The document is an Air Force Form 3052 Construction Cost Estimate Breakdown template for Solicitation # FA252125B0009, designed to provide a detailed cost breakdown for a construction project at Ascension Auxiliary Airfield. The template requires contractors to itemize costs across multiple construction categories including general requirements, sitework, concrete, metals, doors and windows, finishes, mechanical, and electrical work, with specific columns for material costs, labor costs, manhours, and other direct costs.
The form includes comprehensive instructions for completing each column, emphasizing the need for detailed, verifiable cost data and supporting documentation. Contractors are expected to provide unit costs, quantities, labor rates, and total costs for each line item, with the ultimate goal of developing a transparent and analyzable cost estimate for the government. The template also requires contractors to potentially disclose overhead rates, profit rates, and bonding costs, and grants the contracting officer the right to examine supporting documentation to verify the submitted cost and pricing data.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AF3052 CLIN 001
| CONSTRUCTION COST ESTIMATE BREAKDOWN | Solicitation # FA252125B0009 | ||
| CONTRACTOR | ADDRESS |
CONTRACT FOR PROPOSED TOTAL CONTRACT PRICE
| PURCHASE REQUEST FORM | PROJECT NUMBER | WORK LOCATION | ||||||||
| YXTK 13-1806 RPR FEEDER 5 | ASCENSION AUXILIARY AIRFIELD | |||||||||
| MATERIAL COST | LABOR COST | |||||||||
| UNIT | OTHER | |||||||||
| LINE | ITEM | OF | QUANTITY | MANHOURS | AVERAGE | TOTAL | DIRECT | LINE | ||
| NO. | MEASURE | UNIT | TOTAL | MANDAYS | RATE | COSTS | TOTAL |
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
| 1 | General requirements | 0.00 | 0.00 | 0.00 | |||||
| Administrative requirements | 0.00 | 0.00 | |||||||
| EXAMPLE: Project Manager | ? | ? | ? | ? | ? | ||||
| Temporary facilities and controls | 0.00 | 0.00 | |||||||
| Execution requirements | 0.00 | 0.00 | |||||||
| Facility operations | 0.00 | 0.00 | |||||||
| 2 | Sitework | 0.00 | |||||||
| Site preparation | 0.00 | ||||||||
| 3 | Concrete | 0 | 0.00 | ||||||
| Formwork | 0.00 | 0.00 | |||||||
| EXAMPLE: Isolated Beam Side Forms | ? | ? | ? | ? | ? | ? | ? | ? | |
| Concrete reinforcing | 0.00 | 0.00 | |||||||
| Cast in place concrete | 0.00 | ||||||||
| 4 | Metals | 0.00 | 0.00 | ||||||
| Basic metal materials and methods | 0.00 | 0.00 | |||||||
| Structural framing | 0.00 | 0.00 | |||||||
| Metal restoration and cleaning | 0.00 | ||||||||
| 6 | Wood and plastics | 0.00 | |||||||
| Basic wood and plastic materials and methods | 0.00 | 0.00 |
| Subtotals for Col 5, 8, 9 and 10 | 0.00 | 0.00 | 0.00 | 0.00 | |
| CECC FORM 3052 | PAGE 1 | ||||
| INSTRUCTIONS FOR COMPLETING CECC FORM 3052 |
| Col (Column) 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient |
| detail to permit itemizing of all direct costs. |
| Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples--square yards--SY, cubic yards-- |
| CY, square feet--SF, linear feet--LF, board feet--BF, each--EA, pound--LB). |
| Col 3 Quantity. Constractor's estimate of quantity required in terms of unit of measure (Col 2). Items and units of measure may |
| be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price |
| contract will be issued. Otherwise, the contractor is responsible for determining all quantity estimates. |
Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total costs (Col 5) for items listed in column 1.
| Col 6, 7 and 8 Labor Costs. Enter in column 6 the estimated number of manhours or mandays needed to perform the work listed in |
| column 1. Enter in Col 7 the average rate per manhour (manday) and in Col 8 the total labor cost. |
| Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1) which are special to the |
| contract and of significant dollar value. |
Col 10 Line Total. Self-explanatory.
| NOTE: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on |
| the last page as follows. |
TOTAL MATERIAL COSTS $
TOTAL LABOR COSTS $
TOTAL OTHER DIRECT COSTS $
TOAL DIRECT COSTS $
OVERHEAD (RATE: __________________%) $
SUBTOTAL $
PROFIT (RATE: __________________%) $
SUBTOTAL $
BOND (RATE: __________________%) $
TOTAL PRICE $
DATE FIRM NAME
| TITLE | BY | |
| (Signature) |
INSTRUCTIONS TO OFFERORS
| 1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of |
| incurred and estimated costs (and attached supporting information) suitable for detailed review and analysis. Prior to the award |
| of a contract resulting from this proposal the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a |
| certificate of current cost or pricing data (see ASPR 3-807.3(e) and 3.807.4). |
| 2. In addition to the specific information required by this form, the offeror is expected, in good faith, to incorporate in and submit | |
| with this form any additional data, supporting schedules, or substantiation which are reasonably required for the conduct of an | |
| appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that | |
| there be a clear understanding of | |
| a. The existing, verifiable data | |
| b. The judgmental factors applied in projecting from known data to the estimate, and | |
| c. The contingencies used by the offeror in his proposed price. |
In short, the offeror's estimating process itself needs to be disclosed.
| 3. When attachment of supporting cost or pricing data to this form is impracticalbe, the data will be described (with schdules as |
| appropriate), and made available to the contracting officer or his authorized representative on request. |
| 4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, |
| for the purpose of verifying the cost or pricing data submitted, those books, records, documents, and other supporting data which |
| will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right |
| may be exercised in connection with any negotiations prior to contract award. |
(Reverse of CECC Form 3052, Jul 17)
AF3052 CLIN 001 (2)
| CONSTRUCTION COST ESTIMATE BREAKDOWN | Solicitation # FA252125B0009 | FA252125B0009 | ||
| CONTRACTOR | ADDRESS |
CONTRACT FOR PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST FORM PROJECT NUMBER WORK LOCATION
| MATERIAL COST | LABOR COST | |||||||||
| UNIT | OTHER | |||||||||
| LINE | ITEM | OF | QUANTITY | MANHOURS | AVERAGE | TOTAL | DIRECT | LINE | ||
| NO. | MEASURE | UNIT | TOTAL | MANDAYS | RATE | COSTS | TOTAL |
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
| 7 | Doors and windows | 0.00 | 0.00 | 0.00 | ||
| Basic door and window materials and methods | 0.00 | 0.00 | ||||
| Entrances and storefronts | 0.00 | 0.00 | ||||
| Windows | 0.00 | 0.00 | ||||
| Hardware | 0.00 | 0.00 | ||||
| Glazing | 0.00 | 0.00 | ||||
| 8 | Finishes | 0.00 | ||||
| Basic finish materials and methods | 0.00 | |||||
| Ceilings | 0 | 0.00 | ||||
| Paints and coatings | 0.00 | 0.00 | ||||
| Specialties | 0.00 | 0.00 | ||||
| Fire protection devices | 0.00 | 0.00 | ||||
| Furnishings | 0.00 | |||||
| Furnishings | 0.00 | 0.00 | ||||
| Fabrics | 0.00 | 0.00 | ||||
| 9 | Special construction | 0.00 | 0.00 | |||
| Hazardous material remediation | 0.00 | |||||
| Detection and alarms | 0.00 | |||||
| 10 | Mechanical | 0.00 | 0.00 | |||
| Subtotals for Col 5, 8, 9 and 10 | 0.00 | 0.00 | 0.00 | 0.00 | ||
| AF FORM 3052 | PAGE 1 | |||||
| INSTRUCTIONS FOR COMPLETING AF FORM 3052 |
| Col (Column) 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient |
| detail to permit itemizing of all direct costs. |
| Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples--square yards--SY, cubic yards-- |
| CY, square feet--SF, linear feet--LF, board feet--BF, each--EA, pound--LB). |
| Col 3 Quantity. Constractor's estimate of quantity required in terms of unit of measure (Col 2). Items and units of measure may |
| be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price |
| contract will be issued. Otherwise, the contractor is responsible for determining all quantity estimates. |
Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total costs (Col 5) for items listed in column 1.
| Col 6, 7 and 8 Labor Costs. Enter in column 6 the estimated number of manhours or mandays needed to perform the work listed in |
| column 1. Enter in Col 7 the average rate per manhour (manday) and in Col 8 the total labor cost. |
| Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1) which are special to the |
| contract and of significant dollar value. |
Col 10 Line Total. Self-explanatory.
| NOTE: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on |
| the last page as follows. |
TOTAL MATERIAL COSTS $
TOTAL LABOR COSTS $
TOTAL OTHER DIRECT COSTS $
TOAL DIRECT COSTS $
OVERHEAD (RATE: __________________%) $
SUBTOTAL $
PROFIT (RATE: __________________%) $
SUBTOTAL $
BOND (RATE: __________________%) $
TOTAL PRICE $
DATE FIRM NAME
| TITLE | BY | |
| (Signature) |
INSTRUCTIONS TO OFFERORS
| 1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of |
| incurred and estimated costs (and attached supporting information) suitable for detailed review and analysis. Prior to the award |
| of a contract resulting from this proposal the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a |
| certificate of current cost or pricing data (see ASPR 3-807.3(e) and 3.807.4). |
| 2. In addition to the specific information required by this form, the offeror is expected, in good faith, to incorporate in and submit | |
| with this form any additional data, supporting schedules, or substantiation which are reasonably required for the conduct of an | |
| appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that | |
| there be a clear understanding of | |
| a. The existing, verifiable data | |
| b. The judgmental factors applied in projecting from known data to the estimate, and | |
| c. The contingencies used by the offeror in his proposed price. |
In short, the offeror's estimating process itself needs to be disclosed.
| 3. When attachment of supporting cost or pricing data to this form is impracticalbe, the data will be described (with schdules as |
| appropriate), and made available to the contracting officer or his authorized representative on request. |
| 4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, |
| for the purpose of verifying the cost or pricing data submitted, those books, records, documents, and other supporting data which |
| will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right |
| may be exercised in connection with any negotiations prior to contract award. |
| (Reverse of AF Form 3052, Jan 88) | |
| *U.S. GOVERNMENT PRINTING OFFICE: 1988-24D-979:51319 |
AF3052 CLIN 001 (3)
| CONSTRUCTION COST ESTIMATE BREAKDOWN | Solicitation # FA252125B0009 | ||
| CONTRACTOR | ADDRESS |
CONTRACT FOR PROPOSED TOTAL CONTRACT PRICE
PURCHASE REQUEST FORM PROJECT NUMBER WORK LOCATION
| MATERIAL COST | LABOR COST | |||||||||
| UNIT | OTHER | |||||||||
| LINE | ITEM | OF | QUANTITY | MANHOURS | AVERAGE | TOTAL | DIRECT | LINE | ||
| NO. | MEASURE | UNIT | TOTAL | MANDAYS | RATE | COSTS | TOTAL |
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10)
| Mechanical | 0.00 | 0.00 | 0.00 | |||
| 11 | Electrical | 0.00 | 0.00 | |||
| Basic electrical materials and methods | 0.00 | 0.00 | ||||
| Lighting | 0.00 | 0.00 | ||||
| 0.00 | 0.00 | |||||
| 0.00 | 0.00 | |||||
| 0.00 | ||||||
| 0.00 | ||||||
| 0 | 0.00 | |||||
| 0.00 | 0.00 | |||||
| 0.00 | 0.00 | |||||
| 0.00 | 0.00 | |||||
| 0.00 | ||||||
| 0.00 | 0.00 | |||||
| 0.00 | 0.00 | |||||
| 0.00 | 0.00 | |||||
| 0.00 | ||||||
| 0.00 | ||||||
| 0.00 | 0.00 | |||||
| Subtotals for Col 5, 8, 9 and 10 | 0.00 | 0.00 | 0.00 | 0.00 | ||
| AF FORM 3052 | PAGE 1 | |||||
| INSTRUCTIONS FOR COMPLETING AF FORM 3052 |
| Col (Column) 1 Item. Description of materials required, work to be done, special equipment needed, etc. Breakdown should be in sufficient |
| detail to permit itemizing of all direct costs. |
| Col 2 Unit of Measure. Description of the unit in which each item is to be estimated (examples--square yards--SY, cubic yards-- |
| CY, square feet--SF, linear feet--LF, board feet--BF, each--EA, pound--LB). |
| Col 3 Quantity. Constractor's estimate of quantity required in terms of unit of measure (Col 2). Items and units of measure may |
| be furnished by the Government. Quantity estimates will be furnished by the Government only when it is anticipated that a unit price |
| contract will be issued. Otherwise, the contractor is responsible for determining all quantity estimates. |
Col 4 and 5 Material Costs. Enter unit cost (Col 4) of material to be supplied and total costs (Col 5) for items listed in column 1.
| Col 6, 7 and 8 Labor Costs. Enter in column 6 the estimated number of manhours or mandays needed to perform the work listed in |
| column 1. Enter in Col 7 the average rate per manhour (manday) and in Col 8 the total labor cost. |
| Col 9 Other Direct Costs. Enter estimated costs of special equipment and other items (listed in column 1) which are special to the |
| contract and of significant dollar value. |
Col 10 Line Total. Self-explanatory.
| NOTE: In addition to other totals entered on various pages, the grand total of column 10, plus overhead and profit will be shown on |
| the last page as follows. |
TOTAL MATERIAL COSTS $
TOTAL LABOR COSTS $
TOTAL OTHER DIRECT COSTS $
TOAL DIRECT COSTS $
OVERHEAD (RATE: __________________%) $
SUBTOTAL $
PROFIT (RATE: __________________%) $
SUBTOTAL $
BOND (RATE: __________________%) $
TOTAL PRICE $
DATE FIRM NAME
| TITLE | BY | |
| (Signature) |
INSTRUCTIONS TO OFFERORS
| 1. The purpose of this form is to provide a standard format by which the offeror submits to the Government a summary of |
| incurred and estimated costs (and attached supporting information) suitable for detailed review and analysis. Prior to the award |
| of a contract resulting from this proposal the offeror shall, under the conditions stated in ASPR 3-807.3, be required to submit a |
| certificate of current cost or pricing data (see ASPR 3-807.3(e) and 3.807.4). |
| 2. In addition to the specific information required by this form, the offeror is expected, in good faith, to incorporate in and submit | |
| with this form any additional data, supporting schedules, or substantiation which are reasonably required for the conduct of an | |
| appropriate review and analysis in the light of the specific facts of this procurement. For effective negotiations, it is essential that | |
| there be a clear understanding of | |
| a. The existing, verifiable data | |
| b. The judgmental factors applied in projecting from known data to the estimate, and | |
| c. The contingencies used by the offeror in his proposed price. |
In short, the offeror's estimating process itself needs to be disclosed.
| 3. When attachment of supporting cost or pricing data to this form is impracticalbe, the data will be described (with schdules as |
| appropriate), and made available to the contracting officer or his authorized representative on request. |
| 4. By submission of this proposal the offeror grants to the contracting officer, or his authorized representative, the right to examine, |
| for the purpose of verifying the cost or pricing data submitted, those books, records, documents, and other supporting data which |
| will permit adequate evaluation of such cost or pricing data, along with the computations and projections used therein. This right |
| may be exercised in connection with any negotiations prior to contract award. |
| (Reverse of AF Form 3052, Jan 88) | |