5. Record of EqmtMat List Template (OM Database).xlsx

XLSX spreadsheet 64 KB Posted

Attached to
YXTK 13-1806 Repair Electrical Distribution Lines, Feeder 5, Ascension Auxiliary Airfield (AAAF), South Atlantic Ocean
Solicitation number
FA252125B0009
Issued by

About this file

The file is an Equipment and Materials List Template Excel spreadsheet designed for documenting equipment details across multiple project systems. The template includes standardized tabs for tracking equipment inventory in seven key areas: Finishes, Communication, Electrical, Fire Alarm, Fire Suppression, Mechanical, Plumbing, and Roofing/Project Specific Items. Each tab provides fields for capturing comprehensive equipment information such as quantity, description, room number, manufacturer details, model number, serial number, warranty start and end dates, and additional specification-related information.

The template is intended for contractors to comprehensively document all equipment and systems per a project's Statement of Work (SOW), with instructions to add or delete tabs as required and note any extended manufacturer warranties. The related federal contract opportunity, issued by the Department of the Air Force Space Command, involves repairing electrical distribution lines at the Ascension Auxiliary Airfield, which includes removing and replacing overhead electrical lines, poles, hardware, and installing new underground duct banks and electrical equipment.

View the file

Other files

File Type Posted
FA252125B0009 SF1409.pdf PDF
24. Geology Study-Investigation (1997) (Ref Only).pdf PDF
23. YXTK 13-1806 RPR FDR 5 Design Analysis (Section 5) (Ref Only)).pdf PDF
22. Government Response to Contractor Submitted Questions.pdf PDF
FA252125B0009 A004.pdf PDF
FA252125B0009 A003.pdf PDF
FA252125B0009 A002.pdf PDF
Solicitation Amendment FA252125B00090001 SF 30.pdf PDF
19. Ascension Island PSD.pdf PDF
18. Catherine Point PSD (Services Distribution).pdf PDF
17. Installation Facility Standards Ascension Auxiliary Airfield.pdf PDF
13. YXTK 13-1806 (FY23 Historical Contractor Question-Govt Responses).pdf PDF
2. YXTK 13-1806 Specifications.pdf PDF
1. YXTK 13-1806 DWG.pdf PDF
21. Facility 800 Photos.pdf PDF
10. QA Template.docx DOCX document
7. Contractor Travel Request Form.pdf PDF
FA252125B0009 (YXTK 13-1806 RPR Electrical Dist Sys (Feeder 5)) IFB.pdf PDF
16. Enivronmental Final Governing Standards Ascension Island.pdf PDF
14. YXTK 13-1806 DWG E-409 (RevA).pdf PDF
6. CECC Form 3052 Template.xlsx XLSX spreadsheet
4. Contractor HAZMAT Usage Worksheet.xlsx XLSX spreadsheet
3. YXTK 13-1806 Recovered Materials Determination Form (Green Procurement).pdf PDF
20. Fiber Wall Mount Dist Cabinets Photos.pdf PDF
15. Concrete Mix Design (Local Aggregate).pdf PDF
12. MH 42 Photos.pdf PDF
11. Site Visit Procedures.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Finishes

Project No:
Project Title:
Date:
Submitted by: (contractor's name)
ItemQty.DescriptionRoom No.Manufacturer (MFR)MFR AddressMFR PhoneModel #Serial #Warranty Start DateWarranty Ending DateAdditional Informaiton per Spec's Section 01 78 00 & 01 78 23
1. Contractor to inlcude all Equipment/Systems per project's SOW. Add or delete tabs as required.
2. If additoinal time periods beyond what is listed is being provided, include extended manufacture's warranty (show with an asterisk under the warranty cells).

Communication

Project No:
Project Title:
Date:
Submitted by: (contractor's name)
ItemQty.DescriptionRoom No.Manufacturer (MFR)MFR AddressMFR PhoneModel #Serial #Warranty Start DateWarranty Ending DateAdditional Informaiton per Spec's Section 01 78 00 & 01 78 23
1. Contractor to inlcude all Equipment/Systems per project's SOW. Add or delete tabs as required.
2. If additoinal time periods beyond what is listed is being provided, include extended manufacture's warranty (show with an asterisk under the warranty cells).

Electrical

Project No:
Project Title:
Date:
Submitted by: (contractor's name)
ItemQty.DescriptionRoom No.Manufacturer (MFR)MFR AddressMFR PhoneModel #Serial #Warranty Start DateWarranty Ending DateAdditional Informaiton per Spec's Section 01 78 00 & 01 78 23
Equipment (Transformers, Panel Boards, Disconnects, etc)

Interior Elect Distribution (Lighting, Switches, Receptacles)

Feeders

Grounding

Flooring Grounding (ESD Flooring)

1. Contractor to inlcude all Equipment/Systems per project's SOW. Add or delete tabs as required.
2. If additoinal time periods beyond what is listed is being provided, include extended manufacture's warranty (show with an asterisk under the warranty cells).

Fire Alarm

Project No:
Project Title:
Date:
Submitted by: (contractor's name)
ItemQty.DescriptionRoom No.Manufacturer (MFR)MFR AddressMFR PhoneModel #Serial #Warranty Start DateWarranty Ending DateAdditional Informaiton per Spec's Section 01 78 00 & 01 78 23
1. Contractor to inlcude all Equipment/Systems per project's SOW. Add or delete tabs as required.
2. If additoinal time periods beyond what is listed is being provided, include extended manufacture's warranty (show with an asterisk under the warranty cells).

Fire Suppression

Project No:
Project Title:
Date:
Submitted by: (contractor's name)
ItemQty.DescriptionRoom No.Manufacturer (MFR)MFR AddressMFR PhoneModel #Serial #Warranty Start DateWarranty Ending DateAdditional Informaiton per Spec's Section 01 78 00 & 01 78 23
1. Contractor to inlcude all Equipment/Systems per project's SOW. Add or delete tabs as required.
2. If additoinal time periods beyond what is listed is being provided, include extended manufacture's warranty (show with an asterisk under the warranty cells).

Mechanical

Project No:
Project Title:
Date:
Submitted by: (contractor's name)
ItemQty.DescriptionRoom No.Manufacturer (MFR)MFR AddressMFR PhoneModel #Serial #Warranty Start DateWarranty Ending DateAdditional Informaiton per Spec's Section 01 78 00 & 01 78 23
Dedicated Outside Air

Condensing Unit

Duct Heater

FN Coil-VRF System

Exhaust Fans

Thermostat

1. Contractor to inlcude all Equipment/Systems per project's SOW. Add or delete tabs as required.
2. If additoinal time periods beyond what is listed is being provided, include extended manufacture's warranty (show with an asterisk under the warranty cells).

Plumbing

Project No:
Project Title:
Date:
Submitted by: (contractor's name)
ItemQty.DescriptionRoom No.Manufacturer (MFR)MFR AddressMFR PhoneModel #Serial #Warranty Start DateWarranty Ending DateAdditional Informaiton per Spec's Section 01 78 00 & 01 78 23
Equipment, Fixtures, Piping, etc.
1. Contractor to inlcude all Equipment/Systems per project's SOW. Add or delete tabs as required.
2. If additoinal time periods beyond what is listed is being provided, include extended manufacture's warranty (show with an asterisk under the warranty cells).

Roofing or Proj Specific Items

Project No:
Project Title:
Date:
Submitted by: (contractor's name)
ItemQty.DescriptionRoom No.Manufacturer (MFR)MFR AddressMFR PhoneModel #Serial #Warranty Start DateWarranty Ending DateAdditional Informaiton per Specifications Section 07 78 00
1. Contractor to inlcude all Equipment/Systems per project's SOW. Add or delete tabs as required.
2. If additoinal time periods beyond what is listed is being provided, include extended manufacture's warranty (show with an asterisk under the warranty cells).

File details come from the government source that posted it. Updated .