This is Standard Form 30, Amendment 0002 to Solicitation 36C26026R0080, issued by NCO 20 Network Contracting Office (ATTN: V4CONT, 1601 E. Fourth Plain Blvd, Bldg. 17, Suite B428, Vancouver WA 98661). The amendment is effective August 19, 2026, with project number 687-24-101 and requisition number 08-19-2026. The amendment is not extended, meaning offerors must acknowledge receipt of this amendment prior to the original solicitation deadline or face rejection of their offer.

The amendment adds 11 attachments to the solicitation: Attachment 18 (Questions and Answers for 36C26026R0080), Attachment 19 (00 01 10 Table of Contents), Attachment 20 (01 45 00 Quality Control rev1), Attachment 21 (02 82 11.1 Hazmat Survey Report dated 06-12-25), Attachment 22 (02 83 33.13.1 Lead Based Paint Survey from 07-2006), Attachment 23 (28 23 00 Video Surveillance rev1), Attachment 24 (Civil GC101 Staging Area), Attachment 25 (Civil C-401 and C-404 Safety Railings), Attachment 26 (Electrical WW R2 dated 20260818), Attachment 27 (GeoTech Report #1), and Attachment 28 (GeoTech Report #2). Contracting Officer Susan Howe issued the amendment; all terms and conditions of the referenced solicitation remain in full force and effect except as modified herein.

View the file

Other files

File Type Posted
Amendment 0005.pdf PDF
20260821 Walla Walla_E-504.pdf PDF
36C26026R0080 0004.pdf PDF
20260821 Walla Walla_EP106.pdf PDF
Amendment 0003.pdf PDF
Atch 21 - 02 82 11.1 Hazmat Survey Report 06-12-25.pdf PDF
Atch 23 - 28 23 00 Video Surveillance rev1.pdf PDF
Atch 28 - GeoTech Report 2.pdf PDF
Atch 20 - 01 45 00 - QUALITY CONTROL rev1.pdf PDF
Atch 26 - Electrical WW R2 20260818.pdf PDF
Atch 18 - QUESTIONS and ANSWERS - 36C26026R0080.pdf PDF
Atch 19 - 00 01 10 TOC.pdf PDF
Atch 22 - 02 83 33.13.1 Lead Based Paint Survey 07-2006.pdf PDF
Atch 25 - Civil_C-401 and C-404 Safety Railing.pdf PDF
Atch 27 - GeoTech Report 1.pdf PDF
Atch 24 - Civil_GC101 Staging Area.pdf PDF
Atch 16 - Site Visit Sign In Sheet.pdf PDF
Amendment 0001.pdf PDF
Atch 17 - Wage Determination 05.18.2026.pdf PDF
Atch 6 - Bldg 74 Phase 4 PCRA_Connect Corridor 687-24-101.pdf PDF
Atch 9 - Bldg 78 Phase 1 PCRA_Connect Corridor 687-24-101.pdf PDF
Atch 5 - Bldg 68 Sprinkler Demo Install PCRA_Connect Corridor 687-24-101.pdf PDF
Atch 10 - Bldg 80 Phase 3 PCRA_Connect Corridor 687-24-101.pdf PDF
Atch 14 - Past Performance Questionnaire_Connect Corridor 687-24-101.docx DOCX document
Atch 15 - Wage Determination 01.23.2026, Connect Corridor, 687-24-101.pdf PDF
Solicitation 36C26026R0080_Connect Corridor 687-24-101.pdf PDF
Atch 1 - SOW_Connect Corridor 687-24-101.docx DOCX document
Atch 7 - Bldg 74 Sprinkler Demo PCRA_Connect Corridor 687-24-101.pdf PDF
Atch 11 - Divisional Price Breakout_Connect Corridor 687-24-101.xlsx XLSX spreadsheet
Atch 2 - Drawings_Connect Corridor 687-24-101.pdf PDF
Atch 3 - Specs_Connect Corridor 687-24-101.pdf PDF
Atch 4 - Bldgs 68 and 69 Phase 3 PCRA_Connect Corridor 687-24-101.pdf PDF
Atch 8 - Bldg 75 Phase 2 PCRA_Connect Corridor 687-24-101.pdf PDF
Atch 12 - Limitations on Subcontracting_Connect Corridor 687-24-101.pdf PDF
Atch 13 - Contractor Rules of Behavior_Connect Corridor 687-24-101.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 1

0002 08-19-2026

687-24-101

36C260

NCO 20 Network Contracting Office

ATTN: V4CONT

1601 E. Fourth Plain Blvd Bldg.17, Suite B428 Vancouver WA 98661

NCO 20 Network Contracting Office

ATTN: V4CONT

1601 E. Fourth Plain Blvd Bldg.17, Suite B428 Vancouver WA 98661

To all Offerors/Bidders

36C26026R0080

X

X X

X one

The purpose of this amendment is to add the following attachments:

Atch 18 - QUESTIONS and ANSWERS - 36C26026R0080 Atch 19 - 00 01 10 TOC Atch 20 - 01 45 00 - QUALITY CONTROL rev1 Atch 21 - 02 82 11.1 Hazmat Survey Report 06-12-25 Atch 22 - 02 83 33.13.1 Lead Based Paint Survey 07-2006 Atch 23 - 28 23 00 Video Surveillance rev1 Atch 26 - Electrical WW R2 20260818 Atch 24 - Civil GC101 Staging Area Atch 27 - GeoTech Report #1 Atch 25 - Civil C-401 and C-404 Safety Railings Atch 28 - GeoTech Report #2

Susan Howe Contracting Officer