This document is a Table of Contents for VHA Master Specifications applicable to Project No. 687-24-101, the Demolish and Regrade Connecting Corridor project at Johnathan M. Wainwright Memorial VAMC, dated 28 April 2026. The specifications are organized into 14 divisions covering general requirements, existing conditions, construction trades, and systems installation standards. Division 00 includes special sections such as drawing sheets and facility data requirements. Division 01 encompasses general requirements including project schedules for small design/bid/build projects, shop drawing submissions, safety requirements, quality control, testing and laboratory services, temporary environmental controls, construction waste management, and closeout procedures. Division 02 addresses existing conditions including site surveys, demolition work, asbestos abatement, and lead-based paint removal with corresponding hazardous materials reports.

The remaining divisions specify technical standards for masonry work (Division 04), metals fabrications (Division 05), carpentry (Division 06), thermal and moisture protection including roofing, flashing, and sealants (Division 07), openings such as doors and hardware (Division 08), finishes including painting and drywall (Division 09), fire suppression systems (Division 21), plumbing and general-duty valves (Division 22), HVAC systems (Division 23), electrical installations and lighting (Division 26), communications systems (Division 27), electronic safety and security including video surveillance and fire detection (Division 28), earthwork (Division 31), and exterior improvements including concrete work and planting (Division 32). Each specification section includes an associated date indicating the version or revision date of that standard.

View the file

Other files

File Type Posted
Amendment 0005.pdf PDF
20260821 Walla Walla_E-504.pdf PDF
36C26026R0080 0004.pdf PDF
20260821 Walla Walla_EP106.pdf PDF
Amendment 0003.pdf PDF
Atch 18 - QUESTIONS and ANSWERS - 36C26026R0080.pdf PDF
Atch 22 - 02 83 33.13.1 Lead Based Paint Survey 07-2006.pdf PDF
Atch 25 - Civil_C-401 and C-404 Safety Railing.pdf PDF
Atch 27 - GeoTech Report 1.pdf PDF
Atch 20 - 01 45 00 - QUALITY CONTROL rev1.pdf PDF
Atch 26 - Electrical WW R2 20260818.pdf PDF
Amendment 0002.pdf PDF
Atch 21 - 02 82 11.1 Hazmat Survey Report 06-12-25.pdf PDF
Atch 23 - 28 23 00 Video Surveillance rev1.pdf PDF
Atch 28 - GeoTech Report 2.pdf PDF
Atch 24 - Civil_GC101 Staging Area.pdf PDF
Atch 16 - Site Visit Sign In Sheet.pdf PDF
Amendment 0001.pdf PDF
Atch 17 - Wage Determination 05.18.2026.pdf PDF
Solicitation 36C26026R0080_Connect Corridor 687-24-101.pdf PDF
Atch 1 - SOW_Connect Corridor 687-24-101.docx DOCX document
Atch 7 - Bldg 74 Sprinkler Demo PCRA_Connect Corridor 687-24-101.pdf PDF
Atch 11 - Divisional Price Breakout_Connect Corridor 687-24-101.xlsx XLSX spreadsheet
Atch 5 - Bldg 68 Sprinkler Demo Install PCRA_Connect Corridor 687-24-101.pdf PDF
Atch 10 - Bldg 80 Phase 3 PCRA_Connect Corridor 687-24-101.pdf PDF
Atch 14 - Past Performance Questionnaire_Connect Corridor 687-24-101.docx DOCX document
Atch 15 - Wage Determination 01.23.2026, Connect Corridor, 687-24-101.pdf PDF
Atch 6 - Bldg 74 Phase 4 PCRA_Connect Corridor 687-24-101.pdf PDF
Atch 9 - Bldg 78 Phase 1 PCRA_Connect Corridor 687-24-101.pdf PDF
Atch 2 - Drawings_Connect Corridor 687-24-101.pdf PDF
Atch 3 - Specs_Connect Corridor 687-24-101.pdf PDF
Atch 4 - Bldgs 68 and 69 Phase 3 PCRA_Connect Corridor 687-24-101.pdf PDF
Atch 8 - Bldg 75 Phase 2 PCRA_Connect Corridor 687-24-101.pdf PDF
Atch 12 - Limitations on Subcontracting_Connect Corridor 687-24-101.pdf PDF
Atch 13 - Contractor Rules of Behavior_Connect Corridor 687-24-101.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BD Submittal Project No. 687-24-101

Johnathan M. Wainwright Memorial VAMC 28 April 2026

Demolish and Regrade Connecting Corridor

00 01 10-1

DEPARTMENT OF VETERANS AFFAIRS

VHA MASTER SPECIFICATIONS

TABLE OF CONTENTS

Section 00 01 10

SECTION NO DIVISION AND SECTION TITLES DATE

DIVISION 00 - SPECIAL SECTIONS

00 01 15 List of Drawing Sheets 05-20

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 General Requirements 11-21

01 00 00

01B

Rule of the Station

01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build) 01-24

01 33 23 Shop Drawings, Product Data, and Samples 11-23

01 35 26 Safety Requirement

01 42 19 Reference Standards 11-20

01 45 00 Quality Control 02-21

01 45 29 Testing & Laboratory Services 11-18

01 57 19 Temporary Environmental Controls 01-21

01 74 19 Construction Waste Management 04-22

01 78 00 Closeout Submittal

01 78 23 Operation and Maintenance Data

01 78 24.00

Facility Data Requirements

01 78 24.00

Facility Data Workbook (FDW)

DIVISION 02 – EXISTING CONDITIONS

02 21 13 Site Surveys 12-23

02 41 00 Demolition 08-17

02 82 11 Traditional Asbestos Abatement 01-21

02 82 11.1 Hazardous Materials Report

02 83 33.13 Lead-Based Paint Removal and Disposal 01-21

02 83

33.13.1

Lead-Based Paint Report

DIVISION 04 – MASONRY

04 01 20 Maintenance of Unit Masonry

04 01 40 Maintenance of Stone Assemblies

04 01 40.61 Stone Repair

04 01 40.62 Stone Repointing

04 03 10 Historic Masonry Cleaning

04 03 22 Historic Brick Unit Masonry Repair

04 03 23 Historic Brick Unit Masonry Repointing

04 05 13 Masonry Mortaring 10-17

00 01 10-2

04 05 16 Masonry Grouting 01-21

04 20 00 Unit Masonry 08-17

DIVISION 05 – METALS

05 50 00 Metal Fabrications 08-18

DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES

06 10 00 Rough Carpentry 10-17

06 20 00 Finish Carpentry 01-21

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 31 13 Asphalt Shingles 02-21

07 60 00 Flashing and Sheet Metal 01-21

07 92 00 Joint Sealants 04-22

DIVISION 08 - OPENINGS

08 11 13 Hollow Metal Doors and Frames 01-21

08 71 00 Door Hardware 03-24

DIVISION 09 – FINISHES

09 06 00 Schedule for Finishes 01-21

09 22 16 Non-Structural Metal Framing 06-18

09 29 00 Gypsum Board 04-20

09 91 00 Painting 01-21

DIVISION 21- FIRE SUPPRESSION

21 13 16 Dry-Pipe Sprinkler Systems 01-15

DIVISION 22 – PLUMBING

22 05 23 General-Duty Valves for Plumbing Piping 09-20

DIVISION 23 – HEATING, VENTILATING, AND AIR

CONDITIONING (HVAC)

23 05 11 Common Work Results for HVAC 03-23

23 07 11 HVAC and Boiler Plant Insulation 02-20

23 23 00 Refrigerant Piping 03-24

23 81 43 Air Source Unitary Heat Pump

00 01 10-3

DIVISION 25 – INTEGRATED AUTOMATION

DIVISION 26 – ELECTRICAL

26 05 11 Requirements for Electrical Installations 11-22

26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22

26 05 26 Grounding and Bonding for Electrical Systems 11-22

26 05 33 Raceway And Boxes For Electrical Systems

26 05 41 Underground Electrical Construction 11-22

26 05 73 Overcurrent Protective Device Coordination Study

26 09 23 Lighting Controls 11-22

26 32 13 Engine Generators

26 56 00 Exterior Lighting 11-22

DIVISION 27 – COMMUNICATIONS

27 05 11 Requirements for Communications Installations 09-19

27 05 26 Grounding and Bonding for Communications Systems 06-15

27 05 33 Raceways and Boxes for Communications Systems 10-18

27 10 00 Control, Communication and Signal Wiring

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

28 23 00 Video Surveillance

28 31 00 Fire Detection and Alarm 10-11

DIVISION 31 – EARTHWORK

31 20 00 Earth Moving 10-12

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 23 Cement and Concrete for Exterior Improvements 08-16

32 84 00 Planting Irrigation 08-16

32 90 00 Planting 08-16

DIVISION 33 – UTILITIES

DIVISION 34 – TRANSPORTATION

DIVISION 48 – Electrical Power Generation