2. YXTK 13-1806 Specifications.pdf

PDF 2 MB Posted

Attached to
YXTK 13-1806 Repair Electrical Distribution Lines, Feeder 5, Ascension Auxiliary Airfield (AAAF), South Atlantic Ocean
Solicitation number
FA252125B0009
Issued by

About this file

This document is a detailed project specification for the repair and replacement of the existing overhead Feeder 5 electrical distribution lines at Ascension Auxiliary Airfield (AAAF) in the South Atlantic Ocean. The project involves comprehensive electrical infrastructure work, including removing existing overhead distribution lines, poles, hardware, guy cables/anchors, and electrical equipment, and replacing them with new overhead open wire and triplex circuit infrastructure. Key components include installing new poles, pole hardware, guy cables/anchors, electrical equipment, a Load Break Switch, manholes, and underground duct banks near Hogan's Bypass to allow distribution lines to pass underneath roads without clearance issues.

The specification provides extensive technical requirements for materials and installation, covering concrete poles, medium-voltage cables, overhead transmission and distribution equipment, transformers, switches, and telecommunications optical backbone cabling. The project requires precise installation methods, including specific grounding techniques, cable pulling procedures, and comprehensive testing protocols. The work will be performed under a Department of the Air Force Space Command contract, with a focus on ensuring high-quality electrical infrastructure that meets stringent military engineering standards and performance requirements.

View the file

Other files

File Type Posted
FA252125B0009 SF1409.pdf PDF
24. Geology Study-Investigation (1997) (Ref Only).pdf PDF
23. YXTK 13-1806 RPR FDR 5 Design Analysis (Section 5) (Ref Only)).pdf PDF
22. Government Response to Contractor Submitted Questions.pdf PDF
FA252125B0009 A004.pdf PDF
FA252125B0009 A003.pdf PDF
FA252125B0009 A002.pdf PDF
Solicitation Amendment FA252125B00090001 SF 30.pdf PDF
19. Ascension Island PSD.pdf PDF
18. Catherine Point PSD (Services Distribution).pdf PDF
17. Installation Facility Standards Ascension Auxiliary Airfield.pdf PDF
13. YXTK 13-1806 (FY23 Historical Contractor Question-Govt Responses).pdf PDF
1. YXTK 13-1806 DWG.pdf PDF
16. Enivronmental Final Governing Standards Ascension Island.pdf PDF
14. YXTK 13-1806 DWG E-409 (RevA).pdf PDF
6. CECC Form 3052 Template.xlsx XLSX spreadsheet
4. Contractor HAZMAT Usage Worksheet.xlsx XLSX spreadsheet
3. YXTK 13-1806 Recovered Materials Determination Form (Green Procurement).pdf PDF
21. Facility 800 Photos.pdf PDF
10. QA Template.docx DOCX document
7. Contractor Travel Request Form.pdf PDF
FA252125B0009 (YXTK 13-1806 RPR Electrical Dist Sys (Feeder 5)) IFB.pdf PDF
20. Fiber Wall Mount Dist Cabinets Photos.pdf PDF
15. Concrete Mix Design (Local Aggregate).pdf PDF
12. MH 42 Photos.pdf PDF
11. Site Visit Procedures.pdf PDF
5. Record of EqmtMat List Template (OM Database).xlsx XLSX spreadsheet
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Orlando Office | The Day Building | 605 East Robinson Street, Suite 750 | Orlando, FL 32801 TRACES Office |14655 S.C. Phillips ParkwayFAC 1708 | Hangar R, Southside CCAFS, FL 32920

Nelson Engineering Co.

5455 N Courtenay Pkwy Merritt Island, FL 32953

PROJECT SPECIFICATIONS

YXTK 13-1806

Repair Electrical Distribution Lines, Feeder 5

100% Submittal

12/10/2021

Contract Number: TRACES-FA2521-18-D-0002

Ascension Auxiliary Airfield, South Atlantic Ocean

Prime Consultant:

Rhodes+Brito Architects

605 E. Robinson Street, Suite 750 Orlando, FL 32801

Sub-Consultants:

Repair Electrical Distribution Lines, Feeder 5 YXTK 13-1806

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 03/17 GENERAL SPECIFICATIONS

01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES

01 35 26 11/20 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 11/16, CHG 1: 02/20 QUALITY CONTROL

01 74 19 02/19 CONSTRUCTION WASTE MANAGEMENT AND

DISPOSAL

01 78 00 05/19 CLOSEOUT SUBMITTALS

01 78 23 08/15, CHG 1: 11/20 OPERATION AND MAINTENANCE DATA

DIVISION 03 - CONCRETE

03 30 00 02/19 CAST-IN-PLACE CONCRETE

DIVISION 26 - ELECTRICAL

26 05 00.00 40 11/20 COMMON WORK RESULTS FOR ELECTRICAL

26 05 13.00 40 05/20 MEDIUM-VOLTAGE CABLES

26 08 00 08/08, CHG 2: 08/21 APPARATUS INSPECTION AND TESTING

26 12 19.00 40 11/14, CHG 1: 08/17 PAD-MOUNTED, LIQUID-FILLED,

MEDIUM-VOLTAGE TRANSFORMERS

DIVISION 27 - COMMUNICATIONS

27 13 23.00 40 11/14 COMMUNICATIONS OPTICAL BACKBONE CABLING

DIVISION 31 - EARTHWORK

31 00 00 08/08 EARTHWORK

DIVISION 33 - UTILITIES

33 71 01.00 40 11/14, CHG 1: 02/17 OVERHEAD TRANSMISSION AND DISTRIBUTION

33 77 19.00 40 08/16 MEDIUM-VOLTAGE SWITCH

33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 00 00

GENERAL SPECIFICATIONS

03/17

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 LOCATION

1.4 SCOPE

1.4.1 Summary of Work

1.4.1.1 Civil

1.4.1.2 Electrical

1.4.2 Equipment Availability

1.5 Preconstruction Survey

1.6 OCCUPANCY OF PREMISES/ACCESS REQUIREMENTS

1.6.1 Facility Contents

1.6.1.1 Responsibilities

1.6.1.2 Maintain Clean Work Areas

1.6.1.3 Damage To Existing Equipment

1.6.1.4 New Material and Construction Equipment

1.6.2 Construction Area Access And Control

1.6.2.1 Access and Control Requirements

1.6.3 Vehicle Parking

1.6.3.1 Requirements

1.7 QUALITY CONTROL

1.8 DRAWINGS

1.9 REMOVAL AND DISPOSAL

1.10 MATERIALS SUBMITTALS

1.11 SUPERINTENDENT

1.12 TURN-IN OF IDENTIFIED EQUIPMENT, SPARE PARTS, TOOLS, ETC.

1.13 AS-BUILT RECORD DRAWINGS

1.14 EQUIPMENT LIST

1.15 PREFINAL INSPECTION SPECIAL REQUIREMENTS

1.16 FINAL INSPECTION ONLY

1.17 SCHEDULES

1.17.1 Work Schedules

1.17.2 Construction Progress Schedules

1.17.3 Working Hours

1.18 UTILITIES

1.19 LAYOUT OF WORK AND ELEVATIONS

1.20 PROTECTION OF EXISTING FACILITY

1.21 ACCESS

1.21.1 Listing of Personnel

1.21.2 Parking

1.22 DELIVERY AND STORAGE

1.22.1 Storage Facilities

1.22.2 Post Transport/Delivery Inspection

1.23 DIGGING/EXCAVATION REQUIREMENTS

1.23.1 Location of Buried Structures and Utility Lines

12/10/2021 SECTION 01 00 00 Page 1

1.23.2 Excavation, Trenching and Backfilling

1.24 GOVERNMENT-FURNISHED MATERIALS AND EQUIPMENT

1.25 SALVAGEABLE MATERIALS

1.26 GENERAL SAFETY REQUIREMENTS

1.26.1 Safeguards for Construction, Alteration, and Demolition

Operations

1.26.2 Traffic Safety

1.26.3 Electrical Work Safety

1.26.4 Fire/Explosives Safety

1.26.4.1 Fire Prevention

1.26.4.2 Smoking/Open Flames

1.26.4.3 Flammable Materials

1.26.4.4 Powder-Actuated Tools

1.26.5 Elevated Work Area Safety

1.26.5.1 Hoisting Equipment

1.26.6 Confined Space Entry

1.27 ENVIRONMENTAL REQUIREMENTS

1.27.1 Storage and Protection

1.27.2 Hazardous Materials/Wastes

1.27.3 Environmental Awareness

1.27.4 Stormwater Protection

1.28 ASBESTOS REMOVAL AND DISPOSAL

1.28.1 Scope and General Responsibilities

1.28.2 Liability

1.29 TOXIC PAINTS/MATERIALS

1.30 TREATED WOOD PRODUCTS

1.31 OZONE DEPLETING CHEMICAL LIMITATION

1.31.1 Affirmative Procurement

1.32 EXISTING CONDITIONS

1.33 PATCHING GOVERNMENT-OWNED FACILITIES

1.34 CONTROL AND DISPOSAL OF SOLID WASTE AND DEBRIS

1.34.1 Toxic Paints and Material Waste Management

1.34.2 Used Oil

1.35 UTILITIES

1.36 BREAKDOWN OF PRICES

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

12/10/2021 SECTION 01 00 00 Page 2

SECTION 01 00 00

GENERAL SPECIFICATIONS

03/17

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 101 (2015; ERTA 2015) Life Safety Code

NFPA 241 (2019) Standard for Safeguarding Construction, Alteration, and Demolition Operations

U.S. DEPARTMENT OF DEFENSE (DOD)

UFC 3-600-01 (2004) Fire Protection Engineering for Facilities

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910 Occupational Safety and Health Standards

29 CFR 1926 Safety and Health Regulations for Construction

40 CFR 370 Hazardous Chemical Reporting: Community Right-To-Know

40 CFR 372 Toxic Chemical Release Reporting:

Community Right-To-Know

40 CFR 260 Hazardous Waste Management System: General

40 CFR 261 Identification and Listing of Hazardous Waste

40 CFR 262 Standards Applicable to Generators of Hazardous Waste

40 CFR 263 Standards Applicable to Transporters of Hazardous Waste

40 CFR 268 Land Disposal Restrictions

49 CFR 172 Hazardous Materials Table, Special Provisions, Hazardous Materials Communications, Emergency Response Information, and Training Requirements

12/10/2021 SECTION 01 00 00 Page 3

49 CFR 178 Specifications for Packagings

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI Z117.1 (2003) Safety Requirements for Confined Spaces

1.2 SUBMITTALS

Government review/approval is required for all submittals. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Contractor's self-inspection and quality control program; G

Project-specific quality control and inspection plan (QC&IP; G)

Schedule of Submissions; G

Initial Schedule; G

Phasing Plan; G

Premises/Access Plan; G

Revised Schedules Monthly; G

Listing of Personnel; G

Accident Prevention Plan; G

Safety Data Sheets; G

(AF Form 3952 for all hazardous materials); G

Assessment Report; G

Shop Drawings; G

SD-11 Closeout Submittals

Prefinal Inspection Submittals; G

As-Built Record Drawings; G

Equipment List; G

Monthly Records of the Weight and Volume of Debris Disposed; G

Unused/Salvageable Equipment Forms DD1149 or AF2005; G

1.3 LOCATION

The work to be accomplished under the subcontract is at Ascension Island Auxiliary Airfield (AAF). Ascension Island is in the South Atlantic Ocean approximately 5,000 miles southeast of Cape Canaveral, Florida and half-way between Africa and South America.

12/10/2021 SECTION 01 00 00 Page 4

1.4 SCOPE

The work to be performed under this project consists of providing the labor, equipment and materials to replace the existing Feeder 5 overhead electrical distribution system for Ascension Auxiliary Airfield to meet current regulations and requirements.

1.4.1 Summary of Work

1.4.1.1 Civil

Civil work includes the installation of new concrete utility poles, trenching for concrete encased duct bank and communication conduit, installation of concrete equipment pads, and demolition of existing wood utility poles.

1.4.1.2 Electrical

Electrical work includes installation of new medium voltage overhead lines on new concrete utility poles, new medium voltage conductor routed through new concrete encased duct bank at every road crossing, and new communication cables routed on same medium voltage concrete utility poles.

The existing Feeder 5 infrastructure will remain operational during construction and will be de-energized and demolished upon installation of new Feeder 5.

1.4.2 Equipment Availability

The Contractor will be responsible to provide or ensure the availability of all equipment required to perform the work in accordance with the Contract Documents. Access to Station equipment will be very limited given the intense requirements for this project. The Contractor should be prepared to provide all required equipment needed for the various placement processes and ensure that it is suitable for working safely on such slopes.

1.5 Preconstruction Survey

Perform a preconstruction survey to validate design conditions, prior to mobilization. Submit an assessment report with shop drawings for any changes to the design scope, as verified in the field. Submit preconstruction survey report and shop drawings including but are not limited to: pole lengths, pole locations, guy wire geometry and locations per pole, concrete pad locations, existing manhole conditions, new manhole locations and orientation, existing duct bank configuration and conditions to support reuse, and new duct bank configurations.

1.6 OCCUPANCY OF PREMISES/ACCESS REQUIREMENTS

Ascension AAF facilities will be partially occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area. Contractor shall post warning signs in accordance with OSHA requirements.

Before work is started, the Contractor shall submit a Premises/Access Plan to the Contracting Officer or Representative for approval. The plan shall include a sequence of procedures, means of access, space plan for storage of materials and equipment, and use of approaches, corridors, and stairways.

12/10/2021 SECTION 01 00 00 Page 5

This plan must comply with NFPA 101 requirements that all exits and exit access must be maintained at all times. Base Fire Department is required to approve any deviations which affect the exiting or exit access from the building.

1.6.1 Facility Contents

1.6.1.1 Responsibilities

The schedule of work must be closely coordinated with the Contracting Officer. Unless otherwise stated, remove all furniture, equipment, curtains, drapes, pictures, blackboards, etc., as required to perform the work. Any movable or fixed furniture, equipment, carpet, etc., remaining in the work area must be covered and protected from damage. All relocated items must also be protected from damage throughout the construction period. After completion of work and prior to final acceptance, replace removed items in their original location.

The entire area will not be available to the Contractor at one time.

Contractor must coordinate with the Contracting Officer the extent of occupancy possible during the construction process.

Demolition of critical facility systems mechanical, electrical, etc. must not be started until replacement equipment is on site.

1.6.1.2 Maintain Clean Work Areas

All work areas must be kept clean at all times. Contractor must prevent introduction of dirt or dust into areas adjacent to the work areas. All materials, tools and equipment must be thoroughly cleaned prior to being brought into the work areas or adjacent areas.

1.6.1.3 Damage To Existing Equipment

Any damage must be reported to the Contracting Officer immediately. Damage to existing materials, equipments, systems, or properties occurring from Contractor activities or neglect, must, at the sole discretion of the Contracting Officer, be repaired or replaced by the Contractor at no cost to the Federal Government.

1.6.1.4 New Material and Construction Equipment

Only material and construction equipment designated for performance of contract work may be stored at the construction site or located in Government-controlled warehouses or shop facilities.

1.6.2 Construction Area Access And Control

1.6.2.1 Access and Control Requirements

Exclusive use or control of any area will not be allowed as the Government must have access to all areas at all times. All work must be scheduled around operational constraints.

1.6.3 Vehicle Parking

1.6.3.1 Requirements

Job and support vehicles for workers will be parked in designated parking

12/10/2021 SECTION 01 00 00 Page 6 areas within reasonable access to the worksite. All vehicle operators must comply with all traffic laws including mandatory seat belt usage, speed limits and hauling restrictions. Contractor will be responsible for repairing or replacing any facility/grounds damaged areas.

1.7 QUALITY CONTROL

The Contractor must use skilled workers, an adequate number of which are thoroughly trained and have a minimum of 3 years experience in the necessary crafts and who are completely familiar with the specified requirements and the methods needed for the proper performance of the work in each section of these specifications. The Contractor will submit to the Contracting Officer's Representative, during the submittal process, a copy of the Contractor's self-inspection and quality control program and a project-specific quality control and inspection plan (QC&IP) listing all test and inspection requirements in the contract documents. The QC&IP must list all tests and inspections by their applicable specification and/or drawing reference. It must also include those tests and inspections recommended by the manufacturer.

Licenses: The General Contractor and their lower-tiered subcontractors must be licensed by the State of Florida or have an equivalent out-of-state license in all areas applicable to this contract.

1.8 DRAWINGS

The drawings indicate the general location and arrangement of existing conditions. It is strongly recommended that the Contractor visit the site to determine the complexity of the work and the existing conditions affecting the work. Field measurements may be necessary to determine the size and quantity of materials. Conditions that are obvious/visible or that should be reasonably anticipated by the Contractor on inspection will not be considered under the Differing Site Conditions Provisions of this contract. Contractor must check furnished drawings and notify the Government of any discrepancies.

1.9 REMOVAL AND DISPOSAL

Remove and/or relocate those materials or items indicated on the drawings.

Remove and/or relocate those materials necessary for the installation of new material for the correct function of same. Perform removal operations in a safe and suitable manner that will not damage the adjacent areas, or existing utilities. Repair any damage incurred during removal operations at no expense to the Government.

1.10 MATERIALS SUBMITTALS

Reference Section 01 33 00 SUBMITTAL PROCEDURES for material submittals.

Within 15 days after Notice to Proceed, Contractor must submit a schedule of submissions. Schedule must indicate approximate dates for submittals to be received by the Contracting Officer's Representative. Schedule must include all materials requiring submittals. All materials and equipment provided in the performance of this Contract must be new and currently being manufactured.

1.11 SUPERINTENDENT

Designate a competent superintendent who must have full authority to act for the Contractor and who will be the primary contact with the Government

12/10/2021 SECTION 01 00 00 Page 7 until acceptance. Provide name and qualifications of superintendent for review during the submittal process. The Contractor's superintendent must be at the job site at all times and will have full authority to act for the Contractor. During the submittal process, provide name and qualifications of superintendent for review.

1.12 TURN-IN OF IDENTIFIED EQUIPMENT, SPARE PARTS, TOOLS, ETC.

Items indicated in construction documents for turn-in to the Government must be delivered as directed before prefinal inspection. Obtain receipts from Government employees receiving the materials and deliver them to the Government before prefinal inspection. Provide a copy of AF form AF2005 for each applicable item.

1.13 AS-BUILT RECORD DRAWINGS

Contractor must maintain two sets of Contract drawings at the jobsite at all times. These drawings will be used as "Progress" As-Builts, and must be continually updated to show all deviations that have been made from the drawings, including buried or concealed construction and utility features revealed, during the course of construction. Contractor must record the horizontal and vertical location of all buried utilities that differ from the contract drawings. These Progress As-Built drawings must be available for review by the Contracting Officer's Representative at any time. Upon completion of the work, submit the marked sets of prints to the Contracting Officer's Representative. Additionally, the Contractor must submit an electronic copy of drawings in AutoCAD 2007 (.DWG format), on CD, clearly indicating as built conditions. Drawings submitted in Drawing Exchange Format (DXF) will not be accepted. Contractor must provide all symbol and text files required. Requests for partial payments may not be approved if the marked Progress As-Builts are not kept current, and the request for final payment will not be approved until Progress As-Builts as well as the electronic copy are acceptable to the Contracting Officer's Representative.

1.14 EQUIPMENT LIST

Provide an equipment list to the Government. Indicate the make, model number, serial number and warranty expiration date of equipment installed by Contractor. The Project Engineer will inform the Contractor which equipment should be on the list. After the list is approved, Contractor must complete GSA Form 274 obtained from the Project Engineer and place it on the equipment, as indicated on the list, before prefinal inspection.

1.15 PREFINAL INSPECTION SPECIAL REQUIREMENTS

Contractor must request in writing, a minimum of 7 days in advance, for a prefinal inspection. At this inspection, Contractor must have work accessible for inspection.

1.16 FINAL INSPECTION ONLY

If the Contracting Officer's Representative elects to have only a final inspection, turn in prefinal inspection submittals before the final inspection.

12/10/2021 SECTION 01 00 00 Page 8

1.17 SCHEDULES

1.17.1 Work Schedules

Work schedules for all on-site activities must be reviewed and approved by the Contracting Officer's Representative prior to start, and all activities coordinated with the Contracting Officer's Representative once work has begun.

Contractor will allow for a maximum of 3 days where a construction activity is prohibited due to hazardous operations or launch activity. The Government will provide a 24-hour notification, if possible, each time the restrictions are invoked.

Project must be scheduled to meet the following requirements:

Length of time between the issuance of a Notice to Proceed and the completion of the work will not exceed 357 days.

On-site construction will not exceed 297 days. (Coordinate with the Government.)

NOTE: The Contractor must attend (on-site) weekly project meetings, not to exceed 2 hours per week. Discussions will address the progress schedule, potential factors of delay, deficiencies, material delivery schedules, Base equipment and operational requirements for next 2 weeks, submittals, and safety issues.

1.17.2 Construction Progress Schedules

Submit for approval an initial schedule including a phasing plan for performance of work within 30 days of Notice to Proceed or as directed by Contracting Officer's Representative. Schedule must be submitted as a Gantt Chart developed in Microsoft Project 2007. Schedule format will duplicate the template format. Template provided upon request. Show complete sequence of construction by activity, identifying work of separate stages and other logically grouped activities. Indicate the early and late start, early and late finish, float dates, and duration.

After initial schedule is approved it will be established as an MSP4 baseline.

Revise and resubmit on a monthly basis. Submit revised schedules with each Application for Payment. Provide copy to Contracting Officer's Representative.

Indicate estimated percentage of completion for each item of work at each submission.

Indicate submittal dates required for shop drawings, product data, samples, and product delivery dates.

1.17.3 Working Hours

Ascension working hours for the Contractor will normally be between 7:30 a.m. and 4:00 p.m. excluding Sundays and Station holidays. If the Contractor desires to work during periods other than above, additional Government inspection forces may be required. Notify the Contracting Officer's Representative 3 days in advance of intention to work during

12/10/2021 SECTION 01 00 00 Page 9 other periods to allow assignment of additional inspection forces when the Contracting Officer's Representative determines that they are reasonably available. If such force is reasonably available, the Contracting Officer's Representative may authorize the Contractor to perform work during periods other than normal duty hours/days.

Ascension Holidays

· New Year's Day

· The 4th of July

· Thanksgiving Day

· The day after Thanksgiving Day

· Christmas Day

· Boxing Day (the day after Christmas)

1.18 UTILITIES

Utility outages must be requested in writing to the Contracting Officer's Representative a minimum for 14 days prior to desired outage. Outages must be limited to 4 hours maximum at any one time, unless otherwise approved by the Contracting Officer's Representative due to unusual circumstances.

Existing utility services may be interrupted only when approved by the Contracting Officer's Representative. The interruption must be scheduled at a time of minimum demand on the utility, convenient to the Government.

Outages on weekends, holidays or evenings will be performed at no additional cost to the Government.

The Contractor must make all necessary arrangements to schedule and provide connections to existing utilities and to cause minimum interruption to system operation. All temporary utility hook-ups and disconnections must be made by the Contractor. All connections and disconnections to existing utilities will be made or approved by Range Operation Support Contractor.

If the Contractor fails to comply with a scheduled outage, the cost to reschedule the outage will be deducted from the final contract payment.

1.19 LAYOUT OF WORK AND ELEVATIONS

Dimensions and elevations indicated in the layout of work will be verified by the Contractor. Contractor must provide his own staking and surveying.

Discrepancies between the drawings, specifications, and/or existing conditions will be referred to the Contracting Officer's Representative in writing, for review, before the affected work is performed. Failure to make notification will place the responsibility upon the Contractor to carry out the work in a satisfactory and workman-like manner.

1.20 PROTECTION OF EXISTING FACILITY

Protect the facility and its contents at all times from weather or damage.

Repair any damage incurred at no additional cost to the Government.

1.21 ACCESS

Exclusive use of any area will not be allowed because Range Contractors must have access to all areas at all times. System will not be operational at all times. Periodic shutdowns will occur. Schedule outages for individual components to perform the work.

12/10/2021 SECTION 01 00 00 Page 10

1.21.1 Listing of Personnel

Submit a numbered listing of all personnel who will be working in the area to Contracting Officer's Representative at the pre-performance conference.

This list will be used for access control. Update this list as necessary.

1.21.2 Parking

Park job and support vehicles in areas designated by the Construction Inspector.

1.22 DELIVERY AND STORAGE

Equipment and materials must be carefully handled, properly stored, and adequately protected to prevent damage before and during installation, in accordance with the manufacturer's recommendations and as approved by the Contracting Officer's Representative. Damaged or defective items, in the opinion of the Contracting Officer's Representative, must be replaced.

1.22.1 Storage Facilities

The Contracting Officer's Representative with the approval of the Fire Department may designate an on-base storage site where the Contractor will provide a temporary weatherproof shelter for storage of Contractor's material. A closed van-type semi-trailer, portable building, or similar structure, all with adequate ventilation, hurricane tie downs, and proper grounding, will be an acceptable shelter if approved by the Contracting Officer's Representative.

Contractor storage and facilities must comply with NFPA 241.

1.22.2 Post Transport/Delivery Inspection

The Contractor will inspect all materials within 5 days of materials arriving on site. Notification of damage occurring in transit or during unloading must be filed with the Contracting Officer's Representative at this time. If a statement of damage is not filed, the Contractor accepts the materials as undamaged and usable, and assumes responsibility for storage and protection.

1.23 DIGGING/EXCAVATION REQUIREMENTS

Contractor must obtain AF Form 103, Base Civil Engineering Work Clearance Request, and Form ERTS 12-004, Ascension AAF Notification of Intention to Excavate, from The Government. The Contractor must prepare and properly complete both forms, including coordination, before beginning any work involving digging/excavation and location of buried structures and utility lines. The Government will be the first and the last to coordinate on these forms. Ten to 15 working days will be allowed for coordination on AF Form 103 and ERTS 12-004. Contact COMM before digging begins.

1.23.1 Location of Buried Structures and Utility Lines

Accurately locate and stake structures and utility lines indicated. On-site personnel will be available to assist in locating existing structures and utility lines. Requests for such assistance will be made through the Government. Provide a drawing indicating the full extent of digging/excavation such as width, depth and length of trench or hole.

12/10/2021 SECTION 01 00 00 Page 11

1.23.2 Excavation, Trenching and Backfilling

Open only those trenches for which material is ready to be placed. As soon as approved by the Government, trenches must be backfilled and tamped as required by the drawings and specifications.

1.24 GOVERNMENT-FURNISHED MATERIALS AND EQUIPMENT

None

1.25 SALVAGEABLE MATERIALS

Identify with the Contracting Officer's Representative all salvageable materials to be turned over to the Government.

1.26 GENERAL SAFETY REQUIREMENTS

The Contractor is required to follow all OSHA regulations. The Contractor may not expose Government property, the public and workers of the Government or of any other contractor to hazards which they may create. The Contractor must submit for approval to the Contracting Office and to the Wing Ground Safety Office (SLD 45/SEG) an Accident Prevention Plan which details how Government property, the public and workers from other employers will be protected. This plan will not include details of the Contractor's internal safety program for the protection of their workers since that is an issue between the Contractor and OSHA.

1.26.1 Safeguards for Construction, Alteration, and Demolition Operations

Provide safeguards for construction, alteration and demolition operations as required per NFPA 241, Latest Edition. All storage and storage locations must be coordinated and approved by the Contracting Officer's Representative and Fire Department. All work must comply with the latest edition of the Unified Facilities Criteria, UFC 3-600-01 and the National Fire Protection Association Standards and the applicable Air Force Technical Letters.

1.26.2 Traffic Safety

Keep fire and exit lanes clear of vehicles and materials at all times. The Contractor must comply with Florida Department of Transportation Standard Specifications for Road and Bridge Construction, latest edition and Roadway and Traffic Design Standards for Design, Construction, Maintenance and Utility Operations on the State Highway System, latest edition, regulations in regard to safety, barrier, and marking requirements for road construction.

1.26.3 Electrical Work Safety

All permanent and temporary electrical work, installed or used in accomplishment of this contract, will be in compliance with the applicable sections of the latest National Electrical Code or National Electrical Safety Code, as appropriate. Supervisor and workers must be properly trained on lockout/tagout procedures.

Except for testing, de-energize all electrical equipment and circuits through a scheduled power outage before any work is started. Request exceptions, in writing, from the Contracting Officer's Representative 5 days in advance of the actual work to be performed. Provided the exception

12/10/2021 SECTION 01 00 00 Page 12 is approved by the Contracting Officer's Representative, work and/or testing may proceed when proper electrical personnel protective support equipment is provided and worn by Contractor personnel. Lockout/tagout log must be maintained at the site at all times.

1.26.4 Fire/Explosives Safety

The Contractor will be responsible for furnishing adequate and proper fire protection for all phases of the contract work. All structures occupied by the Contractor or lower-tiered subcontractors must be equipped with smoke detectors.

1.26.4.1 Fire Prevention

A weld/burn permit must be obtained from the Station Fire Department through the Contracting Officer's Representative before any welding, cutting, or burning operations are allowed. Submit requests to the Contracting Officer's Representative at least 24 hours prior to start of the operation. Do not start cutting, welding, or open-flamed operations without permit or approval and a fire watch where required. Post the telephone number of the fire department on job site. Do not store equipment and flammable material in the facility. Field welding may require a fire watch, if deemed necessary by Fire Protection personnel.

Contractor must provide fire extinguisher on site before performing cutting or welding operations.

1.26.4.2 Smoking/Open Flames

Smoking, any open flames, non-explosion-proof electrical equipment/tools, and spark-producing devices are strictly prohibited in all areas where explosive vapor from adhesives, dopes, varnishes, lacquers, thinners or paints may be present and when these materials are used.

1.26.4.3 Flammable Materials

Do not store flammable material of any kind inside any facility without approval of the Contracting Officer's Representative. Keep packages containing paints, dopes, varnishes, lacquers, thinners or other volatile painting materials tightly closed when not in actual use; store in accordance with current recommendations of the National Fire Protection Association. Keep containers of paints, dopes, varnishes, lacquers, thinners, and other flammable materials in a well-ventilated location, free of excessive heat, smoke, sparks, and flames. Remove paint scrapings and paint-saturated debris from the premises daily. Place all paint- or solvent-soiled cloths, paper towels, rags, and cloth waste in properly labeled United Nations Class 1A2 or 1H2 (UN1A2 or UN1H2) steel or plastic drums for solid waste. Use UN1A1 or UN1H1 drums for liquid paints and related materials. Do not mix liquid and solid waste. Do not mix non-hazardous waste with hazardous waste.

1.26.4.4 Powder-Actuated Tools

Powder-actuated tools are not allowed on this Contract.

1.26.5 Elevated Work Area Safety

1.26.5.1 Hoisting Equipment

All hoisting equipment, to include suspended scaffolds and support rigging, 12/10/2021 SECTION 01 00 00 Page 13 must have a minimum 4:1 Safety Factor and be currently inspected and certified. Before hoisting of materials and/or personnel is started, the hoist/scaffold and all slings, cables, shackles, etc., must be load tested to two times the maximum total load to be hoisted. The hoist/scaffold must be tested in the presence of the Contracting Officer's Representative. The hoisting area must be roped off or adequately barricaded to 20 feet on all sides beneath the elevated work area and signs installed to keep personnel and equipment out of the hazardous area. Spreader bars will be used wherever necessary to prevent hoisting cables from contacting equipment.

1.26.6 Confined Space Entry

This project does not require access to confined spaces. Contractor is responsible to assure the safety of his workers and must follow all OSHA regulations when entering confined spaces. Refer to OSHA 29 CFR 1910.120 and 29 CFR 1926.21. See ANSI Z117.1, "Safety Requirements for Confined Spaces." Provide all equipment and monitoring for employees. Contractor must notify Fire/Security prior to entering any confined spaces. Workers must be trained in confined space entry.

1.27 ENVIRONMENTAL REQUIREMENTS

It is the Contractor's responsibility to ensure all work to be accomplished will be in compliance with Federal, Final Governing Standards, Air Force, and local environmental regulations.

1.27.1 Storage and Protection

Contractor must be responsible for the storage and protection of all materials, equipment, and wastes, whether incorporated into the job or not. Hazardous Materials and Petroleum Product Containers must be stored on an impervious surface with proper containment. Incompatible materials must be segregated and have separate containment systems. No materials or wastes must be discharged onto land or to the storm sewers, sanitary sewers, etc., without prior approval from the Environmental Technician.

1.27.2 Hazardous Materials/Wastes

The Contractor must follow all requirements found in any and all USAF (including Hazardous Waste Management Plan), Federal, Final Governing Standards, and local regulations pertaining to the handling, treatment, disposal, management, etc. of any hazardous wastes and/or materials used or discovered in the performance of this contract including, but not limited to, the obligations in the 40 CFR. Contractor must ensure that all personnel have been properly trained in accordance with 29 CFR, which includes a Hazard Communication program and, if applicable, hazardous waste and DOT transportation of hazardous materials training. All hazardous waste will be turned over to the Range Operation Support Contractor for disposal.

Waste will be segregated by waste streams to ensure proper characterization. Waste will be stored in closed non-leaking DOT containers. Containers will be labeled, marked, and dated in accordance with 40 CFR and 49 CFR regulations. Waste containers will be managed and inspected weekly to avoid releases to the environment. The Contracting Officer's Representative will assign an area for interim storage of waste containing drums.

The Contractor must notify the Contracting Officer's Representative and

12/10/2021 SECTION 01 00 00 Page 14

Environmental Technician immediately if any contaminated soil, ground water or suspect hazardous debris is encountered during excavation, demolition or construction of the project.

The Contractor must provide the Contracting Officer's Representative current training certificates for all applicable Federally required training for all Contractor personnel performing work under the scope of this contract.

The Contractor must be liable to the Government for all costs incurred to clean up, manage, and dispose of any spilled material/waste resulting from the Contractor's action. The Contractor must notify the Contracting Officer's Representative and Environmental Technician of all spills of hazardous material or waste.

Contractor must provide a completed authorization request (AF Form 3952) (including container type and quantity for each container) for each hazardous material to be incorporated into the project, including up-to-date Safety Data Sheets (SDS) and the estimated quantities of those materials. Copies of SDS of all hazardous material used at the site must be maintained at the construction site at all times. Contractor must maintain an inventory and SDS's of all hazardous materials at Contractor storage areas.

Hazardous Material (HAZMAT) encompasses all items (including medical supply items) covered under the Emergency Planning Community Right-to-Know Act Toxic Release Inventory (EPCRA TRI) reporting requirements, the OSHA Hazard Communication Standard, all Class I and II Ozone Depleting Substances (ODS), and materials which can reasonably be anticipated to generate a hazardous waste. It does not include munitions. Reference FAR Part 23.301 definition in the latest version of FED-STD-313D, Tables I & II. This includes any item or chemical which is a "health hazard" or "physical hazard" as defined by OSHA in 29 CFR 1910.1200, which includes the following:

a. Chemicals which are carcinogens, toxic or highly toxic agents, reproductive toxins, irritants, corrosives, sensitizes, hepatotoxins, nephrotoxins, neurotoxins, agents which act on the hematopoietic system, and agents which damage the lungs, skin, eyes, or mucous membranes.

b. Chemicals which are combustible liquids, compressed gases, explosives, flammable liquids, flammable solids, organic peroxides, oxidizers, pyrophorics, unstable (reactive) or water reactive; and

c. Chemicals which in the course of normal handling, use, or storage operations may produce or release dusts, gases, fumes, vapors, mists, or smoke which may have any of the above characteristics.

It also includes any item or chemical which is reportable or potentially reportable or notifiable as inventory under the reporting requirements of the Hazardous Chemical Reporting (40 CFR 370), or as an environmental release under the reporting requirements of the Toxic Chemical Release Reporting: Community Right to Know (40 CFR 372-SUBPART D), which includes the following:

Chemicals which can cause harm to people, plants, or animals when released by spilling, leaking, pumping, pouring, emitting, emptying, discharging, injecting, escaping, leaching, dumping, or disposing into

12/10/2021 SECTION 01 00 00 Page 15 the environment.

A hazardous material is anything that you can spread, squirt, brush on, shake, pour, squeeze, or otherwise apply as part of your activities.

Typical examples are: adhesives, sealants, oils, grease, detergents, cleaners, disinfectants, drain opener, spray/brush paints & thinners, insecticides, herbicides, fungicides, sakrete, lab chemicals, form release agents or bottles of ink (not pen refills) etc.

1.27.3 Environmental Awareness

Contractor personnel must be familiar with the environmental requirements for the project and ensure all requirements are met as stipulated in the project. Environmental training will be available on Station. It is the Contractor's responsibility to ensure that all work to be accomplished will be in compliance with the Island's Finial Governing Standards and local regulations.

The contractor is not permitted to bring any pesticides or herbicides on SLD 45 installations without prior written approval from the SLD 45 Environmental Sections.

1.27.4 Stormwater Protection

The Contractor must establish/construct storm drainage features at the earliest stages of construction, and throughout construction, grade the construction area to provide positive surface water runoff away from construction activity and/or provide temporary ditches, swales, and other drainage features and equipment, as required, preventing erosion. Excavated slopes and backfill surfaces must be protected to prevent erosion and sloughing.

Structural practices will include the following:

Silt fences Diversion dikes Drainage swales Check dams Sediment basins Pipe slope drains Subsurface drains

1.28 ASBESTOS REMOVAL AND DISPOSAL

ACM has not been identified in the contract area.

Removal of ACM will be through the use of a separate Asbestos Removal Contractor. Removal of the ACM is included in the Contract as shown on the plans and in the specifications. Contractor must comply with all Federal, State, and Local Regulations and the SLD 45 Plan 32-1052 concerning the removal and disposal of asbestos-containing materials and the protection of all personnel working in and around the work site. All asbestos abatement Contractors and their employees must have current Florida Asbestos Abatement Contractor Licenses to perform the work. Florida does not have reciprocity with any other state; therefore, no other license except for a current Florida license is acceptable. Workers must renew their licenses each year, and the license must be current for the duration of the project.

12/10/2021 SECTION 01 00 00 Page 16

1.28.1 Scope and General Responsibilities

ACM is hazardous and requires special handling and disposal procedures. If the Contractor suspects the presence of any ACM not identified as such by this contract, but is required to be disturbed to perform the contract work, inform the Contracting Officer's Representative at once. Resolution of the situation will be in accordance with the changes clause of the Contract.

1.28.2 Liability

The Contractor will be liable to the Government for all ACM-related costs incurred from the Contractor's actions that do not comply with the requirements of this paragraph.

1.29 TOXIC PAINTS/MATERIALS

Lead-based paint has not been identified in the contract work area.

Lead-based paint removal can create potential health hazards for workers.

All applicable provisions of standards and requirements listed in this specification and Occupational Safety and Health Administration requirements 29 CFR 1926.55, 29 CFR 1926.62, and 29 CFR 1926.1127 must be observed by the Contractor. Contractor must submit a Lead-Based Paint Compliance Plan to the Contracting Officer's Representative for approval by the Bio-environmental Engineer, SLD 45 ADOS/SGGB, Patrick AFB, FL 32925, in accordance with 29 CFR 1926.62 or 29 CFR 1926.1127 as applicable.

Contractor's Lead-Based Paint Compliance Plan must be approved prior to starting work. All work must comply with the SLD 45 Lead Plan and other references identified in this section. If the Contractor suspects the presence of toxic paint/materials not shown on the drawings or must disturb toxic paint/materials which are not part of the Contract, the Contractor must immediately inform the Contracting Officer's Representative. The Contracting Officer's Representative will determine whether removal of the questionable material is required and who will accomplish the removal.

1.30 TREATED WOOD PRODUCTS

Wood products that have been treated using arsenic, such as Yella-Wood, will not be used.

1.31 OZONE DEPLETING CHEMICAL LIMITATION

In accordance with the National Defense Authorization Act for Fiscal Year 1993, Title III, Section 326 (Public Law 102-484), the Contractor must not make use of, nor provide to the Government, any chemical, solvent, material, or any system making use of materials, classified as a Class I Ozone Depleting Chemical (ODC). Class I ODC's include chlorofluorocarbons (CFC's -11, -12, -113, -114, -115, -13, -111, -112, -211, -213, -214, -215, -126, -217 and -502), carbon tetrachloride, methyl chloroform, methyl bromide, and Halons 1211, 1301, 1202, and 1011. Contractor must also comply with the requirements identified in Section 608 of the "Clean Air Act."

Contractors working with Class I ODC refrigerants must comply with all requirements identified in Section 603 of the Clear Air Act.

Refrigerant must be recovered from all non-salvageable air conditioning and refrigeration equipment in accordance with DOD 6050.9 prior to turn-in.

Refrigerant recovery must be performed by a certified refrigerant recovery

12/10/2021 SECTION 01 00 00 Page 17 technician. The Contractor will provide refrigerant recovery equipment including cylinders. The cylinders will remain on-station.

Refrigerant should not be extracted from usable self-contained air conditioning wall units or refrigerators. The Contractor must turn-in all materials to the Contracting Officer's Representative.

1.31.1 Affirmative Procurement

The Contractor and all Contractors involved in this project must comply with Air Force Affirmative Procurement (AP) requirements. Affirmative Procurement is the purchase of environmentally friendly products and services (e.g., products made from recycled or recovered materials).

Federal agencies, their contractors and subcontractors are required to maximize the purchase materials on the list of "EPA Designated Guideline Items" with the minimum recycled or recovered materials content whenever practicable according to RCRA 6002 and Executive Order 13101.

(http://afcee.brooks.af.mil)

Detailed information on EPA AP approved products and manufacturers providing these products is available at http://afcee.brooks.af.mil.

Contractors must maximize the purchase of AP approved items; that is, items that meet the minimum recycled or recovered material content guideline.

Contractors must provide AF Contracting with a report itemizing all AP approved items used in the project. Contractors must also provide Contracting a written justification for all items purchased that are on the EPA CPG list and are not AP approved. The Contractor must provide this report during the submittal process.

1.32 EXISTING CONDITIONS

Dimensions of existing facilities/structures are for reference only. Field verify all dimensions prior to performing the work.

1.33 PATCHING GOVERNMENT-OWNED FACILITIES

Government-owned structures, facilities, streets, curbs, walks, etc., that are damaged or removed due to required excavations or other construction work must be patched, repaired or replaced, and be left in their original state of repair by the Contractor, to the satisfaction of the Contracting Officer's Representative.

1.34 CONTROL AND DISPOSAL OF SOLID WASTE AND DEBRIS

Includes control and disposal of waste and debris resulting from the performance of the Contract. Conduct handling and disposal in a manner that will prevent contamination of the job site and any other areas. On completion of the Contract, leave the area in a clean and natural state.

Remove all signs of temporary construction activities.

The Contractor must package, segregate, and identify hazardous wastes.

Double-bagged asbestos will be placed in contractor supplied tri-wall hazardous waste containers manufactured by Weyerhauser, or equivalent.

Asbestos and all other hazardous wastes are to be disposed by the Government. Non-hazardous, non-asbestos containing debris is disposed at Area 5000 construction debris landfill. The Contractor will maintain and submit monthly records of the weight and volume of debris disposed in the Area 5000 Demolition and Construction Debris Landfill.

12/10/2021 SECTION 01 00 00 Page 18

Dispose of all paint and sandblast debris and media in accordance with HAZARDOUS MATERIALS/WASTES in this section. Contractor must supply all disposal containers.

1.34.1 Toxic Paints and Material Waste Management

Collect lead-contaminated waste scrap, debris, bags, containers equipment and lead contaminated clothing that may produce airborne concentrations of lead particles. Waste will be segregated by type to ensure proper characterization, i.e., paint chips and vacuumed material, scrap and debris, lead contaminated clothing. Label containers in accordance with 29 CFR 1926.62 and 40 CFR 262.

Place waste materials in U.S. Department of Transportation 49 CFR 178 approved 55-gallon drums. Properly label each drum to identify the type of waste, 49 CFR 172, and the date the drum was filled. For hazardous waste, the collection drum requires marking/labeling in accordance with 40 CFR 262 during the accumulation/collection timeframe. The Contracting Officer's Representative will assign an area for interim storage of waste-containing drums. Do not store hazardous waste drums in interim storage longer than 90 calendar days from the date affixed to each drum.

Handle and transport lead or lead-contaminated material classified as hazardous waste in accordance with 40 CFR 260, 40 CFR 261, 40 CFR 263, 40 CFR 264, and 40 CFR 265. Comply with land disposal restriction notification requirements as required by 40 CFR 268.

All potentially hazardous waste material that has been segregated, packaged, and labeled as specified above will be turned over to the Station's Environmental Technician. All waste material, whether hazardous or non-hazardous, must be disposed in accordance with laws and provisions and Federal, Final Governing Standards, or local regulations.

1.34.2 Used Oil

Used oil will be stored in closed non-leaking DOT drums. All drums will be labeled with the words "Used Oil." Full containers of used oil must be turned in to the Station's Environmental Technician. Used oil must not be mixed with any other wastes. Used oil will be managed to prevent the addition of water and avoid releases to the environment.

1.35 UTILITIES

Utilities will be provided to the Contractor at no cost.

1.36 BREAKDOWN OF PRICES

Submit a schedule of prices at the pre-award conference. The schedule of prices shall consist of a detailed breakdown of the contract price, as bid, giving quantities for each of the various kinds of work; the unit prices;

and the total prices therefore. The detailed breakdown shall be segregated under each of the construction categories stated in this contract. Payments will not be considered until the schedule of prices is acceptable to the Contracting Officer's Representative.

PART 2 PRODUCTS

Not Used

12/10/2021 SECTION 01 00 00 Page 19

PART 3 EXECUTION

Not Used

-- End of Section --

12/10/2021 SECTION 01 00 00 Page 20

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 33 00

SUBMITTAL PROCEDURES

08/18, CHG 4: 02/21

PART 1 GENERAL

1.1 DEFINITIONS

1.1.1 Submittal Descriptions (SD)

1.1.2 Approving Authority

1.1.3 Work

1.2 SUBMITTALS

1.3 SUBMITTAL CLASSIFICATION

1.3.1 Government Approved (G)

1.3.2 For Information Only

1.4 PREPARATION

1.4.1 Transmittal Form

1.4.2 Submittal Format

1.4.2.1 Format of SD-01 Preconstruction Submittals

1.4.2.2 Format for SD-02 Shop Drawings

1.4.2.2.1 Drawing Identification

1.4.2.3 Format of SD-03 Product Data

1.4.2.3.1 Product Information

1.4.2.3.2 Standards

1.4.2.3.3 Data Submission

1.4.2.4 Format of SD-04 Samples

1.4.2.4.1 Sample Characteristics

1.4.2.4.2 Sample Incorporation

1.4.2.4.3 Comparison Sample

1.4.2.5 Format of SD-05 Design Data

1.4.2.6 Format of SD-06 Test Reports

1.4.2.7 Format of SD-07 Certificates

1.4.2.8 Format of SD-08 Manufacturer's Instructions

1.4.2.8.1 Standards

1.4.2.9 Format of SD-09 Manufacturer's Field Reports

1.4.2.10 Format of SD-10 Operation and Maintenance Data (O&M)

1.4.2.11…