This solicitation is for a firm fixed-price construction contract to install new boilers in Building 13 at the Robert J. Dole VA Medical Center in Wichita, Kansas. The work includes demolishing existing boilers and associated equipment; installing two new high-efficiency natural gas-fired boilers, a new fuel oil system, steam and condensate piping, HVAC equipment and controls; and related mechanical, electrical and structural work. The period of performance is 450 calendar days. The solicitation was issued by the Department of Veterans Affairs Veterans Health Administration VISN 15. The anticipated award date is September 2022. Pricing is on a lump sum basis. The solicitation is unrestricted and available to all responsible sources.

View the file

Other files

File Type Posted
36C25522R0079 0005.docx DOCX document
589A7-18-302 Wichita Bid Drawings - 2_Civil 1 of 3.pdf PDF
589A7-18-302 Wichita Bid Drawings - 2_Civil 2 of 3.pdf PDF
36C25522R0079 0004.docx DOCX document
589A7-18-302 Wichita Bid Drawings - 2_Civil 3 of 3.pdf PDF
S02 Pre-Bid Questions Solicitation No 36C25522R0079_VA Response.pdf PDF
36C25522R0079 0003.docx DOCX document
589-18-302 Boiler Pre Bid Attendance.pdf PDF
PROPOSAL SUBMITTAL INSTRUCTIONS 589A7-18-302 REV 08052022.docx DOCX document
36C25522R0079 0002.pdf PDF
589A7-18-302 Wichita Bid Drawings - 3 Structural.pdf PDF
589A7-18-302 Wichita Bid Drawings - 2_Civil (SI) 2 of 3.pdf PDF
589A7-18-302 Wichita Bid Drawings - 7_Mechanical 3 of 4.pdf PDF
589A7-18-302 Wichita Bid Drawings - 6_Plumbing 1 of 2.pdf PDF
589A7-18-302 Wichita Bid Drawings - 6_Plumbing 2 of 2.pdf PDF
589A7-18-302 Wichita Bid Drawings - 7_Mechanical 1 of 4.pdf PDF
36C25522R0079 0001.docx DOCX document
589A7-18-302 Wichita Bid Drawings - 7_Mechanical 2 of 4.pdf PDF
589A7-18-302 Wichita Bid Drawings - 7_Mechanical 4 of 4.pdf PDF
589A7-18-302 Wichita Bid Drawings - 3_Structural (SI).pdf PDF
589A7-18-302 Wichita Bid Drawings - 4_Architectural (SI) 2 of 2.pdf PDF
S02 P09 - 589A7-18-302 Wichita Bid Specs VOL 3 of 3.pdf PDF
589A7-18-302 Wichita Bid Drawings - 6_Plumbing (SI).pdf PDF
S02 P09 - 589A7-18-302 Wichita Bid Specs VOL 2 of 3.pdf PDF
589A7-18-302 Wichita Bid Drawings - 8_Electrical (SI) 5 of 6.pdf PDF
589A7-18-302 Wichita Bid Drawings - 8_Electrical (SI) 6 of 6.pdf PDF
589A7-18-302 Wichita Bid Drawings - 7_Mechanical (SI) 1 of 4.pdf PDF
589A7-18-302 Wichita Bid Drawings - 8_Electrical 3 of 6.pdf PDF
36C25522R0079_1.docx DOCX document
S02 ATTACMENT 3 Past Performance Questionnaire 36C25522R0079 Project 589A7-18-302.pdf PDF
589A7-18-302 Wichita Bid Drawings - 2_Civil (SI) 3 of 3.pdf PDF
589A7-18-302 Wichita Bid Drawings - 8_Electrical (SI) 2 of 6.pdf PDF
589A7-18-302 Wichita Bid Drawings - 1_Hazardous Materials (SI).pdf PDF
589A7-18-302 Wichita Bid Drawings - 8_Electrical (SI) 1 of 6.pdf PDF
589A7-18-302 Wichita Bid Drawings - 2_Civil (SI) 1 of 3.pdf PDF
589A7-18-302 Wichita Bid Drawings - 5_ Fire Protection (SI).pdf PDF
589A7-18-302 Wichita Bid Drawings - 7_Mechanical (SI) 4 of 4.pdf PDF
589A7-18-302 Wichita Bid Drawings - 8_Electrical 4 of 6.pdf PDF
589A7-18-302 Wichita Bid Specs VOL 1 of 3 (800pgs).pdf PDF
589A7-18-302 Wichita Bid Drawings - 4_Architectural (SI) 1 of 2.pdf PDF
589A7-18-302 Wichita Bid Drawings - 7_Mechanical (SI) 3 of 4.pdf PDF
P07 Wage Determination 20220708.docx DOCX document
589A7-18-302 Wichita Bid Drawings - 0_General (SI).pdf PDF
Show all 43

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 2 3 4 5 6 7 8

F

H

K

D

C

B

A

E

E1 E2 E3 E4 E5 E6 E7

J

G

(TYP.)

CONTROL

ROOM

OFFICE

TOILETBREAK

ROOM

IT

ROOM

BOILER

ROOM

(E) 38FOS & 38FOR REFER TO

DRAWING MP121.02 FOR

CONTINUATION

REFER TO MP101.02

FOR CONTINUATION

10 (E)32PC

IN TRENCH TO REMAIN AS IS

(E)38PC

DOWN TO REMAIN

AS IS

(E)38HPS

TO BLDG 20

IN EXISTING TRENCH

(E)32PC DOWN TO

EXISTING TRENCH.

REFER TO MD111.03 FOR CONTINUATION

EXISTING WATER TREATMENT

EQUIPMENT. REFER TO PLUMBING DRAWINGS

FOR SCOPE.

(E)254HPS DOWN

FROM MAIN LEVEL

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ENGINEER OF RECORDCONSULTANTS

321 4 5 6 7 8 9 10

NO. DESCRIPTION DATE

PRINTS OF THIS DRAWING SHALL NOT BE USED FOR ANY PURPOSE

WHATSOEVER WITHOUT THE SEAL AND SIGNATURE OF THE

PROFESSIONAL ENGINEER

o n e e ig h th i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e i n c h o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t th re e i n c h e s o n e f o o t

MILLER-REMICK LLC

PROFESSIONAL ENGINEER

MR PROJECT NO:

NORTHKEYPLAN

HAZARDOUS MATERIALS

MABBETT & ASSOCIATES, INC.

105 CENTRAL STREET, STONEHAM, MA 02180

PHONE: (781)275-6050

CIVIL / STRUCTURAL

PROFESSIONAL ENGINEERING CONSULTANTS, P.A.

303 SOUTH TOPEKA, WICHITA, KS 67202

PHONE: (316)262-2691

ARCHITECTURAL

OCULUS INC.

1 SOUTH MEMORIAL DRIVE, SUITE 1500, SAINT LOUIS, MO 63102

PHONE: (314)367-6100

FIRE SUPPRESSION

KOFFEL ASSOCIATES

8815 CENTRE PARK DRIVE, SUITE 200, COLUMBIA, MD 21045

PHONE: (410)750-2246

ELECTRONIC SECURITY

MAGNA ENGINEERS

861 CORPORATE DRIVE, SUITE 210, LEXINGTON, KY 40503

PHONE: (859)309-2990

PHYSICAL SECURITY

FORCE PROTECT

3210 GULF BLVD, UNIT 304, BELLEAIR BEACH, FL 33786

PHONE: (502)836-4232

C U s e rs

\g s tr o h \D o c u m e n ts

\0 -0

-W ic h it a B o ile rs -M e tr ic M

E P

-C E

N T

R A

L -R g s tr o h Q

H E

Z

.r v t

/9

/2

:4

:3

A

M

13-MD111.03

MECHANICAL

DEMOLITION PLAN

SHOP & MAIN LEVELS, PHASE 3

INSTALL NEW BOILERS IN

BUILDING 13

ROBERT J. DOLE VA MEDICAL CENTER

WICHITA, KANSAS

589A7-18-302

Project Director

2021-09-03 Checker Author0499-0121

100% BID SET

FULLY SPRINKLERED

SCALE: 1 : 481 MECHANICAL DEMOLITION PLAN - SHOP & MAIN LEVELS, PHASE 3

GENERAL SHEET NOTES:

SHEET KEYNOTES:

1 ONCE THE FUEL-OIL (FOS/FOR) PIPING FROM THE EXISTING UNDERGROUND TANKS HAS BEEN

EXTEND TO NEW FUEL-OIL EQUIPMENT IN THE NEW BOILER PLANT. THE EXISTING FUEL-OIL

PUMPS SHALL BE DISCONNECTED AND REMOVED.

2 ONCE NEW BOILERS ARE OPERATIONAL THE EXISTING BOILERS SHALL BE DECOMMISSIONED,

DISCONNECTED AND REMOVED

3 EXISTING DEAERATOR AND CONDENSATE TANKS SHALL BE DISCONNECTED AND REMOVED IN ITS

ENTIRETY.

4 EXISTING STEAM PIPING WITHIN EXISTING BOILER PLANT SHALL BE DISCONNECTED AND

REMOVED AS INDICATED ON THE DRAWINGS.

5 CONTRACTOR SHALL DISCONNECT AND REMOVED EXISTING HVAC FOR EXISTING CONTROL ROOM, RESTROOM AND OFFICE INCLUDING EQUIPMENT, CONTROLS, DUCTWORK, HANGERS, SUPPORTS, AIR DEVICES, AND ASSOCIATED PIPING, VALVES, ETC. IN ITS ENTIRETY.

6 EXISTING HPS AND PC TO/FROM BUILDING 20 THRU EXISTING PIPE TRENCH TO REMAIN AS IS.

7 TEMPORARY NATURAL GAS MAIN TO BE PURGED AND DISCONNECTED AND REMOVED. CAP PIPE.

8 DISCONNECT AND REMOVE ALL EXISTING UNIT HEATER AND ASSOCIATED PIPING.

9 DISCONNECT AND REMOVE EXISTING 127 HPS WITHIN EXISTING BOILER PLANT.

10 EXISTING LPG TANK AND ENCLOSURE TO REMAIN AS IS. REFER TO DRAWING MP604 FOR

ADDITIONAL DETAILS.

11 EXISTING NATURAL GAS PIPING FEEDING THE EXISTING BOILERS AMD DOMESTIC HOT WATER

HEATER TO BE PURGED AND DISCONNECTED AND REMOVED.

12 EXISTING SUMP PUMP. REFER TO PLUMBING DRAWINGS FOR SCOPE.

13 DISCONNECT AND RELOCATE SHOP AIR COMPRESSOR. REFER TO DRAWING MP111.03 FOR NEW

LOCATION.

14 EXISTING 102 DIA HPS SHALL BE DISCONNECTED AND REMOVED. REFER TO DETAIL 9 ON

DRAWING M-502 FOR ADDITIONAL DETAILS.

1. REFER TO DRAWING M-001 FOR NOTES, SYMBOLS AND ABBREVIATIONS.

2. REFER TO DRAWINGS MP601, MP602, MP603 AND MP604 FOR SYSTEM FLOW

DIAGRAMS.

3. REFER TO DRAWINGS M-701, M-702, M-703 AND M-704 FOR EQUIPMENT

SCHEDULES.

4. CONTRACTOR SHALL SUBMIT A DETAILED LOCKOUT/TAGOUT PROCEDURE TO THE VA A

MINIMUM OF 4 WORKING DAYS PRIOR TO PERFORMING ANY WORK ON ANY LIVE

STEAM OR STEAM CONDENSATE SYSTEM OR EQUIPMENT.

5. ALL VALVE HANDLES MUST BE ACCESSIBLE FROM A WALKABLE SURFACE. COORDINATE

LOCATION WITH ALL TRADES.

H

K

D

C

B

A

E

E1 E2 E3 E4 E5 E6 E7

J

G

BOILER

ROOM

M-18

STORAGE

C-1

DN. TO

BLDG 20

38HPS

PHASE 2

(E)102 NATURAL GAS LINE

UP FROM BELOW

(E)38HPS

(E)38PC 1

(E)38HPS

INSTALLED IN PHASE 2

254HPS

TO REMAIN AS IS

(E)38PC DN.

(E)19LPG

(E)38HPS

(E)19LPG DN.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ENGINEER OF RECORDCONSULTANTS

321 4 5 6 7 8 9 10

NO. DESCRIPTION DATE

PRINTS OF THIS DRAWING SHALL NOT BE USED FOR ANY PURPOSE

WHATSOEVER WITHOUT THE SEAL AND SIGNATURE OF THE

PROFESSIONAL ENGINEER

o n e e ig h th i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e i n c h o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t th re e i n c h e s o n e f o o t

MILLER-REMICK LLC

PROFESSIONAL ENGINEER

MR PROJECT NO:

NORTHKEYPLAN

HAZARDOUS MATERIALS

MABBETT & ASSOCIATES, INC.

105 CENTRAL STREET, STONEHAM, MA 02180

PHONE: (781)275-6050

CIVIL / STRUCTURAL

PROFESSIONAL ENGINEERING CONSULTANTS, P.A.

303 SOUTH TOPEKA, WICHITA, KS 67202

PHONE: (316)262-2691

ARCHITECTURAL

OCULUS INC.

1 SOUTH MEMORIAL DRIVE, SUITE 1500, SAINT LOUIS, MO 63102

PHONE: (314)367-6100

FIRE SUPPRESSION

KOFFEL ASSOCIATES

8815 CENTRE PARK DRIVE, SUITE 200, COLUMBIA, MD 21045

PHONE: (410)750-2246

ELECTRONIC SECURITY

MAGNA ENGINEERS

861 CORPORATE DRIVE, SUITE 210, LEXINGTON, KY 40503

PHONE: (859)309-2990

PHYSICAL SECURITY

FORCE PROTECT

3210 GULF BLVD, UNIT 304, BELLEAIR BEACH, FL 33786

PHONE: (502)836-4232

C U s e rs

\g s tr o h \D o c u m e n ts

\0 -0

-W ic h it a B o ile rs -M e tr ic M

E P

-C E

N T

R A

L -R g s tr o h Q

H E

Z

.r v t

/9

/2

:4

:1

A

M

13-MD121.03

MECHANICAL

DEMOLITION PLAN

EX CATWALK & CATWALK LVLS, PH 3

INSTALL NEW BOILERS IN

BUILDING 13

ROBERT J. DOLE VA MEDICAL CENTER

WICHITA, KANSAS

589A7-18-302

Project Director

2021-09-03 AP GDS0499-0121

100% BID SET

FULLY SPRINKLERED

SCALE: 1 : 481

MECHANICAL DEMOLITION PLAN - EXISTING CATWALK & CATWALK

LEVELS, PHASE 3

GENERAL SHEET NOTES:

SHEET KEYNOTES:

1 EXISTING UTILITY RACK TO REMAIN AS IS. PROTECT DURING CONSTRUCTION.

2 EXISTING STEAM PIPING IN EXISTING BOILER PLANT TO BE DEACTIVATED, DISCONNECTED AND

REMOVED.

3 EXISTING BOILER STACK TO BE DISCONNECTED AND REMOVED.

4 CONTRACTOR SHALL DISCONNECT AND REMOVED EXISTING HVAC FOR EXISTING CONTROL ROOM, RESTROOM AND OFFICE INCLUDING EQUIPMENT, CONTROLS, DUCTWORK, HANGERS, SUPPORTS, AIR DEVICES, AND ASSOCIATED PIPING, VALVES, ETC. IN ITS ENTIRETY.

5 EXISTING 254 DIA HPS DOWN TO LOWER LEVEL TO REMAIN AS IS. EXISTING CONDENSATE DRIP

TRAP PIPING TO BE CONNECTED INTO NEW CONDENSATE SYSTEM. REFER TO DETAIL 8 ON

DRAWING M-502.

1. REFER TO DRAWING M-001 FOR NOTES, SYMBOLS AND ABBREVIATIONS.

2. REFER TO DRAWINGS MP601, MP602, MP603 AND MP604 FOR SYSTEM FLOW

DIAGRAMS.

3. REFER TO DRAWINGS M-701, M-702, M-703 AND M-704 FOR EQUIPMENT

SCHEDULES.

4. CONTRACTOR SHALL SUBMIT A DETAILED LOCKOUT/TAGOUT PROCEDURE TO THE VA A

MINIMUM OF 4 WORKING DAYS PRIOR TO PERFORMING ANY WORK ON ANY LIVE

STEAM OR STEAM CONDENSATE SYSTEM OR EQUIPMENT.

H

K

D

C

B

A

E

E1 E2 E3 E4 E5 E6 E7

J

G

PHASE 2

(E)DUCT

GOOSENECK

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ENGINEER OF RECORDCONSULTANTS

321 4 5 6 7 8 9 10

NO. DESCRIPTION DATE

PRINTS OF THIS DRAWING SHALL NOT BE USED FOR ANY PURPOSE

WHATSOEVER WITHOUT THE SEAL AND SIGNATURE OF THE

PROFESSIONAL ENGINEER

o n e e ig h th i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e i n c h o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t th re e i n c h e s o n e f o o t

MILLER-REMICK LLC

PROFESSIONAL ENGINEER

MR PROJECT NO:

NORTHKEYPLAN

HAZARDOUS MATERIALS

MABBETT & ASSOCIATES, INC.

105 CENTRAL STREET, STONEHAM, MA 02180

PHONE: (781)275-6050

CIVIL / STRUCTURAL

PROFESSIONAL ENGINEERING CONSULTANTS, P.A.

303 SOUTH TOPEKA, WICHITA, KS 67202

PHONE: (316)262-2691

ARCHITECTURAL

OCULUS INC.

1 SOUTH MEMORIAL DRIVE, SUITE 1500, SAINT LOUIS, MO 63102

PHONE: (314)367-6100

FIRE SUPPRESSION

KOFFEL ASSOCIATES

8815 CENTRE PARK DRIVE, SUITE 200, COLUMBIA, MD 21045

PHONE: (410)750-2246

ELECTRONIC SECURITY

MAGNA ENGINEERS

861 CORPORATE DRIVE, SUITE 210, LEXINGTON, KY 40503

PHONE: (859)309-2990

PHYSICAL SECURITY

FORCE PROTECT

3210 GULF BLVD, UNIT 304, BELLEAIR BEACH, FL 33786

PHONE: (502)836-4232

C U s e rs

\g s tr o h \D o c u m e n ts

\0 -0

-W ic h it a B o ile rs -M e tr ic M

E P

-C E

N T

R A

L -R g s tr o h Q

H E

Z

.r v t

/9

/2

:4

:1

A

M

13-MD131.03

MECHANICAL

DEMOLITION PLAN

ROOF, PHASE 3

INSTALL NEW BOILERS IN

BUILDING 13

ROBERT J. DOLE VA MEDICAL CENTER

WICHITA, KANSAS

589A7-18-302

Project Director

2021-09-03 AP GDS0499-0121

100% BID SET

FULLY SPRINKLERED

SCALE: 1 : 481 MECHANICAL DEMOLITION PLAN - ROOF, PHASE 3

GENERAL SHEET NOTES:

SHEET KEYNOTES:

1 DISCONNECT AND REMOVE EXISTING ROOF MOUNTED EXHAUST FANS, STEAM SILENCER, BOILER

EXHAUST STACKS AND ALL STEAM VENT PIPING AND ASSOCIATED SUPPORTS. FILL IN ALL

ROOF OPENINGS AND PATCH ROOF. REFER TO ARCHITECTURAL AND STRUCTURAL DRAWINGS

FOR DETAILS.

1. REFER TO DRAWING M-001 FOR NOTES, SYMBOLS AND ABBREVIATIONS.

2. REFER TO DRAWINGS MP601, MP602, MP603 AND MP604 FOR SYSTEM FLOW

DIAGRAMS.

3. REFER TO DRAWINGS M-701, M-702, M-703 AND M-704 FOR EQUIPMENT

SCHEDULES.

4. CONTRACTOR SHALL SUBMIT A DETAILED LOCKOUT/TAGOUT PROCEDURE TO THE VA A

MINIMUM OF 4 WORKING DAYS PRIOR TO PERFORMING ANY WORK ON ANY LIVE

STEAM OR STEAM CONDENSATE SYSTEM.

1 2 3 4 5 6

H

K

D

C

B

A

E

E1 E2 E3 E5 E6 E7

J

G

EXISTING

PUMP ROOM

B-1

PHASE 2

REFER TO ROOM STORAGE

B-2 ABOVE THIS AREA.

REF. PLAN THIS SHEET

NEW PUMP

ROOM

B-4

CO

CO

(E)FIRE MAIN

TO REMAIN AS IS

C

B

A

E5 E6

STORAGE

B-2

305x152

SG-1

94 L/s

102x305UP

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ENGINEER OF RECORDCONSULTANTS

321 4 5 6 7 8 9 10

NO. DESCRIPTION DATE

PRINTS OF THIS DRAWING SHALL NOT BE USED FOR ANY PURPOSE

WHATSOEVER WITHOUT THE SEAL AND SIGNATURE OF THE

PROFESSIONAL ENGINEER

o n e e ig h th i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e i n c h o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t th re e i n c h e s o n e f o o t

MILLER-REMICK LLC

PROFESSIONAL ENGINEER

MR PROJECT NO:

NORTHKEYPLAN

HAZARDOUS MATERIALS

MABBETT & ASSOCIATES, INC.

105 CENTRAL STREET, STONEHAM, MA 02180

PHONE: (781)275-6050

CIVIL / STRUCTURAL

PROFESSIONAL ENGINEERING CONSULTANTS, P.A.

303 SOUTH TOPEKA, WICHITA, KS 67202

PHONE: (316)262-2691

ARCHITECTURAL

OCULUS INC.

1 SOUTH MEMORIAL DRIVE, SUITE 1500, SAINT LOUIS, MO 63102

PHONE: (314)367-6100

FIRE SUPPRESSION

KOFFEL ASSOCIATES

8815 CENTRE PARK DRIVE, SUITE 200, COLUMBIA, MD 21045

PHONE: (410)750-2246

ELECTRONIC SECURITY

MAGNA ENGINEERS

861 CORPORATE DRIVE, SUITE 210, LEXINGTON, KY 40503

PHONE: (859)309-2990

PHYSICAL SECURITY

FORCE PROTECT

3210 GULF BLVD, UNIT 304, BELLEAIR BEACH, FL 33786

PHONE: (502)836-4232

C U s e rs

\g s tr o h \D o c u m e n ts

\0 -0

-W ic h it a B o ile rs -M e tr ic M

E P

-C E

N T

R A

L -R g s tr o h Q

H E

Z

.r v t

/9

/2

:4

:1

A

M

13-MH101.03

MECHANICAL

DUCTWORK PLAN

TUNNEL & BSMT LEVELS, PHASE 3

INSTALL NEW BOILERS IN

BUILDING 13

ROBERT J. DOLE VA MEDICAL CENTER

WICHITA, KANSAS

589A7-18-302

Project Director

2021-09-03 AP GDS0499-0121

100% BID SET

FULLY SPRINKLERED

SCALE: 1 : 481 DUCTWORK PLAN - TUNNEL & BASEMENT LEVELS, PHASE 3

GENERAL SHEET NOTES:

1. REFER TO DRAWING M-001 FOR NOTES, SYMBOLS AND ABBREVIATIONS.

2. REFER TO DRAWINGS M-701, M-702, M-703 AND M-704 FOR EQUIPMENT

SCHEDULES.

SCALE: 1 : 482 DUCTWORK PLAN - STORAGE B-2, PHASE 3

SHEET KEYNOTES:

1 MOUNT CO DETECTORS 1372 AFF. CONFIRM QUANITY AND LOCATION OF SENSORS W/ GAS

DETECTION VENDOR TO ENSURE COMPLETE COVERAGE.

R E

F

13-M-301

1 2 3 4 5 6 7 8

F

H

K

D

C

B

A

E

E1 E2 E3 E4 E5 E6 E7

J

G

13-FOM-1

CONTRACTOR

TOUCHDOWN

M-6

TOILET

M-2

TOILET

M-1

PASSAGE

M-7

LOCKER

ROOM

M-3

EQUIPMENT

M-19

SHOWER

ROOM

M-4

BREAK

AREA

M-5

13-RO-01

CD-4

142 L/s

CD-4

142 L/s

CD-1

71 L/s

CD-1

71 L/s

ER-2

24 L/s

ER-3

83 L/s

CD-2

94 L/s

ER-1

47 L/s

ER-1

59 L/s

CD-3

47 L/s

CD-3

35 L/s

PHASE 2

13-M-301

CO NG

T

13-AC-4

ER-1

24 L/s

RG-3

295 L/s

T

13-UH-12/13

T13-EF-3/4

13-M-305

13-TNK-03

13-TNK-04

13-TNK-05

13-TNK-06

102x305

SA

UP/DN

RG-3

295 L/s

REFER TO SHEET

13-MH121.03 FOR

DUCTWORK PLAN ABOVE.

T

13-UH-10/11

CO 1

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ENGINEER OF RECORDCONSULTANTS

321 4 5 6 7 8 9 10

NO. DESCRIPTION DATE

PRINTS OF THIS DRAWING SHALL NOT BE USED FOR ANY PURPOSE

WHATSOEVER WITHOUT THE SEAL AND SIGNATURE OF THE

PROFESSIONAL ENGINEER

o n e e ig h th i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e i n c h o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t th re e i n c h e s o n e f o o t

MILLER-REMICK LLC

PROFESSIONAL ENGINEER

MR PROJECT NO:

NORTHKEYPLAN

HAZARDOUS MATERIALS

MABBETT & ASSOCIATES, INC.

105 CENTRAL STREET, STONEHAM, MA 02180

PHONE: (781)275-6050

CIVIL / STRUCTURAL

PROFESSIONAL ENGINEERING CONSULTANTS, P.A.

303 SOUTH TOPEKA, WICHITA, KS 67202

PHONE: (316)262-2691

ARCHITECTURAL

OCULUS INC.

1 SOUTH MEMORIAL DRIVE, SUITE 1500, SAINT LOUIS, MO 63102

PHONE: (314)367-6100

FIRE SUPPRESSION

KOFFEL ASSOCIATES

8815 CENTRE PARK DRIVE, SUITE 200, COLUMBIA, MD 21045

PHONE: (410)750-2246

ELECTRONIC SECURITY

MAGNA ENGINEERS

861 CORPORATE DRIVE, SUITE 210, LEXINGTON, KY 40503

PHONE: (859)309-2990

PHYSICAL SECURITY

FORCE PROTECT

3210 GULF BLVD, UNIT 304, BELLEAIR BEACH, FL 33786

PHONE: (502)836-4232

C U s e rs

\g s tr o h \D o c u m e n ts

\0 -0

-W ic h it a B o ile rs -M e tr ic M

E P

-C E

N T

R A

L -R g s tr o h Q

H E

Z

.r v t

/9

/2

:4

:4

A

M

13-MH111.03

MECHANICAL

DUCTWORK PLAN

SHOP & MAIN LEVELS, PHASE 3

INSTALL NEW BOILERS IN

BUILDING 13

ROBERT J. DOLE VA MEDICAL CENTER

WICHITA, KANSAS

589A7-18-302

Project Director

2021-09-03 AP GDS0499-0121

100% BID SET

FULLY SPRINKLERED

SCALE: 1 : 481 DUCTWORK PLAN - SHOP & MAIN LEVELS, PHASE 3

SHEET KEYNOTES:

1 MOUNT CO DETECTORS 1372 AFF. CONFIRM QUANITY AND LOCATION OF SENSORS W/ GAS

DETECTION VENDOR TO ENSURE COMPLETE COVERAGE.

2 MOUNT NATURAL GAS DETECTOR 305 BELOW CEILING. CONFIRM QUANITY AND LOCATION OF

SENSORS WITH GAS DECTECTION VENDOR TO ENSURE COMPLETE COVERAGE.

3 INSTALL THERMOSTAT 1321 AFF.

GENERAL SHEET NOTES:

1. REFER TO DRAWING M-001 FOR NOTES, SYMBOLS AND ABBREVIATIONS.

2. REFER TO DRAWINGS MP601, MP602, MP603 AND MP604 FOR SYSTEM FLOW

DIAGRAMS.

3. REFER TO DRAWINGS M-701, M-702, M-703 AND M-704 FOR EQUIPMENT

SCHEDULES.

4. CONTRACTOR SHALL SUBMIT A DETAILED LOCKOUT/TAGOUT PROCEDURE TO THE VA A

MINIMUM OF 4 WORKING DAYS PRIOR TO PERFORMING ANY WORK ON ANY LIVE

STEAM OR STEAM CONDENSATE SYSTEM.

13-M-301

1 2 3 4 5 6 7 8

F

H

K

D

C

B

A

E

E1 E2 E3 E4 E5 E6 E7

J

G

BOILER

ROOM

M-18

STORAGE

C-1

305x305 OA

UP TO 13-

GRV-6

457x305

152Ø

152Ø

305x305 EA UP

TO 13-GRV-7

152x152

PHASE 2

13-M-301

13-UH-11

13-UH-10

305x305

203Ø

SA UP TO

13-SF-3

762x762

UP TO

13-EF-4

13-ERV-2

864x203

762x762

EA UP TO

13-EF-3

914x914

SA UP TO

13-SF-4

914x914

152x152

152x152

U P

13-M-305

152x152

152x203

203x203

13-AC-4

914x406

SG-2

1055 L/s

660Ø 508Ø

660Ø508Ø

Ø

Ø

914x406

SG-2

1055 L/s

TYP(3)

TYP(3)

254x254 x x

Ø

Ø

SAOA

RA EA

(N)RS/RL

(N)19CD

ON MEZZ. PLATFORM,

HUNG FROM ABOVE

305x102

MEZZANINE ABOVE

CONTRACTOR TOUCHDOWN AREA

13-UH-12

13-UH-13

102x305

SA DN

(N)RS/RL

FC

FC

19CD

REFER TO SHEET

13-MH111.03 FOR AIR

DEVICE CONNECTIONS

BELOW.

13-ACCU-4

ON LOW ROOF

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ENGINEER OF RECORDCONSULTANTS

321 4 5 6 7 8 9 10

NO. DESCRIPTION DATE

PRINTS OF THIS DRAWING SHALL NOT BE USED FOR ANY PURPOSE

WHATSOEVER WITHOUT THE SEAL AND SIGNATURE OF THE

PROFESSIONAL ENGINEER

o n e e ig h th i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e i n c h o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t th re e i n c h e s o n e f o o t

MILLER-REMICK LLC

PROFESSIONAL ENGINEER

MR PROJECT NO:

NORTHKEYPLAN

HAZARDOUS MATERIALS

MABBETT & ASSOCIATES, INC.

105 CENTRAL STREET, STONEHAM, MA 02180

PHONE: (781)275-6050

CIVIL / STRUCTURAL

PROFESSIONAL ENGINEERING CONSULTANTS, P.A.

303 SOUTH TOPEKA, WICHITA, KS 67202

PHONE: (316)262-2691

ARCHITECTURAL

OCULUS INC.

1 SOUTH MEMORIAL DRIVE, SUITE 1500, SAINT LOUIS, MO 63102

PHONE: (314)367-6100

FIRE SUPPRESSION

KOFFEL ASSOCIATES

8815 CENTRE PARK DRIVE, SUITE 200, COLUMBIA, MD 21045

PHONE: (410)750-2246

ELECTRONIC SECURITY

MAGNA ENGINEERS

861 CORPORATE DRIVE, SUITE 210, LEXINGTON, KY 40503

PHONE: (859)309-2990

PHYSICAL SECURITY

FORCE PROTECT

3210 GULF BLVD, UNIT 304, BELLEAIR BEACH, FL 33786

PHONE: (502)836-4232

C U s e rs

\g s tr o h \D o c u m e n ts

\0 -0

-W ic h it a B o ile rs -M e tr ic M

E P

-C E

N T

R A

L -R g s tr o h Q

H E

Z

.r v t

/9

/2

:0

:5

A

M

13-MH121.03

MECHANICAL

DUCTWORK PLAN

EX CATWALK & CATWALK LVLS, PH 3

INSTALL NEW BOILERS IN

BUILDING 13

ROBERT J. DOLE VA MEDICAL CENTER

WICHITA, KANSAS

589A7-18-302

Project Director

2021-09-03 AP GDS0499-0121

100% BID SET

FULLY SPRINKLERED

SCALE: 1 : 481 DUCTWORK PLAN - EXISTING CATWALK & CATWALK LEVELS, PHASE 3

GENERAL SHEET NOTES:

SHEET KEYNOTES:

1 19 DIA CONDENSATE DRAIN PIPING. PITCH DOWNWARD IN DIRECTION OF FLOW MINIMUM 1%.

ROUTE DOWN TO MOP SINK. TERMINATE WITH AIR GAP.

2 REFRIGERANT PIPING (SUCTION & LIQUID) UP THRU ROOF PIPE PORTAL. PROVIDE SEPARATE

BOOT FOR EACH PIPE. ROUTE PER MANUFACTURER'S RECOMMENDATIONS. PROVIDE SUPPORTS

AS REQUIRED.

3 MAINTAIN LADDER ACCESS CLEARANCE TO EXISTING ROOF HATCH ABOVE.

4 GENERATOR EXHAUST MUFFLER.

1. REFER TO DRAWING M-001 FOR NOTES, SYMBOLS AND ABBREVIATIONS.

2. REFER TO DRAWINGS MP601, MP602, MP603 AND MP604 FOR SYSTEM FLOW

DIAGRAMS.

3. REFER TO DRAWINGS M-701, M-702, M-703 AND M-704 FOR EQUIPMENT

SCHEDULES.

4. CONTRACTOR SHALL SUBMIT A DETAILED LOCKOUT/TAGOUT PROCEDURE TO THE VA A

MINIMUM OF 4 WORKING DAYS PRIOR TO PERFORMING ANY WORK ON ANY LIVE

STEAM OR STEAM CONDENSATE SYSTEM.

1 2 3 4 5 6

H

K

D

C

B

A

E

E1 E2 E3 E5 E6 E7

J

G

EXISTING

PUMP ROOM

B-1

(E) 254HPS DOWN

FROM MAIN LEVEL

51FOS

51FOR

19FOS/FOR

51FOS

51FOR

PHASE 2

REFER TO DRAWINGS

MP101.03, MP604 & MP605

FOR ADDITIONAL DETAILS

102PC

(E)38PC

EXISTING 254HPS

51PC

REFER TO DETAIL 9

ON DRAWING MP502

REFER TO 2/MP101.03

FOR CONTINUATION

(E)FUEL OIL

PIPING

D

C

B

A

E

E5 E6

13-FOM-1

STORAGE

B-2

RELOCATED SHOP

AIR COMPRESSOR

REFER TO DRAWINGS

MP101.03, MP605 & MP606

FOR PIPING DETAILS

REFER TO

DRAWING MP101.03

FOR PIPING

254HPS DOWN

FROM MAIN LEVEL

38FOR

38FOS

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ENGINEER OF RECORDCONSULTANTS

321 4 5 6 7 8 9 10

NO. DESCRIPTION DATE

PRINTS OF THIS DRAWING SHALL NOT BE USED FOR ANY PURPOSE

WHATSOEVER WITHOUT THE SEAL AND SIGNATURE OF THE

PROFESSIONAL ENGINEER

o n e e ig h th i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e i n c h o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t th re e i n c h e s o n e f o o t

MILLER-REMICK LLC

PROFESSIONAL ENGINEER

MR PROJECT NO:

NORTHKEYPLAN

HAZARDOUS MATERIALS

MABBETT & ASSOCIATES, INC.

105 CENTRAL STREET, STONEHAM, MA 02180

PHONE: (781)275-6050

CIVIL / STRUCTURAL

PROFESSIONAL ENGINEERING CONSULTANTS, P.A.

303 SOUTH TOPEKA, WICHITA, KS 67202

PHONE: (316)262-2691

ARCHITECTURAL

OCULUS INC.

1 SOUTH MEMORIAL DRIVE, SUITE 1500, SAINT LOUIS, MO 63102

PHONE: (314)367-6100

FIRE SUPPRESSION

KOFFEL ASSOCIATES

8815 CENTRE PARK DRIVE, SUITE 200, COLUMBIA, MD 21045

PHONE: (410)750-2246

ELECTRONIC SECURITY

MAGNA ENGINEERS

861 CORPORATE DRIVE, SUITE 210, LEXINGTON, KY 40503

PHONE: (859)309-2990

PHYSICAL SECURITY

FORCE PROTECT

3210 GULF BLVD, UNIT 304, BELLEAIR BEACH, FL 33786

PHONE: (502)836-4232

C U s e rs

\g s tr o h \D o c u m e n ts

\0 -0

-W ic h it a B o ile rs -M e tr ic M

E P

-C E

N T

R A

L -R g s tr o h Q

H E

Z

.r v t

/9

/2

:4

:1

A

M

13-MP101.03

MECHANICAL

PIPING PLAN

TUNNEL & BSMT LEVELS, PHASE 3

INSTALL NEW BOILERS IN

BUILDING 13

ROBERT J. DOLE VA MEDICAL CENTER

WICHITA, KANSAS

589A7-18-302

Project Director

2021-09-03 AP GDS0499-0121

100% BID SET

FULLY SPRINKLERED

SCALE: 1 : 481 PIPING PLAN - TUNNEL & BASEMENT LEVELS, PHASE 3

GENERAL SHEET NOTES:

SHEET KEYNOTES:

1 INSTALL NEW FUEL-OIL FILTRATION SKID. PROVIDE 152 HIGH CONCRETE HOUSEKEEPING PAD.

2 INSTALL NEW 38FOS & 38FOR THROUGH STORAGE AREA. KEEP PIPING TIGHT TO BOTTOM

STRUCTURE ABOVE.

1. REFER TO DRAWING M-001 FOR NOTES, SYMBOLS AND ABBREVIATIONS.

2. REFER TO DRAWINGS MP601, MP602, MP603 AND MP604 FOR SYSTEM FLOW

DIAGRAMS.

3. REFER TO DRAWINGS M-701, M-702, M-703 AND M-704 FOR EQUIPMENT

SCHEDULES.

4. CONTRACTOR SHALL SUBMIT A DETAILED LOCKOUT/TAGOUT PROCEDURE TO THE VA A

MINIMUM OF 4 WORKING DAYS PRIOR TO PERFORMING ANY WORK ON ANY LIVE

STEAM OR STEAM CONDENSATE SYSTEM.

5. ALL VALVE HANDLES MUST BE ACCESSIBLE FROM A WALKABLE SURFACE. COORDINATE

SCALE: 1 : 482 PIPING PLAN - STORAGE B-2, PHASE 3

R E

F

1 2 3 4 5 6 7 8

F

H

K

D

C

B

A

E

E1 E2 E3 E4 E5 E6 E7

J

G

13-FOM-1

CONTROL

ROOM

M-8

BOILER

ROOM

M-18

CONTRACTOR

TOUCHDOWN

M-6

TOILET

M-2

TOILET

M-1

PASSAGE

M-7

LOCKER

ROOM

M-3

EQUIPMENT

M-19

SHOWER

ROOM

M-4

BREAK

AREA

M-5

PHASE 2

REFER TO DRAWING

MP605 & MP606

FOR PIPING DETAILS

CONTROL

ROOM

M-8

REFER TO

2/MP101.03

FOR PIPING

(E)38HPS

TO BLDG 20

(E)32PC

FROM BLDG 20

(E)38HPS

FROM ABOVE

(E)32PC DOWN TO

EXISTING TRENCH.

REFER TO MD111.02 FOR CONTINUATION

REFER TO 2/MP101.03

FOR CONTINUATION

(E)254HPS

UP/DN

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ENGINEER OF RECORDCONSULTANTS

321 4 5 6 7 8 9 10

NO. DESCRIPTION DATE

PRINTS OF THIS DRAWING SHALL NOT BE USED FOR ANY PURPOSE

WHATSOEVER WITHOUT THE SEAL AND SIGNATURE OF THE

PROFESSIONAL ENGINEER

o n e e ig h th i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e i n c h o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t th re e i n c h e s o n e f o o t

MILLER-REMICK LLC

PROFESSIONAL ENGINEER

MR PROJECT NO:

NORTHKEYPLAN

HAZARDOUS MATERIALS

MABBETT & ASSOCIATES, INC.

105 CENTRAL STREET, STONEHAM, MA 02180

PHONE: (781)275-6050

CIVIL / STRUCTURAL

PROFESSIONAL ENGINEERING CONSULTANTS, P.A.

303 SOUTH TOPEKA, WICHITA, KS 67202

PHONE: (316)262-2691

ARCHITECTURAL

OCULUS INC.

1 SOUTH MEMORIAL DRIVE, SUITE 1500, SAINT LOUIS, MO 63102

PHONE: (314)367-6100

FIRE SUPPRESSION

KOFFEL ASSOCIATES

8815 CENTRE PARK DRIVE, SUITE 200, COLUMBIA, MD 21045

PHONE: (410)750-2246

ELECTRONIC SECURITY

MAGNA ENGINEERS

861 CORPORATE DRIVE, SUITE 210, LEXINGTON, KY 40503

PHONE: (859)309-2990

PHYSICAL SECURITY

FORCE PROTECT

3210 GULF BLVD, UNIT 304, BELLEAIR BEACH, FL 33786

PHONE: (502)836-4232

C U s e rs

\g s tr o h \D o c u m e n ts

\0 -0

-W ic h it a B o ile rs -M e tr ic M

E P

-C E

N T

R A

L -R g s tr o h Q

H E

Z

.r v t

/9

/2

:4

:1

A

M

13-MP111.03

MECHANICAL

PIPING PLAN

SHOP & MAIN LEVELS, PHASE 3

INSTALL NEW BOILERS IN

BUILDING 13

ROBERT J. DOLE VA MEDICAL CENTER

WICHITA, KANSAS

589A7-18-302

Project Director

2021-09-03 AP GDS0499-0121

100% BID SET

FULLY SPRINKLERED

SCALE: 1 : 481 PIPING PLAN - SHOP & MAIN LEVELS, PHASE 3

GENERAL SHEET NOTES:

SHEET KEYNOTES:

1 INSTALL NEW FUEL-OIL FILTRATION SKID. PROVIDE 152 HIGH CONCRETE HOUSEKEEPING PAD.

2 REFER TO MH SERIES DRAWINGS FOR GAS DETECTION SENSOR LOCATIONS.

1. REFER TO DRAWING M-001 FOR NOTES, SYMBOLS AND ABBREVIATIONS.

2. REFER TO DRAWINGS MP601, MP602, MP603 AND MP604 FOR SYSTEM FLOW

DIAGRAMS.

3. REFER TO DRAWINGS M-701, M-702, M-703 AND M-704 FOR EQUIPMENT

SCHEDULES.

4. CONTRACTOR SHALL SUBMIT A DETAILED LOCKOUT/TAGOUT PROCEDURE TO THE VA A

MINIMUM OF 4 WORKING DAYS PRIOR TO PERFORMING ANY WORK ON ANY LIVE

STEAM OR STEAM CONDENSATE SYSTEM.

H

K

D

C

B

A

E

E1 E2 E3 E4 E5 E6 E7

J

G

BOILER

ROOM

M-18

STORAGE

C-1

38HPS

38HPS

(E)254DIA. HPS DN.

(SOUTH TUNNEL)

PHASE 2

51HPS DOWN

REFER TO DRAWING

MP111.02 FOR CONTINUATION

(E)38HPS

TO BUILDING 12

(E)38PC

13-UH-11

13-UH-10

(E)38 PC DOWN

REF. MP111.03

ON MEZZ. PLATFORM

HUNG FROM ABOVE

19LPR

19HPS

25LPR (E)38HPS

PLATFORM ABOVE

CONTRACTOR

TOUCHDOWN AREA

(E)254HPS

13-AC-4

254HPS DOWN

13-UH-12

13-UH-13

32LPS

19LPS

19LPR

19LPG

32LPS 25LPR

19LPG

13-ACCU-4

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ENGINEER OF RECORDCONSULTANTS

321 4 5 6 7 8 9 10

NO. DESCRIPTION DATE

PRINTS OF THIS DRAWING SHALL NOT BE USED FOR ANY PURPOSE

WHATSOEVER WITHOUT THE SEAL AND SIGNATURE OF THE

PROFESSIONAL ENGINEER

o n e e ig h th i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e i n c h o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t th re e i n c h e s o n e f o o t

MILLER-REMICK LLC

PROFESSIONAL ENGINEER

MR PROJECT NO:

NORTHKEYPLAN

HAZARDOUS MATERIALS

MABBETT & ASSOCIATES, INC.

105 CENTRAL STREET, STONEHAM, MA 02180

PHONE: (781)275-6050

CIVIL / STRUCTURAL

PROFESSIONAL ENGINEERING CONSULTANTS, P.A.

303 SOUTH TOPEKA, WICHITA, KS 67202

PHONE: (316)262-2691

ARCHITECTURAL

OCULUS INC.

1 SOUTH MEMORIAL DRIVE, SUITE 1500, SAINT LOUIS, MO 63102

PHONE: (314)367-6100

FIRE SUPPRESSION

KOFFEL ASSOCIATES

8815 CENTRE PARK DRIVE, SUITE 200, COLUMBIA, MD 21045

PHONE: (410)750-2246

ELECTRONIC SECURITY

MAGNA ENGINEERS

861 CORPORATE DRIVE, SUITE 210, LEXINGTON, KY 40503

PHONE: (859)309-2990

PHYSICAL SECURITY

FORCE PROTECT

3210 GULF BLVD, UNIT 304, BELLEAIR BEACH, FL 33786

PHONE: (502)836-4232

C U s e rs

\g s tr o h \D o c u m e n ts

\0 -0

-W ic h it a B o ile rs -M e tr ic M

E P

-C E

N T

R A

L -R g s tr o h Q

H E

Z

.r v t

/9

/2

:4

:1

A

M

13-MP121.03

MECHANICAL

PIPING PLAN

EX CATWALK & CATWALK LVLS, PH 3

INSTALL NEW BOILERS IN

BUILDING 13

ROBERT J. DOLE VA MEDICAL CENTER

WICHITA, KANSAS

589A7-18-302

Project Director

2021-09-03 AP GDS0499-0121

100% BID SET

FULLY SPRINKLERED

SCALE: 1 : 481 PIPING PLAN - EXISTING CATWALK & CATWALK LEVELS, PHASE 3

GENERAL SHEET NOTES:

1. REFER TO DRAWING M-001 FOR NOTES, SYMBOLS AND ABBREVIATIONS.

2. REFER TO DRAWINGS MP601, MP602, MP603 AND MP604 FOR SYSTEM FLOW

DIAGRAMS.

3. REFER TO DRAWINGS M-701, M-702, M-703 AND M-704 FOR EQUIPMENT

SCHEDULES.

4. CONTRACTOR SHALL SUBMIT A DETAILED LOCKOUT/TAGOUT PROCEDURE TO THE VA A

MINIMUM OF 4 WORKING DAYS PRIOR TO PERFORMING ANY WORK ON ANY LIVE

STEAM OR STEAM CONDENSATE SYSTEM.

13-M-301

1 2 3 4 5 6 7 8

F

H

K

D

C

B

A

E

E1 E2 E3 E4 E5 E6 E7

J

G

13-M-301

13-GRV-7

PHASE 2

EXISTING

ROOF ACCESS HATCH

13-EF-3 13-EF-4

13-SF-4

13-SF-3

13-M-305

13-GRV-8

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ENGINEER OF RECORDCONSULTANTS

321 4 5 6 7 8 9 10

NO. DESCRIPTION DATE

PRINTS OF THIS DRAWING SHALL NOT BE USED FOR ANY PURPOSE

WHATSOEVER WITHOUT THE SEAL AND SIGNATURE OF THE

PROFESSIONAL ENGINEER

o n e e ig h th i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e i n c h o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t th re e i n c h e s o n e f o o t

MILLER-REMICK LLC

PROFESSIONAL ENGINEER

MR PROJECT NO:

NORTHKEYPLAN

HAZARDOUS MATERIALS

MABBETT & ASSOCIATES, INC.

105 CENTRAL STREET, STONEHAM, MA 02180

PHONE: (781)275-6050

CIVIL / STRUCTURAL

PROFESSIONAL ENGINEERING CONSULTANTS, P.A.

303 SOUTH TOPEKA, WICHITA, KS 67202

PHONE: (316)262-2691

ARCHITECTURAL

OCULUS INC.

1 SOUTH MEMORIAL DRIVE, SUITE 1500, SAINT LOUIS, MO 63102

PHONE: (314)367-6100

FIRE SUPPRESSION

KOFFEL ASSOCIATES

8815 CENTRE PARK DRIVE, SUITE 200, COLUMBIA, MD 21045

PHONE: (410)750-2246

ELECTRONIC SECURITY

MAGNA ENGINEERS

861 CORPORATE DRIVE, SUITE 210, LEXINGTON, KY 40503

PHONE: (859)309-2990

PHYSICAL SECURITY

FORCE PROTECT

3210 GULF BLVD, UNIT 304, BELLEAIR BEACH, FL 33786

PHONE: (502)836-4232

C U s e rs

\g s tr o h \D o c u m e n ts

\0 -0

-W ic h it a B o ile rs -M e tr ic M

E P

-C E

N T

R A

L -R g s tr o h Q

H E

Z

.r v t

/9

/2

:4

:4

A

M

13-M-131.03

MECHANICAL

NEW WORK PLAN

ROOF, PHASE 3

INSTALL NEW BOILERS IN

BUILDING 13

ROBERT J. DOLE VA MEDICAL CENTER

WICHITA, KANSAS

589A7-18-302

Project Director

2021-09-03 AP GDS0499-0121

100% BID SET

FULLY SPRINKLERED

SCALE: 1 : 481 MECHANICAL NEW WORK PLAN - ROOF, PHASE 3

GENERAL SHEET NOTES:

1. REFER TO DRAWING M-001 FOR NOTES, SYMBOLS AND ABBREVIATIONS.

2. REFER TO DRAWINGS MP601, MP602, MP603 AND MP604 FOR SYSTEM FLOW

DIAGRAMS.

3. REFER TO DRAWINGS M-701, M-702, M-703 AND M-704 FOR EQUIPMENT

SCHEDULES.

4. CONTRACTOR SHALL SUBMIT A DETAILED LOCKOUT/TAGOUT PROCEDURE TO THE VA A

MINIMUM OF 4 WORKING DAYS PRIOR TO PERFORMING ANY WORK ON ANY LIVE

STEAM OR STEAM CONDENSATE SYSTEM OR EQUIPMENT.

MAIN LEVEL

CATWALK LEVEL

UPPER ROOF -

LOW POINT

12060

FHK DJ G

13-GRV-2

254 DIA.

MAIN STEAM HEADER

76FWPD

76FWPD

203HPS 13-FHX-2

13-UH-2

76NG

152SV

152SV

38 FOS

38 FOR

76HPS

254 HPS

BYPASS LINE 38HPS

BOILER STACK

MIN. 3048 ABOVE ROOF.

51FWPD

DOUBLE CONE

RAIN CAP

NATURAL GAS

TRAIN VENTS

BOILER

ROOM

M-18

13-SF-1

(N)25SBO

609 DIA.

BOILER FLUE

STACK

19LPR

102PC

203HPS

6 (TYP.)

x

13-B-2

19LPS

SHOP LEVEL

TUNNEL LEVEL

-1829

INTERMEDIATE

ROOF PARAPET

MAIN LEVEL

CATWALK LEVEL

E5 E6

E7

51FOS

51FOR

EXISTING ROOF STRUCTURE

(E) 254 HPS

(E)152FIRE

NEW 101 PC

(E)CONDENSATE PUMP

(E)CONDENSATE RECEIVER

BREAK

ROOM

BATH

ROOM

EXISTING

PUMP ROOM

13-1

SHOP LEVEL

INTERMEDIATE

ROOF - HIGH

POINT

MAIN LEVEL

E3 E4

EQUIPMENT

M-19

13-SF-3

914x914

13-UH-12

19LPS

19LPR

SHOP LEVEL

INTERMEDIATE

ROOF - LOW

POINT

E3 E4

13-SF-4

914x914

EQUIPMENT

M-19

13-UH-1319LPS

19LPR

762Ø

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ENGINEER OF RECORDCONSULTANTS

321 4 5 6 7 8 9 10

NO. DESCRIPTION DATE

PRINTS OF THIS DRAWING SHALL NOT BE USED FOR ANY PURPOSE

WHATSOEVER WITHOUT THE SEAL AND SIGNATURE OF THE

PROFESSIONAL ENGINEER

o n e e ig h th i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e i n c h o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t th re e i n c h e s o n e f o o t

MILLER-REMICK LLC

PROFESSIONAL ENGINEER

MR PROJECT NO:

HAZARDOUS MATERIALS

MABBETT & ASSOCIATES, INC.

105 CENTRAL STREET, STONEHAM, MA 02180

PHONE: (781)275-6050

CIVIL / STRUCTURAL

PROFESSIONAL ENGINEERING CONSULTANTS, P.A.

303 SOUTH TOPEKA, WICHITA, KS 67202

PHONE: (316)262-2691

ARCHITECTURAL

OCULUS INC.

1 SOUTH MEMORIAL DRIVE, SUITE 1500, SAINT LOUIS, MO 63102

PHONE: (314)367-6100

FIRE SUPPRESSION

KOFFEL ASSOCIATES

8815 CENTRE PARK DRIVE, SUITE 200, COLUMBIA, MD 21045

PHONE: (410)750-2246

ELECTRONIC SECURITY

MAGNA ENGINEERS

861 CORPORATE DRIVE, SUITE 210, LEXINGTON, KY 40503

PHONE: (859)309-2990

PHYSICAL SECURITY

FORCE PROTECT

3210 GULF BLVD, UNIT 304, BELLEAIR BEACH, FL 33786

PHONE: (502)836-4232

C U s e rs

\g s tr o h \D o c u m e n ts

\0 -0

-W ic h it a B o ile rs -M e tr ic M

E P

-C E

N T

R A

L -R g s tr o h Q

H E

Z

.r v t

/9

/2

:4

:4

A

M

13-M-301

MECHANICAL

SECTIONS

INSTALL NEW BOILERS IN

BUILDING 13

ROBERT J. DOLE VA MEDICAL CENTER

WICHITA, KANSAS

589A7-18-302

Project Director

2021-09-03 MH GDS0499-0121

100% BID SET

FULLY SPRINKLERED

SCALE: 1 : 481 MECHANICAL SECTION @ BOILER 2

SCALE: 1 : 482 PHASE 2 - HPS CONNECTION TO SOUTH LOOP

GENERAL SHEET NOTES:

SHEET KEYNOTES:

1 COORDINATE ROUTING OF NEW FUEL OIL PIPING IN LOWER LEVEL WITH EXISTING CONDITIONS

AND ALL TRADES.

2 EXTEND EXISTING 102 CONDENSATE PIPE (PC) TO NEW PUMP ROOM. PIPING TO BE INSTALLED

IN PHASE 2. KEEP PIPE AS CLOSE TO WALL AS POSSIBLE, COORDINATE ROUTING WITH

EXISTING CONDITIONS.

3 GAS TRAIN VENTS UP THROUGH ROOF. VENTS MUST BE A MINIMUM OF 3048 FROM ANY

INTAKES. SIZE VENTS PER SCHEDULE ON DETAIL #2 ON DRAWING MP504.

4 REFER TO DETAIL 2 ON DRAWING M-504 FOR ADDITIONAL GAS TRAIN DETAILS.

5 REFER TO DETAIL 2 ON DRAWING M-502 FOR ADDITIONAL INFORMATION.

6 INSTALL NEW PIPE ANCHOR ATTACHED TO FOUNDATION WALL. REFER TO DETAIL 15 ON

STRUCUTRAL DRAWING S-502.

SCALE: 1 : 483 SECTION SUPPLY FAN DUCT RISER

SCALE: 1 : 484 SECTION - SUPPLY FAN DUCT RISER

1. REFER TO DRAWING M-001 FOR NOTES, SYMBOLS AND ABBREVIATIONS.

2. REFER TO DRAWINGS MP601, MP602, MP603 AND MP604 FOR SYSTEM FLOW

DIAGRAMS.

3. REFER TO DRAWINGS M-701, M-702, M-703 AND M-704 FOR EQUIPMENT

SCHEDULES.

4. CONTRACTOR SHALL SUBMIT A DETAILED LOCKOUT/TAGOUT PROCEDURE TO THE VA A

MINIMUM OF 4 WORKING DAYS PRIOR TO PERFORMING ANY WORK ON ANY LIVE

STEAM OR STEAM CONDENSATE SYSTEM OR EQUIPMENT.