This document is Amendment No. 2 to Solicitation 47PC0624R0001 for the General Construction of a Land Port of Entry (LPOE) Facility in Rouses Point, New York. The amendment reiterates requirements related to the Inflation Reduction Act (IRA), including the need to consult material requirements websites and use the IRA Weighted Score form. It extends the proposal deadline to July 2, 2024, opens a third round of questions through June 13, 2024, and provides updated contact information. The amendment also incorporates additional details on possible IRA-related expenses for concrete, reinforcing steel, formwork, and emerging/sustainable technologies. Several new attachments are added, including the IRA Sustainability Factor Table and IRA Project Submittal Form. The overall solicitation is for the construction of an approximately 13,000 square foot LPOE facility, which will include vehicle inspection capabilities, a railway platform, and utility work. The project is significantly funded through the IRA and has a construction value between $25-35 million. Proposals are due by June 12, 2024.

View the file

Other files

File Type Posted
C3. Questions & Answers from RFI Period 3_rev070124.pdf PDF
C3. Questions & Answers from RFI Period 3_v062824.pdf PDF
C5. 47PC0624R0001 Solicitation Rouses LPOE General Construction vJune2024.pdf PDF
C2. Attachment 5 - IRA Sustainability Factor Table_rev060524 w GSA weights.xlsx XLSX spreadsheet
C1. RFP Amendment 2_Latest Changes and Attachments.pdf PDF
C6. SF30 47PC0624R0001 RFP Amendment03 - acknowledge by signing and returning.pdf PDF
B4. 47PC0624R0001 Rouses GC_Reps and Certs GC v0424 (Form C301).docx DOCX document
B5. SF30 47PC0624R0001 RFP Amendment02 - acknowledge by signing and returning.pdf PDF
B10. Instructions to SAM Entities Trying to Request Controlled Docs Access rev051524.pdf PDF
B8. IRA Project Submittal_ Reporting Form (Reference Doc for Post-Award).xlsx XLSX spreadsheet
B6. Attachment 4 - IRA Weighted Score - addtl concrete_cement note added 053124.docx DOCX document
B3. 47PC0624R0001 Solicitation Rouses LPOE General Construction amend02_053124.pdf PDF
B11. Questions & Answers from RFI Period 2.pdf PDF
B9. IRA Project Submittal Form and Data Dictionary PDF.pdf (Reference Doc for Post-Award).pdf PDF
B7. Attachment 5 - IRA Sustainability Factor Table.xlsx XLSX spreadsheet
A4. Local Unions' Contact Information - Rouses Point, NY.pdf PDF
A2. SF30 47PC0624R0001 RFP Amendment01 - acknowledge by signing and returning.pdf PDF
A6. Rouses LPOE GC Contractor Deliverables Checklist_updated 8May2024.pdf PDF
A5. Instructions to SAM Entities Trying to Request Controlled Docs Access.pdf PDF
A1. Rouses GC RFP 47PC0624R0001 Amendment 01 table of contents - QA - Scope Considerations.pdf PDF
A3. SF1442 Corrected for 47PC0624R0001 v050824.pdf PDF
Pricing Proposal Attachments 47PC0624R0001.zip ZIP file
47PC0624R0001 Solicitation Rouses LPOE General Construction vApril2024.pdf PDF
47PC0624R0001 Rouses Point LPOE Proposals Checklist.xlsx XLSX spreadsheet
Technical Proposal Attachments 47PC0624R0001.zip ZIP file
47PC0624R0001 Rouses LPOE GC Draft Agreement vApril2024.pdf PDF
Reference Docs 47PC0624R0001.zip ZIP file
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment no. 2 of solicitation 47PC0624R0001 is being issued to

1. Reiterate attention to IRA-related requirements noted in the solicitation:

a. Materials Requirements website and links for each LEC material that need to be consulted for a response to Factor 5 - Sustainability, page 21 of 53 of The Solicitation:

https://www.gsa.gov/real-estate/gsa-properties/inflation-reduction-act/lec-program -details/material-requirements#asphalt

b. See the Attachment 4 IRA Weighted Score form. The following updated information has been added for clarification regarding concrete vs cement weights for evaluation: There is no LEC Materials Evaluation Weight is specifically assigned to Concrete, but offerors may consider the weight assigned to Cement as equivalent. In the event an offeror cannot submit an environmental product declaration (EPD) for concrete that meets GSA’s global warming potential (GWP) limits, the alternative is to submit an EPD to meet the GWP limits for cement. Also note that a new attachment is being added to this solicitation that pairs with Attachment 4, the IRA Sustainability Factor Table.

And incorporate the following changes, highlighted in yellow in The Solicitation:

2. The deadline for submission of proposals is being extended to Tuesday July 2nd, 2024, no later than 5:00 pm EST.

3. A third RFI period to receive contractor questions is now open through Thursday June 13th, 2024. Answers will not be collected by email. In order to ensure GSA captures all questions, please submit yours via this Google form link:

https://forms.gle/YoHFiNSFkW6wDu3r9

4. Please email CS Allan.Preston@gsa.gov along with the CO Sonah.Lee@gsa.gov on all contracting matters. Allan Preston is now the Contract Specialist in support of this project as Sonah Lee still remains as the Contracting Officer.

5. The Solicitation Page 14 of 53, which includes the following list of possible Low-Embodied Carbon (LEC) Materials and Emerging and Sustainable Technology (EST) expenses, which is not exhaustive. The highlighted additional bullets are now incorporated as part of this amendment:

Concrete

● Cost of submittals preparation

● Reinforcing steel, incl. Shop drawings, fabrication, delivery, installation

● Formwork, formwork erection, takedown, handling, and accessories.

47PC0624R0001 Amendment 02 https://www.gsa.gov/real-estate/gsa-properties/inflation-reduction-act/lec-program-details/material-requirements#asphalt https://www.gsa.gov/real-estate/gsa-properties/inflation-reduction-act/lec-program-details/material-requirements#asphalt https://forms.gle/YoHFiNSFkW6wDu3r9 mailto:Allan.Preston@gsa.gov mailto:Sonah.Lee@gsa.gov

● Concrete joints, joint assemblies, and sealants

● Concrete admixtures, curing compounds and materials, bonding agents

● Concrete finishing and polishing

● Lightweight concrete topping

● Testing and inspections

● Embedded conduits serving IRA Emerging and Sustainable Technologies

● equipment (in accordance with electric vehicle supply equipment (EVSE)

● Guidance)

● Precast concrete products

● Concrete Masonry Units (CMU)

The following new attachments are incorporated into the RFP:

B2. Amendment 02 of Specifications, Drawings, Sketches and Wetland Impacts.

B3. 47PC0624R0001 Solicitation Rouses LPOE General Construction amend02_053124

B4. 47PC0624R0001 Rouses GC_Reps and Certs GC v0424 (Form C301)

B5. SF30 form for acknowledgement of RFP amendment 02.

B6. Attachment 4 - IRA Weighted Score - addtl concrete/cement note added 053124

B7. Attachment 5 - IRA Sustainability Factor Table (to pair with self-scoring table Attachment 4)

B8. IRA Project Submittal / Reporting Form. The GC team is expected to support the CM team by providing all necessary requested information. (Reference Doc for Post-Award)

B9. IRA Project Submittal Form and Data Dictionary PDF (Reference Doc for Post-Award)

B10. Instructions to SAM Entities Trying to Request Controlled Docs Access Updated 051524

B11. RFI period 2 answers

47PC0624R0001 Amendment 02

File details come from the government source that posted it. Updated .