5b Arc Flash Concepts.pdf

PDF 837 KB Posted

Attached to
H130--Amendment to Answer Questions for the Electrical Power Distribution System
Solicitation number
36C25925Q0292
Issued by

About this file

This document is a comprehensive technical overview of Arc Flash Concepts, detailing the technical and safety considerations associated with electrical arc flash hazards. The document explains arc flash as a rapid energy release resulting from an electrical fault, which can create explosive conditions with temperatures capable of vaporizing copper and generating deadly shrapnel. It outlines four key industry standards governing arc flash prevention: OSHA 29 CFR Part 1910 Subpart S, NFPA 70 National Electrical Code, NFPA 70E Standard for Electrical Safety Requirements, and IEEE Standard 1584 for Arc Flash Hazard Calculations.

The document provides an in-depth analysis of arc flash risk assessment methodologies, focusing on the Incident Energy Analysis Method, which determines personal protective equipment (PPE) requirements based on potential energy exposure. It discusses complex technical considerations such as short-circuit studies, coordination studies, and the nuanced interactions between bolted fault currents and arc fault currents. A key finding is that seemingly conservative electrical analysis can paradoxically increase safety risks by misapplying circuit protection equipment, with the study revealing that in a survey of 33 plants, 24% of electrical buses had incident energy levels exceeding 8 cal/cm², 12% over 40 cal/cm², and 5% at levels considered deadly with no protection.

View the file

Other files

File Type Posted
36C25925Q0292 0009.docx DOCX document
P09 - Final SOW 9 Sep 25.docx DOCX document
36C25925Q0292 0009_1.docx DOCX document
36C25925Q0292 0008.docx DOCX document
36C25925Q0292 0008_1.docx DOCX document
36C25925Q0292 0007.docx DOCX document
S02 36C25925Q0292 0007_1.docx DOCX document
36C25925Q0292 0005.docx DOCX document
36C25925Q0292 0005_1.docx DOCX document
36C25925Q0292 0004.docx DOCX document
36C25925Q0292 0003_1.docx DOCX document
P09 Final SOW.docx DOCX document
S02 36C25925Q0292 0003.docx DOCX document
36C25925Q0292 0002.docx DOCX document
36C25925Q0292 0002_1.docx DOCX document
2022 GJ VA Combined Triennial Electrical Report.pdf PDF
4a Coordination Study Opening Section.pdf PDF
5c Arc Flash Study Reports Interpretation.pdf PDF
5a Arc Flash Study Opening Section.pdf PDF
1 Introduction.pdf PDF
36C25925Q0292 0001_1_01.docx DOCX document
2022 GJ VA Triennial Electrical Vol2.pdf PDF
20220911 Electrical One Line Diagram Final.pdf PDF
6b Disclaimer.pdf PDF
4c TCC Finding and Observations.pdf PDF
4b Coordination Study Reports Interpretation.pdf PDF
3d Equipment Duty Reports Findings.pdf PDF
3b Short Circuit LV Monentary Report Interpretation.pdf PDF
3a Short Circuit Study Opening Section.pdf PDF
2 Executive Summary.pdf PDF
36C25925Q0292 0001.docx DOCX document
7 Building Division Index.pdf PDF
6a Glossary of Terms.pdf PDF
3c Short Circuit Equipment Duty Interpretation.pdf PDF
0 Grand Junction VA Table of Contents Vol 1.pdf PDF
S02_ 36C25925Q0292_1.docx DOCX document
36C25925Q0292.docx DOCX document
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Arc Flash Concepts

Arc Flash Concepts Page 1

What is Arc Flash? Arc Flash is the result of a rapid release of energy due to an arcing fault between a phase bus bar and another phase bus bar, neutral or a ground. During an arc fault the air is the conductor.

Arc faults are generally limited to systems where the bus voltage is greater or equal to 120 volts. Lower commonly used voltage levels normally will not sustain an arc. An arc fault is similar to the arc obtained during electric welding and the fault has to be started by something creating the path of conduction or a failure such as a breakdown in insulation.

The cause of the short normally burns away during the initial flash and the arc fault is then sustained by the establishment of highly conductive plasma (ionized air and vaporized metal). The plasma will conduct as much energy as is available and is only limited by the impedance of the arc and the system impedance.

This massive energy discharge can vaporize copper and is conservatively estimated to expand as much as 40,000 to 1in volume. This process is so fast the volumetric increase creates a blast. This fiery explosion can burn or damage everything in its path plus creating deadly shrapnel.

The arc fault current is usually much less than the available bolted fault current and below the rating of circuit breakers. Unless these devices have been selected to handle the arc fault condition, they will not trip and the full force of an arc flash will occur. The electrical equation for energy is Volts times Current times Time. The transition from arc fault to arc flash takes a finite time, increasing in intensity as the pressure wave develops. The challenge is to sense the arc fault current and shut off the voltage in a timely manner before it develops into a serious arc flash condition.

In the early 1980's a paper "The Other Electrical Hazard: Electric Arc Blast Burns" by Ralph Lee was published in the IEEE Transactions on Industrial Applications. The effect of this paper was to realize the need to protect people from the hazards of arc flash. Four separate industry standards concern the prevention of arc flash incidents:

OSHA 29 Code of Federal Regulations (CFR) Part 1910 Subpart S.

NFPA 70 National Electrical Code.

NFPA 70E Standard for Electrical Safety Requirements for Employee Workplaces.

IEEE Standard 1584 Guide for Performing Arc Flash Hazard Calculations.

NFPA offers free access to their documents and standards and can be access at the following link:

https://www.nfpa.org/Codes-and-Standards/All-Codes-and-Standards/Free-access

Compliance with OSHA involves adherence to a six-point plan:

A facility must provide, and be able to demonstrate, a safety program with defined responsibilities.

Calculations for the degree of arc flash hazard.

Correct personal protective equipment (PPE) for workers.

Training for workers on the hazards of arc flash.

Appropriate tools for safe working.

Warning labels on equipment. Note the equipment owners, not the manufacturers is responsible for labeling equipment and their information. The labels shall contain sufficient information allow for the selection of appropriated PPE.

Arc Flash Concepts Page 2

Companies will be cited and fined for not complying with these standards.

Arc Flash Risk Assessment

The Arc Flash Risk Assessment method used in this report is the Incident Energy Analysis Method. This method uses the incident energy exposure level based on working distance of the employee from the prospective arc source. Arc-rated clothing and other PPE shall be based on the incident energy exposure associated with the task.

The incident energy analysis shall take into consideration overcurrent protective device characteristics and fault clearing time. This study shall be updated when changes occur that could affect these results and reviewed for accuracy at intervals not to exceed 5 year.

Personal Protective Equipment (PPE)

NFPA 70E permits Table 130.5(G) be used to identify the arc-rated clothing and other PPE requirements.

Equipment Labeling

Incident Energy Method requires specific information be included on equipment labels. For this study the following information is included:

1. 1 Nominal system voltage

2. Arc Flash boundary

3. Available incident energy

4. Working distance

Steps required for a flash hazard analysis

To perform an arc flash hazard analysis, data is collected about the facility's power distribution system.

The data includes the arrangement of components on a one-line drawing with nameplate specifications of every device. Also required are details of the lengths and cross section area of all cables. The utility should be contacted for information including the minimum and maximum fault currents that can be expected at the entrance to the facility. Once the data has been collected, a short circuit analysis followed by a coordination study should be performed. The resultant data is then used to determine arc flash incident energy levels based on equations described by IEEE Standard 1584. These equations will produce the necessary flash protection boundary distances and incident energy to determine the minimum PPE requirement.

Short-Circuit Study

The short-circuit study is based on a review of one-line drawings. The drawings must be created if they do not exist, and field-verified if they do. Maximum available fault current is calculated at each significant point in system. Each interrupting protective device is then analyzed to determine whether it is appropriately designed and sized to interrupt the circuit in the event of a bolted type of short circuit. Next, the associated equipment must be reviewed to insure that the bus bar is adequately braced to handle the

Arc Flash Concepts Page 3 available fault current. Finally, the bolted fault currents are converted into arc fault currents for additional analysis.

Coordination Study

A coordination study is the examination of the electrical system and available documentation with the goal of ensuring that over-current protection devices are properly designed and coordinated. Over-current protective devices are rated, selected and adjusted so only the fault current carrying device nearest the fault opens to isolate a faulted circuit from the system. This permits the rest of the system to remain in operation, providing maximum service continuity. The study consists of time-current coordination curves that illustrate coordination among the devices shown on the one-line diagram. Note that protective devices are set or adjusted so that pickup currents and operating times are short but sufficient to override system transient overloads such as inrush currents experienced when energizing transformers or starting motors.

The Problems

Now that the hazards associated with arc flash have been brought to our attention, we face the problem of trying to eliminate or at least reduce those hazards. The following discusses some of these problems and the subtleties in implementing corrective actions.

There are several problems in dealing with Arc Flash Analysis:

1. Being overly conservative in your short circuit analysis may result in the required PPE protection category being set at a level higher than necessary.

Category 4 PPE

The above figure is a person in a full Category 4 suit. This suit will provide the necessary protection, but it is cumbersome to work in, it is hot, and it provides poor visibility.

Arc Flash Concepts Page 4

The suits will make many tasks very difficult, if not impossible, to perform. Because of their restrictions to vision and movement, they may even make some tasks more dangerous. There are definitely times when this type of protection is both necessary and required, but being overly conservative will result in excessive stress to workers and unacceptable time to make repairs or adjustments.

2. Relying upon quick analysis methods can expose you to unexpected liabilities. There are a number of shortcuts being offered by individuals and companies that can have disastrous results. Be sure that your methods will stand up to analysis and peer review.Cure-all solutions are being promoted, such as the installation of current-limiting fuses. Pfeiffer Engineering is a firm believer in the use of fuses, particularly current-limiting types, but as will be shown below, they are not always the answer. They are definitely not a quick fix solution.

3. Being overly conservative when performing a short circuit analysis results in the misapplication of circuit protection equipment, which in turn has the consequence of calculated Arc Flash levels being higher than they actually are.

4. The calculated bolted fault or short circuit current is a worst-case calculation that assumes very low short circuit impedance. It is a short circuit connection based upon two conductors being bolted together to form the short. In reality, most short circuits are less than ideal resulting in fault currents that are less than the calculated bolted short circuit condition.

5. On the other hand, the Arc Fault should be a more predictable occurrence. The arc fault calculations assume that there is a physical gap between conductors that was bridged by something resulting in the formation of an arc. Once the arc is formed and plasma is produced, the arc current should closely approximate the calculated fault levels. The Arc Fault calculations are an approximation based upon research and testing similar to the short circuit analysis methods. They are not exact and therefore one needs to be careful when using the results.

Solution

The solution is to first perform, as accurately as practical, a short circuit analysis. The goal for most people performing a short circuit analysis has always been to error toward the conservative. For example, when a cable length was needed, it is the practice to always use the shortest practical value, which would result in higher calculated short circuit current values. When the public utility is contacted, it is the practice to only ask for the worse case short circuit value.

The overall result is that the short circuit values are always calculated on the high side. When doing a short circuit analysis for sizing the interrupting capability of protection equipment, this is the best practice.

But, it is not the best practice when evaluating equipment for Arc Faults and establishing PPE requirements. This is extremely significant, and quite non-intuitive, situation.

Arc Fault current (Ifc) is derived from the available bolted short circuit or fault current (Isc) and is always substantially less than its corresponding short circuit current. The IEEE has established formula for calculating (estimating) the Ifc and they provide a spreadsheet. The following are example results from using their formula:

Bolted Fault Current Arc Fault Current

@ 480 V

Arc Flash Concepts Page 5

10 kA = 6.56 kA

20 kA = 11.85 kA

30 kA = 16.76 kA

40 kA = 21.43 kA

What is now important is to obtain:

1. The expected maximum (worse case) bolted short circuit current.

2. The minimum and maximum voltage to the facility.

3. The minimum expected short circuit current.

Also needed are definitions of the operating modes of the facility such as:

1. What are the minimum and maximum motor loads expected during normal operation and off-hour operation.

2. Variation in the sources of supply to the plant, such as alternate feeders or co-generation.

The data from the public utility and the determination of the facility's modes of operation should be converted into the maximum and minimum Arc Fault current at various locations in the plant. These results are applied to protective device coordination studies, where the protective devices are evaluated, and adjusted, if necessary, allowing the proper PPE categories to be determined.

The following coordination curve illustrates the point:

Arc Flash Concepts Page 6

The figure above shows the coordination curve for the secondary of a 1000 kVA 480 V transformer. The curve shows two types of secondary protection, a fuse and a circuit breaker, each selected based upon the National Electrical Code requirements. The fuse is a KLP-C 1600A and the circuit breaker is a Westinghouse HND breaker with a Digitrip.

All transformers limit the amount of fault current that can pass through the transformer. This is a function of the transformer's impedance. The coordination curve shows a line for the Isc, the maximum short circuit current that can pass through this transformer (20,741 amps). The Isc value used assumes that there actually is sufficient current available at the primary to provide 20,741 amps on the secondary.

Based upon the IEEE formula, the calculated Arc Fault current Ifc is 12,230 amps. Using these two currents and the coordination curve one can estimate the time the circuit breaker and the fuse will take to clear the fault.

Bolted Fault Condition:

Fuse clears in 0.22 seconds Circuit Breaker clears in 0.02 seconds

Arc Fault Condition

Fuse clears in 1.80 seconds Circuit Breaker clears in 0.02 seconds

In 2000, Doughty, Floyd, and Neal published Predicting Incident Energy to Better Manage the Electric Arc Hazard on 600-V Power Distribution Systems, which defined incident energy based on fault duty, working distance and clearing time for arcs in air or in an enclosure as follows:

EMA = 5271 DA

-1.9593 tA[0.0016F2 – 0.0076F + 0.8939]

EMB = 1038.7 DB

-1.4738 tA[0.0093F2 – 0.3453F + 5.9675]

Where:

EMA = Incident Energy (cal/cm2 for an arc in open air EMB = Incident Energy (cal/cm2 for an arc in a box (20 inch maximum) DA, DB = Distance from the arc in inches F = Bolted Fault Current (kA) tA = Time or arc exposure in seconds

From the incident energy levels the PPE category can be determined.

Fuse 74 cal/cm2 Category 4 PPE Circuit Breaker 0.8 cal/cm2 Category 0 PPE

Clearly, in this example the circuit breaker outperforms the current-limiting fuse resulting in a minimal "worker friendly" PPE requirement.

In the above example both the Arc Fault current and the Bolted Fault current are less than the current-limiting point for the fuse, which is approximately 28,000 amps. Thus, there is no current-limit effect from

Arc Flash Concepts Page 7 using the fuse. Current-limiting fuses often do provide additional protection and they are very good devices but they must be applied properly. In this example, the circuit breaker provides the best protection.

Studying this example further, let us assume that the fuse and the circuit breaker are at the main of a facility and the facility is served by a much larger transformer where the worse-case bolted short circuit current as reported by the utility is 60,000 amps. Under this condition the arc fault current would be 30,300 amps. In this case, the fuse would open in 1/4 cycle and would limit the fault current.

The EMB would equal 1.15 cal/ cm2, which falls under a category 0 PPE.

In the next example we have a fuse and a circuit breaker protecting a 125 Hp motor. The fuse is a LLS-RK 200 A and the circuit breaker is a Westinghouse HKD with a Digitrip. There are three Arc Fault currents analyzed.

Currents:

Point 1 Arc Fault Current 3100 Amps Bolted Fault Current 4200 Amps

Point 2 Arc Fault Current 2200 Amps Bolted Fault Current 2800 Amps

Point 3 Arc Fault Current 1800 Amps Bolted Fault Current 2200 Amps Results:

Clearing Times:

Point 1 Circuit Breaker clears in .02 seconds 1.42 cal/ cm2 PPE Cat. 1

Arc Flash Concepts Page 8

Fuse clears in .02 seconds 1.42 cal/ cm2 PPE Cat. 1 Point 2

Circuit Breaker clears in .02 seconds 1.42 cal/ cm2 PPE Cat. 1 Fuse clears in .1 seconds 7.7 cal/ cm2 PPE Cat. 2

Point 3 Circuit Breaker clears in .02 seconds 1.42 cal/ cm2 PPE Cat. 1 Fuse clears in 1.0seconds 78.8 cal/ cm2 PPE Cat. 4

At an Arc Fault current of 4000 amps the fuse will begin to current limit and will open the circuit in ¼ cycle reducing the PPE category to 0.

The three points analyzed show that a relatively small change in calculated bolted fault current has a major effect on the calculated arc fault current. This situation could easily lead to the misapplication of circuit protection equipment or inappropriate adjustment of same. It should also be noted that as the calculated arc fault current is reduced, the clearing time increases, resulting in the incident energy level increasing and thus, the PPE requirement increases.

In reality, the arc current is primarily affected by facility operating conditions, i.e. motor contribution and changes in the fault current coming from the utility. The examples illustrate that the accuracy required when calculating short currents has to be improved over traditional methods. Both reliability and arc fault conditions must now be considered when performing coordination studies.

The Risk

In a study of 33 plants with 4892 busses or switch points under 600 volts, the median incident energy was only 2.1 cal/ cm2, however many busses had quite high incident energy levels1:

24% of busses over 8 cal/ cm2 PPE 2 12% of busses over 40 cal/ cm2 PPE 4 5% of busses over 85 cal/ cm2 Deadly - no protection 1% of busses over 205 cal/ cm2 Deadly - no protection

Risks to personnel include:

Burns Damaging sound levels High pressure - 720 lbs/ft2 eardrums rupture, 1728 to 2160 lbs/ft2 lung damage

Conclusions

1. A reduction in bolted fault current and thus a reduction in arc fault current can actually result in a worse situation. In the motor example above an arc fault current reduction from 4000 amps to 1800 amps resulted in an increase in arc fault energy from 0.6 cal/ cm2 to 78.8 cal/ cm2. Exactly the opposite one would expect before doing the math. In terms of the above example coordination curves, this occurs because the arc fault current moves from the instantaneous portion at the bottom of the coordination curve to a point higher up, incurring a the time delay before the device trips.

Arc Flash Concepts Page 9

2. Overly conservative short circuit analysis will result in bolted short circuit numbers that may well result in the misapplication of circuit protection equipment.

3. It is very important to obtain the minimum available short circuit current as well as the maximum short circuit current from the electric utility. Voltage fluctuations in the plant supply should be considered when developing the short circuit calculations. The arc fault calculations need to be evaluated at more than just the worst case and the minimum case conditions. In the example above, a reduction in the arc fault current actually resulted in worse conditions. This represents a subtle, but extremely significant, change in the methodology of short circuit analysis.

4. Apart from the fines, nominal compliance with the regulations will cause workers to have to wear cumbersome PPE. This will result in little or no high voltage maintenance being performed, eventually compromising safety, equipment operation, and ultimately productivity. Arc flash is a risk management issue.

5. Have a registered professional engineering firm perform the calculations for arc flash hazards for the devices in your facility and have them recommend any necessary plans that when executed would result in the lowest category of PPE being required.

Notes:

Short circuit analysis is based upon a number of assumptions; any or all may change over time;

1. Available short circuit current from the utility may vary, particularly in areas where there has been a significant expansion of, or change to, the electrical systems.

2. The number of motors running at the time of a fault affects the amount of short circuit current and arc fault current available (motor contribution).

3. The facility voltage often varies as a function of time of day. The utility is often more loaded during the day.

Similarly, the arc fault may also be affected by variations in any of the following:

1. The available short circuit current.

2. Dirt buildup in the equipment that may affect the conductive path.

3. Moisture (humidity).

4. Circuit supply voltage.

5. Amount of motor contribution during a fault

Definitions

Bolted Fault - Short circuit current resulting from conductors at different potentials becoming solidly connected together.

Arc Fault – Is short circuit current through an air gap resulting in an open air arc. This results in higher circuit impedance with respect to a bolted fault and thus lower fault current.

File details come from the government source that posted it. Updated .