6-Civil Specs-Fire School.pdf
PDF 1 MB Posted
- Solicitation number
- US.251947
- Issued by
- Somerset County, Pennsylvania
About this file
This civil specifications document pertains to the construction of the Schuylkill County Emergency Training Facility in Pennsylvania, a project managed by Schuylkill County. The project is divided into four separate prime contracts: General Construction, Plumbing Construction, HVAC Construction, and Electrical Construction. Sealed bids will be received online through the PennBid Program until Wednesday, October 21, 2026, at 9:00 AM, with results available following the Board of Commissioners meeting. The tentative award date is Wednesday, October 28, 2026. All bidding documents are available at no cost via http://PennBid.bonfirehub.com. Technical assistance for PennBid access is available through email at info@pennbid.net or by phone at 610-693-4769. Site visits and a bidders' conference are referenced in the opportunity documentation, though specific dates and details are not provided in this specifications file.
Each bid must be accompanied by bid security in the form of a certified check, bank draft, or bid bond payable to Schuylkill County in an amount equal to 10 percent of the total bid. The successful bidder will be required to furnish Performance and Payment Bonds each equal to 100 percent of the contract price with an approved corporate surety. Davis-Bacon wage rates will apply to all contracts. The County reserves the right to waive any informalities or reject any or all bids in its best interest. Contractors must ensure compliance with non-discrimination requirements regarding race, age, color, religion, sex, national origin, and handicap status. Money orders and personal checks are not acceptable forms of bid security.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EMA Fire School Building Project No. 0325-900015.01
MOBILIZATION/DEMOBILIZATION Section 01060
MOBILIZATION/DEMOBILIZATION Section 01060 - Page 1
SECTION 01060 - MOBILIZATION/DEMOBILIZATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
1. Drawings and general provisions of Contract, including General and
Supplementary Conditions and other Division-1 Specification Sections, apply to this Section.
2. Pennsylvania Department of Transportation, Specifications, Publication 408, Section 608 in latest revision and documents referenced within, apply to this section. Use PennDOT Publication 408 for any discrepancies between specifications provided in this document and the PennDOT Highway
Construction Specifications.
1.2 SUMMARY
This work shall consist of assembling/disassembling and setting up/tearing down for the project, the Contractor's necessary general plant, including field office, shops, plants, storage areas, sanitary and any other facilities, transportation of all equipment and materials to and from the site, as required by the specifications and special requirements of the contract, as well as by local or State law and regulation. The determination of the adequacy of the Contractor's facilities, except as noted above, shall be made by the
Contractor. Mobilization includes any required insurance and bonds and/or other initial expenses required for the start of work and all items indicated as incidental shall be included in this item.
PART 2 - PRODUCTS (NOT APPLICABLE)
PART 3 - EXECUTION
The Contractor shall furnish all materials and furnishings required for this item. These materials and furnishings will not be considered as a part of the various items of the completed contract.
The Contractor shall provide all tools, equipment, materials, labor and work for the construction and furnishings of the required facilities and services. All work under this item shall be performed in a safe and workmanlike manner.
END OF SECTION 01060
EMA Fire School Building SUMMARY Section 01120
SUMMARY Section 01120 - Page 1
SECTION 01120 - SUMMARY
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes:
1. Project information.
2. Work covered by Contract Documents.
3. Phased construction.
4. Work by Owner.
5. Access to site.
6. Coordination with occupants.
7. Maintaining Storage Yard
8. Requirements for Blasting Operation
9. Utility
10. Waterline and Fitting locations
11. Maintenance and Protection of Traffic
12. Burning
13. Damage to Private or Public Property
14. Cutting Existing Pavement
15. Street Restoration
16. Use of Private Land
17. Location of Waste Area for Excavation
18. Pre-Drilling, Pre-Blasting, and Rock Excavation
19. Work restrictions.
20. Specification and drawing conventions.
21. Project Identification
22. Permit Fees
B. Related Section:
1. Division 01 Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.
1.3 PROJECT INFORMATION
A. Project Identification: EMA Fire School Building
1. Project Location: Adjoining existing fire training facility along Firemen’s Road in Ryan and West Mahanoy Townships.
SUMMARY Section 01120 - Page 2
B. Owner: Schuylkill County
Owner's Representative: Y. Kim Architects
729 W. Market Street (Rear Door) Pottsville, PA 17901
C. Administrative Engineer:
a) Alfred Benesch & Company Kevin A. Marmas, P.E.
400 One Norwegian Plaza Pottsville, PA 17901 Phone: (570) 622-4055
1.4 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of the Project is defined by the Contract Documents and consists of the following:
1. The scope of the project includes improvements to the property in addition to the proposed building such as bituminous paving, concrete sidewalk, stormwater drainage and management facilities, fence, and access gates with curbed islands. These items are more fully described in unit prices specification, special construction specification, plans and specifications.
B. Type of Contract
1. Project will be constructed under a single prime contract.
1.5 PHASED CONSTRUCTION (NOT APPLICABLE)
1.6 WORK AND USE BY OWNER
A. General: Cooperate fully with Owner so work may be carried out smoothly, without interfering with or delaying work under this Contract or work and use by Owner. Coordinate the Work of this Contract with work and use performed by Owner.
B. Preceding Work: Owner will perform the following construction operations at Project site. Those operations are scheduled to be substantially complete before work under this Contract begins.
1. None.
C. Concurrent Work: Owner will perform the following construction operations at Project site. Those operations will be conducted simultaneously with work under this Contract.
1. None.
D. Subsequent Work: Owner will perform the following additional work at site after Substantial Completion. Completion of that work will depend on successful completion of preparatory work under this Contract.
1. Site stabilization, one year operation and maintenance agreement.
SUMMARY Section 01120 - Page 3
1.7 ACCESS TO SITE
A. General: Contractor shall have full use of Project sites for construction operations during construction period. Contractor's use of Project site is limited only by Owner's right to use the property, perform work or to retain other contractors on portions of Project.
1.8 COORDINATION WITH OWNER
A. Owner Occupancy: Owner will occupy the adjacent fire training facility premises periodically during entire construction period. Construction should not interfere with adjacent property usage and contractor to cooperate with Owner during construction operations to eliminate or minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's operations on the adjacent property.
Maintain existing exits unless otherwise indicated.
1. Access to the adjacent facility is separate from the construction site off of Firemen’s Road and contractor shall avoid obstructing access to the adjoining facility Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and authorities having jurisdiction.
2. Provide not less than 72 hours' notice to Owner of activities that will affect Owner's operations.
1.9 MAINTAINING STORAGE YARD
The CONTRACTOR is required to maintain his field office and storage yard in a neat and orderly fashion, and provide for the protection of the general public by a fence or other protective device. The CONTRACTOR shall remove from the site all surplus and discarded materials.
1.10 REQUIREMENTS FOR BLASTING OPERATION – Not Applicable
No blasting is allowed unless authorized by the owner. The CONTRACTOR’S attention is directed to the
Paragraphs entitled “Predrilling, Preblasting and Rock Excavation, which occur later in this section. The CONTRACTOR must at all times comply with TITLE 25, Rules and Regulations, Part I - Department of Environmental Resources, Sub part D - Environmental Health of Safety, Article IV - Occupational Health and Safety, Chapter 211 - Storage, Handling and Use of Explosives.
The CONTRACTOR shall be required to familiarize himself with the above Rules and Regulations and shall place in charge of all blasting operations competent and responsible persons who are blasters, licensed by the Department of Environmental Resources. All blasting procedures used shall be in conformance with the above Regulations.
1.11 UTILITY
It shall be the responsibility of the Contractor to exactly locate, as necessary, all existing utilities on the project site and to avoid all unnecessary conflicts therewith. The Engineer or the owner does not guarantee the accuracy of the location of the present subsurface utility installation or structures shown on the plans. Neither does the Engineer guarantee that all subsurface installations are shown.
The CONTRACTOR shall cooperate with all utility companies involved in this project, and shall, within two
(2) weeks after Notice To Proceed, provide each utility company with a copy of the approved project schedule. The CONTRACTOR shall be required to notify the affected utility company at least forty-eight
(48) hours in advance of starting work in any area of conflict. The list of utility companies given below is
SUMMARY Section 01120 - Page 4 provided for information only and does not relieve the CONTRACTOR of his responsibility of securing names and addresses of utilities involved in the contract project from the Schuylkill County Courthouse in accordance with the current laws.
The following public utilities were located in the PA One Call System:
West Mahanoy Township:
Frackville Area Municipal Authority
PO Box 471
42 S Center St
Frackville, PA 17931
Rhonda Frantz famainfo@fama874.com
570-874-3589
PPL Electric Utilities Corp.
437 Blue Church Road Paximos, PA 17860
Doug Haupt dhaupt@pplweb.com
(610) 297-2461
Pennsylvania American Water
306 West Front Street
PO Box 249
Berwick, PA 18603
Michael Spaide
Email – Michael.spaide@amwater.com
Service Electric Cablevision Inc
380 Maplewood Drive
PO Box R
Hazleton, PA 18201
Timothy Trently
Timothy.trently@secv.com
570-454-5079
Municipal Authority of the Borough of
Shenandoah
110 N Ferguson Street
PO Box 110
Shenandoah, PA 17967
Kiara Tapia
Office1@mabswater.com
570-462-1904
Ryan Township:
PPL Electric Utilities Corp.
437 Blue Church Road Paximos, PA 17860
Doug Haupt dhaupt@pplweb.com
(610) 297-2461
Ryan Township
380 Maplewood Drive
PO Box R
Hazleton, PA 18201
Robert Trently
Robert.trently@secv.com
570-454-3841
West Mahanoy Township
190 Pennsylvania Avenue
Shenandoah, PA 17976
Michael Michalik wmtoffice@pto.net
570-462-2958
380 Maplewood Drive
PO Box R
Hazleton, PA 18201
Robert Trently
Robert.trently@secv.com
570-454-3841
SUMMARY Section 01120 - Page 5
36 N Fifth Avenue
Barnesville, PA 18214
Jim Palaio
570-467-2771
The CONTRACTOR will be held responsible for all damage to utility facilities and / or drainage structures, caused by the CONTRACTOR, and such damage will be repaired at the expense of the Contractor in accordance with applicable utility or Municipal specifications. Repair to any utility line may be made by the CONTRACTOR or the utility company at the discretion and with the approval of the utility company, and will not be part of this contract.
1.12 WATERLINE AND FITTINGS LOCATIONS
The location of the waterlines and fittings shown on the drawings are approximate. The exact location of the waterline and fittings shall be determined at the time of construction. Any adjustment to the locations of the waterline and fittings will not constitute a claim for additional compensation by the CONTRACTOR.
1.13 MAINTENANCE AND PROTECTION OF TRAFFIC
The Contractor shall schedule the work to insure the least inconvenience to the vehicular and pedestrian traffic. Roads / Driveways shall not be unnecessarily obstructed, and unless prior approval is received from the Police Chief, Fire Chief, Owner and Engineer for both Townships, none of the streets shall be closed.
Fire alarm boxes and fire hydrants adjacent to the work shall at all times, be readily accessible to fire apparatus and equipment, and no material or other obstructions shall be placed within fifteen feet (15’) of any hydrant.
The cost of providing and maintaining the necessary signs, flashing warning lights, barricades, markers and other protection devices for the maintenance and protection of traffic shall incidental to the project.
1.14 BURNING
The burning of debris or other matter shall not be permitted except by written permission of the Police and
Fire Chief. A copy of the approval shall be furnished to the Engineer in advance of the burning. Any approved burning shall be in conformity with the regulations of the State Air Pollution Control Commission.
1.15 DAMAGE TO PRIVATE OR PUBLIC PROPERTY
The CONTRACTOR shall prior to the start of construction, photograph or video all existing physical features which are damaged. See Section 013233 for Photographic documentation.
Unnecessary damage to private or public property, caused by the CONTRACTOR, shall be repaired to the satisfaction of the OWNER at the CONTRACTOR’S expense. The CONTRACTOR shall restore to a condition similar to the condition that existed prior to the damage, any direct or indirect damages caused by the CONTRACTOR or in consequence of an act or omission on the part of the CONTRACTOR, his employees, agents or subcontractor. Should any property require repair or replacement or rebuilding by the OWNER, as a result of, therefore will be deducted from any money due or to become due to the CONTRACTOR, a sum sufficient to reimburse the OWNER of the property for damage incurred.
1.16 CUTTING EXISTING PAVEMENT
1. If required, before any excavation takes place, the CONTRACTOR shall neatly saw cut all surfaces and base coarses of the streets, to the widths indicated in the specifications governing the
SUMMARY Section 01120 - Page 6 acceptable trench widths, or as required by the Engineer. In no case shall the Contractor proceed without first saw cutting the trench outline to preclude extensive tearing of the surface. Cutting of existing pavement will include cutting any bituminous, concrete, or brick pavement as necessary for construction. At a minimum, the saw cut must conform to PENNDOT Standards, regardless of whether it’s a state road, municipal road, private driveway, etc.
2. Non-mechanically/hydraulically driven asphalt cutters are prohibited. These types of prohibited asphalt cutters are commonly called “pizza cutters”, and are typically attached to loader buckets or excavators/backhoes. Additionally, milling machines are not an acceptable alternative to saw cutting.
1.17 STREET RESTORATION
The CONTRACTOR shall, at all times, maintain in satisfactory condition all trenches within the contract limits.
1.18 USE OF PRIVATE LAND
The CONTRACTOR shall confine his operations to the areas, as indicated on the plans. All additional land required for the erection of temporary construction facilities, storage of material, dumping of excavated material, together with the right of access thereto, shall be provided by the CONTRACTOR. No use of any private land will be permitted until written permission from the Owner of the land is furnished to the
ENGINEER.
1.19 LOCATION OF WASTE AREA FOR EXCAVATION
All additional land required for dumping of excavated, suitable soil and rock materials, together with the right of access thereto, shall be provided by the CONTRACTOR. No use of any private land will be permitted until permission from the Owner of the land is furnished to the ENGINEER and the OWNER. Appropriate Erosion and Sedimentation Control Approval is required by the Contractor for this area.
1.20 PRE-DRILLING, PRE-BLASTING AND ROCK EXCAVATION – Not Applicable
A. Pre-drilling and Pre-blasting, when permitted by the owner and Chapter 211of the Pennsylvania DEP
Rules and Regulations for the Storage Handling and Use of Explosives, shall be performed so that the drilling and blasting is limited to that which is required to complete the installation of the underground utilities shown on the Contract Drawings.
Pre-drilling and pre-blasting as necessary shall be considered incidental to construction.
1.21 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets and other requirements of authorities having jurisdiction.
B. On-Site Work Hours: Limit work to normal business working hours of 7:00 a.m. to 7:00 p.m., Monday through Friday, except as otherwise indicated or if approved by Owner and Engineer.
1. Weekend Hours: Requires approval from Owner and Engineer.
2. Early Morning Hours: Requires approval from Owner and Engineer.
SUMMARY Section 01120 - Page 7
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
1. Notify ENGINEER and Owner not less than two days in advance of proposed utility interruptions.
2. Obtain ENGINEER's written permission before proceeding with utility interruptions.
D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.
1. Notify ENGINEER and Owner not less than two days in advance of proposed disruptive operations.
2. Obtain ENGINEER's and Owner's written permission before proceeding with disruptive operations.
1.22 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
C. Drawing Coordination: Requirements for materials and products identified on the Drawings are described in detail in the Specifications. One or more of the following are used on the Drawings to identify materials and products:
1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.
2. Abbreviations: Materials and products are identified by abbreviations published as part of the U.S. National CAD Standard and scheduled on Drawings.
3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.
1.23 PERMIT FEES
A. Permit fees by the municipalities or utilities shall be paid by the Contractor. The Contractor shall provide any and all municipal and utility permitting fees. Contractor shall provide proof of payment for all fees.
SUMMARY Section 01120 - Page 8
1.24 INSPECTION FEES
A. An allowance is provided in the amount of $12,000 for inspection fees by the municipalities or utilities.
Contractor shall provide proof of payment for all inspection fees. If fees exceed the allowance, the Owner shall reimburse the Contractor for the amount beyond the allowance. If the allowance is not reached, there shall be a credit to the Contract under Mobilization for the remainder of the allowance.
1.25 TAPPING AND SERVICE CONNECTION FEES
A. Utility tapping or service connection fees, including sanitary sewer, water, and electric shall be paid by the Owner. Contractor shall coordinate with the owner on payment of any tapping or service connection fees including amount of the fee and whom to make payment to.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01120
CONSTRUCTION SURVEY Section 01712
CONSTRUCTION SURVEY Section 01712 - Page 1
SECTION 01712 – CONSTRUCTION SURVEY
1.1 Related Documents:
A. Drawings and general provisions of contract, including general and supplementary conditions and Division 1 specification sections apply to this section.
B. PENNDOT Publication 408 specifications, Section 686 “Construction Survey”, latest revision. Use PennDOT Publication 408 for any discrepancies between specifications provided in this document and the PennDOT Highway Construction
Specifications.
1.2 Description of Work:
A. This work shall consist of the following:
1. Surveying for general construction to achieve proposed site elevations and slopes based on site plans. The drawings or detail sketches are developed using topographic survey. Benchmarks, elevations and slopes are provided.
2. ADA compliant sidewalks, ramps, and driveways. Contractor shall layout sidewalks, ramps, and driveways in accordance with the plan drawings and
PennDOT RC Standards. If the Standards cannot be met, the Contractor must immediately notify the Engineer. Sidewalks cross slope shall be 2% or less.
3. Drainage system. Contractor shall place all drainage structures, including all inlets and pipes so a 0.5% minimum pipe slope is achieved. Invert of inlets shall be established based on the proposed invert at the tie in location and pipe length. Do not order inlets until contractor has verified inverts.
4. Parking Lot Profile and Cross Sections. A 1% minimum slope has been calculated from the perimeter of the parking lot to the inlet invert.
Contractor shall verify minimum slope is achieved.
PART 2 - EXECUTION
1. As per PennDOT Publication 408 specifications, Section 686.
END OF SECTION 01712
CAST-IN-PLACE CONCRETE – SITE WORK Section 03300
CAST-IN-PLACE CONCRETE Section 03300 - Page 1
SECTION 03300 - CAST-IN-PLACE CONCRETE – SITE WORK
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
B. Pennsylvania Department of Transportation, Specifications, Publication 408, in latest revision and documents referenced within, apply to this section. Use PennDOT Publication 408 for any discrepancies between specifications provided in this document and the PennDOT Highway
Construction Specifications.
1.2 SUMMARY
A. This Section specifies cast-in place concrete, including formwork, reinforcement, concrete materials, mixture design, placement procedures, and finishes, for the following:
1. Cement Concrete Sidewalks
2. Plain Cement Concrete Curbs
3. Door Landings
B. Related Sections include the following:
1. PennDOT Pub 408 in its latest revision, Section 704, Cement Concrete
2. PennDOT Pub 408 in its latest revision, Section 676, Concrete Sidewalks
3. PennDOT Pub 408 in its latest revision, Section 630, Plain Cement Concrete Curb
4. PennDOT Pub 72M in its latest revision, RC-64M and RC-67M
1.3 DEFINITIONS
A. Cementitious Materials: Portland cement alone or in combination with one or more of the following: blended hydraulic cement, fly ash and other pozzolans, ground granulated blast-furnace slag, and silica fume; subject to compliance with requirements.
1.4 SUBMITTALS
A. Material Certificates: For each of the following, signed by manufacturers:
1. Cementitious materials.
2. Aggregate
3. Admixtures.
4. Form materials and form-release agents.
5. Steel reinforcement and accessories.
6. Fiber reinforcement.
7. Waterstops.
CAST-IN-PLACE CONCRETE Section 03300 - Page 2
8. Curing compounds.
9. Floor and slab treatments.
10. Bonding agents.
11. Adhesives.
12. Vapor retarders.
13. Semirigid joint filler.
14. Joint-filler strips.
15. Repair materials.
B. Quality Control: Submit a Minimum Quality Control Plan for Field Placement Concrete
Operations (CS-704). Prepare a field operation QC Plan for the Representative’s review, on
Form CS-704, to evaluate concrete field operation. Submit the field operation QC Plan at the
Pre-construction conference or at least 3 weeks before the first concrete pour. Describe the construction equipment, personnel, and methods necessary to construct and test concrete courses for all structural elements. Include testing frequencies and action points to initiate corrective measures. Do not establish action points at either the upper or lower specification limits.
1.5 QUALITY ASSURANCE
A. Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C 94/C 94M requirements for production facilities and equipment.
1. Manufacturer certified according to NRMCA's "Certification of Ready Mixed Concrete
Production Facilities."
B. Testing Agency Qualifications: An agency, acceptable to authorities having jurisdiction, qualified according to ASTM C 1077 and ASTM E 329 for testing indicated, as documented according to ASTM E 548.
1. Personnel performing laboratory tests shall be ACI-certified Concrete Strength Testing
Technician and Concrete Laboratory Testing Technician - Grade I. Testing Agency laboratory supervisor shall be an ACI-certified Concrete Laboratory Testing Technician -
Grade II.
C. ACI Publications: Comply with the following unless modified by requirements in the Contract
Documents:
1. ACI 301, "Specification for Structural Concrete," Sections 1 through 5.
2. ACI 117, "Specifications for Tolerances for Concrete Construction and Materials."
D. Concrete Testing Service: Engage a qualified independent testing agency to perform material evaluation tests and to design concrete mixtures.
1. Provide sufficient thermometers, air meters conforming to AASHTO T 196 and T 152, and slump cones conforming to AASHTO T 119 for each separate project operation as needed. In the presence of the Inspector, calibrate all air meters a maximum 2 weeks before beginning concrete placement. Recalibrate all air meters, in the presence of the
Inspector, every 2 weeks during concrete placement. Have back-up equipment available to ensure no tests are missed. Provide sufficient 6-inch by 12-inch cylinder molds and tight-fitting domed caps(PTM No. 611) for QC, acceptance, verification, and QA
CAST-IN-PLACE CONCRETE Section 03300 - Page 3 samples. Provide sufficient incidental equipment such as wheelbarrows, shovels, and scoops as needed
2. Provide acceptable means to conduct compressive strength testing using a compression machine and capping device conforming to PTM No. 604. Provide a curing tank conforming to PTM No. 611. Provide curing boxes, or other acceptable equipment, conforming to PTM No. 611 and capable of maintaining the temperature immediately adjacent to the field-cured cylinders in the range of 60F to 80F for the first 24 ± 2 hours.
Provide a digital system, accessible by Bluetooth, that records and stores temperature in the curing box at least every hour, within the range of 30F to 120 °F and to an accuracy of 1°F. Collect temperature data for the first 24 hours and provide it to the
Representative. Have the output from the automated temperature measuring device made available in real time to the Representative, upon request. If required, cap cylinders at the testing site under the Representative’s supervision.
3. Test of concrete shall include tests for:
a. Air Content,
b. Slump, and
c. Concrete temperature
d. Compressive Strength.
4. All testing and payments shall be based on PennDOT Pub 408 and Contractor’s approved
CS-704.
PART 2 - PRODUCTS – Per PennDOT Publication 408
2.1 CEMENT CONCRETE SIDEWALK AND DOOR LANDING
A. In accordance with PennDOT Pub 408, Section 704, Table A. Acceptable concrete mixes as follows:
1. Class A Modified Concrete
a. Revise Class A Concrete as follows to create Class A Modified Concrete.
1) Revise cement factor (lbs/cu. Yd) min from 564 to 634.5.
2) Revise Water Cement Ratio from 0.50 to 0.45.
2. Class AAA Concrete
B. Other Materials in accordance with PennDOT Pub 408, Section 676
1. Subbase No. 2A
2. Premolded expansion joint filler
3. Concrete Curing Compound
4. Joint Sealing Material
5. Penetrating Sealer
2.2 PLAIN CEMENT CONCRETE CURB
A. In accordance with PennDOT Pub 408, Section 630.
2.3 DETECTABLE WARNING SURFACE
A. In accordance with PennDOT Pub 408 Section 695.
CAST-IN-PLACE CONCRETE Section 03300 - Page 4
PART 3 - EXECUTION - Per PennDOT Publication 408 and PennDOT Pub 72M
END OF SECTION 03300
SPECIAL CONSTRUCTION Section 13000
SPECIAL CONSTRUCTION Section 130000 - Page 1
SECTION 13000 - SPECIAL CONSTRUCTION
A. Drawings and general provisions of Contract, including General and Supplementary Conditions and other Division-1 Specification Sections, apply to this Section.
1.2 SCOPE
A. This section shall include installing equipment in accordance with the Contract Drawings and
Specifications and the manufacturer's specifications at the locations shown on the contract drawings, or as directed by the Owner/Engineer. This shall include all labor necessary to complete the items of special construction defined herein.
1.3 METHODS OF MEASUREMENT AND PAYMENT
A. This work shall be measured and paid for at the Contract Price for each individual item of Special
Construction, acceptability completed in accordance with these specifications.
1.4 CONSTRUCTION REQUIREMENTS
A. Bollard:
Supply and install bollards in accordance with the contract drawings and documents including excavation, concrete foundation, and full installation.
Bollard to be Schedule 40 steel pipe filled with concrete and domed on top for drainage.
1. Size: 6” Dia. X 48” (High Above Ground)
2. Color: Yellow (Painted or with fitted bollard cover)
3. Anchor Method: Concrete filled Steel Pipe extended minimum 3’-6” below ground, which is placed in the center of a 1’-6” diameter concrete footing that extends from the ground surface to a minimum of 6” below the bottom of the steel pipe, i.e. a minimum of 4’-0” from ground surface to bottom of concrete footing.
4. Material: Schedule 40 steel pipe filled with concrete and concrete footing.
Install per drawing details. Excavation and paint or bollard cover are incidental to this item.
B. Skimmer:
All work necessary to fabricate, supply, and install a skimmer at the proposed locations for the temporary sediment trap(s) as shown in the contract drawings and documents per manufacturer’s specifications and recommendations. Skimmer to be manufactured by Faircloth or be an approved equal. Temporary modifications to the proposed outlet structure may be necessary. Also includes all items of work
SPECIAL CONSTRUCTION Section 13000
Section 130000- Page 2 SPECIAL CONSTRUCTION necessary to install and maintain a working skimmer including the stone landing berm.
C. Compost Amended Soils:
All work necessary supply and install compost amended soils in accordance with as indicated and as shown on the contract drawings. Compost amended soils consists of the contractor spreading 2-3 inches of approved compost into existing soils. Till added compost into existing soil with rotary tiller set to a depth of 6 inches. Add an additional 4 inches of compost to bring the area up to grade. Produce submittals are required. The excavation, spreading, and tilling of the soils are incidental to this item. Account for proposed elevations during preliminary site grading.
Contractor to provide product submittal of compost to Engineer prior to procurement to ensure mixture complies with product specifications. Engineer must be notified 48 hours before critical stages of construction to witness the work.
END OF SECTION 13000
FACILITY SANITARY SEWERS – SITE WORK Section 22131
FACILITY SANITARY SEWERS Section 22131 - Page 1
SECTION 22131 - FACILITY SANITARY SEWERS – SITE WORK
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes waste piping outside of the building.
1.3 SUBMITTALS
A. Product Data for the following:
1. Pipe and fittings.
2. Cleanouts.
3. Expansion joints and deflection fittings.
B. Shop Drawings for the following:
1. Pipe and fittings.
2. Cleanouts.
3. Expansion joints and deflection fittings.
1.4 DELIVERY, STORAGE, AND HANDLING
A. Do not store plastic pipe and fittings in direct sunlight.
B. Protect pipe, pipe fittings, and seals from dirt and damage.
PART 2 - PRODUCTS
2.1 PVC PIPE AND FITTINGS
A. PVC Gravity Sewer Piping:
1. Pipe: ASTM D 3034, SDR 35, PVC Type PSM sewer pipe with bell-and-spigot ends for gasketed joints.
2. Fittings: ASTM D 3034, PVC with bell ends.
3. Gaskets: ASTM F 477, elastomeric seals.
FACILITY SANITARY SEWERS Section 22131 - Page 2
2.2 NONPRESSURE-TYPE TRANSITION COUPLINGS
A. Comply with ASTM C 1173, elastomeric, sleeve-type, reducing or transition coupling, for joining underground nonpressure piping. Include ends of same sizes as piping to be joined and corrosion-resistant-metal tension band and tightening mechanism on each end.
B. Sleeve Materials:
1. For Plastic Pipes: ASTM F 477, elastomeric seal or ASTM D 5926, PVC.
2. For Dissimilar Pipes: ASTM D 5926, PVC or other material compatible with pipe materials being joined.
C. Unshielded, Flexible Couplings:
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
2. Basis-of-Design Product: Subject to compliance with requirements, provide product indicated on Drawings or comparable product by one of the following:
a. Dallas Specialty & Mfg. Co.
b. Fernco Inc.
c. Logan Clay Pipe.
d. Mission Rubber Company; a division of MCP Industries, Inc.
e. NDS.
f. Plastic Oddities; a division of Diverse Corporate Technologies, Inc.
g. Approved equal.
3. Description: Elastomeric sleeve with stainless-steel shear ring and corrosion-resistant-metal tension band and tightening mechanism on each end.
D. Shielded, Flexible Couplings:
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
2. Basis-of-Design Product: Subject to compliance with requirements, provide product indicated on Drawings or comparable product by one of the following:
a. Cascade Waterworks Mfg.
b. Dallas Specialty & Mfg. Co.
c. Mission Rubber Company; a division of MCP Industries, Inc.
d. Approved equal.
3. Description: ASTM C 1460, elastomeric or rubber sleeve with full-length, corrosion-resistant outer shield and corrosion-resistant-metal tension band and tightening mechanism on each end.
E. Ring-Type, Flexible Couplings:
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
2. Basis-of-Design Product: Subject to compliance with requirements, provide product indicated on Drawings or comparable product by one of the following:
FACILITY SANITARY SEWERS Section 22131 - Page 3
a. Fernco Inc.
b. Logan Clay Pipe.
c. Mission Rubber Company; a division of MCP Industries, Inc.
d. Approved equal.
3. Description: Elastomeric compression seal with dimensions to fit inside bell of larger pipe and for spigot of smaller pipe to fit inside ring.
F. Nonpressure-Type, Rigid Couplings:
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
2. Basis-of-Design Product: Subject to compliance with requirements, provide product indicated on Drawings or comparable product by one of the following:
a. ANACO-Husky.
b. Approved equal.
3. Description: ASTM C 1461, sleeve-type, reducing- or transition-type mechanical coupling, molded from ASTM C 1440, TPE material; with corrosion-resistant-metal tension band and tightening mechanism on each end.
2.3 CLEANOUTS
A. PVC Cleanouts:
1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:
2. Basis-of-Design Product: Subject to compliance with requirements, provide product indicated on Drawings or comparable product by one of the following:
a. Canplas LLC.
b. IPS Corporation.
c. NDS.
d. Plastic Oddities; a division of Diverse Corporate Technologies, Inc.
e. Sioux Chief Manufacturing Company, Inc.
f. Zurn Light Commercial Products Operation; Zurn Plumbing Products Group.
g. Approved equal.
3. Description: PVC body with PVC threaded plug. Include PVC sewer pipe fitting and riser to cleanout of same material as sewer piping.
2.4 CONCRETE
A. General: Cast-in-place concrete complying with ACI 318, ACI 350/350R and the following:
1. Cement: ASTM C 150, Type II.
2. Fine Aggregate: ASTM C 33, sand.
3. Coarse Aggregate: ASTM C 33, crushed gravel.
FACILITY SANITARY SEWERS Section 22131 - Page 4
4. Water: Potable.
B. Portland Cement Design Mix: 4000 psi minimum, with 0.45 maximum water/cementitious materials ratio.
1. Reinforcing Fabric: ASTM A 185/A 185M, steel, welded wire fabric, plain.
2. Reinforcing Bars: ASTM A 615/A 615M, Grade 60 (420 MPa) deformed steel.
C. Manhole Channels and Benches: Factory or field formed from concrete. Portland cement design mix, 4000 psi minimum, with 0.45 maximum water/cementitious materials ratio.
Include channels and benches in manholes.
1. Channels: Concrete invert, formed to same width as connected piping, with height of vertical sides to three-fourths of pipe diameter. Form curved channels with smooth, uniform radius and slope.
2. Benches: Concrete, sloped to drain into channel.
a. Slope: 4 percent.
D. Ballast and Pipe Supports: Portland cement design mix, 3000 psi minimum, with 0.58 maximum water/cementitious materials ratio.
1. Reinforcing Fabric: ASTM A 185/A 185M, steel, welded wire fabric, plain.
2. Reinforcing Bars: ASTM A 615/A 615M, Grade 60 (420 MPa) deformed steel.
PART 3 - EXECUTION
3.1 EARTHWORK
A. Excavating, trenching, and backfilling are specified in Division 31 Section "Earth Moving."
Perform excavation and backfill work conforming to the requirements of Section 306
Trenching, Excavation and Backfill, of the International Plumbing Code.
3.2 PIPING INSTALLATION
A. General Locations and Arrangements: Drawing plans and details indicate general location and arrangement of underground sanitary sewer piping. Location and arrangement of piping layout take into account design considerations. Install piping as indicated, to extent practical. Where specific installation is not indicated, follow piping manufacturer's written instructions.
B. Install piping beginning at low point, true to grades and alignment indicated with unbroken continuity of invert. Place bell ends of piping facing upstream. Install gaskets, seals, sleeves, and couplings according to manufacturer's written instructions for using lubricants, cements, and other installation requirements.
C. Install proper size increasers, reducers, and couplings where different sizes or materials of pipes and fittings are connected. Reducing size of piping in direction of flow is prohibited.
FACILITY SANITARY SEWERS Section 22131 - Page 5
D. When installing pipe under streets or other obstructions that cannot be disturbed, use pipe-jacking process of microtunneling.
E. Install gravity-flow, nonpressure, drainage piping according to the following:
1. Install piping pitched down in direction of flow, at minimum slope of 0.40 percent unless otherwise indicated.
2. Install piping with 48-inch minimum cover.
3. Install PVC gravity sewer piping according to ASTM D 2321 and ASTM F 1668.
F. Clear interior of piping and manholes of dirt and superfluous material as work progresses.
Maintain swab or drag in piping and pull past each joint as it is completed. Place plug in end of incomplete piping at end of day and when work stops.
3.3 PIPE JOINT CONSTRUCTION
A. Join gravity-flow, nonpressure, drainage piping according to the following:
1. Join PVC gravity sewer piping according to ASTM D 2321 and ASTM D 3034 for elastomeric-seal joints or ASTM D 3034 for elastomeric-gasket joints.
2. Join dissimilar pipe materials with nonpressure-type, flexible or rigid couplings.
B. Pipe couplings, expansion joints, and deflection fittings with pressure ratings at least equal to piping rating may be used in applications below unless otherwise indicated.
1. Use nonpressure flexible couplings where required to join gravity-flow, nonpressure sewer piping unless otherwise indicated.
2. Use pressure pipe couplings for force-main joints.
3.4 CONCRETE PLACEMENT
A. Place cast-in-place concrete according to ACI 318.
3.5 CLEANOUT INSTALLATION
A. Install cleanouts and riser extensions from sewer pipes to cleanouts at grade. Install piping so cleanouts open in direction of flow in sewer pipe.
1. Use Light-Duty, top-loading classification cleanouts in earth or unpaved foot-traffic areas.
2. Use Medium-Duty, top-loading classification cleanouts in paved foot-traffic areas.
3. Use Heavy-Duty, top-loading classification cleanouts in vehicle-traffic service areas.
4. Use Extra-Heavy-Duty, top-loading classification cleanouts in roads.
B. Set cleanout frames and covers in earth in cast-in-place-concrete block, 18 by 18 by 12 inches deep. Set with tops 1 inch above surrounding grade.
C. Set cleanout frames and covers in concrete pavement and roads with tops flush with pavement surface.
FACILITY SANITARY SEWERS Section 22131 - Page 6
3.6 CONNECTIONS
A. Make connections to existing piping and underground manholes.
1. Use commercially manufactured wye fittings for piping branch connections. Remove section of existing pipe, install wye fitting into existing piping, and encase entire wye fitting plus 6-inch overlap with not less than 6 inches of concrete with 28-day compressive strength of 3000 psi.
2. Make branch connections from side into existing piping, NPS 4 to NPS 20. Remove section of existing pipe, install wye fitting into existing piping, and encase entire wye with not less than 6 inches of concrete with 28-day compressive strength of 3000 psi.
3. Make branch connections from side into existing piping, NPS 21 or larger, or to underground manholes by cutting opening into existing unit large enough to allow 3 inches of concrete to be packed around entering connection. Cut end of connection pipe passing through pipe or structure wall to conform to shape of and be flush with inside wall unless otherwise indicated. On outside of pipe or manhole wall, encase entering connection in 6 inches of concrete for minimum length of 12 inches to provide additional support of collar from connection to undisturbed ground.
a. Use concrete that will attain a minimum 28-day compressive strength of 3000 psi unless otherwise indicated.
b. Use epoxy-bonding compound as interface between new and existing concrete and piping materials.
4. Protect existing piping and manholes to prevent concrete or debris from entering while making tap connections. Remove debris or other extraneous material that may accumulate.
3.7 IDENTIFICATION
A. Materials and their installation are specified in Division 31 Section "Earth Moving." Arrange for installation of green warning tapes directly over piping and at outside edges of underground manholes.
1. Use detectable warning tape over ferrous piping.
2. Use detectable warning tape over nonferrous piping and over edges of underground manholes.
3.8 CLEANING
A. Clean dirt and superfluous material from interior of piping.
END OF SECTION 22131
EARTHWORK Section 31000
EARTHWORK Section 31000 - Page 1
SECTION 31000 - EARTHWORK
A. Drawings and general provisions of Contract, including General and Supplementary Conditions and
Division 1 Specification Sections, apply to this Section.
B. Related sections include the following:
1. PennDOT Publication 408 in its latest revision, Section 204 Class 2, Class 3 and Class 4 Exca-vation and Section 203 Class 1, Class 1A, Class 1B and Class 1C Excavation. Use PennDOT
Publication 408 for any discrepancies between specifications provided in this document and the
PennDOT Highway Construction Specifications.
A. This Section includes all items of work necessary to complete excavation and grading of the entire site to finished grades. This item includes excavation required for pavement, subbase, curbs, side-walk, drainage structures and pipe, utilities, rain gardens, basins, channels, swales, spillways, BMP’s and all other site work. Stripping of topsoil, stockpiling topsoil and other fill materials, storage of ex-cavated materials, respreading of topsoil and/or other fill material is included. This work includes over-excavation for planting soil media installation. Excavation shall include removal, grading and placement of material to meet proposed grades as shown on the plans. Contractor to determine over-all cut/fill quantities and confirm if project requires importing or exporting of material. Work in-cludes suitable borrow material if necessary. Material slips for materials brought onto site shall be submitted to Engineer for review and approval. Waste material removal/stockpile locations to an approved site to be determined by Contractor and coordinated with Engineer. All grades, elevations, slopes, and surfaces are the responsibility of the contractor. Excavation includes placement and re-moval of temporary fill material as indicated on the plans.
1.3 DEFINITIONS
A. Excavation consists of removal of material encountered to subgrade elevations indicated and subse-quent disposal of materials to be removed.
1. Mass excavation including removal of unsuitable materials offsite and placement of accepta-ble fill materials over the remainder of site.
B. Unauthorized excavation consists of removal of materials beyond indicated subgrade elevations or dimensions without specific direction of Engineer. Unauthorized excavation, as well as remedial work directed by Engineer, shall be at Contractor's expense.
1. Backfill and compact unauthorized excavations as specified for authorized excavations of same classification, unless otherwise directed by Engineer.
C. Additional Excavation: When excavation has reached required subgrade elevations, notify Engineer, who will make an inspection of conditions. If Engineer determines that bearing materials at required subgrade elevations are unsuitable, continue excavation until suitable bearing materials are encoun-tered and replace excavated material as directed by Engineer. The contract sum may be adjusted by an appropriate contract modification.
1. Removal of unsuitable material and its replacement as directed will be paid on basis of unit
EARTHWORK Section 31000 - Page 2 prices relative to changes in work.
D. Subgrade: The undisturbed earth or the compacted soil layer immediately below granular subbase, drainage fill, compost amended soil, planting soil media or topsoil materials.
E. Structure: Culverts, Buildings, foundations, slabs, tanks, culverts, curbs, or other man-made station-ary features occurring above or below ground surface.
1.4 SUBMITTALS
A. Test Reports: Submit the following reports directly to Engineer from the testing services, with copy to Contractor:
1. Test reports on borrow material.
2. Verification of suitability of each footing subgrade material, in accordance with specified re-quirements.
3. Field reports; in-place soil density tests.
4. Report of actual unconfined compressive strength and/or results of bearing tests of each strata tested.
1.5 QUALITY ASSURANCE
A. Codes and Standards: Perform excavation work in compliance with applicable requirements of au-thorities having jurisdiction.
B. Testing and Inspection Service: Contractor shall employ and pay for a qualified independent ge-otechnical testing laboratory to perform soil testing and inspection service during earthwork opera-tions.
1.6 PROJECT CONDITIONS
A. Existing Utilities: Locate existing underground utilities in areas of excavation work. If utilities are indicated to remain in place, provide adequate means of support and protection during earthwork op-erations.
1. Should uncharted, or incorrectly charted, piping or other utilities be encountered during exca-vation, consult utility owner immediately for directions. Cooperate with Owner and utility companies in keeping respective services and facilities in operation. Repair damaged utilities to satisfaction of utility owner.
2. Do not interrupt existing utilities serving facilities occupied by Owner or others, during occu-pied hours, except when permitted in writing by Engineer and then only after acceptable tem-porary utility services have been provided.
a. Provide minimum of 48-hour notice to Engineer and receive written notice from affect-ed utility to proceed before interrupting any utility.
3. Demolish and completely remove from site existing underground utilities indicated to be re-moved. Coordinate with utility companies for shutoff of services if lines are active.
B. Use of Explosives: Use of explosives is not permitted.
C. Protection of Persons and Property: Barricade open excavations occurring as part of this work and post with warning lights.
1. Operate warning lights as recommended by authorities having jurisdiction.
EARTHWORK Section 31000 - Page 3
2. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earthwork operations.
3. Perform excavation by hand within dripline of large trees to remain. Protect root systems from damage or dryout to the greatest extent possible. Maintain moist condition for root sys-tem and cover exposed roots with moistened burlap.
PART 2 - PRODUCTS
2.1 SOIL MATERIALS
A. Satisfactory soil materials are defined as those complying with ASTM D2487 soil classification groups GW, GP, GM, SM, SW, and SP. GEOSCIENCE REVIEW
B. Unsatisfactory soil materials are defined as those complying with ASTM D2487 soil classification groups GC, SC, ML, MH, CL, CH, OL, OH, and PT.
C. Subbase Material: PennDOT No. 2A Coarse Aggregate.
D. Drainage Fill: Washed, evenly graded mixture of crushed stone, or crushed or uncrushed gravel, with
100 percent passing a 1-1/2 inch sieve and not more than 5 percent passing a No. 4 sieve.
E. Backfill and Fill Materials: As specified in subsurface investigation and foundation report.
F. RipRap: PennDOT Publication 408, Section 850.
3.1 EXCAVATION
A. Excavation is unclassified and includes excavation to elevations indicated or subgrade elevations re-quired, regardless of character of materials and obstructions encountered.
3.2 STABILITY OF EXCAVATIONS
A. General: Comply with local codes, ordinances, and requirements of agencies having jurisdiction.
B. Slope sides of excavations to comply with local codes, ordinances, and requirements of agencies having jurisdiction. Shore and brace where sloping is not possible because of space restrictions or stability of material excavated. Maintain sides and slopes of excavations in safe condition until completion of backfilling.
C. Shoring and Bracing: Provide materials for shoring and bracing, such as sheet piling, uprights, stringers, and cross braces, in good serviceable condition. Maintain shoring and bracing in excava-tions regardless of time period excavations will be open. Extend shoring and bracing as excavation progresses.
D. The contractor is responsible for the stability and safety of all excavated areas.
3.3 DEWATERING
A. Prevent surface water and subsurface or ground water from flowing into excavations and from…