B11. Questions & Answers from RFI Period 2.pdf

PDF 92 KB Posted

Attached to
General Construction of Land Port of Entry Facility GSA PBS Region 2 in Rouses Point, New York
Solicitation number
47PC0624R0001
Issued by

About this file

This document contains Questions and Answers from the Request for Information (RFI) period for the solicitation 47PC0624R0001 for the General Construction of a new Land Port of Entry (LPOE) Facility in Rouses Point, New York.

The key details are:

  • The solicitation is for a qualified General Contractor to provide full construction services for a new LPOE facility at the U.S.-Canada border in Rouses Point, NY. The project scope includes constructing a 13,000 square foot main LPOE building, site work, utilities, and a railway platform system.
  • The project will be funded in part by the Inflation Reduction Act of 2022 and the estimated total contract value is between $25-35 million.
  • Proposals are due by 5:30pm ET on June 12, 2024. A pre-proposal conference and site visit will be held on May 15, 2024.
  • The solicitation will use a Best Value Trade-Off source selection method, with non-price factors being significantly more important than price. Key evaluation factors include sustainability, project labor agreement, and small business subcontracting.
  • The document also addresses specifics on micropile design, buy American requirements, joint details, and other technical clarifications requested during the RFI period.

View the file

Other files

File Type Posted
C3. Questions & Answers from RFI Period 3_rev070124.pdf PDF
C3. Questions & Answers from RFI Period 3_v062824.pdf PDF
C5. 47PC0624R0001 Solicitation Rouses LPOE General Construction vJune2024.pdf PDF
C2. Attachment 5 - IRA Sustainability Factor Table_rev060524 w GSA weights.xlsx XLSX spreadsheet
C1. RFP Amendment 2_Latest Changes and Attachments.pdf PDF
C6. SF30 47PC0624R0001 RFP Amendment03 - acknowledge by signing and returning.pdf PDF
B4. 47PC0624R0001 Rouses GC_Reps and Certs GC v0424 (Form C301).docx DOCX document
B5. SF30 47PC0624R0001 RFP Amendment02 - acknowledge by signing and returning.pdf PDF
B10. Instructions to SAM Entities Trying to Request Controlled Docs Access rev051524.pdf PDF
B8. IRA Project Submittal_ Reporting Form (Reference Doc for Post-Award).xlsx XLSX spreadsheet
B1. RFP Amendment 2_ IRA link - Latest Changes - Table of Contents.pdf PDF
B6. Attachment 4 - IRA Weighted Score - addtl concrete_cement note added 053124.docx DOCX document
B3. 47PC0624R0001 Solicitation Rouses LPOE General Construction amend02_053124.pdf PDF
B9. IRA Project Submittal Form and Data Dictionary PDF.pdf (Reference Doc for Post-Award).pdf PDF
B7. Attachment 5 - IRA Sustainability Factor Table.xlsx XLSX spreadsheet
A4. Local Unions' Contact Information - Rouses Point, NY.pdf PDF
A2. SF30 47PC0624R0001 RFP Amendment01 - acknowledge by signing and returning.pdf PDF
A6. Rouses LPOE GC Contractor Deliverables Checklist_updated 8May2024.pdf PDF
A5. Instructions to SAM Entities Trying to Request Controlled Docs Access.pdf PDF
A1. Rouses GC RFP 47PC0624R0001 Amendment 01 table of contents - QA - Scope Considerations.pdf PDF
A3. SF1442 Corrected for 47PC0624R0001 v050824.pdf PDF
Pricing Proposal Attachments 47PC0624R0001.zip ZIP file
47PC0624R0001 Solicitation Rouses LPOE General Construction vApril2024.pdf PDF
47PC0624R0001 Rouses Point LPOE Proposals Checklist.xlsx XLSX spreadsheet
Technical Proposal Attachments 47PC0624R0001.zip ZIP file
47PC0624R0001 Rouses LPOE GC Draft Agreement vApril2024.pdf PDF
Reference Docs 47PC0624R0001.zip ZIP file
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions & Answers from RFI Period 2

47PC0624R0001 Amendment 02

QUESTION GSA ANSWER

As a subcontractor, we need to solicit the firms that are pursuing this project as a Prime GC. Is it possible to see the sign-in sheet for the recent project walk through that was hosted?

Yes, please email Sonah.Lee@gsa.gov directly to request this information.

Specification Section 316600.2.2.G.2: Please confirm the appropriate Buy America(n) provision for the project. It is our understanding that the micropiles installed for a government project shall require prime mill certifications for the steel.

Please see section I.V.F. of The Solicitation 47PC0624R0001 that provides the reference to FAR 52.225-12 Notice of Buy American Requirement-Construction Materials Under Trade Agreements (May 2014).

Drawing S002, note FN-1. Identifies the foundation design is based on preliminary geotechnical investigation… Based on the preliminary geotechnical report the subsurface conditions at the locations of the contractor designed micropiles have not been identified. Please provide what subsurface information/test boring data should be utilized for the micropile pricing.

Assume the geotechnical borings provided with the contract documents represent the geotechnical conditions at the location of the piles. Additional borings and geotechnical analysis will be performed post-construction contract award, in order to validate the assumed geotechnical engineering properties used for design. Any required design engineering or scope adjustments will be completed prior to the issuance of the Phase 2 Notice to Proceed.

Drawing S002, note FN-2. Can you confirm that the 60 ton capacity is 60 ton ultimate (so 30 ton design) compression and 45 ton ultimate uplift (22.5 ton design)?

Per S002 note FN-2 and 3/S202, the pile capacities and characteristics stated are all service-level. Service-level forces are unfactored forces. That is equivalent to the bidder's question of "design" forces. Service level is defined in note GR-1 on S002.

Specification Section 316600 – Drilled Displacement Micropiles, identifies the basis of design is a “STELCOL” by IDEAL Group.

Are other Micropiles allowed to be substituted for a “STELCOL” pile, (i.e.

conventional drilled pressure grouted micropiles) providing the piles meet the pile capacities on Drawing S002, note FN-2.

Yes, it is acceptable to substitute a drilled displacement micropile with a conventional drilled and grouted micropile, provided that it provides equivalent strength and stiffness as the basis of design pile characteristics stated on S002 note FN-2.

Are there any working restrictions adjacent to the railroad tracks, such as fowl distance, work hours, flaggers, etc. Please provide railroad restrictions if applicable.

Contract documents require contractors to account for construction requirements that may have specific railroad safety considerations. Contractor to comply with Canadian National Railroad safety requirements.

Specification Section 316600.3.8.A & D:

Industry standard for pile location deviation is 3-inches. The structural engineer should confirm this deviation for the pile locations.

3" maximum plan deviation in the pile is acceptable.

The finish schedule references Room #128 East Corridor, however I don’t see it labeled on the finish drawings. I believe it to be the long corridor in the Main Building as the Vestibule that meets it to the left is 128A but want to be certain. Can you confirm room # 128 East Corridor for us?

Correct. East Corridor #128 is long corridor on east side of Main Building directly north of Vestibule #128A. Refer to #1 on AE100, included as a part of Amendment #2 clouded drawings, which provides room tag for East Corridor #128.

Can a section view of the heavy duty concrete on either side of a curb be provided? Similar to detail 18/C500 but for the heavy duty concrete areas in the lanes. I am trying to identify the joint between concrete road to curb to median area.

Yes. Refer to #25 on C500, included as a part of Amendment #2 clouded drawings, which provides heavy duty concrete to curb detail.

Please clarify if Contractor is required to include costs for wetland bank credits. If so, please provide required quantity along with listing of approved wetland banks and contacts so we can obtain pricing information.

Contractor is not required to include the cost of wetland bank credits. Wetland mitigation is not included in the contract scope.

Please reference The Solicitation Part II.E.

Other Information to Submit with Proposal.

This section references form C301 and identifies that Offeror may request this form from the Contracting Officer. Please provide this form so we can review and submit with our proposal as instructed.

Form C301 is now attached to this amendment posting.

Reference excel pricing spreadsheet titled "Rouses LPOE GC Pricing Sheet": Please confirm if the costs for options #1 - #5 are NOT to be included in the Base Contract Total. Confirm if the options are intended to be additional costs above and beyond the Base Contract Total.

Options are additional costs beyond the Base Total. Separate total sums should auto-populate for each Option CLIN under the second tab and are formulaicly linked to also appear for auto-summing on the cover tab "Totals Overview & Options Rates."

Regarding final bid submittal for Price Proposal, please clarify if we are required to submit the actual excel file of the Pricing sheet or if the contents of this sheet should be made into a .pdf

You are required to submit the actual excel file. The accuracy of calculations and the integrity of all formulas will be verified, so please ensure to check there are no errors in your file.

Please confirm that Base Contract costs are to include installation of electric and telecommunications utilities overhead.

Confirmed. That is a correct interpretation of the Base Contract requirement.

If Base Contract includes installation of electric and telecommunications utilities overhead, please confirm if Pricing Option 3 is meant to include only the additional cost to install the utilities underground.

Confirmed. That is a correct interpretation of the Contract Option requirement.