This is a comprehensive electrical specification document for the Schuylkill County Emergency Training Facility construction project in Pennsylvania. The specifications outline basic electrical requirements, mechanical equipment electrical connections, concrete work for utilities, underground enclosures, common electrical construction requirements, wiring and cable standards, grounding systems, supporting devices, and raceway systems for Contract No. 4—Electrical Construction. The project involves sealed bids received online via the PennBid Program with a deadline of Wednesday, October 21, 2026, at 9:00 AM, with anticipated award on Wednesday, October 28, 2026. The electrical scope includes submittal of shop drawings for light fixtures, switchgear, wire devices, occupancy sensors, coordination drawings, panelboards, disconnects, lighting fixtures, fire alarm equipment, data equipment, and emergency systems. Contractors must conduct independent inspections and commissioning, coordinate with other trades to eliminate conflicts, provide all required permits and inspection fees, and verify existing conditions before proceeding with work. The project requires compliance with the National Electrical Code (NEC), NEMA standards, UL standards, and local electrical codes, with all materials to be new and of domestic manufacture unless otherwise specified.

Bid security in the amount of 10 percent of the total bid must accompany each submission, and the successful bidder will be required to furnish performance and payment bonds each in the amount of 100 percent of the contract price with a corporate surety approved by the owner. Davis-Bacon wage rates apply to this contract. The specifications mandate copper conductors rated at 600V for all wires and cables, prohibit use of aluminum cables, and require Type MC cables only in approved locations such as lighting and receptacle branch circuits and equipment connections. All feeder wiring must run in continuous conduit systems, and low-voltage wiring must be plenum-rated above ceilings or installed within conduit in exposed spaces. The contractor bears responsibility for all electrical work permits, certificates, tests, and inspection fees, including any required electrical licenses, while utility company fees and charges will be paid directly by the owner to the utility companies. Comprehensive testing and quality control procedures are mandated, including insulation resistance testing, continuity testing, phase load balancing within 10 percent, and documentation in operations and maintenance manuals.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BASIC ELECTRICAL REQUIREMENTS 260010 - 1

SECTION 260010 - BASIC ELECTRICAL REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes general administrative and procedural requirements for electrical installations. The following administrative and procedural requirements are included in this Section to expand the requirements specified in Division 1:

1. Submittals.

2. Coordination Drawings.

3. Record documents.

4. Maintenance manuals.

5. Rough-ins.

6. Electrical installations.

7. Cutting and patching.

1.2 SUBMITTALS

A. Follow the procedures specified in Division 1.

B. Submit, in electronic format, as a PDF, electrical related Shop Drawings and Product Data. Provide requested Samples of sufficient quantity, to allow for required distribution to Owner, Owner's Representative, Architect and Engineer.

C. Submittals must be provided with all catalog information clearly identified indicating all options to be provided as part of the product. Any submittal not containing this information will be rejected.

D. Provide the following shop drawings in booklet form:

1. Light fixtures cuts shall be submitted all at one (1) time in a single packet.

2. Electrical switchgear, including, but not limited to panelboards, disconnect switches, manual motor starters, combination motor starters / disconnect switches, and contactors shall be submitted all at one

(1) time in a single packet. All equipment shall be of one manufacturer.

3. Wire devices shall be submitted all at one (1) time in a single packet and be from one (1) manufacturer.

4. Occupancy sensors shall be submitted all at one (1) time in a single packet and be from one (1) manufacturer whether connected to a lighting control system or provided with power packs, unless noted otherwise. Layout drawings may be submitted after the devices are approved.

5. All required layout drawings shall be shown on architectural backgrounds and not the electrical drawings to ensure that the manufacturer locates all devices. It is the contractor's responsibility to acquire the CAD drawings per Division 1 requirements.

1.3 PRODUCT REVIEWS AND SUBSTITUTIONS

A. Refer to Division 1 for substitutions requirements under this contract. Division 1 requirements supersede requirements listed elsewhere.

B. No Manufacturer's products will be reviewed as an equivalent to the specified products unless submitted by a Bidding Contractor for review ten (10) calendar days prior to bid due date. No products will be reviewed after that time. Product review requests must be submitted in accordance with Division 1 and this section. An addendum will be issued to all Bidding Contractors listing any Manufacturers whose products have been added to the Contract Documents as equivalents to the specified products.

BASIC ELECTRICAL REQUIREMENTS 260010 - 2

C. No substitutions will be reviewed by the Engineer after the Bid Due Date unless specifically requested by the Owner or Architect in writing with an associated credit, proposed by the contractor, included with the substitution request.

1.4 SHOP DRAWINGS

A. Refer to the Conditions of the Contract (General and Supplementary) and Division-1 for submittal definitions, requirements, and procedures.

B. Where submittals include multiple items, a bill of material (not including quantity) shall be provided at the front of the shop drawing. The bill of material shall include product identification, manufacturer and model number.

C. Submittal of Shop Drawings, Product Data, and Samples will be reviewed only when submitted by the Prime Contractor. Submittals from sub-Contractors and material suppliers directly to the Architect/Engineer will not be reviewed. No equipment/materials shall be installed until the Shop Drawings have been stamped with "No Exceptions Taken" or "Make Corrections Noted" by the Architect/Engineer.

D. Submit Shop Drawings as listed in each specification section. Following is a list of shop drawings to assist the contractor; however, the contractor shall supply all shop drawings as listed in each individual section whether listed below or not.

1. Coordination Drawings.

2. In Ground Pull Boxes.

3. Secondary Distribution Board.

4. Power and Lighting Panelboards.

5. Disconnect Switches.

6. Individually-Mounted Circuit Breakers.

7. Combination Motor Starter/Disconnect Switches.

8. Fuses.

9. Contactors.

10. Thermal Overload Switches.

11. Wiring Devices and Wall Plates.

12. Flush Floor Outlets / Boxes and/or poke-thrus.

13. Dimmer Switches.

14. All Lighting Fixtures (submit in booklet form and with detail drawings where required).

15. Low Voltage Lighting Control Equipment and associated wiring diagrams and layout drawings.

16. Occupancy Sensors and associated layout drawings.

17. Emergency Generator and Emergency Lighting Equipment.

18. Automatic and Manual Transfer Switches.

19. Fire Alarm Equipment and associated wiring diagrams, and layout drawings.

20. Data Equipment including, but not limited to equipment shop drawings, warranty information, Installer information, testing information and layout drawings.

21. Fire Stopping Material.

22. Access Panels.

E. When preparing submittals and any required final programming, use a room number schedule generated by the architect and/or the owner, which indicates the actual room numbers that will be used when the building is occupied. If the schedule is not available, revise the initial submittal, when a schedule is available, to reflect the proper room numbers.

F. Submittal Plans: Submittal plans MUST be provided with only the system being presented. Plans not submitted that have not been cleaned of extraneous systems (i.e. a low voltage system being installed on the power drawing, showing all the power and other low voltage systems), will be grounds for immediate rejection without review.

BASIC ELECTRICAL REQUIREMENTS 260010 - 3

1.5 COORDINATION SUBMITTALS

A. The Contractor shall coordinate with other trades, and provide building coordination drawings for all major components. Following is a MINIMUM list of components that must be included on the coordination drawings; however, the Contractor must also include all other components and systems of substantial size to ensure proper coordination.

1. Conduit pathways, denoting pathways for larger conduits (3” and larger) as well as bundles of MC cable.

2. Switchgear (panelboards, transformers, large disconnect switches (200A and larger).

3. Generator set (if inside) and associated transfer equipment.

4. Lighting.

1.6 PRODUCT OBSOLESCENCE

A. In all cases, the most current iteration of the specified product shall be submitted. Where the specified product is no longer manufactured, the contractor shall submit an equivalent product with the same or better specifications. Where specific manufacturers are specified, the contractor shall supply from the same manufacturer the recommended replacement; however, under no circumstances shall the replacement product be deficient in any aspect to the specified product.

B. In the submittal for the product, the Contractor shall provide a signed letter clearly indicating the reason for the replacement product, and confirmation that the replacement product meets or exceeds all of the specified product's specifications to the best of the Contractor's knowledge.

C. The replacement product shall be provided at no additional cost to the owner, and shall not constitute any extension to the project schedule.

D. These requirements shall be inclusive to requirements listed elsewhere in the specifications, and shall not void any other requirements.

1.7 INSPECTIONS

A. The Contractor shall provide certificates of approval, in triplicate, for service equipment, building rough wiring, and building finished wiring.

B. Inspection certificates shall be submitted to the Engineer within 30 days after the inspections are made.

Contractor shall use an independent NEC Certified Inspection Agency as the approved agency. Contractor must verify that the Certified Inspection Agency is approved by the local municipality and the Owner to inspect electrical installations in the project locality. All inspection certificates must be received before final payment can be made.

C. Refer to General Conditions for additional information.

1.8 INDEPENDENT COMMISSIONING

A. Independent Commissioning of electrical systems meeting local and state codes, and owner requirements shall be provided as part of this project. The independent commissioning authority may be hired by this Contractor, another project Contractor or the Owner, as indicated in the documents. However, this does not absolve the installing Contractor and manufacturer from ensuring full functionality of the systems, and manufacturer commissioning as outlined in the individual sections.

B. The Contractor shall schedule and coordinate shop drawing submissions, systems installation and systems start-up with the commissioning authority as required to allow the commissioning authority to perform their work.

BASIC ELECTRICAL REQUIREMENTS 260010 - 4

C. Commissioning of the lighting control system shall take place on every project, and shall meet the local currently adopted version of the International Energy Conservation Code. This Contractor shall ensure this takes place, and contract with the applicable party as required.

1.9 MANUFACTURER'S REQUIREMENTS

A. All material shall be new, of the best respective kinds, manufactured by the company or companies mentioned and shall be of domestic manufacture unless specified otherwise.

B. All equipment, material or apparatus of any one system must be the product of one Manufacturer, or system tested products.

C. Manufacturers not listed in the Contract Documents must submit to the Engineer, via a Bidding Contractor, all product information per Division 1 requirements.

1.10 NAMEPLATE DATA

A. Each item of power operated equipment shall be provided with a permanent operational data nameplate on indicating Manufacturer, product name, model number, serial number, capacity, operating and power characteristics, labels of tested compliance, and similar essential data. Nameplates shall be located in an accessible location.

1.11 FAMILIARITY WITH PROPOSED WORK

A. All Contracts are with the understanding that the Contractor, prior to submission of his bid, acquainted himself with the requirements of the Drawings and Specifications, including "Conditions of the Contract," conditions of the site, its terrain, soil conditions, all other requirements of the Contract, and that he obtained all information necessary for completion of the work on or before the date specified for receiving of bids.

B. In all cases where a device or part of the equipment is herein referred to in the singular, such reference shall apply to as many such items as are required to complete the installation.

C. "Existing" information does not necessarily represent "as-built" conditions. The Contractor shall verify all existing conditions. If discrepancies are found the Contractor shall notify the Architect/Engineer for a resolution before proceeding.

1.12 DEFINITIONS

A. The terms "The Contractor" or "This Contractor" mentioned in these Specifications refers to the Electrical Contractor responsible for the work and equipment included in these Specifications.

B. The term Sub-Contractor refers to any reference to, or letting of work contained in these Specifications to any Sub-Contractor or Manufacturer by the Prime Contractor. This does not relieve the Prime Contractor of his responsibility for all work, material and equipment in this Specification.

C. The term "Provide," when used separately, shall mean to "Furnish and Install."

D. The term "Furnish," when used separately, shall mean to obtain and deliver on the job for installation by other trades.

E. The term "Install," when used separately, shall mean to mount in place, connect and make operable.

BASIC ELECTRICAL REQUIREMENTS 260010 - 5

1.13 INTENT OF THE DRAWINGS AND SPECIFICATIONS

A. The Drawings which accompany the Specifications are for the purposes of illustrating the character and extent of the work, and are subject to such modifications by Architect/Engineer as may be found either necessary or advisable before ordering the prosecution of the work. The Contractor shall conform to and abide by whatever Supplementary Drawings and explanations which may be furnished by the Architect/Engineer for the purpose of illustrating the work. The Architect/Engineer shall decide as to the meaning or intention of any portion of the Specifications and Drawings.

B. Where the work is shown in complete detail on only half or a portion of a Drawing, or there is an indication of continuation, the remainder being shown in outline, the work drawn out in detail shall be understood to apply to other like portions of the structure. All work that may be called for in the Specifications and not shown on the Drawings, or shown on the Drawings and not called for in the Specifications, shall be executed and furnished by the Contractor as described in both.

C. Should any incidental work or materials be required, but not set forth in the Specifications or Drawings, either directly or indirectly, but which is necessary to fulfill the intent thereof, the Contractor is to understand same to be implied and required, and he shall perform all such work and furnish all such materials as fully as if they were particularly delineated or described, without additional cost to Owner. This shall include all materials, devices, methods peculiar to the machinery, equipment, apparatus, or systems as described herein.

1.14 EQUIPMENT ENCLOSURE RATINGS

A. Electrical equipment installed within the building shall carry a NEMA rating 1 or higher if indicated in the specifications or on the drawings.

B. Electrical equipment installed outside the building, or in environmentally wet locations shall carry a NEMA rating 3R or higher if indicated in the specifications or on the drawings.

C. Electrical equipment installed in harsh environments (i.e. natatoriums, greenhouses, etc.) shall carry a NEMA rating 4X, and be manufactured from stainless steel.

D. Where specifications and drawings conflict (i.e. drawings indicated NEMA 3R, but specifications indicate NEMA 1), the higher rating shall be provided at no additional cost to the project.

1.15 WIRING LAYOUTS

A. Should it become necessary to rearrange any of the circuit or feeder wiring, approval to do so shall first be obtained from the Engineer. The Contractor will be supplied with a spare set of Drawings on which all such approved changes shall be noted. Upon completion of all work under this Contract, these Drawings shall be returned to the Architect/Engineer, who will issue a receipt for same.

1.16 FIELD MEASUREMENTS

A. Before ordering any materials or doing any work, Contractor shall verify all measurements at the building site, and shall be responsible for correctness of same. At no time shall the Contractor scale Drawings for the purpose of installation.

B. No extra compensation will be allowed on account of differences between actual dimensions and those indicated on the Drawings. Any difference which may be found shall be submitted to the Architect/Engineer for consideration before proceeding with the work.

BASIC ELECTRICAL REQUIREMENTS 260010 - 6

1.17 COORDINATION

A. The Contractor shall cooperate with the other Contractors and shall arrange to eliminate conflicts with the equipment and work of the Contractors.

B. The Contractor shall be responsible for coordinating all electrical devices/equipment with the casework before rough-in. Any conflicts with casework and electrical devices/equipment shall be brought to the attention of the Architect/Engineer before rough-in. Any electrical device/equipment installed in conflict with casework shall be removed and reinstalled at the Contractor's expense.

C. The Contractor shall be responsible to coordinate all electrical conduits which are installed for rooftop equipment. Where the equipment can be fed from within the equipment curb, the contractor shall utilize this space. Where the equipment must be fed from the exterior, the contractor shall furnish and install a roof curb designed for conduit penetrations.

1.18 CHASES AND OPENINGS

A. The Contractor shall determine, in advance, the locations and sizes of all chases and openings necessary for the proper installation of his work and have same provided during construction. Any chase or opening not made during construction, due to the Contractor's failure to determine same in advance, shall be done by the Contractor at his own expense. Any unnecessary cutting shall be repaired to match the original conditions of the area disturbed at the Contractor's expense.

1.19 AIR PLENUMS

A. The Contractor shall use a conduit system or approved plenum rated wiring for all wiring located above ceilings.

1.20 RECORD DOCUMENTS

A. Refer to Division 1 for Record Document requirements. The following requirements supplement the requirements of Division 1.

B. Mark Drawings to indicate revisions to conduit size and location both exterior and interior; actual equipment locations, dimensioned from column lines; concealed equipment, dimensioned from column lines; distribution and branch electrical circuitry; fuse and circuit breaker size and arrangements; support and hanger details; work performed via Change Orders; concealed control system devices.

C. Mark Specifications to indicate changes by addendum or Change Orders; actual equipment and materials used.

D. All new underground utilities shall be marked and dimensioned on site plan as-built drawings.

1.21 OPERATION AND MAINTENANCE DATA

A. Refer to Division 1 for Operation and Maintenance Manual requirements.

B. Contractor shall provide Operation and Maintenance data listed in individual section in addition to requirements listed in Division 1.

C. Included with operation and maintenance data, under a separate tab or volume, complied into a single place, shall be manufacturer recommended preventative maintenance measures for each piece of equipment installed as part of this project.

BASIC ELECTRICAL REQUIREMENTS 260010 - 7

1.22 WARRANTIES

A. Division 1 warranties shall be considered minimum warranties. Any warranties listed in the individual sections that are longer than Division 1 warranties shall be honored.

B. Refer to individual sections for warranty requirements beyond those as specified in Division 1.

1.23 TEST AND ADJUST

A. All systems installed under this Contract shall be tested and adjusted to ensure that all equipment and systems meet or exceed the specified requirements.

1.24 PHASE LOAD BALANCE

A. A reasonable balance shall be secured on the phases of all main distribution feeders and bus bars.

B. Following installation and with the system in operation, the Electrical Contractor shall check the balance and rearrange connections so that the ampacity on any of the two single-phase phases of the main bus shall not vary more than 10% of each other.

1.25 PAINTING

A. Refer to the Division 1 for general painting requirements.

B. The Contractor shall be responsible for all touch up painting on this project for electrical work.

C. The Contractor shall be responsible for painting of all conduits that is installed after general painting has been completed. In areas where the General Trades Contractor is not painting, this Contractor shall be responsible for painting conduits and boxes to match adjacent surfaces.

1.26 CLEANING

A. Refer to Division 1 Section, "Project Closeout" or "Final Cleaning" for general requirements for final cleaning.

B. The Contractor shall keep the building free of rubbish and material during the course of construction insofar as the work under this Contract is concerned.

C. Upon completion of the project, the Contractor shall remove all rubbish, surplus equipment and shipping labels and have all areas broom clean. The Contractor shall thoroughly clean all fixtures, and other electrical equipment, leaving same in first-class working condition.

1.27 INSTRUCTION OF OWNER'S PERSONNEL

A. The Contractor shall provide instruction of the owner's personnel as outlined in Division 1. The following requirements shall be included in addition to Division 1 requirements.

B. The Contractor shall provide the services of competent personnel and/or Manufacturer trained personnel to instruct employees designated by the Owner in the proper operation, care and maintenance of the equipment and system installed under the Contract.

C. A letter of certification itemizing the equipment, system, instructor, and bearing signatures of the employees instructed shall be delivered to the Engineer and the Owner upon completion of the project. The letter of certification shall note the number of hours spent in explanation and actual operation of system with maintenance personnel. If the Contractor cannot turn over this letter of certification with employee signatures, BASIC ELECTRICAL REQUIREMENTS 260010 - 8 the Contractor shall be prepared to provide additional owner training, meeting the specification requirements, at no additional cost to the owner.

1. The Contractor shall keep notes of all of the training sessions, list discussion topics, questions and answers. The contractor shall provide these typed meeting minutes of the training sessions to all of the attendees and owner's representative. A final copy of these minutes shall also be provided with the O and M manuals for the applicable product.

D. The Contractor shall be responsible to video record each trained presentation session with the owner and the manufacturer and turn over the recordings to owner after completion of training session. The recordings may be turned over on DVD or Thumb drive. The Contractor shall obtain a signed receipt for the recordings proving the owner received them. If a copy of the receipt cannot be turned over and validated when requested, the contractor shall be responsible to provide additional training sessions as requested. A generic training video shall be acceptable in lieu of recording the owner's training session; however, this does not absolve the contractor of providing a private training session with the owner.

1.28 DELIVERY AND STORAGE OF MATERIALS

A. Refer to the Division 1 for delivery and storage of materials requirements.

B. The Contractor shall provide for, or secure use of, suitable-dry storage space for the safe delivery and storage of his materials. The Contractor shall be responsible for providing their own storage trailers on site. The use of Owner's inside-building storage will not be permitted, unless specifically noted otherwise.

1.29 PROTECTION OF EQUIPMENT AND MATERIALS

A. Responsibility for care and protection of electrical work rests with the Contractor until it has been tested and accepted by the Owner. After delivery, before and after installation, protect equipment and materials against theft, injury, or damage in all cases.

B. Protect equipment outlets, and pipe openings with temporary plugs, caps, or burlap. Electrical conduit openings shall be covered with capped bushing or fiber disks and bushings.

C. The contractor shall be responsible to protect all existing electrical or communications equipment to remain from construction dirt and debris, whether created from this contractor or another contractor. The contractor shall determine the method needed to protect each piece of equipment to remain. Should existing equipment be damaged during demolition it will be the responsibility of the contractor to provide necessary repairs or replacement of the damaged equipment.

1.30 SCAFFOLDING AND HOISTING

A. The Contractor shall provide all lumber and other material required for the erection of all staging, scaffolding, shoring, protective platforms, railings and ladders. Scaffolding shall be removed at the completion of the work.

B. The Contractor shall protect any flooring that is to remain. The Contractor shall inspect the flooring before the scaffolding is installed and report any damage that exists before the start of construction. The Contractor shall be responsible to repair any damage to the flooring after the scaffolding is removed to the acceptance of the owner at no additional cost to the owner.

1.31 PERMITS AND FEES

A. Refer to the Division 1 for Permits and Fee requirements.

BASIC ELECTRICAL REQUIREMENTS 260010 - 9

B. Unless noted otherwise, all electrical work permits, certificates, tests, and inspection fees required for the electrical work provided under this contract shall be paid by the Contractor, including any electrical licenses required to work on the project.

1.32 UTILITY COMPANY FEES OR CHARGES

A. Unless noted otherwise, all utility company (Electric) fees or charges will be paid by the Owner directly to the utility companies.

PART 2 - PRODUCTS

Not Applicable.

PART 3 - EXECUTION

3.1 ROUGH-IN

A. Verify final locations for rough-ins with field measurements and with the requirements of the actual equipment to be connected.

B. Refer to equipment Specifications in Divisions-2 through -25 for rough-in requirements.

3.2 EXTERIOR AND INTERIOR EXCAVATION

A. Prior to any digging outside and inside the building, the Contractor shall review all available existing documentation and review the excavation path with the owner’s representative to help determine the location of existing utilities and structures. Following review of this documentation, the Contractor shall provide Ground Penetrating Radar (GPR) to ensure there are no utilities in the area of excavation. Should any utilities be found, the contractor shall provide information to the engineer, architect and owner and propose alternate locations for the excavation. If the contractor neglects to perform the research and GPR prior to excavation and destroys any underground utilities, it shall be the responsibility of the contractor to repair the utilities to the engineer, architect and owner's satisfaction without any additional cost to the owner.

3.3 CUTTING AND PATCHING

A. Perform cutting and patching in accordance with Division 1. In addition to the requirements specified in Division 1, the following requirements apply. The Contractor shall be responsible for providing all cutting and patching required to perform his work unless noted otherwise.

B. Perform cutting, fitting, and patching of electrical equipment and materials required to:

1. Uncover work to provide for installation of ill-timed work.

2. Remove and replace defective work.

3. Remove and replace work not conforming to requirements of the Contract Documents.

4. Remove samples of installed work as specified for testing.

5. Install equipment and materials in existing structures.

6. Upon written instructions from the Architect, uncover and restore work to provide for Architect observation of concealed work.

C. Cut, remove, and legally dispose of selected electrical equipment, components, and materials as indicated, including but not limited to removal of electrical items indicated to be removed and items made obsolete by the new work.

BASIC ELECTRICAL REQUIREMENTS 260010 - 10

D. Protect the structure, furnishings, finishes, and adjacent materials not indicated or scheduled to be removed.

E. Provide and maintain temporary partitions or dust barriers adequate to prevent the spread of dust and dirt to adjacent areas.

3.4 PROTECTION OF INSTALLED WORK

A. During construction activities, including cutting and patching operations, protect adjacent installations.

B. Patch existing finished surfaces and building components using new materials matching existing materials and experienced installers. For installers' qualifications refer to the materials and methods required for the surface and building components being patched.

3.5 ELECTRICAL INSTALLATION

A. Coordinate electrical equipment and material installation with other building components. Verify all dimensions by field measurements. If no dimensions are given, Contractor shall verify with Architect or Engineer before starting work. At no time shall the Contractor scale Drawings for the purpose of locating items.

B. Provide for chases, slots, and openings in other building components to allow for electrical installations.

Coordinate the installation of required supporting devices and sleeves to be set in poured-in-place concrete and other structural components, as they are constructed.

C. Sequence, coordinate, and integrate installations of electrical materials and equipment for efficient flow of the work. Give particular attention to large equipment requiring positioning prior to closing-in the building.

D. Where mounting heights are not detailed or dimensioned, install systems, materials, and equipment to provide the maximum headroom possible, or to meet current local, national and ADA codes.

E. Coordinate connection of electrical systems with exterior underground and overhead utilities and services.

Comply with requirements of governing regulations, franchised service companies, and controlling agencies.

Provide required connection for each service.

F. Install systems, materials, and equipment to conform with submittal data, including Coordination Drawings, to greatest extent possible. Conform to arrangements indicated by the Contract Documents, recognizing that portions of the work are shown only in diagrammatic form. Where coordination requirements conflict with individual system requirements, refer conflict to the Architect/Engineer.

G. Install systems, materials, and equipment level and plumb, parallel and perpendicular to other building systems and components, where installed exposed in finished spaces.

H. Install electrical equipment to facilitate servicing, maintenance, and repair or replacement of equipment components. As much as practical, connect equipment for ease of disconnecting, with minimum of interference with other installations.

1. Contractor shall also take care to leave access to other systems located behind electrical components being installed as part of this project. Should it be found that access has been blocked to other equipment requiring access (i.e. filters, valves, etc.), the offending system will be required to be removed and reinstalled at no additional cost to the owner.

I. Install access panel or doors where units are concealed behind finished surfaces. Access panels and doors are specified in Division 26 “Common Requirements – Electrical.”

J. Install systems, materials, and equipment giving right-of-way priority to systems required to be installed at a specified slope.

BASIC ELECTRICAL REQUIREMENTS 260010 - 11

K. Where exterior conduits, duct banks, equipment and pads are installed by this contractor, the contractor shall follow all NEC requirements, as well as those requirements listed on the drawings and in the specifications.

Where excavation, both interior and exterior, is indicated to be performed by this contractor, backfill shall also be performed, meeting all requirements of the applicable drawing notes and specifications. Backfill shall include clean earth and/or stone, as specified in the applicable specifications, placed and tamped as indicated in the specifications. Provide all testing as outlined in the applicable specifications.

L. Electrical component installation in spaces where abuse may occur (i.e. gymnasiums, locker areas, exterior areas) shall be provided with vandal covers. Covers shall be provided with a means to be locked. System components include, but are not limited to light switches/dimmers, occupancy sensors, sound system controls, fire alarm devices, clocks, wireless access points, etc.

3.6 LOW VOLTAGE WIRING INSTALLATION

A. All low voltage wiring, installed above ceilings, must be plenum rated, unless noted otherwise. Wiring shall be installed perpendicular to steel, located in j-hooks and/or cable tray as available and allowed. Refer to individual specification and drawings for allowance if cable installation in cable trays.

B. All low voltage wiring, installed in spaces without ceilings, must be installed within conduit or other approved raceway. This requirement shall apply to finished spaces (i.e. gymnasium, etc.) and unfinished spaces (i.e.

mechanical rooms, electrical rooms, etc.) Under no circumstances is exposed wiring acceptable.

C. The contractor shall be responsible to provide surge protection for all low voltage systems where copper lines leave and/or enter a building. System shall include, but not be limited to, voice, fire alarm, CCTV, television and security. All surge protection for low voltage systems shall be solid state, unless otherwise noted.

3.7 ELECTRICAL REQUIREMENTS FOR EQUIPMENT INSTALLATION

A. Conduit and power wiring of required size and voltage, from a panelboard or similar source, shall be furnished and installed by this Contractor, to the equipment furnished by another Contractor. A junction box or means of disconnect (as required) shall be furnished and installed at the equipment by this Contractor meeting the National Electric Code.

B. Unless noted otherwise, a full complement of electrical control components, required for the intended use and/or operation of specified equipment, including variable frequency controllers, speed controllers and/or other control devices required, whether integral or remote, shall be furnished by the Contractor furnishing the equipment. These control devices as well as power wiring (where required) through these devices shall be installed by this Contractor.

3.8 CONTROL WIRING FOR EQUIPMENT INSTALLED BY ANOTHER CONTRACTOR

A. This Contractor shall be responsible for providing all required control wiring, (except HVAC system control wiring) for any equipment provided by another Contractor which shall include, but not be limited to, motorized backboards, screens, partitions, curtains, motor operated doors, etc, unless noted otherwise.

B. The Contractor shall provide all boxes and conduit required for any equipment provided by another Contractor.

Control wiring shall also include any wiring of motion or occupancy sensors for doors, curtains, etc.

C. Coordinate all required work for a complete and functional system with the Contractor supplying the equipment. Make all required connections.

D. Prior to installing any control wiring to any equipment, acquire control wiring diagrams and direction from the installing contractor.

BASIC ELECTRICAL REQUIREMENTS 260010 - 12

3.9 TEMPORARY ELECTRIC/TELEPHONE

A. Refer to Division 1 "General Conditions."

B. Temporary Electric for Building Construction: Refer to Temporary Facilities for requirements.

C. Temporary Electric for Construction Trailers: Refer to Temporary Facilities for requirements.

D. Temporary Telephone for Construction Trailers: Refer to Temporary Facilities for requirements.

E. Lighting: Provide temporary lighting in accordance with OSHA, (5-footcandles) with local switching to fulfill security requirements and provide illumination for construction operations and traffic conditions.

1. Lamps and Light Fixtures: Provide general service lamps. Provide guard cages or tempered glass enclosures, where exposed to breakage. Provide exterior fixtures where exposed to moisture.

3.10 UTILITY COMPANY CONTACTS

A. Contact the following utility representative for coordination of this project:

1. Electric: Mr. Jason Wolfe Jason.wolfe@execupower.com , Phone: 484- 438-6598, if Jason Wolfe cannot be reached contact Mr. Russell Dehaut at Russell.dehaut@execuppwer.com

B. The Contractor shall contact all utilities as soon as he receives a contract and is provided with the Notice to Proceed in order to ensure that utility coordination does not hold up the project at any time.

Any project extension due to lack of early utility coordination will be this Contractor’s responsibility and may result in Liquidated Damages be applied per contract milestones.

3.11 UTILITY COMPANY PROJECT NUMBERS

A. The Power Company project number for this job is: 13840636

3.12 ELECTRICAL ROOM LAYOUTS

A. The contractor shall be responsible for submitting electrical room layouts to the engineer prior to any panel or equipment rough ins. Layouts shall show that all equipment will be installed to meet the N.E.C. Code clearance requirements. The Contractor shall bare all costs associated with any changes required if electrical rough-ins are done prior to layout approval.

B. It shall be the contractor's responsibility to verify all N.E.C. clearance requirements prior to installation, including, but not limited to ductwork, piping, or other equipment above electrical equipment, as well as all horizontal requirements.

END OF SECTION 260010

mailto:Jason.wolfe@execupower.com mailto:Russell.dehaut@execuppwer.com

ELECTRICAL REQUIREMENTS FOR MECHANICAL EQUIPMENT 260030 - 1

SECTION 260030 – ELECTRICAL REQUIREMENTS FOR MECHANICAL EQUIPMENT

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Electrical connections to equipment specified under other Divisions or furnished by Owner.

1.2 REFERENCES

A. NEMA WD 1 - General Purpose Wiring Devices

B. NEMA WD 6 - Wiring Device Configurations.

C. ANSI/NFPA 70 - National Electric Code.

1.3 COORDINATION

A. Obtain and review shop drawings, product data, and manufacturer's instructions for equipment furnished under other Divisions.

1. Should there be a difference between the design and the installed equipment; change orders shall only be paid for the difference in the rough-ins. If the Division 26 Contractor installs any rough-ins prior to requesting and receiving shop drawings for the equipment to be installed, and the equipment is different than designed, the required rework shall be performed at no additional cost to the owner aside from the difference is cost between the design documents and installed equipment.

2. Should there be a need to install rough-ins ahead of equipment review and final shop drawing, the Division 26 Contractor shall submit a Request for Information, outlining the equipment to be fed, and how the schedule is impacted for review by the Engineer, Architect, Owner and Owner’s Representative.

B. Determined connection locations and requirements.

C. Sequence rough-in of electrical connections to coordinate with installation schedule for equipment.

D. Sequence electrical connections to coordinate with start-up schedule for equipment.

PART 2 - PRODUCTS

2.1 CORDS AND CAPS

A. Attachment Plug Configuration: Match receptacle configuration at outlet provided for equipment.

B. Cord Construction: Oil-resistant thermoset insulated Type SO multiconductor flexible cord with identified equipment grounding conductor, suitable for hard usage in damp locations.

C. Cord Size: Same as rating of branch circuit overcurrent protection.

ELECTRICAL REQUIREMENTS FOR MECHANICAL EQUIPMENT 260030 - 2

3.1 PREPARATION

A. Review equipment submittals prior to installation and electrical rough-in. Verify location, size, and type of connections. Coordinate details of equipment connections with supplier and installer.

B. The Contractor shall be responsible to coordinate all electrical which are installed for roof top equipment.

Refer to “Coordination” in Section 260010 for additional requirements.

3.2 EXAMINATION

A. Verify that equipment is ready for electrical connection, wiring, and energization.

3.3 ELECTRICAL CONNECTIONS

A. Electrical connections shall meet equipment manufacturer's instructions.

B. Conduit connections to equipment shall use flexible conduit. Liquidtight flexible conduit with watertight connectors shall be used in damp or wet locations.

C. Wiring connections shall use wire and cable with insulation suitable for temperatures encountered in heat producing equipment.

D. Receptacle outlets shall be used where connection with attachment plug is indicated. Where attachment plug is required, equipment shall have a cord and cap.

E. Suitable strain-relief clamps and fittings shall be used for cord connections at outlet boxes and equipment connection boxes.

F. Disconnect switches, controllers, control stations, and control devices shall be located as indicated and per NEC requirements.

G. Verify proper rotation of three phase equipment.

H. Where applicable, power wiring shall be extended through external disconnect switches, local control switches, remote mounted control panels, etc. and connected to terminals in the equipment.

I. Where applicable, wire and conduit shall be extended between control device (start/stop pushbuttons or lighted handle switch) and combination starter/disconnect switches.

J. Coolers and Freezers: freezer and cooler walls, floors and ceilings shall be cut and sealed around conduit openings.

3.4 MISCELLANEOUS CONNECTIONS

A. Fire alarm, security, data, telephone and other low voltage connections shall be installed as required at equipment.

3.5 CONTRACTOR RESPONSIBILITIES (DIVISION 23 CONTRACT)

A. HVAC Control System Panels & Equipment Controls

1. 120 volt – 1 phase.

ELECTRICAL REQUIREMENTS FOR MECHANICAL EQUIPMENT 260030 - 3

2. Division 23 Contractor shall provide power connection to control panel from nearest 120/208 volt electrical panel. Power for control panels for equipment being fed from the emergency generator, including, but not limited to boilers, heating pumps, selected air handling and terminal equipment, etc., shall be derived from the nearest 120/208 volt normal/emergency panel.

3. In addition to HVAC control system panels, where terminal equipment, including, but not limited to shut-off VAV boxes are provided with 120V connection, Division 23 Contractor shall provide power connection to the unit as described above.

4. Division 26 Contractor shall assist the Division 23 Contractor in locating the appropriate panel, ensure there is a spare 20A/1P breaker to feed the control panels and label breaker accordingly.

5. All wiring associated with the unit shall be by the Division 23 Contractor per manufacturer requirements.

B. Duct-mounted Smoke Detector

1. Division 26 Contractor shall furnish duct mounted smoke detector, including detector base and appropriately sized sampling tube for duct being installed.

2. Division 23 Contractor shall install sampling tube and detector base in duct. Coordinate exact location with Division 26 Contractor.

3. Division 26 Contractor shall install detector in base, wire and program into fire alarm system.

4. Division 26 Contractor shall provide relay, and wiring to associated HVAC unit from fire alarm system so that unit shuts down and supervisory signal is provided upon detection of smoke. Refer to Division 28 “Fire Alarm and Detection System” and drawings for additional requirements.

5. Any other connections and/or equipment required shall be furnished and installed by the Division 23 Contractor.

6. Any other connections and/or equipment required shall be furnished and installed by the Division 23 Contractor.

C. Ductless Air Conditioner (DAC-1)

1. 208 volt – 1 phase.

2. 2-pole toggle switch shall be furnished and installed by the Division 26 Contractor adjacent to unit.

3. Division 26 Contractor shall wire through switch and make one power connection to the line side terminals in the unit.

4. Power wire for DAC unit shall come from the exterior unit. In systems where indoor unit receives separate power feed, provide junction box adjacent to the disconnect at the outdoor unit and run to the indoor unit for connection so that a single breaker controls both units.

5. All other wiring within the unit and between the unit and associated condensing unit shall be by the Division 23 Contractor per manufacturer requirements.

D. Outdoor Rooftop Packaged Air Handling Units (RTU-1,2,3,4)

1. 208 volt – 3 phase.

2. All wiring from the input terminals to the respective devices in the unit shall be factory installed by the equipment manufacturer.

3. Starters with overload protection or variable frequency drive(s) for the fans shall be furnished and installed by equipment manufacturer.

4. Division 26 Contractor shall provide a NEMA 3R fused disconnect switch, installed, where coordinated with the Division 23 Contractor to ensure all access doors remain functional. This fused disconnect switch shall be provided regardless of whether the unit is provided with a unit mounted disconnect.

5. Division 26 Contractor shall make one power connections to the unit terminals.

6. Equipment manufacturer shall provide control power transformer as required to power controls, unit lighting and convenience outlet and other 120V accessories as required.

7. All other wiring in the unit shall be factory installed by the equipment manufacturer.

8. Any other connections and/or equipment required shall be furnished and installed by the Division 23

Contractor.

ELECTRICAL REQUIREMENTS FOR MECHANICAL EQUIPMENT 260030 - 4

E. Outdoor Rooftop Gas Fired Make-Up Air Units (MAU-1A,1B)

1. 208 volt – 1 phase.

2. All wiring from the input terminals to the respective devices in the unit shall be factory installed by the equipment manufacturer.

3. Starters with overload protection or variable frequency drive(s) for the fans shall be furnished and installed by equipment manufacturer.

4. Division 26 Contractor shall provide a NEMA 3R fused disconnect switch, installed, where coordinated with the Division 23 Contractor to ensure all access doors remain functional. This fused disconnect switch shall be provided regardless of whether the unit is provided with a unit mounted disconnect.

5. Division 26 Contractor shall make one power connections to the unit terminals.

6. Any other connections and/or equipment required shall be furnished and installed by the Division 23

Contractor.

F. Condensing Boiler (Gas) (B-1)

1. 120 volt – 1 phase.

2. Thermal overload switch shall be furnished and installed by the Division 26 Contractor adjacent to unit.

3. Division 26 Contractor shall wire through switch and make one power connection to the line side terminals in the unit.

4. Any other connections and/or equipment required shall be furnished and installed by the Division 23

Contractor.

G. Electric Cabinet Unit Heaters (ECH-1)

1. 120 volt – 1 phase.

2. Fused disconnect switch in unit by equipment manufacturer.

3. Division 26 Contractor shall make one power connection to the unit.

Any other connections and/ or equipment required shall be provided by Division 23 Contractor.

H. Electric Unit Heaters (EUH-1)

1. 208 volt – 3 phase.

2. Fused disconnect switch furnished and installed by Division 26 Contractor adjacent to the unit.

3. Division 26 Contractor shall make one power connection to the unit through the switch.

4. Any other connections and/ or equipment required shall be provided by Division 23 Contractor.

I. Air Cooled Condensing Unit (CU-1)

1. 208 volt – 1 phase

2. Division 26 contractor shall furnish and install a NEMA 3R fused disconnect switch at unit and shall extend power wiring thru switch to unit and shall make one connection to terminals in unit.

3. Where CU is associated with an indoor DAC, power wire for AC unit shall come from the exterior unit.

In systems where indoor unit receives separate power feed, provide junction box adjacent to the disconnect at the outdoor unit and run to the indoor unit for connection so that a single breaker controls both units.

4. All other wiring within the unit and between the unit and associated indoor unit shall be by the Division 23 Contractor per manufacturer requirements.

J. Roof Fans (EF-1,2,3,4)

1. 120 volt – 1 phase.

2. Integral disconnect switch provided by the equipment manufacturer.

3. Division 26 Contractor shall install Division 23 Contractor speed control in space being served by fan.

Coordinate location in field for balancing.

4. Division 26 Contractor shall make one power connection through speed control where applicable.

5. Any other connections and/ or equipment required shall be provided by Division 23 Contractor.

ELECTRICAL REQUIREMENTS FOR MECHANICAL EQUIPMENT 260030 - 5

K. Energy Recovery Units (ERU-1)

1. 208 volt – 3 phase.

2. All wiring from the input terminals to the respective devices in the unit shall be factory installed by the equipment manufacturer.

3. Starters with overload protection or variable frequency drive(s) for the fans shall be furnished and installed by equipment manufacturer.

4. Division 26 Contractor shall provide a fused disconnect switch, extend power wiring through the disconnect switch to the control panel and make one power connection to terminals in unit.

5. All other wiring in the unit shall be factory installed by the equipment manufacturer.

6. Any other connections and/or equipment required shall be furnished and installed by the Division 23

Contractor.

L. Fan Powered Variable Air Volume Box with Electric Reheat (FPV-1,2,3)

1. 208 volt - 3 phase.

2. Division 26 Contractor shall provide a disconnect switch adjacent to unit and shall extend power wiring thru disconnect to unit and shall make one connection to terminals in unit.

3. Any other connections and/or equipment required shall be furnished and installed by the Division 23

Contractor.

M. Pumps (P-1)

1. 120 volt – 1 phase.

2. Thermal overload switch shall be furnished and installed by the Division 26 Contractor. Division 26

Contractor shall install switch adjacent to the unit.

3. Division 26 Contractor shall run power wiring thru overload switch and make one power connection.

4. Any other connections and/or equipment required shall be furnished and installed by the Division 23

Contractor.

3.6 CONTRACTOR RESPONSIBILITIES (DIVISION 22 CONTRACT)

A. Water Heater Package Type Oil/Gas (DWH-1)

1. 120 volt – 1 phase.

2. Integral factory wired control panel shall be provided by the manufacturer. Control panel shall include all starters, overload protection, and control transformer.

3. Division 26 Contractor shall furnish and install toggle switch adjacent to unit and extend power wiring through the switch to the control panel and make one power connection.

4. Any other connections and/or equipment required shall be furnished and installed by the Division 22

Contractor.

B. Recirculating Pumps (CP-1)

1. 120 volt – 1 phase.

2. Thermal overload switch or starter/disconnect switch shall be furnished and installed by the Division

26 Contractor adjacent to the unit. Wire thru switch to pump motor.

3. Any other connections and/or equipment required shall be furnished and installed by the Division 22

Contractor.

C. Electric Water Cooler

1. 120 volt – 1 phase.

2. Division 26 Contractor shall refer to Electric…