C3. Questions & Answers from RFI Period 3_v062824.pdf

PDF 104 KB Posted

Attached to
General Construction of Land Port of Entry Facility GSA PBS Region 2 in Rouses Point, New York
Solicitation number
47PC0624R0001
Issued by

About this file

This document is a set of Questions and Answers related to a Request for Information (RFI) for a federal contract opportunity to construct a new Land Port of Entry (LPOE) facility in Rouses Point, New York.

The key details are:

  • The project scope includes construction of a 13,000 square foot LPOE building, site work, utility extensions, and construction of a railway platform system. Sustainability requirements include geothermal heating/cooling for a LEED Gold facility.
  • The contract will be awarded through a Best Value trade-off source selection process, with non-price factors significantly more important than price. Notable evaluation factors include sustainability, project labor agreements, and small business subcontracting.
  • The contract is anticipated to be a firm-fixed price award between $25-35 million, funded in part by the Inflation Reduction Act. Proposal submissions are due on June 12, 2024 by 5:30pm ET. Bid bonds and performance/payment bonds are required.
  • The federal agency involved is the General Services Administration, Public Buildings Service Region 2. This project is not a small business set-aside.

View the file

Other files

File Type Posted
C3. Questions & Answers from RFI Period 3_rev070124.pdf PDF
C5. 47PC0624R0001 Solicitation Rouses LPOE General Construction vJune2024.pdf PDF
C2. Attachment 5 - IRA Sustainability Factor Table_rev060524 w GSA weights.xlsx XLSX spreadsheet
C1. RFP Amendment 2_Latest Changes and Attachments.pdf PDF
C6. SF30 47PC0624R0001 RFP Amendment03 - acknowledge by signing and returning.pdf PDF
B4. 47PC0624R0001 Rouses GC_Reps and Certs GC v0424 (Form C301).docx DOCX document
B5. SF30 47PC0624R0001 RFP Amendment02 - acknowledge by signing and returning.pdf PDF
B10. Instructions to SAM Entities Trying to Request Controlled Docs Access rev051524.pdf PDF
B8. IRA Project Submittal_ Reporting Form (Reference Doc for Post-Award).xlsx XLSX spreadsheet
B1. RFP Amendment 2_ IRA link - Latest Changes - Table of Contents.pdf PDF
B6. Attachment 4 - IRA Weighted Score - addtl concrete_cement note added 053124.docx DOCX document
B3. 47PC0624R0001 Solicitation Rouses LPOE General Construction amend02_053124.pdf PDF
B11. Questions & Answers from RFI Period 2.pdf PDF
B9. IRA Project Submittal Form and Data Dictionary PDF.pdf (Reference Doc for Post-Award).pdf PDF
B7. Attachment 5 - IRA Sustainability Factor Table.xlsx XLSX spreadsheet
A4. Local Unions' Contact Information - Rouses Point, NY.pdf PDF
A2. SF30 47PC0624R0001 RFP Amendment01 - acknowledge by signing and returning.pdf PDF
A6. Rouses LPOE GC Contractor Deliverables Checklist_updated 8May2024.pdf PDF
A5. Instructions to SAM Entities Trying to Request Controlled Docs Access.pdf PDF
A1. Rouses GC RFP 47PC0624R0001 Amendment 01 table of contents - QA - Scope Considerations.pdf PDF
A3. SF1442 Corrected for 47PC0624R0001 v050824.pdf PDF
Pricing Proposal Attachments 47PC0624R0001.zip ZIP file
47PC0624R0001 Solicitation Rouses LPOE General Construction vApril2024.pdf PDF
47PC0624R0001 Rouses Point LPOE Proposals Checklist.xlsx XLSX spreadsheet
Technical Proposal Attachments 47PC0624R0001.zip ZIP file
47PC0624R0001 Rouses LPOE GC Draft Agreement vApril2024.pdf PDF
Reference Docs 47PC0624R0001.zip ZIP file
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions & Answers from RFI Period 3

QUESTIONS ANSWERS

1 After reviewing the specs for the DD & Micro piles, we did not see a Geotech report. Could you please provide this?

Preliminary Geotechnical report is provided in Bid Documents. Refer to “Scope Specs Drawings” folder > “Vol 4 Division 00 31 00 Available Project Information” folder > 2205 RP Preliminary Subsurface Investigation and Geotechnical Evaluation 2024 0229.

Do we still need to have completed Project Labor Agreements if we intend to subcontract the work through union workers or how does that work exactly?

PLAs are incentivized, but not mandatory for this RFP. You may identify subcontracting with union workers if you'd like, but you will not receive credit under the Factor for PLAs unless you set up a PLA. PLAs are not the same thing as claiming already-established collective bargaining agreements.

3 As a certified WBE for photography can I subcontract to a licensed drone operator who isn't a WBE?

We do not have any subcontracting restrictions specific to WBEs for this procurement. Depending on the context or intent, this question may be better suited for a contact at the Small Business Administration.

For the required on-site web cameras - is that the responsibility of the contractor?

Yes. Refer to Division 1 Specifications.

What is the duration of the project?

The period of performance is specified in the RFP's Draft Agreement page 5 of 53, section I.C. Period of Performance. The total duration is estimated to be 700 calendar days. Please see the chart in this document that breaks down the two phase durations.

Are you expecting color or black and white prints (size x 10?) for documentation?

RESPONSE TO BE ADDED 6/1-2/2024

Please confirm the requirement for the AISC Certified with the Sophisticated Paint Endorsement *SPE-P1) can be switched to "SSPC QP3" which is equivalent.

It is acceptable to modify 051200-1.5.D as follows: “The Fabricator shall be AISC certified with the Certificate for Shop Application of Complex Protective Coating Standards (AISC 420-10 /SSPC-QP 3) and must submit proof of this endorsement."

The Finish for room 134 Mothers Wellness, Can you confirm that the finish plane on AE405 (calls out Tile Floor/wall) is correct and not the finish schedule on AE501 (Calls out Carpet Tile & Paint).

Finish schedule on AE501 is correct.

Elevations of room #134 on AE405 are incorrect.

In the TPO spec section 075423, part 2.2 K & L, it indicates insulation with 7/16” OSB as well as the ½” gyp cover board that appears in the details. The OSB does not seem to be shown in the details. Please advise if the intent is for one or the other, or both?

Intent is for ½” gypsum cover board per details. Amendment #3 removes 7/16” OSB from specification section 075423.

Please specifically explain who is responsible for collecting additional subsurface information from the areas where the displacement piles are to be installed and when this will be done relative to contract award.

The contract documents indicate that the owner will be doing this.

The borings provided are on the other side of the building from the work area for the piles. One of the available borings showed a cobble at 26-ft. Cobbles, boulders and obstructions need to be clearly identified for displacement piles due to most drill methods not being able to

The government is responsible for additional geotechnical borings and analysis. The target schedule for completing this work is January, 2025. The Phase 2 NTP will not be issued until this work has been completed and any potential construction impacts have been accounted for.

penetrate obstructions.

The specification for the displacement piles combines installation methods from displacement piles and other types of micropiles (for example, tremie grouting and pressure grouting do not apply to the specified pile type). Please confirm the owner's engineers understand the pile contractors will not be able to follow all items outlined in this specification and all details will be clarified in the submittal process.

It is structurally acceptable for the contractor to provide drilled displacement piles or traditional micropiles, provided that all of the performance requirements stated in the contract documents are met.

Contractor will submit their proposed installation methods as part of the submission process for team review.

Bidder's comment is noted and understood.

Will the delegated design engineer for the displacement piles be permitted to specify the load testing instrumentation appropriate for the submitted pile? For example, vibrating wire strain gauges and non-destructive integrity testing do not apply to typical micropiles or displacement piles and will add unnecessary cost and time to the project.

It is structurally acceptable for the contractor to propose alternate load testing instrumentation appropriate for their proposed pile design. The quantity of load tests and the specified acceptance criteria shall be maintained.

The finish schedule calls for CF-18 in the connector walkways which is "Fiber Cement Board".

Detail 1/AE114 does not seem to show this fiber cement board, and there are no other details showing how this board is installed or where. Please confirm the finish of the connector walk way ceilings.

No ceiling along Inbound #143 and Outbound #144 Connector. Acoustic metal deck is exposed from the underside. Fiber Cement board ceiling occurs just outside doors D143A and D144A as a part of the Connector Vestibule. Refer to Amendment #2 sheets AE603, AE604, AE605, AE606.

Is there a spec for the bullet resistant fiberglass wall panels?

There is no standalone spec and the gypsum spec does not mention it.

Refer to revised spec 092900 Gypsum Drywall, submitted as a part of Amendment #3, for bullet resistant fiberglass wall panels.

15 Are equal substitutions allowed for the EV charging stations? Yes.

Per section 099000 Painting and Finishing

1.2 Section Includes 7

Mechanical painting exposed to view. Are Mechanical/Electrical rooms considered exposed to view and require mechanical items to be painted?

Mechanical items in the following rooms are not painted: Mechanical #120, Vestibule #120A, Emergency Electrical #123, DEMARC #121, SLAN #119, and

LAN #118.

Questions & Answers from RFI Period 2 pertaining to Base Contract and Option 3 stating that the overhead electric and telecomm utilities are by this contract. The electrical one line diagram on sheet E700 indicates that this work is to be done by the Village of Rouses Point Utility.

Please clarify that this work is not part of the electrical scope but will be provided by the Village of Rouses Point. Also please advise if the cost for the work performed by the Village of Rouses Point is to be included in the electrical scope.

Base Contract overhead electric and telecom utilities and Option 3 for underground utilities described in Phase 1 Civil drawings are a part of the Contract Scope of Work. Any work performed by the Village of Rouses Point is not to be included in Contract Scope of Work.

Dashed line in Drawing E700 separating GSA LPOE Electrical Service from Village of Rouses Point, the electric utility, is to indicate final ownership and maintenance responsibility for these elements.

Contractor responsibilities are as outlined as follows: • Contractor is responsible for telecom utility and pathway. Refer to 01 / TN-801 and Civil drawings for telecom utility requirements.

• Contractor is responsible for electric utility and pathway. Refer to Amendment #3: C 150, C151, Amendment #2: C-152, and Bid Documents C-154.

• Village of Rouses Point, the electric utility, will provide a transformer, at no cost to the project, and will provide the final connection between utility run (by Contractor) and transformer’s primary side. Contractor is responsible for the transformer's secondary side connection to building electrical infrastructure.

• Contractor is responsible for procuring and installing Village approved utility meter.

• Village of Rouses Point, the electric utility, is responsible for the final utility connection at the existing electrical pole at the intersection of Route 2 (Bridge St.) and Route 11.

Drawing GI001 indicates lightning Protection is by the CBP/Contracted vendor. The only lightning protection shown on the roof plans is on the Primary Inspection Canopy metal roof on Electrical drawing E101. Is there any lightning protection going on the Main Building TPO roof that would require TPO flashings by the roofing subcontractor, or is all the work by the lightning protection vendor? If TPO flashings by the roofing subcontractor are required, where are they located, what type and what details are to be used?

There is no lightning protection going on the Main Building TPO roof. GI001 lightning protection is referring to grounding for CBP’s TACCOM radio antennas. Radio antenna grounding pathway is by Contractor. Grounding kit is by CBP Contracted vendor.

ESE (Early Steamer Emission) lighting protection design is used for this building.

The ESE system requires one ESE Mast and utilizes the steel canopy in lieu of down conductors as shown. The system provides lightning protection coverage for the entire site, no additional lighting protection required on the main building.

CBP Contracted Vendor to provide connection of TACCOM radio antennas, to be grounded to a busbar in the CBP LAN room 118 via conduit penetration at the roof with #2 AWG down conductor with 1” conduit and connect to ground busbar in CBP LAN Room 118.

Are roof copings to be .063 aluminum as per spec 077100, or are they painted stainless steel as indicated in the details and spec 076200?

Main building roof coping to be .063” aluminum per Specification Section 077100.

Is the TPO roof system on the Main Building and the three vestibule canopy roofs to have a ½” gypsum ‘DensDeck Prime’ coverboard as shown in most section details, or is the insulation to have a 7/16” OSB on top? Section 075423 part 2.2 K &L indicate both the Gyp and the OSB. Please clarify the

Refer to RFI #9 Response.

makeup of the TPO roof system.

Will the Solar Panel Array have any penetrations through the TPO roof requiring them to be flashed into the TPO roof system? If so, where and what details?

Solar Panel Array is ballasted system.

Refer to Specification Section 263100 Photovoltaic Systems specification included in Amendment #3.

Is there a roof plan that will be provided for the TT vestibule roof canopy?

Yes, refer to revised #26 / AE600 in Amendment #3.

On drawing AE530, at the Typical Mechanical Equipment Curb detail 4/AE530, what is the ‘D’ shaped protrusion above the two-part counter flashing representing?

Refer to revised AE530 in Amendment #3.

Mechanical Equipment Curb flashing detail has been revised.

Do the ballasted solar panel array bases have protection on the bottom of the bases, or will sacrificial TPO slips sheets be required on the TPO roof membrane?

TPO slip sheet to be provided below PV ballasts. Refer to revised Specification Section 075423 in Amendment #3.

In detail 3/AE530 at the Fall Arrest Anchor Posts, are pitch pockets required as shown, or are TPO pipe flashings acceptable to flash in the 70 posts indicated?

TPO pipe flashings are acceptable.

Is there a separate Electrical Spec section for the Electronic Leak Detection for the TPO roof system, or just what is shown in TPO spec section 075423 part 3.3?

There is no separate electric specification for the Electronic Leak Detection.

Please confirm that the inspection canopy box columns, plate girders, box beams, beams, and tapered beams are Galvanized and do not have the requirement for AESS. There is a lot of AESS requirements on Galvanized material. During the galvanizing process welds can swell, and galvanizing can look "runny". Wanted to bring this to the design team's attention as the galvanizing can affect AESS material.

The inspection canopy box columns, plate girders, box beams, beams, and tapered beams do not have AESS requirements.

However, the fascia plate shown on 2&3/S624 is AESS 3. Additionally, HDG AESS material is specified for both the connector bridge and train canopy structures per the Contract Documents.

The steel fabricator shall take care to minimize the effects of the galvanizing process on AESS welds to achieve the design intent. Refer to recommendations provided by the American Galvanizers Association, including the removal of welding slag, flux residues, and welding sprays prior to galvanizing as well as careful selection of compatible low silicon weld electrode material. Fabricator shall consider these approaches as part of the AESS samples required to be submitted to the design team prior to fabrication.

The steel fabricator and galvanizer shall adequately prepare the surface of the galvanized members to receive high performance finish coating per the project specifications. Final surface shall be smooth in accordance with AESS 3 requirements. Refer to recommendations provided by the American Galvanizers Association for preparing galvanized surfaces for high performance finish coating.

Regarding the TPO spec 075323 part 3.3 for the testing procedures, please show in the details the Electric Field Vector Mapping (EFVM) with the stainless-steel grid below the

Refer to AE530 revised in Amendment #3.

TPO membrane? Also, It is not indicated in any of the details in the drawings, nor in the products or installation section of the TPO spec. Please clarify.

In TPO spec section 075423 the entire roof assembly is adhered on the wood deck. It indicates a 20 year warranty with 107 mph wind speed design. I’ve reached out to some of the Manufacturer’s regarding the system. They will warrant the roof up to 90 mph with the vapor barrier adhered on the porous wood deck. To get the 107 mph wind design, which would be a 120 mph system from the manufacturer’s, would mechanically attaching the base layer of insulation be acceptable in order to get the increased wind warranty?

107 mph is the “basic wind speed, V” not V-asd (allowable stress design). V_asd =

82.9 MPH for the building. Refer to S012

“main building component and cladding wind pressures on flat roofs” for pressure requirements. Refer to revised Specification Section 075423. An asphaltic base sheet to be included in roof assembly.

Vapor barrier, insulation, coverboard and TPO membrane all to be adhered.

Spec 131200 for the prefabricated booths indicate the booths with .045 EPDM on the roof. Wall sections on AE125 show TPO roofs with additional parapet wall extensions added to the pre-fab booths and flashed in with TPO flashings and stainless steel flashings. Please clarify if TPO or EPDM will be on the roofs and if this is to fall under the TPO spec section for warranties?

Prefabricated booths to have TPO. Refer to revised Specification Sections 075423 and 131200 included in Amendment #3.

Please clarify the make-up of the wall system in details 9,10/AE125 at the inspection booth parapets?

It appears to show plywood walls but is not indicated, and it appears to show the outside of the parapet skinned with flashing all the way up the parapet, but the flashing in detail 11/AE123 only appears to go up about 8.5”.

Is the outside skinned with the ¼” ballistic resistant steel panel, or a painted stainless steel sheet metal flashing per spec 076200?

Outside is skinned with ¼” thick steel sheet panel over AWB membrane. Parapet framing is 14-ga. mechanical tube. Refer to revised AE125 in Amendment #3.

Detail 03/AE605 shows the fascia from the upper connector roof tying into the coping of the vestibule roof, is that correct?

Fascia does not tie into coping of roof below. Refer to Amendment #2 Detail #3 on

AE605.

Solar panel arrays on warrantied membrane roofs will have waivers from the roof membrane manufacturer about removing and reinstalling the solar array if needed for roof inspection/repairs during the warranty period. Is there a solar panel spec to review to see that it is included as part of the solar panel array system?

Refer to Specification Section 263100 included in Amendment #3.

On the drawings, the camera count is different from the quantities listed on the single line diagram.....should the counts go by drawings or single line diagram?

Refer to revised TY drawings included in Amendment #3.

The legend provided in the drawings does not match the cameras needed on the drawings. Can you provide a better legend and proper placement for each camera? For instance, there are multiple cameras labeled as C1 that can either de an exterior or interior camera. These should be labeled separately for example C1-Indoor Dome, C2-Exterior Dome,etc...

Refer to revised TY drawings included in Amendment #3.

The specifications reference using a Vicon NVR, yet later in the specifications, it references adding a Bosch NVR to work with existing Bosch VSS. Which manufacture should be proposed?

Refer to revised Specification Section 282000 included in Amendment #3.

37 Are there any specifications for the Intercom System to be used?

Refer to revised Specification Section 281000 included in Amendment #3.

38 Are there any specifications for the microphone to be used?

Refer to revised Specification Section 282000 included in Amendment #3.

39 What is the due date for the

RFP?

This amendment extends the RFP due date to July 8th, 2024, timestamped no later than 5:00 PM EST.

The single pole 70 amp breaker shown in panel E-PNB-L-W-1 is not available with LSIG trip. Can we quote a standard thermal magnetic breaker?

Ground fault protection is not required for this breaker; however, electronic trip adjustment is recommended to achieve selective coordination. Please provide selective coordination report to indicate coordination can be achieved with thermal magnetic breaker. Refer to revised single line diagram on E700 included in Amendment #3.

There are several main circuit breakers and feeder breakers with LSIG trip units. There may be a possibility that the ground faults will fight each other. Can these trips be changed to LSI?

Yes, LSIG is only required at the main switchboard E-SWB-H-1. For equipment downstream of E-SWB-H-1 indicated with LSIG trip units, provide LSI trip units instead. Refer to revised single line diagram on E700 included in Amendment #3.

On sheet labeled Base & Five Options on the price proposal workbook, items are structured so that IRA Funded Items are Separated from Non-IRA Funded Items;

Is it acceptable to provide the total value for the bid item and then provide a breakout cost of the acquisition and installation of LEC Materials, in lieu of them summing as currently shown?

Please provide a breakdown of all acquisition and installation of LEC materials as well as the sums currently shown in the pricing proposal sheet. GSA is required to follow this CLIN structure in showing IRA-funds use by the type of LEC materials, so we cannot remove that format.

The train platform specifies 8” hollow core plank, it is not recommended by subcontractors to use hollow core plank in exterior applications such as this because the voids will collect water, freeze, and blow the bottoms off the planks – ending up with having to replace the entire deck. They recommend 8” solid planks instead. Please advise.

The concern is noted. Documents have been revised in Amendment #3 for 8" solid precast planks at the train platform in lieu of hollow-core plank.

The precast wall panel specification calls for 10% of the cement in the mix be replaced with glass pozzolan which is a material not used in this market area, and it also specifies a long list of testing requirements that is not normally dealt with in this

The design mix can be altered. Contractor must still meet the IRA low embodied carbon concrete requirements for the project. Contractor to determine how to meet IRA low-embodied carbon requirements along with the other performance requirements of the material.

area under section 1.9

PERFORMANCE

REQUIREMENTS. Please advise if this design mix/testing can be altered.

Testing requirements cannot be altered.

Looking at the Watermain work in Phase 1, there is not any inline water valves on either the Fire Protection Line or the Domestic watermain. A minimum of 2 valves will be added do to phasing and testing, and the subcontractor recommends, at a minimum, a valve every 1,000LF on the fire line, and 1,500LF on the domestic water. Please advise if the intent of the design was to have valves in these lines.

Refer to revised C150 and C151 included in Amendment 3.

Dwg. C-500, detail 17 explains “ Bollards protecting buildings must be rated M-50 at a minimum”, Dwg. AS-103 the bollard schedule states location – Building - M40 rating. Please advise which was the intent.

Bollards are rated per AS103. C500 has been revised in Amendment #3.

L500 Shows a different detail for the rubber nugget steel edging than that of the 1/AE114. Please advise which detail takes precedence?

L500 takes precedence. #1 on AE114 has been revised in Amendment #3.

1A/L500 also references “Type B” edging at connector. Can you confirm what “Type A” is? Can you confirm extents of steel edging? Is it only at the connecting walkway, or is it at perimeter of all rubber nuggets?

Type A is the typical rubber nugget edge detail found throughout the project site and includes a ½” thick steel plate ¾” above grade. Type B steel edging detail extents are per L100.

49 Is there a spec for the raised Specification provided in Section 131200.

rubber (anti-fatigue, FF-14) mats in the guard booths?

50 Is there a spec for the bullet resistant fiberglass wall panels? Refer to RFI #14 response.

Question from an electrical contractor and submitting a subcontract bid; The specifications show that the contractor is responsible for NYSEG power installation charges (if any). I have reached out to utility company, and they need the NYSEG Service Notification Number to look up this project. They stated that the number starts with 1030. Would it be possible to get this NYSEG Service Notification Number?

NYSEG is not the service provider for utilities. The electric utility provider is the Village of Rouses Point, 139 Lake Street, PO Box 185, Rouses Point, NY 12979;

under account number 757-0.

Vicon Vax is strict in this project, I do not see it stating equal but maybe worth the ask if we can provide another type of access control. Johnson Controls Incorporated has 23 different options. We can cover everything seeing stating Vicon I wanted to ask if possible to provide anything else.

Vicon VAX is not intended for Access Control System. Access control to be HSPD-12/FIPS-201 compatible. This URL lists FIPS approved systems:

https://www.idmanagement.gov/fips201/.

“PACS Infrastructure” column downloads a PDF with approved components of that particular ACS system. Revised Specification Section 281000, issued as a part of Amendment #3, provides three acceptable manufacturers.

Is this project a small business set aside as it pertains to the general contractor or does the GC have to solicit certified small businesses as subcontractors and suppliers?

This project is not a small business set-aside and we are open to potentially awarding a contract with a large business.

Please see the factor that speaks to a Small Business Subcontracting Plan in the solicitation. Large businesses are required to submit one of these plans with their proposals.