38JC212315_A01_c0v0TGI.pdf
PDF 294 KB Posted
- Solicitation number
- N6264925RA009
About this file
This is a Task Group Instruction (TGI) for cleaning, assessing, inspecting, repairing, and preserving Fuel Tank Group-1 (5-126-1-F) on the USS HOWARD (DDG-83). The work involves a 19,625-gallon fuel tank and related components including 94 zinc anodes (ZEP type), 31 zinc anodes (ZHC-23 type), manhole covers, bolting rings, and 5,280 SF of interior surface area.
The work requires dewatering tanks, conducting structural assessments, commercial blast cleaning, repairing deteriorated welds and plates, installing new zinc anodes, and preserving surfaces. Special requirements include Level III cleanliness for piping systems and fabrication of non-flammable closures for fire zone boundaries. The work is to be performed between April 7, 2025 and July 14, 2025 at SRF-JRMC facilities. The TGI provides detailed material requirements including zinc anodes, securing studs, washers, and nuts. Government-furnished services include crane operations, utilities, safety inspections, and quality assurance oversight. The work is part of a larger ship repair availability being contracted through NAVSUP Fleet Logistics Center Yokosuka.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
FOUO: Public availability to be determined under 5 USC 552
TASK GROUP INSTRUCTION
AIM REV 20.11.4.0 (OCTOBER 2020)
TGI COMPONENT NAME: TYPE: PHASE: REPEAT: CHANGE:
NO.: FO TK GP-1 5-126-1-F AY A 0 0
SHIP/HULL NO.: SHIP/HULL NAME: SYSTEM: PROJ/WO NO: CASREP CAT:
DDG-83 USS HOWARD JC2
CU PHASE TITLE:
F/O - CLEAN, ASSESS, INSPECT, REPAIR, AND PRESERVE FUEL TANK GROUP-1 (5-126-1-F)
PREPARING ACTIVITY:
PREPARED BY: CODE PHONE DATE
KENICHIRO ISHIKAWA 231B. 315-243-2479 16-APR-2024
APPROVED BY: CODE PHONE DATE
RYOUTA TAKAGI 231B. 315-243-4502 16-APR-2024
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
CONCURRED BY: CODE PHONE DATE
REASON FOR WORK/NEED FOR CHANGE:
CHANGE INSTRUCTIONS:
SPECIAL REQUIREMENTS:
SURFMEPP
This Work Affects a Fire Zone Boundary. Fabrication and/or Staging of a Non-Flammable Closure is required.
CLEANLINESS FOR PIPING SYSTEM/EQUIPMENT LEVEL III
WORK CERTIFICATION SIGNATURES
COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
ACCEPTANCE OF COMPLETED WORK
PHYSICAL INSPECTION PHYSICAL INSPECTION COMPLETED: BADGE NO.: SHOP/CODE: PHONE: DATE:
REQUIRED:☐YES ☒NO
RECORDS REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:
TGI NO.: FO TK GP-1 5-126-1-F AY A 0
FOUO
SHIP: DDG-83 CHG/VER: 0/0
LIST OF EFFECTIVE PAGES
SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO. SHT NO. CHG NO.
1-8 J1-2 M1-2
1. SCOPE/PURPOSE
1.1 Title: Fuel Tank Group-1 (5-126-1-F); clean, assess, inspect, repair, and preserve
1.2 Location of Work:
1.2.1 Fuel Tank Group-1 (5-126-1-F)
1.2.2 Fuel Receiving Tank Group-1 (4-78-1-F)
1.2.3 Fuel Tank Group-1 (5-78-1-F)
1.2.4 Fuel Receiving Tank Group-2 (4-78-2-F)
1.2.5 Fuel Tank Group-2 (5-78-2-F)
1.2.6 Fuel Tank Group-2 (5-126-2-F)
1.2.7 Fuel Tank Group-1 (5-174-1-F)
1.2.8 Waste Water Drain Collecting Tank (5-174-2-F)
1.2.9 Fuel Receiving Tank Group-3 (4-174-1-F)
1.2.10 Sonar Cooling Equipment Room (4-42-0-Q)
1.2.11 CPO Baggage Room (3-78-1-A)
1.2.12 Crew Baggage Room No. One (3-78-2-A)
1.2.13 Crew Living Space No. 2 (3-97-02-L)
1.2.14 IC and Gyro Room No. One (4-94-0-C)
1.2.15 Special Clothing Storeroom (4-110-3-A)
1.2.16 Vacuum Collection Holding Tank Room No. One (4-110-0-E)
1.2.17 Auxiliary Machinery Room No. One (4-126-0-E)
1.2.18 Engine Room No. One (4-174-0-E)
1.3 Identification:
1.3.1 Fuel Tank Group-1
Tank No.: 5-126-1-F Capacity: 19,625 Gallons
FOUO
SHIP: DDG-83 CHG/VER: 0/0
1.3.2 Quantity (One Lot/6 Tanks), Fuel Tank Group-1
Total Capacity: 79,853 Gallons Required amount of water to dewater: 46,500 Gallons
1.3.2.1 Fuel Receiving Tank Group-1
Tank No.: 4-78-1-F Capacity: 11,840 Gallons
1.3.2.2 Fuel Tank Group-1
Tank No.: 5-78-1-F Capacity: 15,679 Gallons
1.3.2.3 Fuel Tank Group-1
Tank No.: 5-42-0-F Capacity: 13,756 Gallons
1.3.2.4 Fuel Tank Group-1
Tank No.: 5-126-1-F Capacity: 19,625 Gallons
1.3.2.5 Fuel Tank Group-1
Tank No.: 5-174-1-F Capacity: 15,468 Gallons
1.3.2.6 Fuel Expansion Seawater Overflow Tank Group-1
Tank No.: 5-214-1-F Capacity: 3,485 Gallons
1.3.3 Quantity (94 EA), Zinc Anode in 5-126-1-F
Type: ZEP Size: 6 Inches Dia x One Inch Thickness
1.3.3.1 Quantity (94 EA), Securing Stud
Material: Steel Size: 1/2-13UNC x 3 Inches Thread Length
1.3.4 Quantity (31 EA), Zinc Anode in 5-126-1-F
Type: ZHC-23 Size: 6 Inches x 12 Inches x 1-1/4 Inches Thickness
1.3.4.1 Quantity (62 EA), Securing Stud
Material: Steel Size: 1/2-13UNC x 1-1/4 Inches Thread Length
1.3.5 Quantity (2 EA), Bracket in 5-126-1-F, Frames between 126 and 134 Remarks: See Sketch Enclosure-01 for location detail.
1.3.6 Quantity (2 EA), Manhole Cover Plate(s) for 5-126-1-F
Manhole No(s).: 4-133-1 and 4-169-1 Size: 15 Inches x 23 Inches Material: Steel
1.3.7 Quantity (2 EA), Bolting Ring for Manhole Cover Plate(s) for 5-126-1-F Manhole No(s).: 4-133-1 and 4-169-1 Material: Steel
FOUO
SHIP: DDG-83 CHG/VER: 0/0
REF.
NO.
DOCUMENT
/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV CHG
NO.
COPY
REQ’D
(Y/N)
SOURCE
DOC
(Y/N)
PARA SEC PG CHP
1 NSI FY-25 NAVSEA Standard Items - ORG N 2 LI FY-25 Local Standard Items - ORG N
3 TM T-9630-
AB-MMD-
Corrosion Control Assessment and Maintenance Manual (CCAMM)
3 N
4 TM NAVSEA
4790/14
Tank and Void Structural and Coating Condition Survey (MRC G1N5)
- N
5 DWG 633-
6567062
Installation of Cathodic Protection & Zinc Anode
AB Y SE
E N
OT
E
6 TM S9086-
CJ-STM-
010/CH-075
Fasteners 7 N
7 TM
SYSTEMS &
SPECIFICAT
IONS
SSPC Painting Manual Volume 2 - N
8 DWG 100-
7026677
UNIT STRL ARR DWG ASSY UNIT
H Y SE
E N
OT
E
9 DWG 100-
7026682
UNIT STRL ARR DWG ASSY UNIT
J Y SE
E N
OT
E
3. APPENDICES:
3.1 Appendix “J” TGI Job Summary Information Sheet
3.2 Appendix "M" TGI Material List
3.3 Appendix “D” Deficiency Form
1.3.8 Quantity (5,280 SF), Entire Interior Surface of Fuel Tank Group-1 (5-126-1-F)
Remarks: The area includes tank side of manhole cover plate(s) and bolting ring
1.4 Security Classification:
1.4.1 Spaces - 1.2.14
1.5 Initial Condition:
1.5.1 Critical Coated Area: CCNY-DDG83-017-25 for the area listed in 1.3.8.
1.5.2 Dry Dock Work
1.6 Contractor work start date: 4/7/2025
1.7 Contractor work completion date: 7/14/2025
2. REFERENCES:
C1209.3 Shimizu, 11120180, SS, 4/29/2024
Shinya.Shimizu.ja Line
FOUO
SHIP: DDG-83 CHG/VER: 0/0
4. GENERAL REQUIREMENTS:
4.1 Not Applicable.
5. PROCEDURE:
5.1 Accomplish the requirements of 099-902YO of 2.2 for each tank listed in 1.3.1.
5.1.1 Dewater each tank listed in 1.3.2.
5.1.2 Accomplish an assessment of each tank listed in 1.3.1 for existing preservation coating, structural integrity, deterioration, pitting, cracks, and areas of damage or distortion, including sounding tubes, tank/void vents, overflows, piping and associated material, structural members, ladders, anodes, desiccant, tank level indicator (TLI), radar TLI, and their electric cables, stud, and tank top cable penetration, and manhole covers in accordance with 2.3 and 2.4, using 2.5 for guidance. Document the assessment on 2.4.
(I) “CCIMS ASSESSMENT”
5.1.2.1 Submit one legible copy, in hard copy, or approved transferrable media, of completed assessment form 2.4 to the SUPERVISOR.
5.1.3 Accomplish the requirements of 009-107 of 2.1.
5.1.3.1 Ensure General Cleaning must be Level III.
5.1.4 Accomplish installation of each manhole cover for each tank listed in 1.3.1 in accordance with Figure 075-4-1 of 2.6.
5.2 Pump out, clean, and dry the bilge area located in 1.2.17 and 1.2.18 free from oil, debris, and other foreign matter.
5.3 Commercial blast clean each tank listed 1.3.1. Accomplish each requirement of Surface Preparation Specification SSPC-SP 6 of 2.7.
5.4 Accomplish a visual inspection of each tank listed in 1.3.1 for existing preservation coating, structural integrity, deterioration, pitting, each crack, and area of damage or distortion, including each sounding tube, tank vent, overflow, piping, each structural member, and manhole cover, using 2.8 and 2.9 for guidance.
5.4.1 Submit one legible copy, in hard copy or approved transferrable media, of a report listing results of the requirements of 5.3 to the SUPERVISOR.
5.5 Repair each tank listed in 1.3.1, based on the report 5.1.2.1 and 5.4.1 as designated by the SUPERVISOR, using 2.8 and 2.9 for guidance. See 5.13.5 and 5.13.6.
5.5.1 Vee-out and weld a total of one linear foot of each deteriorated and damaged weld. Each area of repair may include deck, bulkhead, shell plating, and overhead.
5.5.2 Chip and grind each surface flush in way of each repair.
5.5.3 Base metal weld buildup a total of 31 square inches of each plate defect in the tank.
5.5.3.1 For bidding purposes the base metal weld buildup must be one quarter inch thick.
5.5.3.2 Surface must be ground to sound metal prior to base metal weld buildup.
5.5.3.3 Fill each local pit and groove with weld material prior to application of each principal buildup layer.
FOUO
SHIP: DDG-83 CHG/VER: 0/0
5.5.3.4 Grind each surface of completed base metal weld buildup smooth if greater than 1/8 inch above plate surface.
5.5.4 Remove existing, fabricate, and install new a total of one square foot of deteriorated plate.
5.5.5 Remove existing, fabricate and install new a total of one linear foot of defective stiffener.
5.5.6 Accomplish the requirements of 009-12 of 2.1, including Table 2, Column(s) A, Lines One through 7.
5.5.6.1 Accomplish nondestructive testing in accordance with Line 11.
5.5.7 Accomplish the requirements of 009-25 of 2.1 for an air hose, water hose, or vacuum box test of each new insert weld seam. Allowable leakage: None.
5.6 Remove existing and install new each zinc anode and stud listed in 1.3.3 and 1.3.4, using 2.5, 2.8, and 2.9 for guidance.
5.6.1 Chip and grind each surface flush in way of each removal.
5.6.2 Accomplish the requirements of 009-12 of 2.1, including Table 2, Column(s) A, Lines One through 7
5.7 Remove unused each existing bracket listed in 1.3.5, using 2.8 for guidance.
5.8 Accomplish the requirements of 009-32 of 2.1, including, Table 3, Line(s) 12, for machinery space side surface of each cover plate listed in 1.3.6.
5.9 Accomplish the requirements of 009-32 of 2.1 for machinery space side surface of each bolting ring listed in 1.3.7.
5.10 Accomplish the requirements of 009-32 of 2.1, including Table 4, Line(s) 11, for each area listed in 1.3.8.
5.10.1 Submit new coating data applied to the SUPERVISOR in accordance with 2.3 and 2.4.
5.11 Accomplish the requirements of 009-25 of 2.1 for a completion air test of each tank listed in 1.3.1. Test pressure must be 2 PSIG. Allowable drop in pressure: None.
5.12 Accomplish the requirements of 009-32 of 2.1 for each new and disturbed surface.
5.13 Notes:
5.13.1 Planner: Code 231B K. Ishikawa, 243-2479
5.13.2 Work Integration Manager (WIM): Code 333 T. Yaginuma, 080-5419-0598
5.13.3 2.4 is available on P:\C200\C225\Enclosures\C231\Tank and Void Structural and Coating Condition Survey
(MRC G1N5).
5.13.4 This TGI meets the intent of DDG CSWT File Nos. 123-133, 123-142, and 123-145.
5.13.5 Removal and installation of interferences, and gas free operation, preservation of boundary spaces relating to front loading structure repair are not included in this TGI. They will be covered by a DL in the future based on Contractor submitted condition report.
5.13.6 Materials for structure members relating to front loading repair will be provided in the future as a DL based on Contractor submitted condition report.
FOUO
SHIP: DDG-83 CHG/VER: 0/0
5.13.7 Work per this instruction involves cutting an access (or removal of a door) through a fire zone bulkhead, through the hull of the ship above the turn of the bilge, through ventilation components (ducting, plenums, etc.), or through any air-tight, fume-tight or watertight bulkheads normally used to control air flow in the event of a shipboard fire. A nonflammable closure is required in accordance with COMNAVSEASYSCOM MSG R 261400Z JUL 12. The closure, if not continuously in use, shall be staged near the access, readily visible and accessible, so that any emergency responder can install the closure to affect proper air flow onboard the ship.
5.13.8 This TGI is in response to Condition Report No. NNR17044-19-02 from Sumitomo Heavy Industries, Ltd.
Dated 07-MAR-2022.
5.13.9 WPC will copy the following pages in reference.
REF 2.5: Pages 4A, 3H, 3J, and 9B11 REF 2.8: Pages 3, 4, 4A, 4B, 4C, 4D, 4E, 5, 5A, 5B, 9A, and 9-2 REF 2.9: Pages 3, 4, 4B, 4C, 4D, 4E, 4F, 5, and 9-2
5.13.10 Opening, initial cleaning, and closing of each space listed in 1.2.2 through 1.2.9 will be covered by the following TGI No(s).
Fuel Receiving Tank Group-1 (4-78-1-F): 38JC212313A01 (KTR TGI) Fuel Tank Group-1 (5-78-1-F): 38JC212313A01 (KTR TGI) Fuel Receiving Tank Group-2 (4-78-2-F): 38JC212314A01 (KTR TGI) Fuel Tank Group-2 (5-78-2-F): 38JC212314A01 (KTR TGI) Fuel Tank Group-2 (5-126-2-F): 38JC212316A01 (KTR TGI) Fuel Tank Group-1 (5-174-1-F): 38JC212332A01 (KTR TGI) Waste Water Drain Collecting Tank (5-174-2-F): 38JC212326A01 (KTR TGI) Fuel Receiving Tank Group-3 (4-174-1-F): 38JC212356A01 (KTR TGI)
5.13.11 Provision of oily/chemical water barge will be coordinated by Project Team.
5.13.12 JCNs EB14-ZBT4, EB14-ZBW9, EB14-ZBY2, ER01-ZAQ3, and ES01-NNX4 are related to this TGI.
5.14 Government Furnished Material (GFM):
5.14.1 SRF-JRMC will provide GFM listed in Appendix “M”.
5.15 SRF-JRMC will provide the following service work: (TGI No. 38JC212315S02).
5.15.1 [C740] Crane and crane rigging service.
5.15.2 [X99E] Utility service, electrical.
5.15.3 [X99M] Utility service, including water supply, steam supply, and low pressure air supply except onboard blasting work.
5.15.4 [C106.1] Safety inspection for SRF-JRMC employees.
5.15.5 [C106.2] Gas free inspection for SRF-JRMC employees.
5.15.6 [C133] QA inspection for (G) symbol(s), review of coating application data, and Surface Corrosion Control Information Management System (CCIMS) entry.
5.15.7 [C135] QA inspection for (G) symbol(s).
FOUO
SHIP: DDG-83 CHG/VER: 0/0
5.15.8 [C250] Technical support and process of the tank/void assessment results.
FOUO
M-1
SHIP: DDG-83 CHG/VER: 0/0
APPENDIX “M”
TGI MATERIAL LIST
SYSTEM: PLANT NO.: COMPONENT NAME: TYPE: PHASE: REPEAT: CU PH
VERSION:
CASREP
CAT:
FO TK GP-1 5-126-1-F AY A 0 0
CU PHASE TITLE:
F/O - CLEAN, ASSESS, INSPECT, REPAIR, AND PRESERVE FUEL TANK GROUP-1 (5-126-1-F)
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING
NUMBER
DOCUMENT/DRAWING TITLE REV
JOB ORDER: KEY OP:
38JC212315 A01
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
001 M ANODE,CO, ZINC ANODE, ZEP,
6"D X 1" THK.
ORDER FOR KTR
ORG: C231B K. ISHIKAWA, 243-
9B 5342 007021371 NA 4 N 41065014 94/EA
002 M ANODE,CORROSION PRE,
ORDER FOR KTR
ORG: C231B K. ISHIKAWA, 243-
9B 5342 008136058 NA 4 N 41065016 31/EA
003 M STUD, WE, STUD, WELDING,
SIZE: 1/2"-13 X 3"THD LG,
OVERALL LENGTH 6", MATL:
CARBON STEEL, MIL-S-
24149/1B, TY II, CL I, FINISH: PL
BLK. BIW CAT# 53222-251
ORDER FOR KTR
ORG: C231B K. ISHIKAWA, 243-
9B 5307 LL6999225 NA 4 N 41067417 94/EA
NOTES:
FOUO
M-2
SHIP: DDG-83 CHG/VER: 0/0
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
004 M STUD,WEL, ORDER FOR KTR
ORG: C231B K. ISHIKAWA, 243-
9B 5307 012813886 NA 4 N 41065018 62/EA
005 M WASHER,L, ORDER FOR KTR
ORG: C231B K. ISHIKAWA, 243-
9B 5310 015492705 NA 4 N 41065020
250/EA
006 M NUT,SELF, ORDER FOR KTR
ORG: C231B K. ISHIKAWA, 243-
9B 5310 005957421 NA 4 N 41065021
156/EA
007 M NUT, HEX, NUT, HEX, 1/2"-
13UNC-2B, ALLOY STEEL, GR
2H,NUT, HEX, ZINC-
COATED,MIL-DTL-1222 TY I
ORDER FOR KTR
ORG: C231B K. ISHIKAWA, 243-
9B 5310 LL4653891 NA 4 N 41067418 94/EA
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR APPENDIX "D"
DEFICIENCY FORM
☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One)
2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
DDG-83 FO TK GP-1 5-126-1-F AY A 0
4a. ICN: 4b. KEY OP: 5. LOC SPACE/LVL: FRAME: P/S/C: 6. CAUSED BY:
38JC212315 A01
7. DESCRIPTION:
8. ORIGINATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
9. CORRECTIVE ACTION:
10. EVALUATOR: NAME: BADGE: SHOP/CODE: DATE: PHONE NO.:
FOR NON-NUCLEAR USE ONLY
11. RFD/RFW REQ’D ☐ LAR REQ'D ☐
ILS MOD REQ’D ☐
SRD/PLAN REV REQ'D ☐
DWG NO.: _____________________ S/A NO.: ___________________
12. ISOLATION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.:
SATISFACTORY:
13. SUBSAFE OQE RECORD? SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
YES ☐ NO ☐
14. CORRECTIVE ACTION SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE:
15. INSPECTION REQ’D? INSPECTION COMPLETE/SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
_________:YES ☐ NO ☐
16. RECORDS REVIEW SIGN: BADGE: SHOP/CODE: DATE: PHONE NO.
COMPLETE (DR ONLY)
DL’s ISSUED
(DR ONLY)
FOUO: Public availability to be determined under 5 USC 552 SHEET_____OF_____
☐ NUCLEAR Deficiency Form Continuation Sheet ☐ NON-NUCLEAR
1. SHIP/HULL NO.: 2a. DL or DR No.
(Circle One) 2b. REVISION: 3a. COMPONENT NAME: 3b. TYPE: 3c. PHASE: 3d. REPEAT:
DDG-83 FO TK GP-1 5-126-1-F AY A 0
38JC212315A01
SKETCH
ENCLOSURE-01
SHEET 1 OF 1
LOCATION OF UNUSED BRACKETS IN 5-126-1-F
FR 134 FR 126
PLAN VIEW
FWD