13. YXTK 13-1806 (FY23 Historical Contractor Question-Govt Responses).pdf

PDF 1 MB Posted

Attached to
YXTK 13-1806 Repair Electrical Distribution Lines, Feeder 5, Ascension Auxiliary Airfield (AAAF), South Atlantic Ocean
Solicitation number
FA252125B0009
Issued by

About this file

This document is a comprehensive set of Questions and Answers (Q&A) for a federal contract solicitation (FA252123B0008) for repairing electrical distribution lines on Ascension Island. The project, designated as YXTK 13-1806 Repair Electrical Distribution Lines Feeder 5, AAAF, involves replacing electrical infrastructure including 148 concrete utility poles (50 feet long, weighing 4,340 to 5,650 pounds each), underground communication lines, and associated electrical components.

Key project details include a 660-day period of performance, with 297 days of on-site construction, and limited logistical support from the government. The contractor must provide all equipment, handle material shipping from Port Canaveral to Ascension Island, and manage on-site logistics including fuel, communications, lodging, and waste disposal. The project requires complex coordination with local authorities, utility providers, and base operations support contractors. Critical technical requirements include specific concrete mix designs, grounding specifications, conduit installations, and compliance with various engineering standards. The contractor will be responsible for utility locates, equipment transportation, and turning over excess materials to the government upon project completion.

View the file

Other files

File Type Posted
FA252125B0009 SF1409.pdf PDF
22. Government Response to Contractor Submitted Questions.pdf PDF
24. Geology Study-Investigation (1997) (Ref Only).pdf PDF
FA252125B0009 A004.pdf PDF
23. YXTK 13-1806 RPR FDR 5 Design Analysis (Section 5) (Ref Only)).pdf PDF
FA252125B0009 A003.pdf PDF
FA252125B0009 A002.pdf PDF
Solicitation Amendment FA252125B00090001 SF 30.pdf PDF
4. Contractor HAZMAT Usage Worksheet.xlsx XLSX spreadsheet
7. Contractor Travel Request Form.pdf PDF
17. Installation Facility Standards Ascension Auxiliary Airfield.pdf PDF
12. MH 42 Photos.pdf PDF
6. CECC Form 3052 Template.xlsx XLSX spreadsheet
16. Enivronmental Final Governing Standards Ascension Island.pdf PDF
20. Fiber Wall Mount Dist Cabinets Photos.pdf PDF
1. YXTK 13-1806 DWG.pdf PDF
18. Catherine Point PSD (Services Distribution).pdf PDF
5. Record of EqmtMat List Template (OM Database).xlsx XLSX spreadsheet
11. Site Visit Procedures.pdf PDF
14. YXTK 13-1806 DWG E-409 (RevA).pdf PDF
3. YXTK 13-1806 Recovered Materials Determination Form (Green Procurement).pdf PDF
15. Concrete Mix Design (Local Aggregate).pdf PDF
2. YXTK 13-1806 Specifications.pdf PDF
19. Ascension Island PSD.pdf PDF
FA252125B0009 (YXTK 13-1806 RPR Electrical Dist Sys (Feeder 5)) IFB.pdf PDF
10. QA Template.docx DOCX document
21. Facility 800 Photos.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 13 includes contractor-submitted questions and corresponding Government responses from the FY23 solicitation for this requirement (Ref FA252123B0008). This information is provided to assist in understanding prior inquiries and clarifications related to the project scope. Bidders should use this information to help with their bid preparation.

All references made to the base operations support contractor are no longer valid. The current base operations support contract is titled AIBOS, performed by V2X

P a g e | 1

•Communications: Is there star link, internet or other form of communication back to the United

States for emails, etc.

Government Response: Starlink resources are currently being used on Ascension. The responsibility for setup and maintenance would be the construction contractor. The other local cellular and internet provider is Sure. https://www.sure.co.ac

•Electricity: do we have access to electricity for recharging hand tools etc. How much does electricity cost.

Government Response: Electric and water hook-up are available and shall be furnished without charge. The construction contractor shall carefully conserve use of these utilities.

•Operating Fuel Station: Where do we purchase fuel (diesel and gas) for our construction equipment. Is there a military or private entity offering gas station services? Do we bring our own fuel to the island? What is a good price per gallon for both diesel and gas for estimating purposes?

Government Response: Only diesel is available through station support. This is provided at no cost to the contractor. Mogas or Unleaded fuel must be purchased on the local economy. There is only one source on Ascension located near Two Boats Village. Fuel prices are set at £1.50 per litre at this time and opening hours are 1630hrs to 1830hrs on Mondays and Thursdays.

•Gravel Pit: There is a fair amount of concrete on the project for road crossings and around each concrete utility pole that require gravel including the #57 stone base (Sheet C-502, Detail Pole setting and sheet C-501 Road Crossings). There appears to be a concrete plant near the airport.

Do we have access to concrete, cement and gravel to utilize for this project including building ecology blocks? Is there a vendor on island that mixes concrete, can we visit the gravel pit and concrete batching plant?

•Cement. Do we need to bring in cement for concrete or replace cement quantities utilized for this project?

Government Response: Reference Attachment 15. These are two concrete mixes using Portland

Type IL and Portland Type II cement. These mix designs have demonstrated the ability to achieve

3,500 - 4,000 PSI. It will still be the construction contractor’s responsibility to ensure that the mix design used achieves the strength requirements as stated in project documents.

Government Response: Elements to be provided by the Government at no cost to the construction contractor identified as station support furnished through the base support contractor (ABOS /

Yang Enterprises) areas are:

P a g e | 2

-Transport of concrete poles from the material staging area to the installation locations

-#57 Stone for concrete (local aggregate)

-Red Hill Fill (local fill material. mining and stockpiling only)

For remaining elements, refer to Specification 01 00 00, Para 1.4.2., whereas all equipment shall be furnished by the construction contractor. Access to Government equipment will be very limited.

•Heavy Equipment Rentals: This project will require a number of pieces of heavy equipment such as excavator, compaction, concrete mixer truck, etc. Can we go to the rental shop to get a rate sheet.

Government Response: No commercial rental sources exist on Ascension. An alternative approach may be to contact the Asension Island Government for availability. That arrangement is at the discretion of the construction contractor and is made directly between the construction contractor and AIG. Their resources are limited for outsourcing. Contact for AIG is Kitty George, Shipping and Operations Officer, kitty.george@ascension.gov.ac

•Small tools rental: Is there a small tool rental shop, can we visit.

Government Response: No commercial rental sources exist on Ascension. All items like this

(small tools) must be furnished by the construction contractor.

•Contractor Staging Ground and port/harbor off-loading. Can we see the contractor staging ground, access, port/barge off-load and space for setting up an office trailer, small maintenance shop or a central staging area for concrete pole and wooden demolition waste? Does the contractor staging area have internet, phone or electricity available, for a site trailer? Who is responsible for off-loading the concrete poles, wire rolls, and conex with small materials from the docks to the contractor staging? Is there a harbor fee, off load fee or other harbor fees.

Government Response.

-There is a centralized staging area for materials that are offloaded from the vessel located near the softball fields.

-Accommodations can be made for a contractor laydown area to include spacing for an office trailer. Location will need to be requested by the construction contractor and approved by the

Government. All utility/communication connections to the trailer will need to be made by the construction contractor.

-All material shipped on the vessel is offloaded by the base operations support contractor and transported to the staging area at no cost to the construction contractors. No customs or other fees are assessed to cargo utilizing the Government vessel.

148 concrete holes are required for this project. They will be 50 feet in length and weigh approximately 4,340 to 5,650 pounds per pole. Total weight will be 322 to 418 tons plus bunk weights for holding the poles. How much room on a barge, do we need to schedule two barge trips.

Government Response: No cargo restrictions exist for downrange vessel shipments.

Material/equipment shipment will need to be forecasted within the contractor construction schedule. This will allow the Shipping & Receiving Section to identify the next vessel according to the current schedule and coordinate with the carrier to ensure a vessel is used that can meet the capacity of shipments.

•Hotel, or sleeping quarters for employees, where located, how many bed(s) are available, shower facilities, bathroom facilities, what do our employees need to provide/bring etc. Also, where do employees eat, available kitchen facilities, etc. do we need to bring food in by barge.

Government Response: Lodging is provided to construction contractor personnel at no cost.

Rooms are in dormitory style facilities that include sinks/showers/toilets. Dependent on mission requirements will dictate room occupancy. Every effort is made to have rooms as single occupancy, but there may be times when double occupancy is required.

•Potable water for concrete mixing, if required.

Government Response: water hook-up is available and furnished without charge. The construction contractor shall carefully conserve use of these utilities.

Question & Answer Template

Solicitation: FA252123B0008

Project Number: YXTK 13-1806 Repair Electrical Distribution Lines

Feeder 5, AAAF

Contractor Name: ___TDX Power Services__________________________

POC: ___Loren Jalbert ___________________________________

IFB Section __L________ Paragraph __L-4_______

SOW/Technical Specification/Drawings paragraph/page ___________

Other (Specify) __Bid Submission Forms _________________________

Question:

Cost Estimate Breakdown (Form CECC 3052), it would appear that we can submit a similar computer-generated form. Is this acceptable.

Government Response: Similar computer generated forms are acceptable that contain the same information as reflected in the CECC 3052

P a g e | 3

P a g e | 4

IFB Section __Plan Set ________ Paragraph ___Flag Notes ______

SOW/Technical Specification/Drawings paragraph/page _____Demolition ______

Other (Specify) ____Wooden Pole removal_______________________

Question:

Two Questions on this subject

1. Per Flag notes, various plan sheets, Demolish wood utility poles and associated guy wires.

Do we excavate the entire pole out of the ground, or do we cut the wooden pole flush with the ground with a chain saw?

Government Response: Wooden poles may be cut 12 inches minimum below grade and backfilled to match existing grade.

2. Are we placing the wooden poles in the land fill cell or at a location by the incinerator to be used as fuel for the burning?

Government Response: All waste debris will be disposed of locally in the landfill.

Contractor will be instructed where to place the poles. Poles are to be stripped of all attachments.

IFB Section ___N/A_______ Paragraph ___N/A______

SOW/Technical Specification/Drawings paragraph/page ____N/A_______

Other (Specify) __Small tools and consumables _________________________

Question:

For this project, the general contractor will be bringing in a large amount of small tools and consumables (blades, drill bits, grease, etc.) Can we leave these items with the military after this project is completed, verses shipping it back to Florida?

Government Response: Yes under the condition the items left behind are in good working condition. All items determined unserviceable for future use will need to be properly disposed of.

IFB Section __N/A________ Paragraph __N/A_______

SOW/Technical Specification/Drawings paragraph/page ______N/A_____

Other (Specify) ___________________________

Question:

1. In the site walk it was mentioned that the Government would furnish gravel, diesel, non-potable water for compaction and barging costs. Are there any other associated costs that the Government will provide in preparing our bid response?

2. Will the Government have any utility maps for utility identification and blue staking for underground utilities, especially at Facility 12240, tank farm facility. Per the specifications we understand that we need to provide our own utility locating, but any as-built maps will assist in this effort.

3. Can the contractor pay for meals and rooms on an invoice basis utilizing either on a credit card, or sending us a invoice at the end of each month based on the sign in sheet at the cafeteria, verses our team carrying large amounts of cash to Ascension Island for meals.

4. It was noted that Amazon and other products are delivered in the Air Cargo, can a contractor utilize air cargo for delivery of small items, products, or construction equipment consumables that may be utilized.

P a g e | 5

Government Responses:

1a. Elements to be provided by the Government at no cost to the construction contractor identified as station support furnished through the base support contractor (ABOS / Yang

Enterprises) areas are:

-Transport of concrete poles from the material staging area to the installation locations

-#57 Stone for concrete (local aggregate)

-Red Hill Fill (local fill material. mining and stockpiling only)

For remaining elements, refer to Specification 01 00 00, Para 1.4.2., whereas all equipment shall be furnished by the construction contractor. Access to Government equipment will be very limited.

1b. Elements to be provided by the Government at no cost to the construction contractor (SF 1442, Section C)

-Para 4. Transportation of contractor furnished materials and equipment from Patrick SFB to

Ascension Island, including loading and offloading along with return shipments (retrograde) from

Ascension Island to Port Canaveral

-Para 8.2 Housing.

-Para 8.3 Fuel (diesel only)

-Para 8.4 Utilities (electric and water)

2. Locates will be done by the Government prior to the start of construction. Currently as-builts are not available for this area.

3. Rooms are furnished at no cost as station support. Meal charges can be consolidated and paid for on a weekly or monthly basis using the sign in sheets to calculate the amount due. Payment can be made by credit card.

4. Para 4.2 Air shipment of material to Ascension using the Government Transportation Account

Code (TAC) where shipping costs are paid for by the Government is restricted to construction material/equipment only and must be approved on a case-by-case basis through the Contracting

Officer. Personal effects must be paid for by the construction contractor.

IFB Section ___Section 01 00 00_______ Paragraph ____1.25 Salvageable Materials_____

SOW/Technical Specification/Drawings paragraph/page ___Page 15 of 264________

Other (Specify) ___________________________

Question:

All demolished electrical conduit, hardware, etc. will be salvageable. Will the government provide a bin, local collection conex, etc. for metal(s).

Government Response: Contractor will be directed where to place demolished material that is determined salvageable. Collection containers will be provided.

P a g e | 6

IFB Section _Site visit _________ Paragraph __SURE Communication Facility_______

SOW/Technical Specification/Drawings paragraph/page ___________

Other (Specify) ___________________________

Question:

During the site visit, we were told that we will need to get permits from the Ascension Government to access this facility and that there may be permits. Do we need know what permits are required.

Will the U.S. Federal Government assist the general contractor with the Ascension Island

Government with the SURE facility connection.

The asphalt at this location looks very beaten up. Is the contractor required to provide asphalt for the top of the trench or can we put a concrete cap, or lease as is with compacted soil?

Government Response: Install according to C-501 Communication Cable Trench Detail.

IFB Section __01 00 00_____ Paragraph __Working Hours _______

SOW/Technical Specification/Drawings paragraph/page _____Page 12 of 264______

Other (Specify) ___________________________

Question:

Working hours are defined as 7:30 AM to 4 PM, with no work on Sundays. Can the contractor work a longer day, starting at 7:00 AM and stopping at 5:00 PM. Once our team is on-island, and in the interest of time, schedule, we would like to work a 10 hour day – six days a week to rapidly complete this project. We would give advance notice as outlined in Section 01 00 00.

Government Response: A Mon-Sat, 10 hour day work schedule has been approved in the past and should be acceptable for this effort. Consideration will need to be made once on site activities start to accommodate the schedule of the assigned Construction Contract Inspector.

IFB Section ____Sheet C-106_& C-425_____ Paragraph ___Facility 16547______

SOW/Technical Specification/Drawings paragraph/page ___________

Other (Specify) ___________________________

Question:

In this section of overhead line replacement (sheet C106 & C 425), we may have some field conflicts with the British RA overhead electrical lines with possible conflicts with the excavation for the guy wire blocks (See Detail BH C-106) on Sheet C425). Can we potentially field fit the guy wire excavation to not conflict with the active overhead line that will be demolished, or can we utilize an above ground concrete block, similar to the guy wire connection at Cross Hill Road

(see picture below)

P a g e | 7

Government Response: Guy anchors may be installed as required provided all proposed guy anchors and medium voltage cabling are tensioned in accordance with Specification Section 33

71 01.00 40 Section 2.2.2 and Section 1.3.2 Sag and Tension Calculations.

If above grade anchorage is proposed, ensure the engineer of record for the pole is in agreement with the method of anchoring and that the location of the proposed anchor does not conflict with or obstruct existing to remain infrastructure or pathways and is not located within five-feet or a buried utility.

IFB Section __01 45 00________ Paragraph __3.4.1 Personnel Requirements _______

SOW/Technical Specification/Drawings paragraph/page ____Page 6 and 7 of Section 01 45

00_______

Other (Specify) ___________________________

Question:

Personnel Requirements: Per this paragraph, the general contractor will require to have the following personnel on site 1) CQC system manager, 2) a safety and health manager, and 3) a superintendent. These are the prime senior management team that will be on site. However in

Section 3.4.3 the CQC organization outlines the individuals or specialized technical employees that need to be on Ascension Island during construction, per this paragraph, These individuals or specialized technical companies are employees of the prime or subcontractor; be responsible to the CQC System Manager; be physically present at the construction site during work on the specialized personnel's areas of responsibility; have the necessary education or experience in accordance with the experience matrix listed herein.

• Civil engineer

• Mechanical Engineer

• Electrical Engineer

• Structural Engineer

• Environmental Engineer

• Submittal Clerk

• Family Housing coordinator

P a g e | 8

• Materials testing Technician

• Testing, Adjusting and Balance Personnel

Per Section 3.4.5 - Do we need all these people on Ascension Island during construction activities?

Government Response: Personnel to be provided based on the scope of work.

IFB Section ___01 45 00_______ Paragraph __3.7.3 Onsite Laboratory_______

SOW/Technical Specification/Drawings paragraph/page ____Page 11_______

Other (Specify) ___________________________

Question:

Does the contractor need an on-site laboratory for material testing? As outlined in Part 2 Products

Section 31 00 00, Offsite soils. We can provide a total hydrocarbon for the bedding sand that is imported. Is the #57 Stone base, from Ascension Island gravel pit at the airport considered “off-site”.

Government Response: Onsite laboratory is not required. Laboratory tests from materials vendors will suffice, ensure materials are free of hazardous and deleterious materials.

IFB Section _31 00 00 _________ Paragraph __3.9.2.1 compaction of subgrade_______

SOW/Technical Specification/Drawings paragraph/page __Page 12_________

Other (Specify) ___________________________

Question:

It notes under 3.9.2.1 that compaction of subgrade has to be 95%, but as the soils on the island are primarily volcanic in nature with very little fines, are we required to hit a 95% compaction? The compacted #57 aggregate from the Ascension Island gravel pit, will be able to meet the 95% compaction. As Ascension is an island, it will be difficult to get a nuclear testing gauge to the island. Does the contractor need to show 95% compaction?

Government Response: Specification 31 00 00 assumes a portion of subgrade soil is fine aggregate material. If fines are not present, compact subgrade in accordance with C-001 Foundation General

Note #5. Perform all other testing as required in the specifications and drawings.

IFB Section ___01 33 00_______ Paragraph __1.2 Submittals _______

SOW/Technical Specification/Drawings paragraph/page ___Page 5 or (28 of 264 on PDF)___

Other (Specify) ___________________________

Question:

The specifications are written similar to the Army Corp of Engineers. Does Space Force utilize

RMS for submittals?

As noted under Section 1.2 Submittals – 5 copies of submittals information for listed items. For bidding purposes we assume that these five copies (of each submittal) will be fedex or mailed to

Space Force.

The Army Corp of Engineers also has their own submittal codes. Does Space Force have a submittal code for approved submittals.

P a g e | 9

Government Response: Reference SF 1442, Section C, Para 3 for procedures to follow regarding material submittals. The USSF does not follow the practices in place by USACE. For the purposes of submittals for this project, they will be submitted using the Air Force Form 3000 in electronic format. No hard copy submissions will be required.

Supplemental Question:

E-101 Flag note 1 states all direct buried comm lines need to be removed in their entirety. Can you confirm that means digging up and disposing of the full length of all buried comm lines, throughout their full length?

Government Response: Design team believes there is direct buried communications at the following locations:

- From existing HH-11 at Catherine Point Road and Gannet Road Junction to Facility 12240 at

RAF POL site and SURE Facility.

- From existing pole 52A at command control to Facility 12225

- From existing pole 72 to Facility 41011

- From MH-53 to Facility 16545

Question & Answer Batch 1, 9-29-2023

Solicitation: FA252123B0008

Project Number: YXTK 13-1806 Repair Electrical Distribution Lines Feeder 5, AAAF

Contractor Name: Togiak Logistics Services LLC

POC: David Roels droels@togiakmgmt.com

1. IFB Section __01 00 00 Paragraph __1.7__

SOW/Technical Specification/Drawings paragraph/page 10

Other (Specify) ___________________________

Question:

Since this project is located OCONUS, is the requirement for a Florida General Contractors license applicable for this project?

*TRACES Response: Yes, unless otherwise noted by SLD 45 Contracting.

2. IFB Section __Solicitation Section C Paragraph

SOW/Technical Specification/Drawings paragraph/page __5 of 54

Other (Specify) ______________________

Question:

Section C of the solicitation reads that the period of performance for the project is 660 days after the receipt of the NTP. Section 01 00 00, 1.17.1 states that the time from NTP to completion is not to exceed 357 days with an onsite construction not to exceed 297 days. Please confirm that

660 days is the total period of performance from receipt of NTP to project completion.

Government Response: Section C is correct at 660 days. The period of performance was updated from the specification information. The number of days identified in Specification

Section 01 00 00, Para 1.17.1 did not take into account the variable logistical timeframes associated with shipment of material from Port Canaveral to Ascension Island utilizing the contracted vessel that is limited to 5 sailings per calendar year. Further review by the

Government determined that it was appropriate to increase the total period of performance from the stated 357 days to 660 days. The stated on site period of performance of 297 should still be used as the basis for direct costs associated with on site performance. The Government will consider a no-cost revision to the period of performance to account for lead time and shipping if necessary, under the conditions of an excusable delay (FAR 52.24-10, Default (Fixed Price

Construction)).

3. IFB Section ___01 00 00_______ Paragraph ___1.17.2

SOW/Technical Specification/Drawings paragraph/page ____12_____

Other (Specify) ___________________________

Question:

Please provide the Microsoft Project 2007 schedule template required for this project.

Government Response: Reference SF 1442, Section C, Para 6. Although the reference noted is contained in the specifications, formats for the construction progress schedule and construction progress reports shall utilize the AF Form 3064 and AF Form 3065. Microsoft Project 2007 is not needed.

4. IFB Section __01 35 26 Paragraph ___3.8.1

SOW/Technical Specification/Drawings paragraph/page ___72 of 264

Other (Specify) ___________________________

Question:

In 01 00 00, 1.23.1, Page 14 of 264 of the specifications it is stated that onsite personnel will be available to assist in locating existing structures and utility lines. In 01 35 26, Par. 3.8.1, page 72 of 264, of the specifications the contractor is required to provide a third party to locate the utility lines in conjunction with the station utility department. On Sheet C-001 in General Civil Notes 1

& 2 it is required that the contractor locate the existing utilities, structures and other features that affect the work to be completed and notify the contracting officer of any conflicts. With the project location being OCONUS and on a remote island with limited resources and transportation, would it be acceptable for the locating activities to be performed by an in-house employee of the contractor with proper training and equipment?

TRACES Response: An in-house locator is acceptable given proof of proper training and equipment is provided, but compliance with all other provisions of 01 35 26, Part 3.8.3 are still required. Please provide resume credentials and equipment to be used.

5. IFB Section __01 00 00____ Paragraph 1.26.2____

SOW/Technical Specification/Drawings paragraph/page __16______

Other (Specify) ___________________________

Question:

A) Since this project is located OCONUS, is the FL DOT standards just a reference for basis of design?

TRACES: FL DOT standards for safety will apply to Ascension AAF as best management practice as well as OSHA and USACE EM 385-1-1 requirements are directly referenced in the specification and are applicable.

6. IFB Section ____ Paragraph ____

SOW/Technical Specification/Drawings paragraph/page ___E-002________

Other (Specify) ____Single Line_______________________

Question:

Provide specifications for new non-fused cutout switches shown on E-002 Single Line Diagram.

A) Are these independently operated non-fused switches?

B) Are they gang operated switches?

C) Ratings?

D) Type?

E) Are any accessories such as arcing reduction or bird guards required?

TRACES Responses:

a. Yes.

b. Yes.

c. 15kV, 200A

d. Loadbreak

e. No additional accessories are necessary.

7. IFB Section ___33 71 01.00 40 Paragraph __2.3.6

SOW/Technical Specification/Drawings paragraph/page ___239

Other (Specify) ___________________________

Question:

Please clarify the following regarding the fused cutout switches:

A) What is the required BIL rating?

B) Are these required to be Load Break Type?

C) Are these single operated or ganged?

D) Are any accessories such as arcing reduction or bird guards required?

E) Insulator material types?

F) Other material or environmental considerations?

TRACES Response:

a. 110kV

b. Load break type

c. Ganged

d. No additional accessories are necessary.

e. Polymer

f. Stainless steel brackets/corrosion resistance.

8. IFB Section ___27 13 23.00 40___ Paragraph 3.1.9.h

SOW/Technical Specification/Drawings paragraph/page 212

Other (Specify) ___________________________

Question:

Please clarify the material specifications for the lashing wire to be used. Is this to be Type 316, .045 stainless steel wire?

TRACES Response: Type 316, 0.45 SST lashing wire is acceptable.

9. IFB Section 33 77 19.00 40 Paragraph __2.1_____

SOW/Technical Specification/Drawings paragraph/page __248_____

Other (Specify) __Drawing E-501, Flag Note 11_________________

Question:

Specification for the MV SDS Switches calls for 316L stainless cabinets. Drawing E-501, Flag

Note 11 calls for 304L SS for the splice cabinet. There is no specification provided for the MV

Splice Enclosure.

A) Are we to assume the applicable sub-clauses of the MV Switch specification (specifically the enclosure and dead-break terminations) apply to the MV Splice Enclosure, i.e., using the

316L stainless steel?

B) If there is a separate specification for the MV Splice Enclosure please provide it.

TRACES Response:

a. Enclosure is to be 304L Stainless Steel. Refer to Key Note 11 on Sheet E-501 for basis of design and specifications. Submit product data for selected enclosure for Government review/approval.

b. No additional specification for MV splice enclosure.

10. IFB Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page __5

Other (Specify) _Solicitation__________________________

Question:

The seaborne transportation guidelines have specific guidelines for palletized freight, 20 ft cargo containers and self-propelled equipment.

A) What are the dimensional and weight restrictions for that equipment and cargo that cannot be contained in a 20 ft shipping container?

B) This project requires a total of 150, 50' power poles, what is the sea transportation and material handling plan for loading and unloading these items at port?

Government Response: Asension offloading weight restriction is a maximum of 35 Tons.

Preference is 20’ seavans, but there is the ability to lift 40’ seavans. Maximum allowable weight for the loaded seavan containers (20 TEU (twenty foot equivalent unit)) is 15T (30K lbs). The vessel carrier does not use tri-axel chassis to move the seavans. Oversized cargo that will not fit into a seavan will be shipped as ‘flat rack’ cargo.

Offloading from the port at Ascension will be furnished by the base operations support contractor at no additional cost. Equipment and Material are taken to the staging area near the softball fields (Facility 12193), near the Volcano Club (Facility 1203).

Additional support will be provided by the Government at no cost to the construction contractor identified as station support furnished through the base support contractor (ABOS / Yang

Enterprises) to transport the concrete poles from the material staging area to the installation locations.

C) There will be the need for 20 ft containers as storage on the site throughout the project.

Will we need to provide them as part of our material loadout for the project? Will there be any transportation costs associated with these items? Is there transportation means on the island or at the facility for the transport and offloading of loaded 20 ft cargo containers at locations other than at the port?

a. Government Response: Storage containers will need to be provided by the construction contractor.

b. Government Response: Transport of construction contractor storage containers will be provided by the Government at no cost. Transport will be through the Ascension vessel.

c. Government Response: Offloading from the port at Ascension will be furnished by the base operations support contractor at no additional cost. Equipment and Material are taken to the staging area near the softball fields (Facility 12193)/Volcano Club (Facility 1203). Support will be provided by the Government at no cost to the construction contractor identified as station support furnished through the base support contractor (ABOS / Yang Enterprises) to transport the concrete poles from the material staging area to the installation locations. Any additional follow on movement will need to be requested and provided as station support through the base support contract. This method is available through proper advance coordination but will need to be limited to an as needed basis to avoid overburdening the base support contractor from their primary contract duties.

11. IFB Section 33 71 01.00 40 Paragraph _________

SOW/Technical Specification/Drawings paragraph/page __231___

Other (Specify) ___________________________

Question:

Please provide the wind load and other specific design criteria for the concrete poles and aerial transmission lines / equipment that is not included in the current specifications or drawings.

TRACES Response: In accordance with Specification 33 71 01.00.40, Part 2.3.2 the required

Professional Engineer will make the wind load and other environmental determinations in accordance with IEEE C2. As the basis of design, 130 mph under the “Extreme Loading” scenario was used, but that needs to be validated by the Contractor’s P.E.

12. IFB Section __C Paragraph ___8.3

SOW/Technical Specification/Drawings paragraph/page ___6______

Other (Specify) _____Solicitation______________________

Question:

There is a specific statement regarding diesel fuel being made available to the contractor for equipment used for the completion of the construction project. Is Gasoline available in the same manner for small engine equipment needed for the project that is not available in diesel?

Government Response: Only diesel is available through station support. Mogas or Unleaded fuel must be purchased on the local economy. There is only one source on Ascension located near Two

Boats Village. Fuel prices are set at £1.50 per litre at this time and opening hours are 1630hrs to

1830hrs on Mondays and Thursdays.

13. IFB Section __________ Paragraph _________

Other (Specify) __Engineering / Geo-tech_______________

Question:

A) What is the general composition of the subgrade soil and bedrock in the designated construction area?

B) What is the general soil depth above bedrock, around the construction area?

TRACES Response:

A) No geotechnical investigation information is available through TRACES; however, the

Gov’t may have historical information available. For information purposes only, the subgrade material will vary substantially due to the large construction area; however, typical subgrade will consist of a mixture of volcanic clinker and volcanic bedrock.

B) Since the design of the pole and their foundation is a delegated to the construction contractor per Specification 33 71 01.00.40, Part 2.3.2, the contractor is responsible for verifying subsurface conditions.

14. IFB Section __________ Paragraph _________

Other (Specify) ___________________________

Question:

Can you provide previous geotechnical report(s) for projects located in the areas near where the underground duct bank installation is required. This will help provide a clear understanding of the underlying structural conditions of the island to facilitate excavation and backfill calculations?

TRACES Response: Reference response to Question 13.

15. IFB Section __________ Paragraph _________

Other (Specify) ____General___________

Question:

Please provide local contacts for the following building materials on Ascension Island.

A) Ready mix concrete

B) Aggregate / 57 stone

C) Utility Bedding Sand

D) Clean fill dirt.

Government Response: Reference Attachment 15. These are two concrete mixes using Portland

Type IL and Portland Type II cement. These mix designs have demonstrated the ability to achieve 3,500 - 4,000 PSI. It will still be the construction contractor’s responsibility to ensure that the mix design used achieves the strength requirements as stated in project documents.

These designs utilize local aggregate. Sand and cement will need to be procured from U.S.

sources and shipped to Ascension.

Elements to be provided by the Government at no cost to the construction contractor identified as station support furnished through the base support contractor (ABOS / Yang Enterprises) areas are:

16. IFB Section __________ Paragraph _________

Other (Specify) _____General

Question:

A) Is there Cellular phone and data service on the island or base that will be available to the workers?

Government Response: The local cellular and internet provider is Sure. https://www.sure.co.ac/

B) Will the Government provide broadband internet access for our business operation throughout the project?

Government Response: No. This is the construction contractor’s responsibility.

C) Is there commercially available broadband internet access that will be available for the workers / contractors?

Government Response: The local cellular and internet provider is Sure. https://www.sure.co.ac/

D) If the above are not available, will the Government allow us to install our own satellite based communication system?

Government Response: Starlink resources are currently being used on Ascension. The responsibility for setup and maintenance would be the construction contractor.

17. IFB Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page __C-001_________

Other (Specify) ___General Civil Note 14

Question:

Civil General Note 14 Requires a Florida Registered Surveyor be employed for surveying and resetting of disturbed benchmarks. Since this is an OCONUS project is it acceptable to utilize employed team members for this task should they be properly trained, equipped, and competent to perform the work?_

TRACES Response: Acceptable under the conditions a resume of properly trained and registered surveyor is provided and approved by the Contracting Officer.

18. IFB Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page ____C-501_______

Other (Specify) ___________________________

Question:

Can we utilize engineered precast switch and equipment pads set in bedding sand, on 57 stone base, on compacted soil; for the transformer, splice cabinets and MV Switch cabinets as opposed to cast in place?

TRACES Response: Per specification 03 30 00, provide cast-in-place concrete pads with

ChromeX reinforcement for all concrete placed on Ascension. Precast concrete, fabricated state side, can use ASTM A615, Grade 60 reinforcement.

19. IFB Section _03 30 00_ Paragraph ____2.5.1.i

SOW/Technical Specification/Drawings paragraph/page 139

Other (Specify) ___________________________

Question: Will alternative dyeing methods for concrete duct bank be acceptable?

A) Can the appropriate color concrete stain / dye be surface applied post pour to the duct banks?

B) Powder dye on the wet concrete pour and trowelled into the surface?

C) Wet dye sprayed onto the surface of the finished pour?

TRACES Response: Per specification 03 30 30 section 2.5.1 (i). All above methods are acceptable as long as color is in accordance with APWA Uniform Color Code.

20. IFB Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page ___C-001________

Other (Specify) __Erosion and Turbidity Control General Notes, Note 2_

Question:

The drawings state that erosion control measures must be in conformance with the Final

Governing Standards of Ascension AAF and Other Local agencies. Please provide a copy of the

"Final Governing Standards" for Ascencion AAF and any other relevant documentation for required erosion control measures for the project.

Government Response: Final Governing Standards-Ascension Island included as Attachment

16.

21. IFB Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page __E-404_________

Other (Specify) ___Facility 800 Power Sequence of Construction, Note 2_____

Question:

Note states "Existing Facility Generator and Portable Generator".

A) What is the anticipated load demand requirements for the portable generator?

Government Response: 60kW is what the installed Gen Set is at FN 800. It is unknown if the existing generator can be configured to fund the facility while the power is off.

B) Who is providing the portable generator?

Government Response: The construction contractor to provide their own generator. 60‐100kW.

The existing generator is owned and maintained by the Royal Air Force (RAF). The age and condition of this equipment is unknown.

C) Who will be responsible for fueling and maintaining the portable generator(s)?

Government Response: Reference response for item B above. The construction contractor will be responsible for maintaining. Fuel (diesel) will be provided as Station Support.

D) What is the operational schedule of Facility 800 while it is on generator power? (ie, 24/7 or other)

Government Response: Alarm systems are for the facility are required to be fully operational.

Power will need to be provided at all times.

E) How long will Facility 800 be allowed to remain on generator power to allow us to construct?

Government Response: As long as needed to complete construction activities.

22. IFB Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page _E-401

Other (Specify) ____Flag Note 6________

Question:

On Drawing E-401, For replacement of the existing transformer XFMR PM 5/12 feeding the

Xontec trailers. The replacement transformer will have to be placed so that it overlays the location of the existing transformer using existing secondary feeders and conduit. This placement will require de-energizing the feed to the transformer, demolition of the existing transformer and equipment pad, grading and placement of the new equipment pad followed by installation and connection of the replacement transformer before re-energizing the feeder.

A) How long will we be allowed to transition from old feeder/ transformer to new?

Government Response: The transition time to properly complete the process is acceptable.

There is no specific number of days that need to be met. Government expectations are to complete in the shortest timeframe needed.

B) Are there critical systems fed from this transformer that will need to be provided temporary power during the portion of the construction timeline that will require a full shutdown of the feed from this transformer location?

Government Response: No Mission Critical loads are on this transformer, but the trailers are living quarters for on-island personnel and will need to be provided power on a 24/7 basis.

a. If so, what load will need to be accounted for?

Government Response: 550kW generator set - 120/240 volt Hz

b. If so, who will provide the temporary generator?

Government Response: Temporary generators will need to be furnished by the construction contractor. The type and size to be provided is ultimately the construction contractor’s decision, however the Government recommends at least one 100kW generator with multi voltage.

23. IFB Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page __C-001_____

Other (Specify) ___Erosion Control General Notes, Note 10_____

The note requires stabilization of excavated soils.

A) Please provide the written standards for the facility, for the purpose of stabilization of excavated and backfilled soils.

B) Are there any standard grass seeds, traditionally used for erosion control, any specifically prohibited for use on the island as erosion control / stabilization planting? Or will you provide a published standard of acceptable materials and methods?

Government Response: Final Governing Standards-Ascension Island included as Attachment 16

24. IFB Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page __E-404____

Other (Specify) __Note #9_______

Question:

There appears to be missing details regarding the new FOC entering Facility 12240. Should note

9 be amended to state that the 12-Str FOC in the 12240 Facility is to be terminated into an existing patch panel?

TRACES Response: Correct. The 12-strand FOC will terminate into existing patch panel.

25. IFB Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page __E-404, E-405, E-407, E-410

Other (Specify) ___Existing Fiber Optics Patch Panels in affected buildings.

Question:

In Sequence of Construction Note 6 it states to remove existing fiber optic cable from patch panel and install new fiber optic cable.

A) Please provide the model numbers of the existing fiber optic patch panels and associated termination assemblies in each of the following buildings.

a. Building 12240

b. ISP Sure Facility

c. Building 12225

d. Building 16545

B) Please provide pictures of the existing equipment to assist in our evaluation and preliminary estimating work prior to the site visit.

Government Response: All four facilities (a-d) are the same. Reference Attachment 20, Photos, Fiber Wall Mount Distribution Cabinets.

26. IFB Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page __E-405____

Other (Specify) ____Note #2______

Question:

There appear to be missing details regarding the new FOC entering the ISP Sure Facility. Should note 2 be amended to state that the 48-Str FOC in the ISP Sure Facility is to be terminated into an existing patch panel?

TRACES Response: Flag Note 2 states to connect new fiber optic cables to existing patch panel.

27. IFB Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page Various Electrical Drawings

Other (Specify) ___________________________

Question:

The specified TII, Model 1581P2, Building Entrance Protector for copper termination in the facilities is discontinued. The manufacturer is recommending TII, Model 1525 or 1525GT (with factory installed modules) as the replacement for the specified unit.

A) Does the installation require the factory installed protection modules?

B) Is this an acceptable alternative to the specified equipment?

Government Response: Any deviation from the specifications will require Government review and approval. If the specified item is discontinued generally the Government would defer to the manufacturer’s recommendations.

28. IFB Section __01 00 00______ Paragraph ___1.34____

SOW/Technical Specification/Drawings paragraph/page ___21________

Other (Specify) ___________________________

Solid Waste Disposal section states that Non-hazardous waste is disposed of at the Area 5000

Construction Debris Landfill. Any hazardous waste must be put in contractor supplied containers as appropriate.

A) Where is the Area 5000 Construction Debris Landfill on the site / island?

B) Will the demoed wooden power poles be accepted for disposal at the Area 5000

Construction Debris Landfill?

C) Will the cabling being removed during the course of the project be accepted for disposal at the Area 5000 Construction Debris Landfill?

D) Will the non-reusable excavated materials from the project be accepted at the Area 5000

Construction Debris Landfill?

E) What means and methods are available at the Area 5000 Construction Debris Landfill for offloading of materials?

Government Response: None. All waste debris will be disposed of locally in the landfill.

Offloading responsibility of the construction contractor.

29. IFB Section __________ Paragraph _________

SOW/Technical Specification/Drawings paragraph/page __E-410___

Other (Specify) ___Scale Discrepancy____

Question:

The scale notes for N-410, Radar Facility Detail on sheet E-410 is shown as 1” = 40’ and the

Graphical Scale shows 1” = 30’. Initial cross reference measurements show that the drawing scale should be shown as 1” = 30’, Is this the accurate scale that should have been noted on this drawing?

TRACES Response: Scale should have read as 1”=30’

30. IFB Section Paragraph

SOW/Technical Specification/Drawings paragraph/page E-502

Other (Specify) Typical Communication Handhole Detail

The handhole schedule with detailed sizing information or a typical size is not listed in the drawings or specifications. Please provide the schedule for the handhole sizes or sizing guidelines based on the cabling installations specified for the project.

TRACES Response: Reference response to Question 33.

*Designer of Record (DOR) is represented as ‘TRACES’

Question & Answer Batch 2, 10/06/2023

Project Number: YXTK 13-1806 Repair Electrical Distribution Lines

Feeder 5, AAAF

Contractor Name: Togiak Logistics Services

POC: David Roels

31. IFB Section Paragraph

SOW/Technical Specification/Drawings paragraph/page C-001

Other (Specify) General Civil Note 15

Question:

Drawing C-001, General Civil Note 15 leads us to believe that there are potentially other public utilities in the area of construction other than indicated on the drawings. What other utilities are in the construction area other than what is drawn?

*TRACES Response: Portions of the project are outside of the Ascension AAF Main Base area and therefore will require coordination with other island utility providers to ensure conflicts do not exist. Coordinate with local base operations contractor for more information on utility services.

32. IFB Section Paragraph

SOW/Technical Specification/Drawings paragraph/page C-502

Other (Specify) Typical Duct Line Drainage Detail

Question:

On C-502, Typical Duct Line Drainage Detail is an exterior building penetration. Please provide the applicable detail.

TRACES Response: Typical Duct Line Drainage Detail is provided on sheet C-501. Ensure conduit drains away from buildings as shown on C-501.

33. IFB Section Paragraph

SOW/Technical Specification/Drawings paragraph/page

Other (Specify) Electrical Drawings

Question:

There is no designation shown for the sizing of the communications handholes for this project.

Please provide the schedule for the communications handholes including sizing and desired orientation.

TRACES Response: Communication handholes are to be minimum 4’x4’x4’. Orientation of each handhole is shown in drawings.

34. IFB Section Paragraph

SOW/Technical Specification/Drawings paragraph/page C-501

Other (Specify)

Question:

On C-501, Typical Duct Entrance to Manhole Detail indicates that #5 rebar from duct bank embedded in the manhole. On the same drawing the typical duct bank details do not indicate rebar installed in the duct banks.

A) Please verify that rebar is only required at the connection of the duct bank to manhole as indicated in a dowel pin configuration to prevent movement.

TRACES Response: Rebar is only required at the connection of the duct bank to manhole per the

Typical Duct Entrance to Manhole Detail on sheet C-501.

35. IFB Section Paragraph

SOW/Technical Specification/Drawings paragraph/page Various

Other (Specify)

Drawing C-501 indicates that the communications duct bank and trench are 4", 2-way conduit configuration. Drawing E-001 Communication General Note 1 that states New Underground

Communication cables must be routed through 4” conduits. Note 9 states to provide a 4” RGS conduit riser to transition from underground to overhead. Drawing C-402, Flag note 4; Drawing

C-405, flag note 3; Drawing C-406, flag note 3; Drawing C-407, Flag Note 1; Drawing C-408, flag note 2, Drawing C-409, flag note 1, Drawing C-410, flag note 1, Drawing C-414, flag note

3; Drawing C-415, flag note 2; Drawing C-417, flag note 3; Drawing C-418, flag note 2;

Drawing C-423, flag note 3; Drawing C-424, flag note 3; Drawing C-430, flag note 3; all indicate the installation of 5" PVC pipe in all of the communications ducts with the 2 way configurations indicated throughout the electrical drawings. Our cable fill calculations indicate that the 900 pair copper would be code legal in 4"conduit, but our recommendation for best practices is to use 5" for a cable of this size. This will prevent damage to the cable during installation. We foresee two viable options listed below for this issue. Please indicate your specified solution.

A) All the communication cable ducts for the 900 pr copper communication cables and 144 strand fiber to be 5" in a 2-way configuration while all others allowed to be 4" 2-way configuration.

B) All communications conduit pathways be 5” PVC in a 2-way configuration.

TRACES Response: UFC requirement is for a minimum of 4” and is the design intent; however, this is a minimum and if 5” facilitates constructability it is acceptable.

36. IFB Section Paragraph

SOW/Technical Specification/Drawings paragraph/page E-409

Other (Specify) Transmitter Enlarged Plan, L/E-409

Question:

There are sections / details missing from this enlarged plan.