 3 Quantity. Constractor's estimate of quantity required in terms of unit of measure (Col 2). Items and units of measure may
be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price
contract will be issued. Otherwise, the contractor is responsible for determining all quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total costs (Col 5) for items listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in column 6 the estimated number of manhours or mandays needed to perform the work listed in
column 1. Enter in Col 7 the average rate per manhour (manday) and in Col 8 the total labor cost.
Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1) which are special to the
contract and of significant dollar value.

Col 10 Line Total. Self-explanatory.

NOTE: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on
the last page as follows.

TOTAL MATERIAL COSTS $

TOTAL LABOR COSTS $

TOTAL OTHER DIRECT COSTS $

TOAL DIRECT COSTS $

OVERHEAD (RATE: __________________%) $

SUBTOTAL $

PROFIT (RATE: __________________%) $

SUBTOTAL $

BOND (RATE: __________________%) $

TOTAL PRICE $

DATE FIRM NAME

TITLEBY
(Signature)

INSTRUCTIONS TO OFFERORS

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of
incurred and estimated costs (and attached supporting information) suitable for detailed review and analysis. Prior to the award
of a contract resulting from this proposal the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a
certificate of current cost or pricing data (see ASPR 3-807.3(e) and 3.807.4).
2. In addition to the specific information required by this form, the offeror is expected, in good faith, to incorporate in and submit
with this form any additional data, supporting schedules, or substantiation which are reasonably required for the conduct of an
appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that
there be a clear understanding of
a. The existing, verifiable data
b. The judgmental factors applied in projecting from known data to the estimate, and
c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticalbe, the data will be described (with schdules as
appropriate), and made available to the contracting officer or his authorized representative on request.
4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine,
for the purpose of verifying the cost or pricing data submitted, those books, records, documents, and other supporting data which
will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right
may be exercised in connection with any negotiations prior to contract award.

(Reverse of CECC Form 3052, Jul 17)

AF3052 CLIN 001 (2)

CONSTRUCTION COST ESTIMATE BREAKDOWNSolicitation # FA252125B0009FA252125B0009
CONTRACTORADDRESS

CONTRACT FOR PROPOSED TOTAL CONTRACT PRICE

PURCHASE REQUEST FORM PROJECT NUMBER WORK LOCATION

MATERIAL COSTLABOR COST
UNITOTHER
LINEITEMOFQUANTITYMANHOURSAVERAGETOTALDIRECTLINE
NO.MEASUREUNITTOTALMANDAYSRATECOSTSTOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

7Doors and windows0.000.000.00
Basic door and window materials and methods0.000.00
Entrances and storefronts0.000.00
Windows0.000.00
Hardware0.000.00
Glazing0.000.00
8Finishes0.00
Basic finish materials and methods0.00
Ceilings00.00
Paints and coatings0.000.00
Specialties0.000.00
Fire protection devices0.000.00
Furnishings0.00
Furnishings0.000.00
Fabrics0.000.00
9Special construction0.000.00
Hazardous material remediation0.00
Detection and alarms0.00
10Mechanical0.000.00
Subtotals for Col 5, 8, 9 and 100.000.000.000.00
AF FORM 3052PAGE 1
INSTRUCTIONS FOR COMPLETING AF FORM 3052
Col (Column) 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient
detail to permit itemizing of all direct costs.
Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples--square yards--SY, cubic yards--
CY, square feet--SF, linear feet--LF, board feet--BF, each--EA, pound--LB).
Col 3 Quantity. Constractor's estimate of quantity required in terms of unit of measure (Col 2). Items and units of measure may
be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price
contract will be issued. Otherwise, the contractor is responsible for determining all quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total costs (Col 5) for items listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in column 6 the estimated number of manhours or mandays needed to perform the work listed in
column 1. Enter in Col 7 the average rate per manhour (manday) and in Col 8 the total labor cost.
Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1) which are special to the
contract and of significant dollar value.

Col 10 Line Total. Self-explanatory.

NOTE: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on
the last page as follows.

TOTAL MATERIAL COSTS $

TOTAL LABOR COSTS $

TOTAL OTHER DIRECT COSTS $

TOAL DIRECT COSTS $

OVERHEAD (RATE: __________________%) $

SUBTOTAL $

PROFIT (RATE: __________________%) $

SUBTOTAL $

BOND (RATE: __________________%) $

TOTAL PRICE $

DATE FIRM NAME

TITLEBY
(Signature)

INSTRUCTIONS TO OFFERORS

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of
incurred and estimated costs (and attached supporting information) suitable for detailed review and analysis. Prior to the award
of a contract resulting from this proposal the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a
certificate of current cost or pricing data (see ASPR 3-807.3(e) and 3.807.4).
2. In addition to the specific information required by this form, the offeror is expected, in good faith, to incorporate in and submit
with this form any additional data, supporting schedules, or substantiation which are reasonably required for the conduct of an
appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that
there be a clear understanding of
a. The existing, verifiable data
b. The judgmental factors applied in projecting from known data to the estimate, and
c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticalbe, the data will be described (with schdules as
appropriate), and made available to the contracting officer or his authorized representative on request.
4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine,
for the purpose of verifying the cost or pricing data submitted, those books, records, documents, and other supporting data which
will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right
may be exercised in connection with any negotiations prior to contract award.
(Reverse of AF Form 3052, Jan 88)
*U.S. GOVERNMENT PRINTING OFFICE: 1988-24D-979:51319

AF3052 CLIN 001 (3)

CONSTRUCTION COST ESTIMATE BREAKDOWNSolicitation # FA252125B0009
CONTRACTORADDRESS

CONTRACT FOR PROPOSED TOTAL CONTRACT PRICE

PURCHASE REQUEST FORM PROJECT NUMBER WORK LOCATION

MATERIAL COSTLABOR COST
UNITOTHER
LINEITEMOFQUANTITYMANHOURSAVERAGETOTALDIRECTLINE
NO.MEASUREUNITTOTALMANDAYSRATECOSTSTOTAL

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Mechanical0.000.000.00
11Electrical0.000.00
Basic electrical materials and methods0.000.00
Lighting0.000.00
0.000.00
0.000.00
0.00
0.00
00.00
0.000.00
0.000.00
0.000.00
0.00
0.000.00
0.000.00
0.000.00
0.00
0.00
0.000.00
Subtotals for Col 5, 8, 9 and 100.000.000.000.00
AF FORM 3052PAGE 1
INSTRUCTIONS FOR COMPLETING AF FORM 3052
Col (Column) 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient
detail to permit itemizing of all direct costs.
Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples--square yards--SY, cubic yards--
CY, square feet--SF, linear feet--LF, board feet--BF, each--EA, pound--LB).
Col 3 Quantity. Constractor's estimate of quantity required in terms of unit of measure (Col 2). Items and units of measure may
be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price
contract will be issued. Otherwise, the contractor is responsible for determining all quantity estimates.

Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total costs (Col 5) for items listed in column 1.

Col 6, 7 and 8 Labor Costs. Enter in column 6 the estimated number of manhours or mandays needed to perform the work listed in
column 1. Enter in Col 7 the average rate per manhour (manday) and in Col 8 the total labor cost.
Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1) which are special to the
contract and of significant dollar value.

Col 10 Line Total. Self-explanatory.

NOTE: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on
the last page as follows.

TOTAL MATERIAL COSTS $

TOTAL LABOR COSTS $

TOTAL OTHER DIRECT COSTS $

TOAL DIRECT COSTS $

OVERHEAD (RATE: __________________%) $

SUBTOTAL $

PROFIT (RATE: __________________%) $

SUBTOTAL $

BOND (RATE: __________________%) $

TOTAL PRICE $

DATE FIRM NAME

TITLEBY
(Signature)

INSTRUCTIONS TO OFFERORS

1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of
incurred and estimated costs (and attached supporting information) suitable for detailed review and analysis. Prior to the award
of a contract resulting from this proposal the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a
certificate of current cost or pricing data (see ASPR 3-807.3(e) and 3.807.4).
2. In addition to the specific information required by this form, the offeror is expected, in good faith, to incorporate in and submit
with this form any additional data, supporting schedules, or substantiation which are reasonably required for the conduct of an
appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that
there be a clear understanding of
a. The existing, verifiable data
b. The judgmental factors applied in projecting from known data to the estimate, and
c. The contingencies used by the offeror in his proposed price.

In short, the offeror's estimating process itself needs to be disclosed.

3. When attachment of supporting cost or pricing data to this form is impracticalbe, the data will be described (with schdules as
appropriate), and made available to the contracting officer or his authorized representative on request.
4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine,
for the purpose of verifying the cost or pricing data submitted, those books, records, documents, and other supporting data which
will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right
may be exercised in connection with any negotiations prior to contract award.
(Reverse of AF Form 3052, Jan 88)
*U.S. GOVERNMENT PRINTING OFFICE: 1988-24D-979:51319

File details come from the government source that posted it. Updated .