36C26024R0087 0010 Attachment 7 Specification Section 275223 Nurse Call.pdf

PDF 163 KB Posted

Attached to
Z1DA--VISN 20 General Construction MATOC Replacement Construction Services
Solicitation number
36C26024R0087
Issued by

About this file

This document is a technical specification section (27 52 23) for a Nurse Call System installation at a Veterans Affairs facility. The specification details the requirements for adding two new nurse call pull stations to the existing Building 20 nurse call head-end system, with a focus on comprehensive installation, testing, and integration standards. Key requirements include:

The contractor must provide a fully integrated nurse call system that complies with multiple federal regulations and standards, including OSHA, UL, NFPA, and Joint Commission on Accreditation of Healthcare Organizations (JCAHO) guidelines. The specific system components include two emergency call pull stations (EK117) with red indicator, a 24 VAC transformer, and a corridor dome light, to be installed in Toilet rooms 214 and 215 and tied into the existing system in Room 237. The specification mandates rigorous installation practices, including separate conduit routing, comprehensive testing, a two-year warranty, and one-hour training for supervisors and system administrators. The contractor must also provide detailed documentation, ensure all equipment is properly labeled, and follow strict grounding and fireproofing protocols.

View the file

Other files

File Type Posted
36C26024R0087 0013.docx DOCX document
36C26024R0087 0013 Attach 1 RFP Questions 7.9.25.docx DOCX document
36C26024R0087 0012 - SF 1442 Block 19 Continuation Page .docx DOCX document
36C26024R0087 0012.docx DOCX document
36C26024R0087 0011.docx DOCX document
36C26024R0087 0010 Attachment 3 Red Line As builts - existing receway.pdf PDF
36C26024R0087 0010.docx DOCX document
36C26024R0087 0010 Attachment 5 Ceiling Plan -A7.1.pdf PDF
36C26024R0087 0010 Attachment 1 Seed Project questions and Answers 6.16.25.docx DOCX document
36C26024R0087 0010 Attachment 2 VAAR 852.219-75 VA notice of LOS.docx DOCX document
36C26024R0087 0010 Attachment 6 Specification Section 232500 HVAC Water Treatment.pdf PDF
36C26024R0087 0010 Attachment 8 Vancouver Site for 648-22-100 Dental.pdf PDF
36C26024R0087 0010 Attachment 4 Existing Plumbing P2.4.pdf PDF
Attachment 6 Seed Project Price Breakout Revised 6.16.25.xlsx XLSX spreadsheet
36C26024R0087 0009.docx DOCX document
36C26024R0087 0008 Attach 1 RFP Questions 5.29.25.docx DOCX document
36C26024R0087 0008.docx DOCX document
36C26024R0087 0007.docx DOCX document
Attachment 9 VANC Dental B20 Drawings AD101 A-601 and A-603 response to prebid questions.pdf PDF
36C26024R0087 0006 Attach 3 Site Visit Sign in Sheet.pdf PDF
Attachment 7 Dental Air Compressor AC-1specs.pdf PDF
Attachment 6 Seed Project Price Breakout Revised 5.6.25.xlsx XLSX spreadsheet
Attachment 5 Past Performance Questionnaire 5.9.25.docx DOCX document
36C26024R0087 0006 Attach 2 Photos of B20 Mech RM 237.pdf PDF
Attachment 1 648-22-100 VA Vancouver Consolidate Dental B20 4.23.25.pdf PDF
36C26024R0087 0006 Attach 4 Seed Project Question and Answers.docx DOCX document
36C26024R0087 0006 Attach 1 RFP Questions 5.7.25.docx DOCX document
Attachment 8 A-dec-DV5 Compressor and Dry Vacuum cut sheet.pdf PDF
36C26024R0087 0006.docx DOCX document
36C26024R0087 0005 Attach 1 RFP Questions 4 24 25.docx DOCX document
36C26024R0087 0005 Attach 2 VAAR 852.219-75 VA Notice of LOS - Certicate of Compliance for Services and Construction Jan 2023 Deviation.docx DOCX document
36C26024R0087 0005.docx DOCX document
36C26024R0087 0004 Attachment 1 RFP Questions 4 22 25.docx DOCX document
36C26024R0087 0004 Attachment 2 CON MATOC pre-proposal meeting attendees.docx DOCX document
36C26024R0087 0004.docx DOCX document
RFP Questions 4.14.25.docx DOCX document
36C26024R0087 0003.docx DOCX document
36C26024R0087 Conformed 4.10.25.docx DOCX document
Attachment 5 Past Performance Questionnaire 4.10.25.docx DOCX document
Panographic backing detail.docx DOCX document
RFP Questions 4.10.25.docx DOCX document
36C26024R0087 0002.docx DOCX document
36C26024R0087 0001.docx DOCX document
36C26024R0087 4.1.25.docx DOCX document
Attachment 1 648-22-100 VA Vancouver Consolidate Dental B20-Specs.pdf PDF
Attachment 6 Seed Project Price Breakout.xlsx XLSX spreadsheet
Attachment 4 648-22-100 Vancouver WA consolidate Dental Building B20 - MATOC Seed Project SOW 10.9.24.docx DOCX document
36C26024R0087.docx DOCX document
Attachment 2 648-22-100 VA Vancouver Consolidate Dental B20 Drawing signatures.pdf PDF
Attachment 5 Past Performance Questionnaire 11.5.24.docx DOCX document
Show 40 more

Latest 50 of 51 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

12-01-20

27 52 23 - 1

SECTION 27 52 23

NURSE CALL SYSTEMS

PART 1 - GENERAL

1.1 SECTION SUMMARY

A. Work covered by this document includes labor, material and products, device and workmanship warranty, training and services for, and incidental to, the addition of two new and nurse call pull stations fully integrated into the existing building 20 nurse call head end.

These items shall be tested and certified capable of interconnecting and supporting Nurse-Call communications signals generated local and remotely as detailed herein.

B. Work shall be complete, Occupational Safety and Health Administration

(OSHA), National Recognized Testing Laboratory (NRTL – i.e.

Underwriters Laboratory [UL]) Listed and Labeled.

C. The System shall be delivered free of manufacturing, installation, and functional defects. Tie into existing Building 20 nurse call system.

D. The term “provide”, as used herein, shall be defined as: furnished, installed, certified, tested, and warranty by the Contractor.

1.2 RELATED SECTIONS

A. 01 33 23 – Shop Drawings, Product Data and Samples.

B. 07 84 00 – Firestopping.

C. 27 05 11 – Requirements for Communications Installations.

D. 27 05 33 – Raceways and Boxes for Communications Systems.

1.3 DEFINITION

A. Provide: Furnish, install, connect complete, test, certify and warranty.

B. Work: Materials furnished and completely installed.

1.4 REFERENCES

A. The installation shall comply fully with all governing authorities, laws and ordinances, regulations, codes and standards, including, but not limited to:

1. United States Federal Law:

a. Departments of:

1) Commerce, Consolidated Federal Regulations (CFR), Title 15 –

Under the Information Technology Management Reform Act (Public

Law 104-106), the Secretary of Commerce approves standards and guidelines that are developed by the:

27 52 23 - 2

a) Chapter II, National Institute of Standards Technology

(NIST – formerly the National Bureau of Standards). Under

Section 5131 of the Information Technology Management

Reform Act of 1996 and the Federal Information Security

Management Act of 2002 (Public Law 107-347), NIST develops

– Federal Information Processing Standards Publication

(FIPS) 140-2—Security Requirements for Cryptographic

Modules.

b) Chapter XXIII, National Telecommunications and Information

Administration (NTIA – aka ‘Red Book’) Chapter 7.8 / 9;

CFR, Title 47 Federal communications Commission (FCC) Part

15, Radio Frequency Restriction of Use and Compliance in

“Safety of Life” Functions & Locations.

2) FCC - Communications Act of 1934, as amended, CFR, Title 47 –

Telecommunications, in addition to Part 15 – Restrictions of use for Part 15 listed Radio Equipment in Safety of Life /

Emergency Functions / Equipment/ Locations (also see CFR, Title 15 – Department of Commerce, Chapter XXIII – NTIA):

a) Part 15 – Restrictions of use for Part 15 listed Radio

Equipment in Safety of Life / Emergency Functions /

Equipment/Locations.

b) Part 58 – Television Broadcast Service.

c) Part 90 – Rules and Regulations, Appendix C.

3) Health, (Public Law 96-88), CFR, Title 42, Chapter IV Health &

Human Services, CFR, Title 46, Subpart 1395(a)(b) JCAHO “a hospital that meets JCAHO accreditation is deemed to meet the

Medicare conditions of Participation by meeting Federal

Directives:”

a) All guidelines for Life, Personal and Public Safety; and, Essential and Emergency Communications.

4) Labor, CFR, Title 29, Part 1910, Chapter XVII - Occupational

Safety and Health Administration (OSHA), Occupational Safety and Health Standard:

a) Subpart 7 - Definition and requirements (for a NRTL – 15

Laboratory’s, for complete list, contact

(http://www.osha.gov/dts/otpca/nrtl/faq_nrtl.html):

1) UL:

a) 44-02 – Standard for Thermoset-Insulated Wires and http://www.osha.gov/dts/otpca/nrtl/faq_nrtl.html

27 52 23 - 3

Cables.

b) 65 – Standard for Wired Cabinets.

c) 83-03 – Standard for Thermoplastic-Insulated Wires and Cables.

d) 467-01 – Standard for Electrical Grounding and

Bonding Equipment

e) 468 – Standard for Grounding and Bonding Equipment.

f) 486A-01 – Standard for Wire Connectors and Soldering

Lugs for Use with Copper Conductors

g) 486C-02 – Standard for Splicing Wire Connectors.

h) 486D-02 – Standard for Insulated Wire Connector

Systems for Underground Use or in Damp or Wet

Locations.

i) 486E-00 – Standard for Equipment Wiring Terminals for

Use with Aluminum and/or Copper Conductors.

j) 493-01 – Standard for Thermoplastic-Insulated

Underground Feeder and Branch Circuit Cable.

k) 514B-02 – Standard for Fittings for Cable and

Conduit.

l) 1069 – Hospital Signaling and Nurse Call Equipment.

m) 1449 – Standard for Transient Voltage Surge

Suppressors.

n) 1479-03 – Standard for Fire Tests of Through-

Penetration Fire Stops.

o) 1666 – Standard for Wire/Cable Vertical (Riser) Tray

Flame Tests.

p) 1863 – Standard for Safety, Communications Circuits

Accessories.

q) 2024 – Standard for Optical Fiber Raceways.

r) 60950-1/2 – Information Technology Equipment –

Safety.

2) Canadian Standards Association (CSA): same tests as for

UL.

3) Communications Certifications Laboratory (CCL): same tests as for UL.

4) Intertek Testing Services NA, Inc. (ITSNA formerly

Edison Testing Laboratory [ETL]): same tests as for UL.

27 52 23 - 4

b) Subpart 35 – Compliance with NFPA 101 – Life Safety Code.

c) Subpart 36 - Design and construction requirements for exit routes.

d) Subpart 268 - Telecommunications.

e) Subpart 305 - Wiring methods, components, and equipment for general use.

5) Department of Transportation, CFR, Title 49 (Public Law 89-

670), Part 1, Subpart C – Federal Aviation Administration

(FAA):

a) Standards AC 110/460-ID & AC 707 / 460-2E – Advisory

Circulars for Construction of Antenna Towers.

b) Forms 7450 and 7460-2 – Antenna Construction Registration.

6) Veterans Affairs (Public Law No. 100-527), CFR, Title 38, Volumes I & II:

a) Office of Telecommunications:

1) Handbook 6100 – Telecommunications.

a) Spectrum Management FCC & NTIA Radio Frequency

Compliance and Licensing Program.

b) Special Communications Proof of Performance Testing, VACO Compliance and Life Safety Certification(s).

b) Office of Cyber and Information Security (OCIS):

1) Handbook 6500 - Information Security Program.

2) Wireless and Handheld Device Security Guideline Version

3.2, August 15, 2005.

c) VA’s National Center for Patient Safety – Veterans Health

Administration Warning System, Failure of Medical Alarm

Systems using Paging Technology to Notify Clinical Staff, July 2004.

d) VA’s Center for Engineering Occupational Safety and Health, concurrence with warning identified in VA Directive 7700.

e) Office of Construction and Facilities Management (CFM):

1) Master Construction Specifications (PG-18-1).

2) Standard Detail and CAD Standards (PG-18-4).

3) Equipment Guide List (PG-18-5).

4) Electrical Design Manual for VA Facilities (PG 18-10), Articles 7 & 8.

5) Minimum Requirements of A/E Submissions (PG 18-15):

a) Volume B, Major New Facilities, Major Additions; and

27 52 23 - 5

Major Renovations, Article VI, Paragraph B.

b) Volume C - Minor and NRM Projects, Article III, Paragraph S.

c) Volume E - Request for Proposals Design/Build

Projects, Article II, Paragraph F.

6) Mission Critical Facilities Design Manual (Final Draft –

2007).

7) Life Safety Protected Design Manual (Final Draft –

2007).

8) Solicitation for Offerors (SFO) for Lease Based Clinics

– (05-2009).

b. Federal Specifications (Fed. Specs.):

1) A-A-59544-00 - Cable and Wire, Electrical (Power, Fixed

Installation).

2. National Codes:

a. American Institute of Architects (AIA): Guidelines for Healthcare

Facilities.

b. American National Standards Institute/Electronic Industries

Association/Telecommunications Industry Association

(ANSI/EIA/TIA):

1) 568-B - Commercial Building Telecommunications Wiring

Standards:

a) B-1 – General Requirements.

b) B-2 – Balanced twisted-pair cable systems.

c) B-3 - Fiber optic cable systems.

2) 569 - Commercial Building Standard for Telecommunications

Pathways and Spaces.

3) 606 – Administration Standard for the Telecommunications

Infrastructure of Communications Buildings.

4) 607 – Commercial Building Grounding and Bonding Requirements for Telecommunications.

5) REC 127-49 – Power Supplies.

6) RS 270 – Tools, Crimping, Solderless Wiring Devices, Recommended Procedures for User Certification.

c. American Society of Mechanical Engineers (ASME):

1) Standard 17.4 – Guide for Emergency Personnel.

27 52 23 - 6

2) Standard 17.5 – Elevator & Escalator Equipment (prohibition of installing non-elevator equipment in Elevator Equipment Room /

Mechanical Penthouse).

d. American Society of Testing Material (ASTM):

1) D2301-04 - Standard Specification for Vinyl Chloride Plastic

Pressure Sensitive Electrical Insulating Tape.

e. Building Industries Communications Services Installation (BICSI):

1) All standards for smart building wiring, connections and devices for commercial and medical facilities.

2) Structured Building Cable Topologies.

3) In consort with ANSI/EIA/TIA.

f. Institute of Electrical and Electronics Engineers (IEEE):

1) SO/TR 21730:2007 - Use of mobile wireless communication and computing technology in healthcare facilities -

Recommendations for electromagnetic compatibility (management of unintentional electromagnetic interference) with medical devices.

2) 0739-5175/08/©2008 IEEE – Medical Grade – Mission Critical –

Wireless Networks.

3) C62.41 – Surge Voltages in Low-Voltage AC Power Circuits.

g. NFPA:

1) 70 - National Electrical Code (current date of issue) –

Articles 517, 645 & 800.

2) 75 - Standard for Protection of Electronic Computer Data-

Processing Equipment.

3) 77 – Recommended Practice on Static Electricity.

4) 99 - Healthcare Facilities.

5) 101 - Life Safety Code.

3. State Hospital Code(s).

4. Local Town, City and/or County Codes.

5. Accreditation Organization(s):

a. Joint Commission on Accreditation of Hospitals Organization

(JCAHO) – Section VI, Part 3a – Operating Features.

1.5 QUALIFICATIONS

A. The OEM shall have had experience with three (3) or more installations of Nurse Call systems of comparable size and interfacing complexity with regards to type and design as specified herein. Each of these installations shall have performed satisfactorily for at least one (1)

27 52 23 - 7 year after final acceptance by the user. Include the names, locations and point of contact for these installations as a part of the submittal.

B. The Contractor shall submit certified documentation that they have been an authorized distributor and service organization for the OEM for a minimum of three (3) years. The Contractor shall be authorized by the

OEM to pass thru the OEM’s warranty of the installed equipment to VA.

In addition, the OEM and Contractor shall accept complete responsibility for the design, installation, certification, operation, and physical support for the System. This documentation, along with the System Contractor and OEM certifications must be provided in writing as part of the Contractor’s Technical submittal.

C. The Contractor’s Communications Technicians assigned to the System shall be fully trained, qualified, and certified by the OEM on the engineering, installation, operation, and testing of the System. The

Contractor shall provide formal written evidence of current OEM certification(s) for the installer(s) as a part of the submittal or to the RE before being allowed to commence work on the System.

D. The Contractor shall display all applicable national, state and local licenses.

E. The Contractor shall submit copy (s) of Certificate of successful completion of OEM’s installation/training school for installing technicians of the System’s Nurse Call and/or Code Blue equipment being proposed.

1.6 CODES AND PERMITS

A. Provide all necessary permits and schedule all inspections as identified in the contract’s milestone chart, so that the system is proof of performance tested, certified and approved by VA and ready for operation on a date directed by the Owner.

B. The contractor is responsible to adhere to all codes described herein and associated contractual, state and local codes.

1.7 SCHEDULING

A. It is the responsibility of the Contractor to coordinate all work with the other trades for scheduling, rough-in, and finishing all work specified. The owner will not be liable for any additional costs due to missed dates or poor coordination of the supplying contractor with other trades.

27 52 23 - 8

1.9 PROJECT RECORD DOCUMENTS (AS BUILTS)

A. Throughout progress of the Work, maintain an accurate record of changes in Contract Documents. Upon completion of Work, transfer recorded changes to a set of Project Record Documents.

B. The floorplans shall be marked in pen to include the following:

1. Each device specific locations with UL labels affixed.

2. Conduit locations.

3. Each interface and equipment specific location.

4. Head-end equipment and specific location.

5. Wiring diagram.

6. Labeling and administration documentation.

7. Warranty certificate.

8. System test results.

1.10 WARRANTIES / GUARANTY

A. The Contractor shall warrant the installation to be free from defect in material and workmanship for a period of two (2) years from the date of acceptance of the project by the owner. The Contractor shall agree to remedy covered defects within four (4) hours of notification of major failures or within twenty-four (24) hours of notification for individual station related problems.

B. The Contractor shall agree to grantee the system according to the guidelines outlined in Article 4 herein.

1.11 USE OF THE SITE

A. Use of the site shall be at the GC’s direction.

B. Coordinate with the GC for lay-down areas for product storage and administration areas.

C. Coordinate work with the GC and their sub-contractors.

D. Access to buildings wherein the work is performed shall be directed by the GC.

1.12 DELIVERY, STORAGE, AND HANDLING

A. Deliver, store, and handle products using means and methods that will prevent damage, deterioration, and loss, including theft.

B. Store products in original containers.

C. Coordinate with the GC for product storage. There may be little or no storage space available on site. Plan to potentially store materials off site.

D. Do not install damaged products. Remove damaged products from the site and replaced with new product at no cost to the Owner.

27 52 23 - 9

1.13 PROJECT CLOSE-OUT

A. Prior to final inspection and acceptance of the work, remove all debris, rubbish, waste material, tools, construction equipment, machinery and surplus materials from the project site and thoroughly clean your work area.

B. Before the project closeout date, the Contractor shall submit:

1. OEM Equipment Warranty Certificates.

2. Evidence of compliance with requirements of governing authorities such as the Low Voltage Certificate of Inspection.

3. Project record documents.

4. Instruction manuals and software that is a part of the system.

5. System Guaranty Certificate.

C. Contractor shall submit written notice that:

1. Contract Documents have been reviewed.

2. Project has been inspected for compliance with contract.

3. Work has been completed in accordance with the contract.

PART 2 – PRODUCTS / FUNCTIONAL REQUIREMENTS

2.0 GENERAL REQUIREMENTS FOR EQUIPMENT AND MATERIALS

A. Furnish and install Nurse call pull cord in Toilet rooms 214 and 215.

Connect to nurse call annunciator and head end. Provide and install

Emergency-Call Kits are EK117. EK117 consists of 1- SF117/2A Emergency-

(RED Indicator style) Pull Cord station, 1- SS106 24 VAC (UL listed) pigtail Transformer and 1- LI381 Corridor Dome Light (Without a buzzer). Manufacturer was Alpha Communications, and vender was

Manchester Corp. Tie into Nurse call head end in RM 237.

B.

C. Coordinate features and select interface components to form an integrated Nurse Call system. Match components and interconnections between the systems for optimum performance of specified functions.

D.

E. Equipment: Active electronic type shall use solid-state components, fully rated for continuous duty unless otherwise indicated. Select equipment for normal operation on input power usually supplied between

110 to 130 VAC, 60 Hz supplied from the Facility’s Emergency Electrical

Power System.

F. Meet all FCC requirements regarding equipment listing, low radiation and/or interference of RF signal(s). The system shall be designed to

27 52 23 - 10 prevent direct pickup of signals from within and outside the building structure.

G. Weather/Water Proof Equipment: Listed and labeled by an OSHA certified

NRTL (i.e. UL) for duty outdoors or in damp locations.

2.1 SYSTEM DESCRIPTION

A. Tie into existing nurse call system in Building 20. This is a standalone nurse call system.

B.

C. The Contractor shall continually employ interfacing methods that are approved by the VA. At a minimum, an acceptable interfacing method requires not only a physical and mechanical connection, but also a matching of signal, voltage, and processing levels with regard to signal quality and impedance. The interface point must adhere to all standards described herein for the full separation of Critical Care and

Life Safety systems.

D. The System Contractor shall connect the System ensuring that all NFPA and UL Critical Care and Life Safety Circuit and System separation guidelines are satisfied. The System Contractor is not allowed to make any connections to the Telephone System.

N. All equipment face plates utilized in the system shall be stainless steel, anodized aluminum or UL approved cycolac plastic for the areas where provided.

2.3 MANUFACTURERS

A. Manufacturer was Alpha Communications, and vender was Manchester Corp.

1. Tie-in two new nurse call pull cords to existing system.

2. Maintain manufacturer operating manuals for the items submitted.

2.4 PRODUCTS

A. General.

1. Contractor is responsible for pricing all accessories and miscellaneous equipment required to tie into existing building 20 nurse call system.

2. Raceways, Back Boxes and conduit:

a. Use existing raceways.

PART 3 - EXECUTION

3.1 PROJECT MANAGEMENT

A. Assign a single project manager to this project who will serve as the point of contact for the General Contractor.

27 52 23 - 11

B. The Contractor shall be proactive in scheduling work at the hospital, specifically the Contractor will initiate and maintain discussion with the general contractor regarding the schedule for ceiling cover up and install cables to meet that schedule.

3.2 COORDINATION WITH OTHER TRADES

A. Coordinate with the cabling contractor the location of the Head end in room 237.

B. Coordinate with the cabling contractor the location of existing nurse call equipment and raceways.

C. Before beginning work, verify the location, quantity, size and access for the following:

1. Junction boxes, wall boxes, wire troughs, conduit stubs and other related infrastructure for the systems.

2. System components installed by others.

D. Immediately notify the Owner, GC and Consultant(s) in writing of any discrepancies.

3.3 NEEDS ASSESSMENT

Provide a meeting with the dental manager affected by the installation of the new nurse call pull stations. Educate the staff with the functions of the equipment that is being provided and gather details specific to the individual units; coverage and priorities of calls;

staffing patterns; and other pertinent details that will affect system programming and training.

3.4 INSTALLATION

A. General:

1. Execute work in accordance with National, State and local codes, regulations and ordinances.

2. Install work neatly, plumb and square and in a manner consistent with standard industry practice. Carefully protect work from dust, paint and moisture as dictated by site conditions. The Contractor will be fully responsible for protection of his work during the construction phase up until final acceptance by the Owner.

3. Install equipment according to OEM’s recommendations. Provide any hardware, adaptors, brackets, rack mount kits or other accessories recommended by OEM for correct assembly and installation.

4. Secure equipment firmly in place.

5. Finishes for any exposed work such as cover plates, etc. shall be approved by the Architect, and Owner.

27 52 23 - 12

6. Coordinate cover plates with field conditions. Size and install cover plates as necessary to hide joints between back boxes and surrounding wall. Where cover plates are not fitted with connectors, provide grommeted holes in size and quantity required.

Do not allow cable to leave or enter boxes without cover plates installed.

7. Active electronic component equipment shall consist of solid state components, be rated for continuous duty service, comply with the requirements of FCC standards for telephone and data equipment, systems, and service.

8. Color code all distribution wiring to conform to the Nurse Call

Industry Standard, EIA/TIA, and this document, whichever is the more stringent. At a minimum, all equipment, cable duct and/or conduit, enclosures, wiring, terminals, and cables shall be clearly and permanently labeled according to and using the provided record drawings, to facilitate installation and maintenance.

9. Product Delivery, Storage and Handling:

a. Delivery: Deliver materials to the job site in original unopened containers, clearly labeled with the vendors name and equipment catalog numbers, model and serial identification numbers. The COR may inventory the cable, and related equipment.

b. Storage and Handling: Store and protect equipment in a manner, which will preclude damage.

D. Wiring Practice -

1. Comply with requirements for raceways and boxes specified in

Division 26 Section "Raceway and Boxes for Electrical Systems."

2. Execute all wiring in strict adherence to the National Electrical

Code, applicable local building codes and standard industry practices.

3. Wiring shall be classified according to the following low voltage signal types:

c. Low voltage DC control or power (less than 48VDC)

4. Where raceway is to be EMT (conduit), wiring of differing classifications shall be run in separate conduit. Where raceway is to be an enclosure (rack, tray, wire trough, utility box) wiring of differing classifications which share the same enclosure shall be mechanically partitioned and separated by at least four (4) inches.

27 52 23 - 13

Where Wiring of differing classifications must cross, they shall cross perpendicular to one another.

5. Do not splice wiring anywhere along the entire length of the run.

Make sure cables are fully insulated and shielded from each other and from the raceway for the entire length of the run.

6. Do not pull wire through any enclosure where a change of raceway alignment or direction occurs. Do not bend wires to less than radius recommended by manufacturer.

7. Replace the entire length of the run of any wire or cable that is damaged or abraided during installation. There are no acceptable methods of repairing damaged or abraided wiring.

8. Use wire pulling lubricants and pulling tensions.

9. Use grommets around cut-outs and knock-outs where conduit or chase nipples are not installed.

10. Do not use tape-based or glue-based cable anchors.

G. Conduit and Signal Ducts: When the Contractor determines additional system conduits and/or signal ducts are required in order to meet the system minimum performance standards outlined herein, the contractor shall provide these items as follows:

1. Conduit:

a. The Contractor shall employ the latest installation practices and materials. The Contractor shall provide conduit, junction boxes, connectors, sleeves, weather heads, pitch pockets, and associated sealing materials not specifically identified in this document as

GFE. Conduit penetrations of walls, ceilings, floors, interstitial space, fire barriers, etc., shall be sleeved and sealed.

b. All cables shall be installed in separate conduit and/or signal ducts (exception from the separate conduit requirement to allow

Nurse Call and/or Code Blue cables to be installed in partitioned cable tray with voice cables may be granted in writing by the RE if requested). Conduits shall be provided in accordance with

Section 27 05 33, RACEWAYS AND BOXES FOR COMMUNICATIONS SYSTEMS, and NEC Articles 517 for Critical Care and 800 for Communications systems, at a minimum.

c. When metal, plastic covered, etc., flexible cable protective armor or systems are specifically authorized to be provided for use in the System, their installation guidelines and standards

27 52 23 - 14 shall be as specified herein, Section 27 05 33, RACEWAYS AND

BOXES FOR COMMUNICATIONS SYSTEMS, and the NEC.

d. When ”interduct” flexible cable protective systems is specifically authorized to be provided for use in the System, it’s installation guidelines and standards shall be as the specified herein, Section 27 05 33, RACEWAYS AND BOXES FOR

COMMUNICATIONS SYSTEMS, and the NEC.

e. Conduit fill (including GFE approved to be used in the system) shall not exceed 40%. Each conduit end shall be equipped with a protective insulator or sleeve to cover the conduit end, connection nut or clamp, to protect the wire or cable during installation and remaining in the conduit. Electrical power conduit shall be installed in accordance with the NEC. AC power conduit shall be run separate from signal conduit.

2. Signal Duct, Cable Duct, or Cable Tray:

a. The Contractor shall use GFE signal duct, cable duct, and/or cable tray, when identified and approved by the CORE.

b. Approved signal and/or cable duct shall be a minimum size of 100 mm x 100 mm (4 in. X 4 in.) inside diameter with removable tops or sides, as appropriate. Protective sleeves, guides or barriers are required on all sharp corners, openings, anchors, bolts or screw ends, junction, interface and connection points.

c. Approved cable tray shall be fully covered, mechanically and physically partitioned for multiple electronic circuit use, and be UL certified and labeled for use with telecommunication circuits and/or systems. The RE shall approve width and height dimensions.

d. All cable junctions and taps shall be accessible. Provide an 8” X

8” X 4” (minimum) junction box attached to the cable duct or raceway for installation of distribution system passive equipment. Ensure all equipment and tap junctions are accessible

3.5 PROTECTION OF NETWORK DEVICES

A. Contractor shall protect network devices during unpacking and installation by wearing manufacturer approved electrostatic discharge

(ESD) wrist straps tied to chassis ground. The wrist strap shall meet

OSHA requirements for prevention of electrical shock, should technician come in contact with high voltage.

27 52 23 - 15

3.6 CUTTING, CLEANING AND PATCHING

A. It shall be the responsibility of the contractor to keep their work area clear of debris and clean area daily at completion of work.

B. It shall be the responsibility of the contractor to patch and paint any wall or surface that has been disturbed by the execution of this work.

C. The Contractor shall be responsible for providing any additional cutting, drilling, fitting or patching required that is not indicated as provided by others to complete the Work or to make its parts fit together properly.

D. The Contractor shall not damage or endanger a portion of the Work or fully or partially completed construction of the Owner or separate contractors by cutting, patching or otherwise altering such construction, or by excavation. The Contractor shall not cut or otherwise alter such construction by the Owner or a separate contractor except with written consent of the Owner and of such separate contractor; such consent shall not be unreasonably withheld. The

Contractor shall not unreasonably withhold from the Owner or a separate

Contractor the Contractor’s consent to cutting or otherwise altering the Work.

E. Where coring of existing (previously installed) concrete is specified or required, including coring indicated under unit prices, the location of such coring shall be clearly identified in the field and the location shall be approved by the Project Manager prior to commencement of coring work.

3.7 FIREPROOFING

A. Where Nurse Call and/or Code Blue wires, cables and conduit penetrate fire rated walls, floors and ceilings, fireproof the opening.

B. Provide conduit sleeves (if not already provided by electrical contractor) for cables that penetrate fire rated walls and

Telecommunications Rooms floors and ceilings. After the cabling installation is complete, install fire proofing material in and around all conduit sleeves and openings. Install fire proofing material thoroughly and neatly. Seal all floor and ceiling penetrations.

C. Use only materials and methods that preserve the integrity of the fire stopping system and its rating.

D. Install fireproofing where low voltage cables are installed in the same manholes with high voltage cables; also cover the low voltage cables with arc proof and fireproof tape.

27 52 23 - 16

E. Use approved fireproofing tape of the same type as used for the high voltage cables, and apply the tape in a single layer, one-half lapped or as recommended by the manufacturer. Install the tape with the coated side towards the cable and extend it not less than 25 mm (one inch) into each duct.

F. Secure the tape in place by a random wrap of glass cloth tape.

3.8 GROUNDING

A. Ground Nurse Call and/or Code Blue cable shields and equipment to eliminate shock hazard and to minimize ground loops, commonmode returns, noise pickup, cross talk, and other impairments as specified in CFM Division 27, Section 27 05 26 – Grounding and Bonding for

Communications Systems.

B. Facility Signal Ground Terminal: Locate at main room or area signal ground within the room (i.e. head end and telecommunications rooms) or area(s) and indicate each signal ground location on the drawings.

C. Extend the signal ground to inside each equipment cabinet and/or rack.

Ensure each cabinet and/or rack installed item of equipment is connected to the extended signal ground. Isolate the signal ground from power and major equipment grounding systems.

D. When required, install grounding electrodes as specified in CFM

Division 26, Section 26 05 26 –Grounding and Bonding for Electrical

Systems.

E. Do not use “3rd or 4th” wire internal electrical system conductors for communications signal ground.

F. Do not connect the signal ground to the building’s external lightning protection system.

G. Do Not “mix grounds” of different systems.

H. Insure grounds of different systems are installed as to not violate OSHA Safety and NEC installation requirements for protection of personnel.

PART 4 – TESTING / GUARANTY / TRAINING

4.0 SYSTEM LISTING

The Nurses Call System is NFPA listed as an “Emergency” Communication system. Therefore, the following testing and guaranty provisions are the minimum to be performed and provided by the contractor.

4.1 PROOF OF PERFORMANCE TESTING

A. Final Acceptance Testing:

27 52 23 - 17

1. After completion of the installation of the pull stations to the head end this portion of the system must be pretested, inspected, and certified. Each item of installed equipment shall be checked to ensure appropriate UL Listing and Certification Labels are affixed as required by NFPA -Life Safety Code 101-3.2 (a) & (b), UL Nurse

Call Standard 1069 and JCHCO evaluation guidelines, and proper installation practices are followed. The intermediate test shall include a full operational test.

2. All inspections and tests shall be conducted by the installation vendor and witnessed by the contractor representative. The results of the inspection will be officially recorded by the Government

Representative and maintained on file by the COR, until completion of the entire project.

3. Test Conclusion:

a. At the conclusion of the Acceptance Test, using the generated punch list (or discrepancy list) the VA and the Contractor shall jointly agree to the results of the test, and reschedule testing on deficiencies and shortages with the COR. Any retesting to comply with these specifications will be done at the Contractor's expense.

b. If the System is declared unacceptable without conditions, all rescheduled testing expenses will be borne by the Contractor.

4.2 WARRANTY

A. Comply with FAR 52.246-21, except that warranty shall be as follows:

B. Contractor’s Responsibility:

1. The Contractor shall warranty that all provided material and equipment will be free from defects, workmanship and will remain so for a period of one year from date of final acceptance of the System by the VA. The Contractor shall provide equipment warranty documents, to the COR.

2. The Contractor's maintenance personnel shall have the ability to contact the Contractor and VA for emergency maintenance and logistic assistance, remote diagnostic testing, and assistance in resolving technical problems at any time. This contact capability shall be provided by the Contractor and OEM at no additional cost to the VA.

3) The Contractor shall respond and correct on-site trouble calls, during the standard work week to:

27 52 23 - 18

a) A routine trouble call within one (1) working day of its report. A routine trouble is considered a trouble which causes a pillow speaker or cordset, one (1) master nurse control station, patient station, emergency station, or dome light to be inoperable.

b) Routine trouble calls in critical emergency health care facilities (i.e., cardiac arrest, intensive care units, etc.) shall also be deemed as an emergency trouble call.

The RE (or Facility Contracting Officer) shall notify the

Contractor of this type of trouble call.

c) An emergency trouble call within four hours of its report.

An emergency trouble is considered a trouble which causes a sub-system (ward), distribution point, terminal cabinet, or code one system to be inoperable at anytime.

C. Work Not Included: Maintenance and repair service shall not include the performance of any work due to improper use; accidents; other vendor, contractor, or owner tampering or negligence, for which the Contractor is not directly responsible and does not control. The Contractor shall immediately notify the COR or Facility Contracting Officer in writing upon the discovery of these incidents. The COR or Facility Contracting

Officer will investigate all reported incidents and render

4.3 TRAINING

A. Provide thorough training of dental staff assigned to those nursing units receiving new networked nurse/patient communications equipment.

B. Provide the following minimum training times and durations:

1. 1 hour for supervisors and dental system administrators.

5.0 ATTACHMENTS

A. The following items are required as a part of the system:

1. COTS Documents:

A.2 Contracting Officer’s Authority. The Contracting Officer is the only person authorized to make or approve any changes in any of the requirements of this Contract, and notwithstanding any provisions contained elsewhere in this Contract/Order, the said authority remains solely within the Contracting Officer. In the event the Contractor makes any changes at the direction of any person other than the Contracting Officer, the changes will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in costs incurred as a result thereof.

A.3 VAAR 852.270-1 Representatives of Contracting Officers (APR 1984). The Contracting Officer reserves the right to designate representatives to act for him/her in furnishing technical guidance and advice or generally supervise the

27 52 23 - 19 work to be performed under this Contract/Order. Such designation will be in writing and will define the scope and limitations of the designee’s authority.

A copy of the designation shall be furnished the Contractor.

A.4 VAAR 852.270-4 Commercial Advertising (NOV 1984). The Contractor will not advertise the award of this Contract/Order in his/her commercial advertising in such a manner as to state or imply that the Department of Veterans Affairs endorses a product, project or commercial line of endeavor.

A.5 VAAR 852.237-70 Contractor Responsibilities (APR 1984) The Contractor shall obtain all necessary licenses and/or permits required to perform this work. He/she shall take all reasonable precautions necessary to protect persons and property from injury or damage during the performance of the Contract/Order.

He/she shall be responsible for any injury to himself/herself, his/her employees, as well as for any damage to personal or public property that occurs during the performance of the Contract/Order that is caused by his/her employees fault or negligence, and shall maintain personal liability and property damage insurance having coverage for a limit as required by the laws of the state where services are performed. Further, it is agreed that any negligence of the Government, its officers, agents, servants and employees, shall not be the responsibility of the Contractor hereunder with the regard to any claims, loss, damage, injury, and liability resulting there from.

A.6 Indemnification. The Contractor shall save and hold harmless and indemnify the Government against any and all liability claims, and cost of whatsoever kind and nature for injury to or death of any person or persons and for loss or damage to any Contractor property or property owned by a third party occurring in connection with or in any way incident to or arising out of the occupancy, use service, operation, or performance of work under the terms of the Contract/Order, resulting in whole or in part from the acts or omissions of the Contractor, any subcontractor, or any employee, agent, or representative of the Contractor or subcontractor.

A.7 Government’s Liability. The Government shall not be liable for any injury to the Contractor's personnel or damage to the Contractor's property unless such injury or damage is due to negligence on the part of the Government and is recoverable under the Federal Torts Claims Act, or pursuant to other Federal statutory authority.

27 52 23 - 20

- - - E N D - - -