Addendum No. 4 Summary

This is Addendum No. 4 to the Schuylkill County Emergency Training Facility construction project, a sealed bid opportunity administered by Schuylkill County, Pennsylvania. The project encompasses the construction of an emergency training facility and is divided into four separate prime contracts: General Construction (Contract No. 1), Plumbing Construction (Contract No. 2), HVAC Construction (Contract No. 3), and Electrical Construction (Contract No. 4). Sealed bids are due online via the PennBid Program by Wednesday, October 21, 2026, at 9:00 AM, with bid results to be made available following the Board of Commissioners Board Meeting. The tentative award date is Wednesday, October 28, 2026. Bidding documents are available at no cost through http://PennBid.bonfirehub.com. A pre-bid meeting or site visit information, if applicable, would be detailed in the project documents.

Bid security in the amount of 10 percent of the total bid must accompany each submission in the form of a certified check, bank draft payable to Schuylkill County, or an acceptable bid bond from a satisfactory surety. The successful bidder will be required to furnish Performance and Payment Bonds, each equal to 100 percent of the contract price. Davis-Bacon Wage Rates apply to this contract. The Owner reserves the right to waive informalities, reject any or all items, or reject any or all bids in the best interest of the County. No specific funding source or contract term renewal options are identified in the available documentation.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

400 One Norwegian Plaza

Pottsville, PA 17901 www.benesch.com

P 570-622-4055

Y:\Pennsylvania\03XX-90S\0325-900015.01\Construction_Management\2026.0903_Bid Package - PennBid (2nd Bidding)\Addenda\Addendum 4 - Not yet issued\Addendum No4_20261009.docx

ADDENDUM NO. 4

To: All Perspective Bidders

Date: October 9, 2026

From: Kevin Marmas, P.E. Benesch

Subject: Schuylkill County – Emergency Training Facility

Addendum No. 4 – Project No. 0325-900015.01

Bid Receipt: Bid will be received online via the PennBid Program by the Schuylkill County Controller until

Wednesday, October 21, 2026, at 9:00 AM, (prevailing time).

This Addendum forms a part of the Contract Documents and modifies the Bidding Documents dated September

2026 as follows:

1. Section 230900 – HVAC Control Systems: Refer to section 2.1, “BAS Installer/supplier Qualifications”.

Add the following additional Subsection 4:

E. Subject to compliance requirements, provide a Tridium Niagara 4 control system, with products finished, engineered, and installed by one of the following:

1. Advanced Enviromation, Fleetwood PA.

2. Nexgen Automation, Harrisburg, PA.

3. OAE Systems, Harrisburg, PA.

4. The Trane Company, Harrisburg PA

2. 230700 – HVAC System Insulation: Refer to section 2.3; “Exterior Duct and Plenum Insulation”. Add the following sub-section:

D. In lieu of the Techna-Duc system specified in A, B and C. contractor can use 2” of rigid exterior Fiberglass duct insulation, (R-12), with a weather tight cover. Weather tight cover shall be Venture Clad 1579GCW-WME, or equal. The exterior insulation is in addition to the 1” duct liner specified.

3. 238725 – Packaged Outdoor Energy Recovery Units: Refer to section 2.1 “Manufactures” add the following manufacturer:

1. Valient HVAC, LLC

4. 238725 – Packaged Outdoor Energy Recovery Units: Add the following section:

2.15 Provide Outdoor Air Flow Station to monitor air flow to the BAS.

5. 230905 – Sequence of Operations: Refer to section 3.5 “MAKE UP AIR UNIT (MAU-1)”

Revise paragraph A to read; The unit shall have the following components, supply fan, two stage indirect gas heater, filters, dampers, and control terminal strip. The BAS contractor shall provide modulating supply and return damper actuators, unit controller and remote interface panel. The BAS contractor shall provide all control devices as required to meet the sequence of operations.

400 One Norwegian Plaza

Pottsville, PA 17901 www.benesch.com

P 570-622-4055

Y:\Pennsylvania\03XX-90S\0325-900015.01\Construction_Management\2026.0903_Bid Package - PennBid (2nd Bidding)\Addenda\Addendum 4 - Not yet issued\Addendum No4_20261009.docx

ADDENDUM NO. 4

6. Drawing Changes:

a. Drawing H.1.1, Floor Plan – HVAC; Return duct size from grille G located in Training 202, 204 and 204 shall be 24”x12”.

b. Architectural Detail 5/A.6.1: Automatic sliding door shall be "Besam SL500" Dark Bronze

Anodized finish

c. Architectural Detail 6/A.6.1: 1" Insulating glass.

d. Architectural Detail 5/A.6.1: 1" Insulating glass.

e. Architectural Detail 7/A.6.1: "Besam SL500" Dark Bronze Anodized finish with tempered glass

(1/4")

f. Architectural Detail 8/A.6.1: Elevation #3. Kawneer Trifab 2" x 4-1/2" with 1/4" Tempered Glass.

g. Drawing A.5.2 – Add the Following General Note: “The perimeter of exterior faces of CMU or

Concrete footers shall receive one of the two coatings: Cold-applied, Emulsified Asphalt

Dampproofing where the earth comes in contact with Vertical Foundation; the rest of the area will receive Masonry Paint where the area does not come in touch with the earth. Furnish and install all miscellaneous materials to complete the coating.”

7. Summary of Roofing System:

a. Roofing Membrane: 60 MIL (20-Year Warranty) Membrane.

b. Roof Insulation Flat, screwed with Vapor Barrier. Sloped to Drain.

c. OS on Roof Plan indicates Overflow Scupper

8. 2026 Ryan Township UCC Application Package and Fee Schedule

9. 2026 Ryan Township Zoning Permit Application Package and Fee Schedule

10. Architectural Plan Detail Revisions

11. Pre-Bid Meeting Sign-In Sheet

12. Sample AIA A101-2017 Draft Document

13. Sample AIA A201-2017 Draft Document

14. Sample AIA A701-2018 Draft Document

15. Section 093010 – Ceramic Tile Specification

16. Exhibit of Excess Material Placement Location on Adjacent Fire Academy Property

17. Questions asked on PennBid: Please note, the attached additional (PENNBID Public Q&A) questions and the official responses are officially included as part of the bid documents.

This Addendum is issued to all registered plan holders pursuant to the Instructions to Bidders and Conditions of the Contract. This Addendum serves to clarify, revise, and supersede information in the Project Manual, Drawings, and previously issued Addenda. Portions of the Addendum affecting the Contract Documents will be incorporated into the Contract by enumeration of the Addendum in the Owner/Contractor Agreement.

The Bidder shall acknowledge receipt of this Addendum in the appropriate space on PennBID.

End of Addendum No. 4

2026 Ryan Township UCC Application Package and Fee

Schedule

PERMIT APPLICATION

Non UCC_______ Page ___ of___

Building Permit __________________________ Fire Protection Permit ____________________

Municipality ________________________________ County _____________________________________ Construction Site Location (Full Address) _______________________________________________________ Tax Map Parcel ID#________________________________________________________________________ Owner __________________________________ Application Contact ___________________________ Company Name___________________________ Application Company__________________________ Address _________________________________ Address _________________________________ City _________________ State _____ Zip ______ City _________________ State _____ Zip_______ Phone # __________ Cell # _________________ Phone # ____________ Cell # _________________ Email ___________________________________ Email _______________________________________ Describe Proposed Work in Detail: ______________________________________________________

BUILDING PERMIT

Contractor__________________________________ (If owner put same as above)

Address ___________________________________ City ____________________ State _____Zip ______ Phone # ______________ Cell _________________ Email _____________________________________

HIC # _____________________________________

Federal Employee# __________________________ (Certification of Insurance for Worker Compensation needed or sign exemption form)

State Classification:

New Residential _______ Other Residential _______ New Commercial _______ Other Commercial_______

# Of Stories ________ Height of Structure________ Total SQ FT ________ Use Group ____________Type Const.___________ Description of Work: _________________________

Other: ____________________________________

Estimate Total Costs For All Work: ______________ (Reasonable Fair Market Value)

FIRE PROTECTION PERMIT

Contractor__________________________________

(If owner put same as above) Address ___________________________________ City ____________________ State _____Zip ______ Phone # ______________ Cell _________________ Email _____________________________________

HIC # _____________________________________

Federal Employee# __________________________ (Certification of Insurance for Worker Compensation needed or sign exemption form)

State Classification:

New Residential _______ Other Residential________ New Commercial _______ Other________________ Commercial_______

Sprinkler System: ___________________________ Alarm System: _____________________________

Commercial Cooking Equip.: __________________ Other: ____________________________________

Estimate Total Costs For All Work: ______________ (Reasonable Fair Market Value)

I hereby acknowledge that I have read this application and state the above is correct to comply with all Municipal ordinances and state laws regarding construction.

Print Name: ____________________________ Signature: ____________________________________ Owner ( ) Application Contact ( ) Contractor ( ) Owner Representative ( )

CODE OFFICIAL USE ONLY

UCC Building Fee: __________ Plans Approved Plan Review Fee: ___________ FP Fee: ___________ Plans Approved with Comments Admin Fee: ________________ Code Official: ______________________ State Fee: _________________ Total UCC: _________ State Cert. #: ______________________ Total Cost: ________________ Date: __________________________

PERMIT APPLICATION

Non UCC_______ Page ___ of___

Mechanical Permit ___________ Plumbing Permit ___________ Electrical Permit ____________

Municipality ________________________________ County _____________________________________ Construction Site Location (Full Address) _______________________________________________________ Tax Map Parcel ID#________________________________________________________________________ Owner __________________________________ Application Contact ___________________________ Company Name___________________________ Application Company__________________________ Address _________________________________ Address ____________________________________ City _________________ State _____ Zip ______ City _________________ State _____ Zip_________ Phone # __________ Cell # _________________ Phone # ____________ Cell # __________________ Email ___________________________________ Email _______________________________________ Describe Proposed Work in Detail: ______________________________________________________

MECHANICAL / PLUMBING PERMIT

Contractor___________________________________ (If owner put same as above)

Address ____________________________________ City ____________________ State _____Zip ______ Phone # ______________ Cell #_________________ Email ______________________________________

HIC # ______________________________________

Federal Employee# ___________________________ (Certification of Insurance for Worker Compensation needed or sign exemption form)

State Classification New Residential _______ Other Residential ________ New Commercial _______ Other Commercial_______

Estimate Total Costs For All Work: ________________

Water: Public __________ On-lot __________ Sewer: Public __________ On-lot __________

Technical Site Data No. Size Fixture/Equip. No. Size Fixture/Equip.

_____ Water Closet _____ Boiler Furnace _____ Urinal/Bidet _____ Sewer at/Conn _____ Bathtub _____ Backflow Prev.

_____ Lavatory _____ HVAC _____ Shower _____ Kitchen Hood & _____ Sink Exhaust System _____ Dishwasher _____ Refrig. Units _____ Washing Mach. _____ Heat Pumps _____ Hose Bib _____ Fire Dampers _____ Water Heater _____ WaterConnect.

Others: ___________________________________

ELECTRICAL PERMIT

Contractor__________________________________ (If owner put same as above)

Address ____________________________________ City ____________________ State _____Zip ______ Phone # ______________ Cell#_________________ Email ______________________________________

HIC # ______________________________________

Federal Employee# ___________________________ (Certification of Insurance for Worker Compensation needed or sign exemption form)

State Classification New Residential _______ Other Residential _______ New Commercial _______ Other Commercial_______

Estimate Total Costs For All Work: ________________

Technical Site Data No. Size Fixture/Equip. No. Size Fixture/Equip.

_____ Lighting Fixture _____ Range _____ Receptacles _____ Dishwasher _____ Switches _____ Garbage Disp.

_____ Detectors _____ HVAC _____ Motor-Fraction. _____ Emergency & _____ Comm. Devices Exit Lights _____ Alarm Dev./Sys. _____ Heater _____ Pool Bonding. _____ Central AC Unit _____ Service _____ Signs _____ Sub-Panels _____ Survey Fee.

Others: ___________________________________

I hereby acknowledge that I have read this application and state the above is correct to comply with all Municipal ordinances and state laws regarding construction.

Print Name: ______________________________ Signature: ____________________________________ Owner ( ) Application Contact ( ) Contractor ( ) Owner Representative ( )

CODE OFFICIAL USE ONLY

Mechanical Plumbing Electrical Plans Approved UCC Fee: ________ ________ ________ Plans Approved with Comments Plan Review Fee: ________ ________ ________ Admin Fee: ________ ________ ________ Code Official: ______________________ State Fee: ________ ________ ________ State Cert. #: ______________________ Total Cost: ________ ________ ________ Date: ____________________________ Non-UCC Fee: ________ ________ ________ Revised 01/22

PENNSYLVANIA WORKERS COMPENSATION INSURANCE COVERAGE AFFIDAVIT OF EXEMPTION

Basis for exemption is (please check one):

The Contractor for this building permit is a sole proprietorship without employees

The Contractor is a corporation, and the only employees working on the project have and are qualified as "Executive Employees" under

Section 104 of the Workers' Compensation Act. Please explain: ______________________________________________________

All of the contractor's employees on the project are exemption religious grounds under Section 304.2 of the Workers' Compensation Act.

Please explain: _________________

Owner is the contractor______________________________________________________

Other. Please explain: ______________________________________________________

Please be aware of the following requirements under the Pennsylvania Workers' Compensation Act:

Any subcontractors used on this project will be required to carry their own workers' compensation coverage.

Violation of the Workers' Compensation Act or the terms of this information form will subject the contractor to a stop-work order and other fines and penalties as provided by law.

My signature on behalf of or as the contractor as stated on this form constitutes my verification that the statements contained here are true.

Signature______________________________________________Date_____________________

Name (Please Print)________________________________________________________________

Title_____________________________________________________________________________

Name of Company _________________________________________________________________

Address _________________________________________________________________

Phone _________________________________________________________________

2026 Ryan Township Zoning Permit Application Package and Fee Schedule

ZONING PERMIT APPLICATION

Fee: $ __________

PERMIT # _____ - _____ - Z Paid: ___________

1. Type of Improvement

Erect a Structure Add to a Structure Add a Use Change a Use/Occupancy

2. Present use of structure or property: _____________________________________________

3. Proposed use of structure or property: ____________________________________________

4. Site Location of Property: _______________________________________________________ (Complete Address Required)

5. Lot Size: ____________________ 6. Zoning District: _____________________________

7. Tax Parcel # (located on tax bill above name): ________ - ________ - _________

8. Work Description: _____________________________________________________________

Length: Width: Height:

Stories: Floor Area: Parking Spaces:

Sewage Permit#:

Type of Sewer (Public / Onsite)

Type of Water (Public / Onsite)

Estimated Cost: Located in floodplain (Y/N) Impervious coverage (SF): Building coverage (SF):

Area Being Disturbed:

Contractor: Address: Phone#:

Email:

9. Property Plan – REQUIRED (Use attached sheet or separate sheet)

Attached is a dimensioned plan of the proposed work and parcel indicating north, property lines, streets, easements, rights-of-way(s), existing structures, proposed structures, existing setbacks, proposed setbacks, size of proposed and existing structures.

10. Applicant Information:

Applicant: Address: Phone #:

Email:

Owner: Address: Phone #:

Email:

I, the Undersigned, do hereby certify that the information contained in this application and supporting documents is true and correct and that I may be subject to prosecution under Penalty of 18 Pa.C.S.A. Section 4904 for making knowingly false statements or representations. I hereby attest, the proposed work, as outlined will conform to the standards of all applicable ordinances / regulations. In addition, I have reviewed and agree to all items contained in the Application Supplement provided by the municipality with this Application.

11. Signature: _______________________________________________ Date: _______________

(FOR ZONING OFFICE USE ONLY)

Application is hereby: APPROVED DENIED INCOMPLETE

Remarks:

Approved by: _________________________________________, Zoning Officer Date: ______________

Resolution No. 2004 - ___

RYAN TOWNSHIP

SCHEDULE OF FEES

Zoning Permit Fee

VALUE ZONING PERMIT FEE

Construction Value Under $10,000.00 $25.00 Construction Value Under $15,000.00 $30.00 Construction Value Under $20,000.00 $50.00 Construction Value Under $30,000.00 $70.00 Construction Value Under $40,000.00 $90.00 Construction Value Under $50,000.00 $110.00 Construction Value Under $60,000.00 $130.00 Construction Value Under $70,000.00 $150.00 Construction Value Under $80,000.00 $175.00 Construction Value Under $90,000.00 $190.00 Construction Value Under $100,000.00 $200.00 Construction Value Over $100,000.00

$200.00 Plus $2.00 Per Thousand Dollars, or portion over

$100,000.00

Note: Construction value must be based on a minimum of $50.00 per square foot of gross floor area for principal structures and $15.00 per square foot of gross floor area for accessory structures or a signed contractor’s proposal must be submitted.

Zoning Hearing Board Applications

Variance Application $500.00 Special Exception Application $500.00 Appeal Application $300.00 Validity Challenge $1,000.00

Note: The applicant shall be responsible for all fees, permitted by the Municipalities Code, when expenses of the Zoning Hearing Board exceed that of the original submission fee.

Application Before the Board of Supervisors

Conditional Use $1,000.00 Curative Amendment $1,000.00 Planned Residential Development $1,000.00

Note: The applicant shall be responsible for all fees, permitted by the Municipalities Code, when expenses of the Board of Supervisors exceed that of the original submission fee.

Change or Addition of Use (Based on Zoning Permit Fee above or schedule below, whichever is greater.)

Home Occupation $60.00 Commercial/Industrial $120.00

Certificate of Use and Occupancy

Principal Residential Structure $60.00 Principal Commercial/Industrial Structure $120.00 Accessory Residential Structure & Additions $15.00 Accessory Commercial/Industrial Structure and Additions $90.00

Driveways – per connection to Township Road

Minimum Use (Residential) $50.00 Commercial/Industrial $100.00

Note: A retainer fee or bond, as required by Ordinance, must be posted prior to construction or reconstruction of all driveways.

Peddlers Permits

Monthly $25.00

Office Reproductions – Paid in Advance

Zoning Ordinance & Zoning Map $25.00 (plus postage if mailed) Zoning Map $5.00 (plus postage if mailed) Subdivision and Land Development Ordinance $30.00 (plus postage if mailed) Ordinance Copies (per Page) $0.25

ADOPTED and RESOLVED this _______ day of ________________, 2004 by the Ryan Township Board of Supervisors.

RYAN TOWNSHIP BOARD OF SUPERVISORS

ATTEST: _________________________________________

Architectural Plan Detail Revisions

Pre-Bid Meeting Sign-In Sheet

Sample AIA A101-2017 Draft Document

AIA

Document A101

– 2017

Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 12:46:14 ET on 10/06/2026 under Order No.500075578_1 which expires on 10/06/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents®

Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (1631680081)

ADDITIONS AND DELETIONS: The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed.

This document has important legal consequences.

Consultation with an attorney is encouraged with respect to its completion or modification.

The parties should complete

A101®–2017, Exhibit A, Insurance and Bonds, contemporaneously with this

Agreement. AIA Document

A201®–2017, General

Conditions of the Contract for Construction, is adopted in this document by reference. Do not use with other general conditions unless this document is modified.

ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document.

AGREEMENT made as of the « » day of « » in the year « » (In words, indicate day, month and year.)

BETWEEN the Owner:

(Name, legal status, address and other information) and the Contractor:

for the following Project:

(Name, location and detailed description)

The Architect:

The Owner and Contractor agree as follows.

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 12:46:14 ET on 10/06/2026 under Order No.500075578_1 which expires on 10/06/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents®

TABLE OF ARTICLES

1 THE CONTRACT DOCUMENTS

2 THE WORK OF THIS CONTRACT

3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION

4 CONTRACT SUM

5 PAYMENTS

6 DISPUTE RESOLUTION

7 TERMINATION OR SUSPENSION

8 MISCELLANEOUS PROVISIONS

9 ENUMERATION OF CONTRACT DOCUMENTS

EXHIBIT A INSURANCE AND BONDS

ARTICLE 1 THE CONTRACT DOCUMENTS

The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary, and other Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed in this Agreement, and Modifications issued after execution of this Agreement, all of which form the Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations, or agreements, either written or oral. An enumeration of the Contract Documents, other than a Modification, appears in Article 9.

ARTICLE 2 THE WORK OF THIS CONTRACT

The Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in the Contract Documents to be the responsibility of others.

ARTICLE 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION

§ 3.1 The date of commencement of the Work shall be:

(Check one of the following boxes.)

[ « » ] The date of this Agreement.

[ « » ] A date set forth in a notice to proceed issued by the Owner.

[ « » ] Established as follows:

(Insert a date or a means to determine the date of commencement of the Work.)

If a date of commencement of the Work is not selected, then the date of commencement shall be the date of this Agreement.

§ 3.2 The Contract Time shall be measured from the date of commencement of the Work.

§ 3.3 Substantial Completion § 3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work:

(Check one of the following boxes and complete the necessary information.)

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 12:46:14 ET on 10/06/2026 under Order No.500075578_1 which expires on 10/06/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents®

[ « » ] Not later than « » ( « » ) calendar days from the date of commencement of the Work.

[ « » ] By the following date: « »

§ 3.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial Completion of such portions by the following dates:

Portion of Work Substantial Completion Date

§ 3.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.3, liquidated damages, if any, shall be assessed as set forth in Section 4.5.

ARTICLE 4 CONTRACT SUM

§ 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor’s performance of the Contract. The Contract Sum shall be « » ($ « » ), subject to additions and deductions as provided in the Contract Documents.

§ 4.2 Alternates § 4.2.1 Alternates, if any, included in the Contract Sum:

Item Price

§ 4.2.2 Subject to the conditions noted below, the following alternates may be accepted by the Owner following execution of this Agreement. Upon acceptance, the Owner shall issue a Modification to this Agreement.

(Insert below each alternate and the conditions that must be met for the Owner to accept the alternate.)

Item Price Conditions for Acceptance

§ 4.3 Allowances, if any, included in the Contract Sum:

(Identify each allowance.)

Item Price

§ 4.4 Unit prices, if any:

(Identify the item and state the unit price and quantity limitations, if any, to which the unit price will be applicable.)

Item Units and Limitations Price per Unit ($0.00)

§ 4.5 Liquidated damages, if any:

(Insert terms and conditions for liquidated damages, if any.)

§ 4.6 Other:

(Insert provisions for bonus or other incentives, if any, that might result in a change to the Contract Sum.)

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 12:46:14 ET on 10/06/2026 under Order No.500075578_1 which expires on 10/06/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents®

ARTICLE 5 PAYMENTS

§ 5.1 Progress Payments § 5.1.1 Based upon Applications for Payment submitted to the Architect by the Contractor and Certificates for Payment issued by the Architect, the Owner shall make progress payments on account of the Contract Sum to the Contractor as provided below and elsewhere in the Contract Documents.

§ 5.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month, or as follows:

§ 5.1.3 Provided that an Application for Payment is received by the Architect not later than the « » day of a month, the Owner shall make payment of the amount certified to the Contractor not later than the « » day of the « » month. If an Application for Payment is received by the Architect after the application date fixed above, payment of the amount certified shall be made by the Owner not later than « » ( « » ) days after the Architect receives the Application for Payment.

(Federal, state or local laws may require payment within a certain period of time.)

§ 5.1.4 Each Application for Payment shall be based on the most recent schedule of values submitted by the Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Contract Sum among the various portions of the Work. The schedule of values shall be prepared in such form, and supported by such data to substantiate its accuracy, as the Architect may require. This schedule of values shall be used as a basis for reviewing the Contractor’s Applications for Payment.

§ 5.1.5 Applications for Payment shall show the percentage of completion of each portion of the Work as of the end of the period covered by the Application for Payment.

§ 5.1.6 In accordance with AIA Document A201™–2017, General Conditions of the Contract for Construction, and subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows:

§ 5.1.6.1 The amount of each progress payment shall first include:

.1 That portion of the Contract Sum properly allocable to completed Work;

.2 That portion of the Contract Sum properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the completed construction, or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing; and

.3 That portion of Construction Change Directives that the Architect determines, in the Architect’s professional judgment, to be reasonably justified.

§ 5.1.6.2 The amount of each progress payment shall then be reduced by:

.1 The aggregate of any amounts previously paid by the Owner;

.2 The amount, if any, for Work that remains uncorrected and for which the Architect has previously withheld a Certificate for Payment as provided in Article 9 of AIA Document A201–2017;

.3 Any amount for which the Contractor does not intend to pay a Subcontractor or material supplier, unless the Work has been performed by others the Contractor intends to pay;

.4 For Work performed or defects discovered since the last payment application, any amount for which the Architect may withhold payment, or nullify a Certificate of Payment in whole or in part, as provided in Article 9 of AIA Document A201–2017; and

.5 Retainage withheld pursuant to Section 5.1.7.

§ 5.1.7 Retainage § 5.1.7.1 For each progress payment made prior to Substantial Completion of the Work, the Owner may withhold the following amount, as retainage, from the payment otherwise due:

(Insert a percentage or amount to be withheld as retainage from each Application for Payment. The amount of retainage may be limited by governing law.)

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 12:46:14 ET on 10/06/2026 under Order No.500075578_1 which expires on 10/06/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents®

§ 5.1.7.1.1 The following items are not subject to retainage:

(Insert any items not subject to the withholding of retainage, such as general conditions, insurance, etc.)

§ 5.1.7.2 Reduction or limitation of retainage, if any, shall be as follows:

(If the retainage established in Section 5.1.7.1 is to be modified prior to Substantial Completion of the entire Work, including modifications for Substantial Completion of portions of the Work as provided in Section 3.3.2, insert provisions for such modifications.)

§ 5.1.7.3 Except as set forth in this Section 5.1.7.3, upon Substantial Completion of the Work, the Contractor may submit an Application for Payment that includes the retainage withheld from prior Applications for Payment pursuant to this Section 5.1.7. The Application for Payment submitted at Substantial Completion shall not include retainage as follows:

(Insert any other conditions for release of retainage upon Substantial Completion.)

§ 5.1.8 If final completion of the Work is materially delayed through no fault of the Contractor, the Owner shall pay the Contractor any additional amounts in accordance with Article 9 of AIA Document A201–2017.

§ 5.1.9 Except with the Owner’s prior approval, the Contractor shall not make advance payments to suppliers for materials or equipment which have not been delivered and stored at the site.

§ 5.2 Final Payment § 5.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the Contractor when

.1 the Contractor has fully performed the Contract except for the Contractor’s responsibility to correct Work as provided in Article 12 of AIA Document A201–2017, and to satisfy other requirements, if any, which extend beyond final payment; and

.2 a final Certificate for Payment has been issued by the Architect.

§ 5.2.2 The Owner’s final payment to the Contractor shall be made no later than 30 days after the issuance of the Architect’s final Certificate for Payment, or as follows:

§ 5.3 Interest Payments due and unpaid under the Contract shall bear interest from the date payment is due at the rate stated below, or in the absence thereof, at the legal rate prevailing from time to time at the place where the Project is located.

(Insert rate of interest agreed upon, if any.)

ARTICLE 6 DISPUTE RESOLUTION

§ 6.1 Initial Decision Maker The Architect will serve as the Initial Decision Maker pursuant to Article 15 of AIA Document A201–2017, unless the parties appoint below another individual, not a party to this Agreement, to serve as the Initial Decision Maker.

(If the parties mutually agree, insert the name, address and other contact information of the Initial Decision Maker, if other than the Architect.)

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 12:46:14 ET on 10/06/2026 under Order No.500075578_1 which expires on 10/06/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents®

§ 6.2 Binding Dispute Resolution For any Claim subject to, but not resolved by, mediation pursuant to Article 15 of AIA Document A201–2017, the method of binding dispute resolution shall be as follows:

(Check the appropriate box.)

[ « » ] Arbitration pursuant to Section 15.4 of AIA Document A201–2017

[ « » ] Litigation in a court of competent jurisdiction

[ « » ] Other (Specify)

If the Owner and Contractor do not select a method of binding dispute resolution, or do not subsequently agree in writing to a binding dispute resolution method other than litigation, Claims will be resolved by litigation in a court of competent jurisdiction.

ARTICLE 7 TERMINATION OR SUSPENSION

§ 7.1 The Contract may be terminated by the Owner or the Contractor as provided in Article 14 of AIA Document A201–2017.

§ 7.1.1 If the Contract is terminated for the Owner’s convenience in accordance with Article 14 of AIA Document A201–2017, then the Owner shall pay the Contractor a termination fee as follows:

(Insert the amount of, or method for determining, the fee, if any, payable to the Contractor following a termination for the Owner’s convenience.)

§ 7.2 The Work may be suspended by the Owner as provided in Article 14 of AIA Document A201–2017.

ARTICLE 8 MISCELLANEOUS PROVISIONS

§ 8.1 Where reference is made in this Agreement to a provision of AIA Document A201–2017 or another Contract Document, the reference refers to that provision as amended or supplemented by other provisions of the Contract Documents.

§ 8.2 The Owner’s representative:

(Name, address, email address, and other information)

§ 8.3 The Contractor’s representative:

(Name, address, email address, and other information)

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 12:46:14 ET on 10/06/2026 under Order No.500075578_1 which expires on 10/06/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents®

§ 8.4 Neither the Owner’s nor the Contractor’s representative shall be changed without ten days’ prior notice to the other party.

§ 8.5 Insurance and Bonds § 8.5.1 The Owner and the Contractor shall purchase and maintain insurance as set forth in AIA Document A101™– 2017, Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum, Exhibit A, Insurance and Bonds, and elsewhere in the Contract Documents.

§ 8.5.2 The Contractor shall provide bonds as set forth in AIA Document A101™–2017 Exhibit A, and elsewhere in the Contract Documents.

§ 8.6 Notice in electronic format, pursuant to Article 1 of AIA Document A201–2017, may be given in accordance with a building information modeling exhibit, if completed, or as otherwise set forth below:

(If other than in accordance with a building information modeling exhibit, insert requirements for delivering notice in electronic format such as name, title, and email address of the recipient and whether and how the system will be required to generate a read receipt for the transmission.)

§ 8.7 Other provisions:

ARTICLE 9 ENUMERATION OF CONTRACT DOCUMENTS

§ 9.1 This Agreement is comprised of the following documents:

.1 AIA Document A101™–2017, Standard Form of Agreement Between Owner and Contractor

.2 AIA Document A101™–2017, Exhibit A, Insurance and Bonds

.3 AIA Document A201™–2017, General Conditions of the Contract for Construction

.4 Building information modeling exhibit, dated as indicated below:

(Insert the date of the building information modeling exhibit incorporated into this Agreement.)

.5 Drawings

Number Title Date

.6 Specifications

Section Title Date Pages

.7 Addenda, if any:

Number Date Pages

Portions of Addenda relating to bidding or proposal requirements are not part of the Contract Documents unless the bidding or proposal requirements are also enumerated in this Article 9.

.8 Other Exhibits:

(Check all boxes that apply and include appropriate information identifying the exhibit where required.)

[ « » ] AIA Document E204™–2017, Sustainable Projects Exhibit, dated as indicated below:

(Insert the date of the E204-2017 incorporated into this Agreement.)

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 12:46:14 ET on 10/06/2026 under Order No.500075578_1 which expires on 10/06/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents®

[ « » ] The Sustainability Plan:

Title Date Pages

[ « » ] Supplementary and other Conditions of the Contract:

Document Title Date Pages

.9 Other documents, if any, listed below:

(List here any additional documents that are intended to form part of the Contract Documents. AIA

Document A201™–2017 provides that the advertisement or invitation to bid, Instructions to Bidders, sample forms, the Contractor’s bid or proposal, portions of Addenda relating to bidding or proposal requirements, and other information furnished by the Owner in anticipation of receiving bids or proposals, are not part of the Contract Documents unless enumerated in this Agreement. Any such documents should be listed here only if intended to be part of the Contract Documents.)

This Agreement entered into as of the day and year first written above.

OWNER (Signature) CONTRACTOR (Signature)

(Printed name and title) (Printed name and title)

Sample AIA A201-2017 Draft Document

AIA

Document A201

– 2017

General Conditions of the Contract for Construction

AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 12:46:21 ET on 10/06/2026 under Order No.500075578_2 which expires on 10/06/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents®

User Notes: (1900168568)

ADDITIONS AND DELETIONS: The author of this document has added information needed for its completion. The author may also have revised the text of the original AIA standard form. An Additions and Deletions Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed.

This document has important legal consequences.

Consultation with an attorney is encouraged with respect to its completion or modification.

For guidance in modifying this document to include supplementary conditions, see AIA Document A503™, Guide for Supplementary

Conditions.

ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document.

for the following PROJECT:

(Name and location or address)

THE OWNER:

(Name, legal status and address)

THE ARCHITECT:

(Name, legal status and address)

TABLE OF ARTICLES

1 GENERAL PROVISIONS

2 OWNER

3 CONTRACTOR

4 ARCHITECT

5 SUBCONTRACTORS

6 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS

7 CHANGES IN THE WORK

8 TIME

9 PAYMENTS AND COMPLETION

10 PROTECTION OF PERSONS AND PROPERTY

11 INSURANCE AND BONDS

12 UNCOVERING AND CORRECTION OF WORK

13 MISCELLANEOUS PROVISIONS

14 TERMINATION OR SUSPENSION OF THE CONTRACT

15 CLAIMS AND DISPUTES

INDEX

(Topics and numbers in bold are Section headings.)

AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 12:46:21 ET on 10/06/2026 under Order No.500075578_2 which expires on 10/06/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents®

Acceptance of Nonconforming Work

9.6.6, 9.9.3, 12.3

Acceptance of Work

9.6.6, 9.8.2, 9.9.3, 9.10.1, 9.10.3, 12.3

Access to Work

3.16, 6.2.1, 12.1

Accident Prevention

Acts and Omissions

3.2, 3.3.2, 3.12.8, 3.18, 4.2.3, 8.3.1, 9.5.1, 10.2.5, 10.2.8, 13.3.2, 14.1, 15.1.2, 15.2

Addenda

1.1.1

Additional Costs, Claims for

3.7.4, 3.7.5, 10.3.2, 15.1.5

Additional Inspections and Testing

9.4.2, 9.8.3, 12.2.1, 13.4

Additional Time, Claims for

3.2.4, 3.7.4, 3.7.5, 3.10.2, 8.3.2, 15.1.6

Administration of the Contract

3.1.3, 4.2, 9.4, 9.5

Advertisement or Invitation to Bid

1.1.1

Aesthetic Effect

4.2.13

Allowances

3.8

Applications for Payment

4.2.5, 7.3.9, 9.2, 9.3, 9.4, 9.5.1, 9.5.4, 9.6.3, 9.7, 9.10

Approvals

2.1.1, 2.3.1, 2.5, 3.1.3, 3.10.2, 3.12.8, 3.12.9, 3.12.10.1, 4.2.7, 9.3.2, 13.4.1

Arbitration

8.3.1, 15.3.2, 15.4

ARCHITECT

Architect, Definition of

4.1.1

Architect, Extent of Authority

2.5, 3.12.7, 4.1.2, 4.2, 5.2, 6.3, 7.1.2, 7.3.4, 7.4, 9.2, 9.3.1, 9.4, 9.5, 9.6.3, 9.8, 9.10.1, 9.10.3, 12.1, 12.2.1, 13.4.1, 13.4.2, 14.2.2, 14.2.4, 15.1.4, 15.2.1

Architect, Limitations of Authority and Responsibility

2.1.1, 3.12.4, 3.12.8, 3.12.10, 4.1.2, 4.2.1, 4.2.2, 4.2.3, 4.2.6, 4.2.7, 4.2.10, 4.2.12, 4.2.13, 5.2.1, 7.4, 9.4.2, 9.5.4, 9.6.4, 15.1.4, 15.2

Architect’s Additional Services and Expenses

2.5, 12.2.1, 13.4.2, 13.4.3, 14.2.4

Architect’s Administration of the Contract

3.1.3, 3.7.4, 15.2, 9.4.1, 9.5

Architect’s Approvals

2.5, 3.1.3, 3.5, 3.10.2, 4.2.7

Architect’s Authority to Reject Work

3.5, 4.2.6, 12.1.2, 12.2.1

Architect’s Copyright

1.1.7, 1.5

Architect’s Decisions

3.7.4, 4.2.6, 4.2.7, 4.2.11, 4.2.12, 4.2.13, 4.2.14, 6.3, 7.3.4, 7.3.9, 8.1.3, 8.3.1, 9.2, 9.4.1, 9.5, 9.8.4, 9.9.1, 13.4.2, 15.2

Architect’s Inspections

3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.8.3, 9.9.2, 9.10.1, 13.4

Architect’s Instructions

3.2.4, 3.3.1, 4.2.6, 4.2.7, 13.4.2

Architect’s Interpretations

4.2.11, 4.2.12

Architect’s Project Representative

4.2.10

Architect’s Relationship with Contractor

1.1.2, 1.5, 2.3.3, 3.1.3, 3.2.2, 3.2.3, 3.2.4, 3.3.1, 3.4.2, 3.5, 3.7.4, 3.7.5, 3.9.2, 3.9.3, 3.10, 3.11, 3.12, 3.16, 3.18, 4.1.2, 4.2, 5.2, 6.2.2, 7, 8.3.1, 9.2, 9.3, 9.4, 9.5, 9.7, 9.8, 9.9, 10.2.6, 10.3, 11.3, 12, 13.3.2, 13.4, 15.2

Architect’s Relationship with Subcontractors

1.1.2, 4.2.3, 4.2.4, 4.2.6, 9.6.3, 9.6.4, 11.3

Architect’s Representations

9.4.2, 9.5.1, 9.10.1

Architect’s Site Visits

3.7.4, 4.2.2, 4.2.9, 9.4.2, 9.5.1, 9.9.2, 9.10.1, 13.4

Asbestos

10.3.1

Attorneys’ Fees

3.18.1, 9.6.8, 9.10.2, 10.3.3

Award of Separate Contracts

6.1.1, 6.1.2

Award of Subcontracts and Other Contracts for

Portions of the Work

5.2

Basic Definitions

1.1

Bidding Requirements

1.1.1

Binding Dispute Resolution

8.3.1, 9.7, 11.5, 13.1, 15.1.2, 15.1.3, 15.2.1, 15.2.5, 15.2.6.1, 15.3.1, 15.3.2, 15.3.3, 15.4.1

Bonds, Lien

7.3.4.4, 9.6.8, 9.10.2, 9.10.3

Bonds, Performance, and Payment

7.3.4.4, 9.6.7, 9.10.3, 11.1.2, 11.1.3, 11.5

Building Information Models Use and Reliance

1.8

Building Permit

3.7.1

Capitalization

1.3

Certificate of Substantial Completion

9.8.3, 9.8.4, 9.8.5

Certificates for Payment

4.2.1, 4.2.5, 4.2.9, 9.3.3, 9.4, 9.5, 9.6.1, 9.6.6, 9.7, 9.10.1, 9.10.3, 14.1.1.3, 14.2.4, 15.1.4

Certificates of Inspection, Testing or Approval

13.4.4

AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 12:46:21 ET on 10/06/2026 under Order No.500075578_2 which expires on 10/06/2027, is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents®

Certificates of Insurance

9.10.2

Change Orders

1.1.1, 3.4.2, 3.7.4, 3.8.2.3, 3.11, 3.12.8, 4.2.8, 5.2.3, 7.1.2, 7.1.3, 7.2, 7.3.2, 7.3.7, 7.3.9, 7.3.10, 8.3.1, 9.3.1.1, 9.10.3, 10.3.2, 11.2, 11.5, 12.1.2

Change Orders, Definition of

7.2.1

CHANGES IN THE WORK

2.2.2, 3.11, 4.2.8, 7, 7.2.1, 7.3.1, 7.4, 8.3.1, 9.3.1.1, 11.5

Claims, Definition of

15.1.1

Claims, Notice of

1.6.2, 15.1.3

CLAIMS AND DISPUTES

3.2.4, 6.1.1, 6.3, 7.3.9, 9.3.3, 9.10.4, 10.3.3, 15, 15.4

Claims and Timely Assertion of Claims

15.4.1

Claims for Additional Cost

3.2.4, 3.3.1, 3.7.4, 7.3.9, 9.5.2, 10.2.5, 10.3.2, 15.1.5

Claims for Additional Time

3.2.4, 3.3.1, 3.7.4, 6.1.1, 8.3.2, 9.5.2, 10.3.2, 15.1.6

Concealed or Unknown Conditions, Claims for

3.7.4

Claims for Damages

3.2.4, 3.18, 8.3.3, 9.5.1, 9.6.7, 10.2.5, 10.3.3, 11.3, 11.3.2, 14.2.4, 15.1.7

Claims Subject to Arbitration

15.4.1

Cleaning Up

3.15, 6.3

Commencement of the Work, Conditions Relating to

2.2.1, 3.2.2, 3.4.1, 3.7.1, 3.10.1, 3.12.6, 5.2.1, 5.2.3, 6.2.2, 8.1.2, 8.2.2, 8.3.1, 11.1, 11.2, 15.1.5

Commencement of the Work, Definition of

8.1.2

Communications

3.9.1, 4.2.4

Completion, Conditions Relating to

3.4.1, 3.11, 3.15, 4.2.2, 4.2.9, 8.2, 9.4.2, 9.8, 9.9.1, 9.10, 12.2, 14.1.2, 15.1.2

COMPLETION, PAYMENTS AND

Completion, Substantial

3.10.1, 4.2.9, 8.1.1, 8.1.3, 8.2.3, 9.4.2, 9.8, 9.9.1, 9.10.3, 12.2, 15.1.2

Compliance with Laws

2.3.2, 3.2.3, 3.6, 3.7, 3.12.10, 3.13, 9.6.4, 10.2.2, 13.1, 13.3, 13.4.1, 13.4.2, 13.5, 14.1.1, 14.2.1.3, 15.2.8, 15.4.2, 15.4.3

Concealed or Unknown Conditions

3.7.4, 4.2.8, 8.3.1, 10.3

Conditions of the Contract

1.1.1, 6.1.1, 6.1.4

Consent, Written

3.4.2, 3.14.2, 4.1.2, 9.8.5, 9.9.1, 9.10.2, 9.10.3, 13.2, 15.4.4.2

Consolidation or Joinder

15.4.4

CONSTRUCTION BY OWNER OR BY

SEPARATE CONTRACTORS

1.1.4, 6

Construction Change Directive, Definition of

7.3.1

Construction Change Directives

1.1.1, 3.4.2, 3.11, 3.12.8, 4.2.8, 7.1.1, 7.1.2, 7.1.3, 7.3, 9.3.1.1

Construction Schedules, Contractor’s

3.10, 3.11, 3.12.1, 3.12.2, 6.1.3, 15.1.6.2

Contingent Assignment of Subcontracts

5.4, 14.2.2.2

Continuing Contract Performance

15.1.4

Contract, Definition of

1.1.2

CONTRACT, TERMINATION OR

SUSPENSION OF THE

5.4.1.1, 5.4.2, 11.5, 14

Contract Administration

3.1.3, 4, 9.4, 9.5

Contract Award and Execution, Conditions Relating to

3.7.1, 3.10, 5.2, 6.1

Contract Documents, Copies Furnished and Use of

1.5.2, 2.3.6, 5.3

Contract Documents, Definition of

1.1.1

Contract Sum

2.2.2, 2.2.4, 3.7.4, 3.7.5, 3.8, 3.10.2, 5.2.3, 7.3, 7.4, 9.1, 9.2, 9.4.2, 9.5.1.4, 9.6.7, 9.7, 10.3.2, 11.5, 12.1.2, 12.3, 14.2.4, 14.3.2, 15.1.4.2, 15.1.5, 15.2.5

Contract Sum, Definition of

9.1

Contract Time

1.1.4, 2.2.1, 2.2.2, 3.7.4, 3.7.5, 3.10.2, 5.2.3, 6.1.5, 7.2.1.3, 7.3.1, 7.3.5, 7.3.6, 7, 7, 7.3.10, 7.4, 8.1.1, 8.2.1, 8.2.3, 8.3.1, 9.5.1, 9.7, 10.3.2, 12.1.1, 12.1.2, 14.3.2, 15.1.4.2, 15.1.6.1, 15.2.5

Contract Time, Definition of

8.1.1

CONTRACTOR

Contractor, Definition of

3.1, 6.1.2

Contractor’s Construction and Submittal

Schedules

3.10, 3.12.1, 3.12.2, 4.2.3, 6.1.3, 15.1.6.2

Contractor’s Employees

2.2.4, 3.3.2, 3.4.3, 3.8.1, 3.9, 3.18.2, 4.2.3, 4.2.6, 10.2, 10.3, 11.3, 14.1, 14.2.1.1

AIA Document A201 – 2017. Copyright © 1911, 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1966, 1970, 1976, 1987, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .