GI104-Addm 1 589A4-24-101.pdf
PDF 546 KB Posted
- Solicitation number
- 36C25525R0114
About this file
This document is a detailed floor plan and infection control drawing for a VA medical facility renovation project located at 800 Hospital Drive in Columbia, Missouri. The drawing (GI104) provides comprehensive infection control and phasing information for the fourth, fifth, sixth floors, machine level, and roof of a building being renovated to correct reusable medical equipment storage (Project Number 589A4-24-101).
The drawing includes critical details such as Infection Control Risk Assessment (ICRA) levels, construction sequencing, and specific work areas. Key elements include installing new heating water systems, clean steam generation, and work in multiple rooms across different floors. The document specifies four levels of infection control precautions, with detailed requirements for dust control, barrier installation, and negative air pressure management. The project involves phased construction with specific sequencing for ACA (likely a specific building area) and non-ACA construction, emphasizing careful coordination to minimize disruption to ongoing medical facility operations.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Na N M La L K Jb J Hb H Ga G F Ea
3.7
4.6
5.4
5.5
6.2
6.3
6.7
7.2
8.2
9.1
7.6
Ja
123 SF
CLEAN
STORAGE
AE307
F3
AE307
F1
LEVEL II - LOW RISK LEVEL IV - HIGH RISK
T
T
T
T
I3
I1
I4
PH9
I5
N M La L K Jb J Hb H Ga G F
3.7
4.6
5.4
5.5
6.2
6.3
6.7
7.2
8.2
9.1
7.6
Ja N M La L K Jb J Hb H Ga G F
3.7
4.6
5.4
5.5
6.2
6.3
6.7
7.2
8.2
9.1
7.6
Ja
LEVEL II - LOW RISK
I2 I6
PH22
STAFF
TLT.
REHAB
COOR.
TELE
HEALTH
PSA
OT
SUPER.
AO
CHIEF
PM&R
EXAM
BREAK
RM.
HSKPG.
PM&R
EXAM
ROOM 3
PM&R
EXAM
ROOM 2
PM&R
EXAM
ROOM 3
PM&R
EXAM
ROOM 4
NURSE
NAVIGATOR
EMG/SCI
PAIN&
PRM
VVC/TM
PAIN BH
STAIR #2
OIT/CLO.
439C
OIT/CLO.
439B
CLO.
439A
PT/OR
STOR.
PT/OT
EXAM
BARIATRIC
ELEC.
PT GYM
PT/OT
SWAMP
CORRIDOR
C43
WAIT.
CORRIDOR
C42
STG.
404A
WC
STOR./SHOP
WOMENS
TLT
MENS TLT
MSA
CHECKIN/OUT
PROCEDURE
ROOM
NURSES
PROCEDURE
ROOM
CORRIDOR
C496
TLT
PM&R
SWAMP
SOILED
HOLDING
492 PAIN
SWAMP
TLT
EXISTING
ELEC.
492A
PAIN
EXAM
CORRIDOR
C499
CORRIDOR
C495
PAIN
PHARM
PAIN
EXAM RM.
PAIN
EXAM RM.
PAIN
EXAM RM.
WORKSTATION
CORRIDOR
C47
CORRIDOR
C498
PROST.
CHEIF
PROST.
REP.
TLT
D385
PROST.
ASST.
CHIEF
DUST RM.
ANTE
FITTING/
EXAM RM.
MAINT.
421A
FUME RM.
PLASTER
CLEAN
LAB
PER.
CLNC.
GROUP
RM.
FITTING/
EXAM RM.
PROST.
PURCHASING
D377
FITTING/
EXAM RM.
CORRIDOR
C46
PER.
CLNC.
MASSAGE
PROST.
WAIT.
STOR.
426A
CHIRO.
EXAM
CHIRO.
EXAM
CORRIDOR
C45
ACUPUNCTURE
ACUPUNCTURE
PELVIC
PELVIC
PT/OT
EXAM
436PT TLT.
437A
EQUIP
PT/OT
EXAM
OT TLT.
440A
OT TRAIN.
RM.
CORRIDOR
C44
PROST.
CHECKIN
405A
PROST.
STOCK
RM.
ELEV.
LOBBY
SOILED
DISP
401A
CLEAN
LINEN
450A
LOBBY/
CORRIDOR
CORRIDOR
C41
ELEC.
OI&T
L K Jb J Hb H
5.4
5.5
6.2
6.3
6.7
7.2
7.6
Ja
C43
L K Jb J Hb H
5.4
5.5
6.2
6.3
6.7
7.2
7.6
Ja
C43
LEVEL OF INFECTION PREVENTION
AND CONTROL PRECAUTIONS*
AREAS OUTSIDE SCOPE OF WORK
LEVEL I - NONINVASIVE WORK
LEVEL II - ALL CONTROL MEASURES IN LEVEL I AND THE
FOLLOWING:
CONTROL AIRBORNE DUST FROM DISPERSING INTO
OCCUPIED AREAS, REMOVE OR ISOLATE AIR
DIFFUSERS (SUPPLY AND RETURN), SEAL DOORS TO
PREVENT DUST MIGRATION. INSTALL A STICKY
(DUST COLLECTION) MAT AT ENTRANCE OF
CONTAINED WORK AREA.
LEVEL III - ALL CONTROL MEASURES IN LEVELS I AND II AND
THE FOLLOWING:
CRITICAL BARRIERS MEETING NFPA 241
REQUIREMENTS MUST EXTEND TO THE CEILING OR
IF CEILING TILE IS REMOVED, TO THE DECK ABOVE.
SEAL ALL PENETRATIONS IN CONTAINMENT
BARRIERS. MAINTAIN NEGATIVE PRESSURIZATION
OF THE ENTIRE WORKSPACE. INSTALL A
DIFFERENTIAL PRESSURE SENSING DEVICE.
LEVEL IV - ALL CONTROL MEASURES IN LEVELS I, II AND III AND
THE FOLLOWING:
BARRIERS MUST BE HARD BARRIERS.
CONTAINMENT MUST INCLUDE AN ANTEROOM
GENERAL ICRA NOTES:
1. ALL "RATINGS" DEPICTED ON THESE DRAWINGS ARE FOR
REFERENCE AND BID PURPOSES ONLY. ICRA SHALL BE
COMPLETED FOR EACH AREA AND RATINGS WILL BE BASED
ON WORK DURATION.
2. FOR FURTHER DIRECTION ON ICRA REQUIREMENTS SEE
SPECIFICATION SECTION 01 00 00 - GENERAL REQUIREMENTS,
PARAGRAPH 1.7, G. AND ATTACHMENT 01 00 10.01, VHA-ICRA
1.2 (OCTOBER 2024), FOR MORE DEFINED CONTROL
MEASURES THAT ARE THE RESPONSIBILITY OF THE GENERAL
CONTRACTOR FOR ALL WORK AREAS.
3. TABLE 5 IN THE DOCUMENT CONTAINED IN THE
SPECIFICATION SECTION 01 00 00, DEFINES SPECIFIC
CONTROLS THAT ARE REQUIRED TO BE IN PLACE BEFORE AN
ACTIVITY BEGINS, DEPENDING ON THE ICRA LEVEL OF
PRECAUTION ASSIGNED ON THIS FLOOR PLAN.
4. TABLE 6 IN THE DOCUMENT CONTAINED IN THE
SPECIFICATION SECTION 01 00 00, DEFINES SPECIFIC
MEASURES THAT ARE REQUIRED UPON COMPLETION OF
ACTIVITIES IN AN AREA, AND INSPECTED PRIOR TO
TERMINATING MEASURES DEFINED IN TABLE
5. ALL AREA CLASSIFIED AS ICRA LEVEL IV SHALL HAVE A
TEMPORARY ANTEROOM, AT EVERY ENTRY DOOR, INSTALLED
TO SEPARATE THAT AREA UNDER CONSTRUCTION FROM ANY
ADJACENT AREAS THAT ARE STILL OCCUPIED BY THE VA.
6. CRAWL SPACES & ATTICS ARE CLASSIFIED AS ICRA LEVEL II.
7. CONTRACTOR TO CONSTRUCT BARRIER TO MEET ICRA
PERFORMANCE REQUIREMENTS.
8. CONTRACTOR TO PROVIDE DUST MATS AT THE DOOR INTO
THE CONSTRUCTION ZONE.
9. SEE ENLARGED FLOOR PLANS ON AE300-SERIES SHEETS FOR
ADDITIONAL ICRA KEYNOTES.
10. CONTRACTOR SHALL PROVIDE AT A MINIMUM ONE (1) HEPA
CART TO WORK FROM IN DEFINED AREAS. VA DOES HAVE A
CART, BUT IT SHALL NOT BE THE PRIMARY AS VA WILL
REQUIRE FOR ITS OWN WORK.
PATIENT RISK GROUP CONSTRUCTION PROJECT TYPE
LOW RISK GROUP
MEDIUM RISK GROUP
HIGH RISK GROUP
HIGHEST RISK GROUP
I
III
TYPE A
I
I
II
III
TYPE B
II
II
IV
IV
TYPE C
III
II
IV
IV
TYPE D
IV
III
Table 4 - VHA-ICRA 1.2 (Oct 2024) - pg 5 of 10
TYPICAL FLOOR PLAN ICRA LABEL*
PATIENT RISK CATEGORY**
(Table 3 - VHA-ICRA 1.2 (Oct 2024) - pg 4 of 10)
LEVEL OF INFECTION
PREVENTION AND
CONTROL PRECAUTIONS**
(Table 5 - VHA-ICRA 1.2 (Oct 2024) - pg 4 of 10)
LEVEL XX - XXX RISK
* SEE LEVEL OF INFECTION PREVENTION PREVENTION AND CONTROL
PRECAUTIONS LEGEND & Table 5 - VHA-ICRA 1.2 (Oct 2024) - pgs 5-6 of 10)
** SEE VHA-ICRA 1.2 VHA INFECTION CONTROL RISK ASSESSMENT FOR
CONSTRUCTION, RENOVATION AND MAINTENANCE
PHASING NOTES:
A. REFER TO PHASING NOTES ON GI100.
PHASING SEQUENCING:
1. REFER TO PHASING GENERAL NOTES ON GI003.
2. REFER TO MECHANICAL, PLUMBING AND ELECTRICAL
DRAWINGS FOR WORK ASSOCIATED WITH HVAC RENOVATION.
3. COORDINATE WITH THE COR HOW MUCH OF THE SPACE THE
CONTRACTOR CAN TAKE OVER AT A TIME, AND IF WORK IS TO
BE DONE ON NIGHTS AND WEEKENDS.
ACA CONSTRUCTION SEQUENCING (PA#)
1. INSTALL ACA HEAT EXCHANGERS, DISTRIBUTION PUMPS,
EXPANSION TANK, AIR SEPARATOR, AND ASSOCIATED NEW
HEATING WATER PIPING IN MECH ROOM E003.
2. REMOVE EXISTING HEATING WATER EQUIPMENT AND
ASSOCIATED PIPING AFTER NEW SYSTEM IS OPERATIONAL.
3. INSTALL ACA CLEAN STEAM GENERATOR.
4. REPLACE ACA-AHU-1, -2, AND -3 ONE AT A TIME. ACA AHUS
#1, #2, AND #3 SERVE A COMMON SUPPLY AIR AND RETURN
AIR AND HAVE N+1 REDUNDANCY. EACH NEW AHU
INSTALLATION SHALL BE COMPLETED AND COMMISSIONED
PRIOR TO THE DEMOLITION OF THE SUBSEQUENT AHU.
5. REPLACE ACA-AHU-4. ACA-AHU-4 DUCT SYSTEM IS
INTERCONNECTED TO ACA AHUS #1, #2, AND #3. ADJUST
APPLICABLE DAMPERS TO BACKFEED ACA-AHU-4 DUCT
SYSTEM PRIOR TO THE DEMOLITION OF ACA-AHU-4.
6. INSTALL REMAINING WORK IN THE ACA.
NON-ACA CONSTRUCTION SEQUENCING (PH#)
1. INSTALL NEW CLEAN STEAM GENERATION SYSTEMS
INCLUDING HUMIDIFIER DISPERSION GRIDS AND
ASSOCIATED PIPING.
2. INSTALL WORK ASSOCIATED WITH ROOM D123 AND THE
PATHOLOGY LAB.
3. INSTALL WORK ASSOCIATED WITH ROOMS G108, G124,
G135, G136, AND G138.
4. INSTALL WORK ASSOCIATED WITH ROOMS A117D, B105,
C136, C137, AND D199.
5. INSTALL WORK ASSOCIATED WITH ROOM B208/B228.
6. INSTALL WORK ASSOCIATED WITH ROOMS B336, B338,
G346, AND G347.
7. INSTALL WORK ASSOCIATED WITH ROOMS A321, A336,
C347, AND D317.
AREAS OUTSIDE
SCOPE OF WORK
SYMBOL
FIRE WALL LEGEND
DESCRIPTION
1-HOUR FIRE BARRIER
2-HOUR FIRE BARRIER
1-HOUR SMOKE BARRIER
1-HOUR HAZARDOUS AREA FIRE BARRIERHZ HZ HZ
RICHARD
JOSEPH
ONKEN
A-5125
A
R C H I T E
C
T
S T
A T
E
O F N E B
R A
S K
A
6/23/2025
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
321 4 5 6 7 8 9 10
Alesia Architecture P.C.
3705 North 200th Street Elkhorn, Nebraska 68022 Phone: (402) 291-6941 o n e e ig h th i n c h o n e f o o t th re e i n c h e s o n e f o o t o n e a n d o n e h a lf i n c h e s o n e f o o t o n e i n c h o n e f o o t th re e q u a rt e rs i n c h o n e f o o t o n e h a lf i n c h o n e f o o t th re e e ig h th s i n c h o n e f o o t o n e q u a rt e r in c h o n e f o o t
100% FINAL BID
DOCUMENTS
CORRECT REUSABLE
MEDICAL EQUIP STORAGE
589A4-24-101
800 HOSPITAL DR, COLUMBIA, MO
Shaffer Stevens & Schaap 1070 Howard Street Omaha, Nebraska 68102 Phone: (402) 455-7698
Astral Engineers P.O. box 190Omaha, Rancho Cucamonga, CA 91729 Phone: (909) 903-0015
Crux Consulting 18312 Harney St. / 663 N 132nd St. #73 Elkhorn, NE 68022 / Omaha, NE 68154 Phone: (402) 708-0383
Brighttree Studios 301 Brush Creek Rd Warrendale, PA 15086
(412) 212-7515
STAMP
06/26/2025
FOURTH, FIFTH, & SIXTH
FLOOR KEYPLAN
NORTH
E & F
OR ADDITION B A
C & D
ACA BUILDING
AREAS
AREA AREA
AREAS
G
AREA
BUILDING 1
A u to d e s k D o c s /1
A
-2
-1
C o rr e c t R e u s a b le M e d ic a l E q u ip m e n t S to ra g e /5
A
-2
-1
.A rc h
R
-C o rr e c t R e u s a b le
M e d ic a l E q u ip m e n t
S to ra g e
.r v t
/2
/2
:3
:2
P
M
GI104
FOURTH, FIFTH, SIXTH, MACH LVL & PH FLOOR
PLANS - INFECTION CONTROL - PHASING
AHT SW
3/64" = 1'-0"1
FOURTH FLOOR - FLOOR PLAN - INFECTION CONTROL
3/64" = 1'-0"2
FIFTH FLOOR - FLOOR PLAN - INFECTION CONTROL
3/64" = 1'-0"3
SIXTH FLOOR - FLOOR PLAN - INFECTION CONTROL
3/64" = 1'-0"6
PENTHOUSE UPPER ELEV. MACH. LEVEL
3/64" = 1'-0"7
PENTHOUSE FLOOR AND ROOF
NO WORK ON FIFTH FLOOR - SHOWN FOR REFERENCE ONLY
I# KEYNOTE LEGEND-ICRA
KEY KEYNOTE
I1 INSTALL TEMPORARY 1 HR CONSTRUCTION
ICRA BARRIER TO SEPARATE CONSTRUCTION
AREA FROM OCCUPIED SPACE - SEE E4/GI601
& F3/GI601.
I2 INSTALL TEMPORARY PLASTIC FIRE
RESISTANT DUST BARRIER. WORK TO
INSTALL MAY ONLY BE DURING NON
FUNCTIONAL MEDICAL CENTER HOURS.
COORDINATE W/ COR. SEE E2/GI601.
I3 INSTALL FIRE RESISTANT TEMPORARY DOOR
AT OPENING AND MATCH RATING OF ICRA
BARRIER, TYP. SEE E4/GI601 & F3/GI601.
I4 PLACE TACKY CONSTRUCTION WALK-OFF
MATS AT ENTRANCE AND EXIT SIDE OF
CONSTRUCTION ACTIVITY AREAS, TYP. SEE
F1/GI601 & F3/GI601.
I5 FOR CLASS III AND GREATER, NEG AIR
MACHINE IS REQUIRED AND SHALL BE
LOCATED EITHER AT THE ICRA BARRIER OR
AT AN EXTERIOR WINDOW. COORDINATE
WITH VA INFECTIOUS PREVENTION TEAM AND
COR.
I6 EXISTING DOOR BEHIND POLY PLASTIC
SHEETING - SEE E2/GI601.
PHASING LEGEND - HOSPITAL
KEY KEYNOTE
PH9 INSTALL WORK ASSOCIATED WITH ROOM
490.
PH22 ROOF DRAIN INSTALL AFFECTS ROOMS 600 &
601.
PH#
KEYNOTE LEGEND-CEILINGS
KEY KEYNOTE
C43 NO ARCHITECTURAL WORK IN THIS ROOM -
SEE MEP.
C#
Mark Revisions: Date:
1 AMENDMENT #1 - BIDDER QUESTIONS-RESPONSES 07/29/2025
1____
| Sheets |
| GI104 - FOURTH, FIFTH, SIXTH, MACH LVL & PH FLOOR PLANS - INFECTION CONTROL - PHASING |
File details come from the government source that posted it. Updated .