This amendment to a federal contract opportunity provides additional clarification to suppliers. It addresses questions received from potential bidders regarding scope details such as equipment responsibilities, drawings, and existing conditions. Clarification is provided on items including fire alarm wiring, door hardware, signage, and access control systems. The amendment also attaches a site visit sign-in sheet. This type of amendment is common in federal contracting to ensure all suppliers have the same understanding of requirements prior to submitting bids.

View the file

Other files

File Type Posted
C01 - Award Notice - 36C26122C0022.pdf PDF
S06 - 36C26121R0079 - Amendment 0009.pdf PDF
S06 - 36C26121R0079 - 0009 - RFI 5 - Reissued AS601 for Correct Door Hardware Sets.pdf PDF
S06 - 36C26121R0079 - Amendment 0008.pdf PDF
S06 - 36C26121R0079 - Amendment 0007 - 2nd site visit sign-in.pdf PDF
S06 - 36C26121R0079 - Amendment 0006.pdf PDF
S06 - 36C26121R0079 - Amendment 0006 - RFI 3 - 140602 Cath Lab Lead Shielding Modification Certification.pdf PDF
S06 - 36C26121R0079 - Amendment 0006 - RFI 3 - 140530 Lead Shielding Protective Barrier Recommendations.pdf PDF
S06 - 36C26121R0079 - Amendment 0005.docx DOCX document
S06 - 36C26121R0079 - Amendment 0004.docx DOCX document
S06 - 36C26121R0079 - Amendment 0003.docx DOCX document
S06 - 36C26121R0079 - Amendment 0003 - site visit sign-in sheet - 11-30-2021.pdf PDF
S06 - 36C26121R0079 - Amendment 0002.docx DOCX document
S06 - 36C26121R0079 - Amendment 0001.docx DOCX document
Cath Lab Spec Vol 1 2021_0423_.pdf PDF
RFP Presentation_VAPA Cath_211130.pdf PDF
640-13-134 Bid Set combined_.pdf PDF
Cath Lab Spec Vol 2 2021_0423_.pdf PDF
S02 - Exhibit A - QC Section 014500.pdf PDF
S02 - Exhibit B - QC Plan Review Checklist.pdf PDF
Factor 2 - Key Personnel Qualifications Resumes.xlsx XLSX spreadsheet
Factor 5 - Attachment B - Past Performance Questionnaire.docx DOCX document
S02 - Government Furnished Property List.pdf PDF
S02 - Large Business Subcontracting Plan Template.docx DOCX document
S02 - Small Business Participation Plan Template.docx DOCX document
Factor 5 - Attachment D - Sample Client Authorization Letter.docx DOCX document
Factor 5 - Attachment C - Consent Letter.docx DOCX document
S02 - DOL Wage Determination - CA20210018 - 10292021 - Santa Clara County.pdf PDF
Factor 1 - Prime Contractor Project Experience.xlsx XLSX spreadsheet
S02 - Solicitation 36C26121R0079 - FINAL.docx DOCX document
S02 - Name Brand Requirements List.pdf PDF
S02 - Request for Information (RFI) Form - 36C26121R0079.docx DOCX document
S02 - Construction Documents Bid Set 2 - DRAFT.pdf PDF
S02 - Construction Documents Bid Set 3 - DRAFT.pdf PDF
S02 - Cath Lab Spec Vol 1 20210115 - DRAFT.pdf PDF
S02 - Cath Lab Spec Vol 2 20210115 - DRAFT.pdf PDF
S02 - Construction Documents Bid Set 1 - DRAFT.pdf PDF
36C26121R0079_2.docx DOCX document
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR

ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 10

640-22-1-5214-0001

640-13-134

36C261

Department of Veterans Affairs

Network Contracting Office (NCO) 21

391 Taylor Boulevard, Suite 110

Pleasant Hill CA 94523

36C261

Department of Veterans Affairs

Network Contracting Office (NCO) 21

391 Taylor Boulevard, Suite 110

Pleasant Hill CA 94523

To all Offerors/Bidders

36C26121R0079

11-23-2021

X

X X

Remains Feb. 10, 2022, 2:00 PM PDT

X 1

See next page for purpose of amendment.

Angela M. Oppenheimer

Contracting Officer

The purpose of this amendment 0007 is as follows:

1. VA response to RFI # 003 (shown in amendment 0006) is revised to the following:

The shielding report used for this project was provided by Stanford (copies attached for reference). Copies were given to the AE at the start of re-design. GC shall verify existing conditions against this report.

This is a standard detail, 2-strand multi-mode fiber is not called for in VA Cath Lab drawings and is not required.

2. Revise section 01 00 00 General Requirements, para. 1.6 Operations & Storage Area, para. K.4, to read as follows:

Major interruptions of any system must be requested, in writing, at least 30 calendar days prior to the desired time and shall be perform as directed by the COR.

3. Attach sign-in sheet from 2nd Site Visit held on January 11, 2022.

4. Respond to additional RFIs received through January 3rd, 2022, as follows:

RFI

NO.

Information Being Requested VA Response to RFI:

009 Please confirm if we can use CPARS evaluations in place of the Past Performance

Questionnaire?

We are assuming your question pertains to your response to

Evaluation Factor 5 - Past

Performance. You may include final

CPARS evaluations, if available, from those completed projects listed in Offeror's response to Factor 1. Do not include Past Performance

Questionnaires (Attachment B) that your references completed and sent back to you instead of sending them directly to VA contracting.

010 We respectfully submit our substitution request for use of our product (ballistic doors and frames rated to UL-752 Level 3 for this project. How do I notify prime contractors about our products?

Prime contractor information (those who attended the site walks) are attached via amendment to the solicitation.

011a The Door Schedule on Sheet AS601 does not list the door material for any of the openings.

All door and door frame components are HM (hollow metal) unless otherwise indicated in the door schedule.

011b The Door Schedule calls for hardware Set 2C for Doors 698 and 699. However, there isn't a corresponding hardware set in the specification manual

See revised Door Schedule on Sheet

AS601.

011c Pages 08 71 00-19 thru 08 71 00-22 provides the Hardware sets for the project. At the end of each hardware set, there is indication as to which door the hardware set goes to.

However, these don't match up to the doors listed in the Door Schedule

Follow the hardware sets listed in the revised Door Schedule on Sheet

AS601.

012 At the site visit I noticed many fire alarm devices were not connected yet there is wire ran in the conduit. This shows that the fire alarm system within this workspace is currently off of the main panel. As much there is a good amount of conduit and wire that looks to have been installed/placed by the previous team. Should new fire alarm wire be required to be ran between new device locations? If not, since all of this wire is currently not connected to the panel and can’t be tested, will the existing wire be warranted to be free of any issues (shorts, ground faults, etc) if we were going to use it?

Refer to Fire Alarm system General notes on Sheet EF1-1. Provide new

Fire Alarm wiring for installed devices. Re-use existing conduit where feasible, otherwise provide new. Verify and test all newly installed cabling as required for full system functionality.

013 In drawing EF1-1 it shows symbols for new

“Horn Strobes” as well as “Strobes”.. In this building the audible notification from the fire alarm system is voice via the speakers and not via horns. Please confirm that any/all symbols that show a horn strobe need to be strobes.

Please clarify if they are meant be otherwise

Refer to symbols list on sheet E0-1.

Provide speaker strobes and strobes as shown on floorplans, no horn strobes.

014 During site visit where the drawing shows existing devices (especially in the enclosed construction area vs outside in the corridor) many of the fire alarm devices were not present in these locations. Should we exclude providing any new devices shown as existing

(because they may be missing/lost or damaged) or should we plan to include a new device for these?

Refer to Fire Alarm system General notes on Sheet EF1-1. If existing devices are damaged, missing, lost, etc. within area of renovation, provide new. Provide Strobe

Synchronization as detailed in FA

General Notes.

015 Without as-build fire alarm drawings it is not readily known if the existing fire alarm panel, voice evac amplifier, and/or NAC booster panel can handle the new devices. Should we assume that the system has enough available circuits, and/or sufficient voltage drop to handle all the NAC or speaker devices? If we need to determine that, we will need access to as-build drawings prior to bidding.

Refer to Fire Alarm System General notes on Sheet EF1-1. Coordinate with Fire Alarm Systems

Manufacturer/Supplier to verify

Existing Fire Alarm System.

016 In Drawing EF1-1, there are some existing strobes that are of an older variety, as example the visual device next to the Electrical/IDF closets in the hallway. These will need to be replaced and may even need to be combined in an existing circuit in order to maintain synchronization, however this device is shown as (E) existing. Should we plan to bid this project based on what is shown and how it is shown in the drawing?

Refer to Fire Alarm System General notes on Sheet EF1-1. Coordinate with Fire Alarm Systems

Manufacturer/Supplier to verify

Existing Fire Alarm System and compatibilities. Contractor is responsible for providing fully functioning and synchronized systems.

017 Is the fire alarm system for this project considered spec’d or design build? Have these fire alarm plans and device locations been approved by the AHJ and should we bid according to the plans provided?

Refer to Fire Alarm System General notes on Sheet EF1-1; Note #1 directly addresses this question.

018 We have performed service on the fire alarm system at the VAPA. Is this project open to any fire alarm vendor or a particular vendor required for the fire alarm scope of this project?

Fire Alarm is Notifier by Honeywell

019 Please confirm secondary steel supports for new AHU have been previously installed at the roof deck.

See 3/SS701 for curb detail. Curb is new, not previously installed, as are all elements to be installed on it.

020 Please provide name and contact information for warranty holder for the roof being affected by work.

Existing roof of building 100 is no longer under warranty.

021 Please confirm the new medical/medical imaging equipment has not changed and is the same as when construction previously started and stopped.

Confirmed. Imaging equipment has not changed. VA already owns this equipment, and it's currently in storage.

022 Please confirm the overhead support structure for the Clean Suite called out on sheet SS302 of the plans is to be furnished and installed by the general contractor.

Confirmed. It is to be furnished and installed by general contractor.

023 Please confirm the Huntair Clean Suite called out on sheets SS302, EQ101, EQ102, is to furnish and installed by facility/facility contracted vendor. General contractor is not to include this scope in their cost.

CleanSuite ceiling system is contractor provided/contractor installed. See sheet AS603 and spec.

section 09 54 33 Cleanroom Ceiling

System.

024 Page 13 of the provided spec book states general contractor to provide unarmed security for the jobsite. Please confirm security is only required for off hours and weekends when contractor superintendent is not onsite.

Unarmed security is not required

025 Page 15 of the provided spec book states parking is available but does not indicate if there is a cost. Please confirm parking is available at no cost to general contractor and subcontractors.

Confirmed. Parking is available at no cost to general contractor and subcontractor.

026 Page 15 of the provided spec book states general contractor to provide temporary sanitary facilities and storage. Please confirm where these items are to be located in proximity to the project area.

Laydown and temporary sanitary areas are in planning and will be within reasonable proximity to the project.

027 Page 32 of the provided spec book states general contractor to provide a job office for resident engineer and COR. Please confirm this office is required and where it is to be located.

Job office for resident engineer and

COR are not required.

028 Please confirm resident engineer and COR are both to be provided by the facility not the general contractor.

Confirmed. Resident engineer and

COR are VA positions; these jobs are not provided by the general contractor.

029 Page 44 of the provided spec book states photographic documentation of the project to be provided by general contractor. Please confirm the general contractor can self-perform this aspect or does the general contractor have to contract a professional photographer.

Confirmed, general contractor does not have to provide a professional photographer to provide photographic documentation of the project. This can be performed by the general contractor themselves.

030 Page 15 of the provided spec book states general contractor to include costs related to accessing the facility TRIRIGA CPMS system. Please provide the cost for accessing the TRIROGA CPMS system.

This is no longer required.

031 Page 97 of the provided spec book states the project includes liquidated damages for any data breach resulting from conduct of the general contractor. However, the spec book does not list the project including liquidated damages related to duration. Please confirm there are no liquidated damages related to duration/schedule extensions.

Confirmed. Liquidated damages related to duration/schedule extensions are not required or included in solicitation.

032 Sheets AS404, 406, AS407 include lists of equipment that are not called out on Medical

Equipment Schedule AS603 but do not indicate who is furnishing and installing.

Please provide a complete list of equipment with notation as to who is furnishing/installing the items not listed on AS603.

Much of this equipment is also shown in the medical equipment schedule with furnish/install responsibilities on sheet AS603.

Equipment without specific responsibilities called out are to be contractor provided/contractor installed.

033 Please confirm items listed on AS603 as owner furnished /vendor installed are not to be included in general contractor’s cost. Confirm vendor in this case refers to vendor contracted directly by facility.

Confirmed. However, GC to provide support system to the point of connection such as conduits, backing, etc.

034 Sheet AS601 Door Schedule indicates 1 existing door and no existing windows. Please confirm that all windows/doors not shown as existing on the schedule need to be furnished and installed by general contractor and have not already been purchased by facility.

Confirmed. Verify during inventory any doors that may have been purchased and stored on site for owner credit.

035 Signage schedule sheet AS606 does not indicate if the signage has already been purchased by facility. Please confirm all signage called out on the schedule is to be furnished and installed by general contractor.

Confirmed. All signage called out on the schedule are to be provided and installed by the General

Contractor.

036 During the site it was noticed that there appear to be new med gas lines ran withing the project area. Please confirm that sheet PG102 accurately depicts the current existing conditions and general contractors should bid per sheet PG102.

Confirmed.

037 Sheets MH002, MH003, MH004 list the following equipment as existing and furnished by facility air separator, AHU, Steam

Humidifier, two fans, duct terminal unit, chiller coil, heat recovering system, chiller, pump, expansion tank, steam heating coil, clean steam generator, vibration isolators, and buffer tank. Please confirm these items are currently located on the roof and will not require rigging by general contractor.

No, existing or owner provided items cannot be assumed to be in final location. Contractor is responsible for any and all required equipment and labor to move owner-stored equipment from current location to proposed location, including roof.

038 Please confirm facility to provide both glycol fill of existing chiller and start up.

General Contractor is to provide glycol fill as well as any other material necessary for startup. The existing chiller is a new unit provided by the VA. General

Contractor is to install equipment in its entirety for full system functionality (including startup) per the SOW.

039 Please confirm startup of existing AHU by facility and general contractor provide assistance.

General Contractor is to provide all work. The existing AHU is a new unit provided by the VA. General

Contractor is to install equipment in its entirety for full system functionality (including startup) per the SOW.

040 Page 13 of

RFP+Presentation_VAPA+Cath_211130 states general contractor to take inventory of inventory of facility furnished general contractor installed equipment and materials currently on site and provide a list of missing or unsuitable items. Please provide a complete list of materials/equipment being furnished by facility/installed by general contractor that is currently onsite/or expected to be onsite that is to be inventoried by general contractor.

Include location of material/equipment.

Refer to equipment schedules and other schedules for furnish/install responsibilities for these items.

Coordinate with VA for access to inventory of all purchased items in storage.

041 Besides the card readers (access control system) that are shown on the plans

(document A.05_1634254468407-C931-

IFC-Specifications-RFQ-FinalwSAND-r), are there any other systems (cameras CCTV, intrusion detection, etc..) desired at this time?

Other than the card readers, no other intrusion detection is required at this time.

042 Is any other specific door hardware required at the doors that the card readers will be installed at?

No, as long as it is compatible with access control system.

043 Is there an existing access control system that will be utilized for the new doors that require access control?

Access control must be compatible with existing building systems, per

Dwg ET2-2 (riser diagrams of access control). VA's Access Control

System vendor is Trofholtz

Technology.

044 We are looking for the best way for Our

Company to submit a bid on the surgical lights

& booms scoped into this OR upgrade project.

I noticed that the equipment is being purchased directly by the VA.

The Steris booms are VA-owned.

Ceiling lights in the OR are an integrated component of the

Cleanroom Ceiling System as described in spec. section 09 54 33.

This project has been partially constructed, therefore, the framing for the Cleanroom Ceiling System is an existing condition -- CleanSuite

Ceiling System was used as the design criteria. Any future components must be compatible with these conditions. Purchase of additional boom(s) will be made under a separate contract; it will not be part of this requirement.

045 Please clarify which doors & frames on the door schedule are to be painted? Locations?

All doors and door frames shall be painted.

046 Please clarify where the breaking point for painting the E2-C36 corridor is. Where should we stop painting? The plans are not clear.

See drawing AS403

047 Regarding Spec 08 71 00, Drawing AS601:

The door schedule on AS601 does not match up with the door hardware groups in specification section 08 71 00. The hardware groups refer to doors with numbering N2.1, N2.2, N2.10, etc. The door schedule and plans have doors numbered 698, 699, etc. In addition, there are four doors with hardware set HW-10 on the door schedule but the specification states “Hardware by Door

Manufacturer” for HW-10 and lists doors

N2.22 & N2.23.

See answer to RFI 011b, and revised

Door Schedule.

048 Regarding Spec 07 81 00: Applied

Fireproofing part 1.1 A states “This section specifies spray-applied mineral fiber and cementitious coverings to provide fire resistance to interior structural steel members shown”. I am unable to find any depiction or notes on the drawings showing where this applied fireproofing is required. Please indicate where this applied fireproofing is required.

Applied fireproofing is required in all main structure, columns & beams.

049 Regarding Spec 10 25 13, Drawings AS407 &

AS603: Specification Section 10 25 13-1.1A states “This section specifies the furnishing, installation and connection of the Patient Bed

Service Wall (PBSW), both horizontal and vertical”. But Sheet AS407 calls the PBSW as

Equipment C-393194 and the ID Legend calls it out as “Headwall, Flatwall, Recessed

(Existing)”. This Equipment Id (C-393194) is listed under the Owner Furnished/Owner

Installed section on Sheet AS603. Please confirm that these PBSW/Headwalls are OFOI and that the contractor is only to make service connections to them.

Headwall system is owner supplied and already installed; Contractor is responsible for service connections and installing finish trims.

050 Regarding Spec 01 00 00: General

Requirements specification 01 00 00 – 1.5 C.1 states “The General Contractor shall provide unarmed guards at the project site at the specific request of the Resident

Engineer/COR. Please state if this service will be requested and if so when would the guards need to be present and for how long. In order to price this service, we need to know if the guards are required 24 hours per day, 7 days

Unarmed guards are not required.

See RFI #024 per week or only during construction hours, or only during non-construction hours, etc.

051 Regarding Spec 01 00 00: General

Requirements specification 01 00 00 – 1.17 is for the Resident Engineer’s Field Office and is to be provided where shown on the drawings.

Since nothing is shown on the drawings are we to assume that a field office for the

Resident Engineer is not required?

Confirmed, field office for Resident

Engineer is not required

ATTACHMENT:

See attached document: S06 - 36C26121R0079 - Amendment 0007 - 2nd site visit sign-in.