This is a Request for Proposal (RFP) for a construction contract issued by the Department of Veterans Affairs Network Contracting Office (NCO) 15. The solicitation (36C25525R0114) is for the Correct Reusable Medical Equipment Storage project at the Harry S. Truman Medical Center in Columbia, Missouri, with an estimated construction magnitude between $5,000,000 and $10,000,000. The contract is set aside exclusively for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) and will be awarded using a Lowest Price Technically Acceptable (LPTA) source selection process.

The project requires a 540-calendar day performance period, with a pre-proposal meeting scheduled for July 11, 2025, and proposal submissions due by 2 PM CDT on August 8, 2025. Contractors must be registered in SAM and certified in SBA VetCert, with proposals evaluated across seven technical factors including past performance, construction experience, subcontractor qualifications, key personnel, safety plan, and infection control plan. The NAICS code is 236220 (Commercial and Institutional Building Construction), with a small business size standard of $45 Million, and the contract will involve renovation work in an active hospital environment.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

36C25525R0114

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C25525R0114 X 07-07-2025 36C25525R0114 589A4-24-101 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth

KS

66048 Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth

KS

66048 James Petrik and Jeanette Mathena 913-946-1143, 913-946-1129 The Department of Veteran Affairs, NCO15, intends to award a Construction Contract for Project 589A4-24-101, Correct Reuseable Medical Equipment Storage located at the Harry S Truman Medical Center, Columbia, MO. This requirement is being solicited as a Service-Disabled Veteran Owned Small Business (SDVOSB) set-aside. Proposals received in response to this solicitation will be evaluated in accordance with the Federal Acquisition FAR 15.102 Best Value Lowest Price Technically Acceptable (LPTA) source Selection process.

The NAICS code for this project is 236220.

General Construction size standard is 45.0 Million.

Estimate of the construction magnitude for this project: $5,000,000.00 to $10,000,000.00.

VENDOR UEI CODE:______________________________

The Pre-Proposal meeting will be held at the Harry S. Truman VAMC, Columbia, MO., on July 11, 2025 starting at 10:00 am with the walk-through of the project immediately following.

All Contractors are to meet at the Facilities Office Trailer Building 22.

Proposals must be e-mailed to jeanette.mathena@va.gov and james.petrik@va.gov Questions on this project are due by 4:00 PM CDT July 18, 2025.

It is the contractors responsibility to make sure proposal documents are received by the contracting officer.

It is the contractors responsibility to monitor https://sam.gov for all amendments to the Solicitation.

All contractor's and joint ventures must be registered in SAM and Certified in SBA VetCert by the proposal due date.

Proposals submitted by teaming arrangements other than VA Joint Ventures will not be considered.

Notice: Clause 52.222-37 Employment Reports on Disabled Veterans and Veterans is incorporated by reference in this Solicitation. Public Law (PL 105-339) Section 1354 provides that no agency may enter into a contract with a contractor who has not filed a VETS-4212 report for the preceding fiscal year under title 38 Section 4212 (d).

The Project period of Performance is 540 calendar days after issuance of Notice to Proceed.

The Period of Performance includes all work, cleanup and closeout documents.

X X 52.211-10 X zero

2 PM

CDT

08-08-2025 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

SEE PAGE 5 for BID ITEMS 36C255 Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway Leavenworth

KS

66048 36C255 Department of Veterans Affairs Financial Services Center http://www.fsc.va.gov/einvoice.asp Austin

TX

877-353-9791 512-460-5429 X

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
A.3 PRICE/COST SCHEDULE5
ITEM INFORMATION5
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS6
1.1PROPOSAL INSTRUCTIONS TO OFFERORS6
1.2 APPENDIX 1 PRICE BREAKDOWN CALCULATION SELF PERFORMANCE AND SUB CONTRACT WORK18
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS21
2.1 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023)21
2.2 52.216-1 TYPE OF CONTRACT (APR 1984)21
2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)21
2.4 52.228-1 BID GUARANTEE (SEP 1996)22
2.5 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)22
2.6 52.233-2 SERVICE OF PROTEST (SEP 2006)23
2.7 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)23
2.8 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)24
2.9 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)24
2.10 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)24
REPRESENTATIONS AND CERTIFICATIONS26
3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2025) (DEVIATION FEB 2025)26
3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)30
3.3 52.204-29 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—REPRESENTATION AND DISCLOSURES (DEC 2023)32
3.4 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)34
3.5 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—CERTIFICATION (NOV 2021)35
GENERAL CONDITIONS38
4.1 52.203-14 DISPLAY OF HOTLINE POSTER(S) (NOV 2021)38
4.2 52.204-19 INCORPORATION BY REFERENCE OF REPRESENTATIONS AND CERTIFICATIONS (DEC 2014)39
4.3 52.204-23 PROHIBITION ON CONTRACTING FOR HARDWARE, SOFTWARE, AND SERVICES DEVELOPED OR PROVIDED BY KASPERSKY LAB COVERED ENTITIES (DEC 2023)39
4.4 52.204-30 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—PROHIBITION (DEC 2023)40
4.5 52.209-9 UPDATES OF PUBLICLY AVAILABLE INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)45
4.6 52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REREPRESENTATION (JAN 2025)46
4.7 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020)49
4.8 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL LABOR RELATIONS ACT (DEC 2010)49
4.9 SUPPLEMENTAL INSURANCE REQUIREMENTS51
4.10 52.236-4 PHYSICAL DATA (APR 1984)51
4.11 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)52
4.12 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)52
4.13 52.204-25 PROHIBITION ON CONTRACTING FOR CERTAIN TELECOMMUNICATIONS AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)53
4.14 52.222-36 EQUAL OPPORTUNITY FOR WORKERS WITH DISABILITIES (JUN 2020)57
4.15 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997) ALTERNATE I (APR 1984)58
4.16 VAAR 852.219-73 VA NOTICE OF TOTAL SET-ASIDE FOR CERTIFIED SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESSES (JAN 2023) (DEVIATION)60
4.17 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)63
4.18 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)64
4.19 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (OCT 2020)65
4.20 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)66
4.21 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)67
4.22 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020)67
4.23 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)67
4.24 MANDATORY WRITTEN DISCLOSURES69
4.25 WAGE DETERMINATION69
4.26 List of Attachments80

A.3 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1.00
JB
__________________
__________________

Bid item 1-Work includes all scope communicated in the drawings and specifications.

Contract Period: Base POP Begin: 09-15-2025 POP End: 03-09-2027 PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: Z2DA - Repair or Alteration of Hospitals and Infirmaries

0.00
JB
__________________
__________________

BID ITEM #2, DEDUCT #1: Includes all scope described in Bid Item #1, excluding Bid Deduct #1 described below:

1. DEDUCT #1: Delete work associated with ACA-AHU-4 and associated utilities.

Contract Period: Base POP Begin: 09-15-2025 POP End: 03-09-2027

1.00
JB
__________________
__________________

BID ITEM #3, DEDUCT #2: Includes all scope described in Bid Item #2, excluding Bid Deduct #2 described below:

1. DEDUCT #2: Delete work associated with ACA-AHU-3 and associated utilities.

Contract Period: Base POP Begin:

POP End:

PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: Z2DA - Repair or Alteration of Hospitals and Infirmaries Dates are estimated

GRAND TOTAL
__________________

Page 1 of Page 1 of

INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS

1.1PROPOSAL INSTRUCTIONS TO OFFERORS

PROPOSAL INSTRUCTIONS TO OFFERORS

FOR LOWEST PRICE TECHNICALLY ACCEPTABLE COMPETITION

SOLICITATION: 36C25525R0114

PROJECT: Correct Reuseable Medical Equipment Storage, 589A4-24-101 LOCATION: Department of Veteran Affairs, Columbia, Missouri VAMC

1. PREPARATION AND SUBMITTAL OF PROPOSALS

a. GENERAL INFORMATION.

Selection of an offeror for contract award will be made based on an assessment of each offeror’s response to the Request for Proposal (RFP). As a Request for Proposals (RFP) based on Lowest Price Technically Acceptable (LPTA) Source Selection Process, in accordance with Federal Acquisition Regulation (FAR) Part 15.101-2, the VA will make the award based on the lowest evaluated price of proposals meeting or exceeding the acceptability standards for non-cost factors. The Seven (7) evaluation factors for determination of technical acceptability consist of:

1. Relevant Past Performance of Prime Contractor.
2. Technical Construction Experience of Prime Contractor.

3.Technical Construction Experience of the Direct Digital Controls Subcontractor.

4.Technical Construction Experience of the Mechanical Subcontractor.

5. Technical Qualifications of Proposed Key Personnel.

6. Prime Contractor Safety Plan.

7. Prime Contractor Infection Control Plan.

NOTE: Failure to comply with the RFP requirements may be grounds to eliminate the proposal from further consideration for contract award.

b. THE OFFER.

The submission of the documentation specified below will constitute the Offeror’s acceptance of the terms and conditions of the RFP, including the Plans & Specifications for the construction of this project. These instructions prescribe the format for the proposal and describe the approach for the development and presentation of proposal data. These instructions are designed to ensure the submission of necessary information to provide for the understanding and comprehensive evaluation of proposals.

c. AWARD BASED ON INITIAL OFFERS.

Pursuant to clause 52.215-1 (included by reference), the Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror’s initial proposal should contain the offeror’s best terms from a cost or price, and technical qualifications standpoint. The VA reserves the right to conduct discussions if the Contracting Officer later determines such discussions to be necessary.

d. NUMBER OF COPIES TO SUBMIT. Offerors shall e-mail a three files to the following e-mail addresses: jeanette.mathena@va.gov and james.petrik@va.gov . The package shall include:

Volume 1 Technical Proposal and 852.219-75 VA Notice of Limitations on Subcontracting - Certificate of Compliance for Services and Construction Volume 2 Price Proposal-1442, Amendments and Appendix 1, Volume 3 - Bid Bond

Marked: ORIGINAL - RESPONSE TO RFP – 36C25524R0104

2. DOCUMENTS TO SUBMIT.

The documents to be included in the e-mail identified above consist of:

a. STANDARD FORM 1442. Submit the SF 1442 issued under this solicitation, with Blocks 10 (DUNS Number) and Blocks 14 through 20 properly filled out by the Offeror. Include acknowledgment of any and all Amendments that may have been issued, either by: (1) listing them in Block 19 of the SF 1442, or (2) including copies of the Amendment document(s) (Standard Form 30) with Blocks 8 and 15 filled in and signed, or (3) including signed acknowledgement in the form of a separate letter that includes a reference to the solicitation and amendment numbers. NOTE: Failure to acknowledge any and all Amendments issued pursuant to this solicitation may be cause for rejection of your offer.

b. OFFER GUARANTEE (BID BOND). In accordance with solicitation provision 52.228-1, Bid Guarantee, failure to furnish a bid guarantee, in the proper form and amount, by the deadline established for submitting offers, may be cause for rejection of the offer.

c. DOCUMENTATION OF TECHNICAL ACCEPTABILITY. Technical Proposal and 852.219-75 VA Notice of Limitations on Subcontracting - Certificate of Compliance for Services and Construction. Price Breakdown by Division.

Proposals received in response to this solicitation will be evaluated in accordance with procedures outlined in Federal Acquisition Regulations (FAR) Part 15.101-2 for the Lowest Price Technically Acceptable (LPTA) Offer.

The following significant Evaluation Factors will be used as the basis for determining Technical Acceptability:

1. Relevant Past Performance of Prime Contractor.

2. Technical Construction Experience of Prime Contractor.

3.Technical Construction Experience of the Direct Digital Controls Subcontractor.

4.Technical Construction Experience of the Mechanical Subcontractor.

5. Technical Qualifications of Proposed Key Personnel.

6. Prime Contractor Safety Plan.

7. Prime Contractor Infection Control Plan.

NOTE: There is a realistic possibility that some offerors may choose to submit the same construction project as a qualifying example for both the past performance and the technical experience evaluation factors. This is not prohibited, but the supporting documentation must demonstrate that the submitted projects absolutely do comply with the specific minimal requirements, identified below, for each separate evaluation factor.

FACTOR 1: RELEVANT PAST PERFORMANCE OF PRIME CONTRACTOR

To be Technically Acceptable, Offerors should identify no less than TWO (2), and no more than THREE (3), previously awarded, and completed construction contracts, which were issued by either: Federal, State, or Local Government Agencies; and/or Private Organizations. To be evaluated as Relevant Past Performance, the construction contracts submitted by offerors must involve:

A. Construction work, in an active hospital or medical facility that also includes HVAC installation, as a prime contractor.

B. A dollar magnitude equal to, or greater than $2,000,000.00.

C. Work that was 100% completed within a time period of no more than FIVE (5) years prior to the date of submitting this proposal. If the contract/work is incomplete or was completed more than five years prior to the date of submitting this proposal, it will not be deemed relevant.

For each of the submitted Relevant Past Performance contracts, provide the following information:

(1) The name of the construction contract, and the contract ID number.

(2) The name of the contracting agency or organization the contract was awarded by.

(3) The date of the construction contract award and the contract award amount in dollars.

(4) The date of the construction contract completion, and the final contract amount, in dollars.

(5) A brief description of the construction contract scope of work; and

(6) Identification of at least one point-of-contact at the organization that awarded the submitted contract, including: the name of the point-of-contact; their current mailing address; phone number; and email address (if applicable).

Factor 1 SPECIAL NOTE for Offerors That May Lack Past Performance Information: In accordance with FAR Part 15.305(a)(2), in the case of an offeror that is without a record of relevant past performance, or for whom information on past performance is not available, the offeror may not be evaluated favorably or unfavorably on past performance. Such offerors may submit relevant past performance information regarding predecessor companies; key personnel who have relevant experience; or subcontractors that will be performing major or critical aspects of this requirement, provided that such information is relevant to the construction in this solicitation. Offerors may provide information on problems encountered on the identified contracts and the offeror’s corrective actions. The government also reserves the right to consider past performance information from all available sources, in addition to any information submitted by offerors.

FACTOR 2: TECHNICAL CONSTRUCTION EXPERIENCE OF PRIME CONTRACTOR.

To be Technically Acceptable, offerors must provide evidence that they have the technical qualifications and experience needed to meet the technical performance requirements of this project. Offerors must submit no less than TWO (2) examples of their technical construction experience with projects that involved technical requirements similar to the requirements of this project. The construction project submitted must involve:

A. Work as a prime under the same NAICS code as this solicitation (236220, Commercial and Intuitional Building Construction), that involved construction for an active hospital or medical facility, that also includes HVAC installation.

B. Work of a dollar magnitude equal to, or greater than $2,000,000.00. If offering subcontracted work as proof of technical construction experience, offerors must submit evidence that supports the magnitude of the work they performed as a subcontractor.

C. Contractor must provide completed “852.219-75 VA Notice of Limitations on Subcontracting - Certificate of Compliance for Services and Construction” with technical proposal.

D. Work that is of a similar nature to the scope of work for this project. This is defined as heavy demolition, carpentry work, work above ceiling renovation including utilities being performed in an active and occupied Hospital or Medical Facility. If an offeror chooses to submit experience that was not conducted in such an area of a hospital, or Medical Facility, they must explain how the nature and complexity of the work conducted involved technical construction requirements equivalent to that described in the Plans & Specifications of this solicitation.

For each of the Technical Construction Experience projects submitted, provide the following information:

(1) The name and location of the construction project.
(2) The performance period, including the starting and completion dates.

(3) The total cost of the project in dollars.

(4) The percentage of total labor self-performed by the offeror's employees.

(5) A brief description of the construction project scope of work, which explains how the project involved work as a prime contractor under NAICS Code 236220 involving construction work that was technically similar to the project work under this Solicitation.

FACTOR 3: TECHNICAL EXPERIENCE OF THE DIRECT DIGITAL CONTROLS SUBCONTRACTOR.

Offerors must provide evidence that the Direct Digital Controls subcontractor has the technical qualifications to self-perform and experience needed to meet the technical performance requirements of this project. To be evaluated as technical experience the information submitted by offerors must involve the following:

A. Work under the NAICS code 238220, Plumbing, Heating, and Air- Conditioning Contractor.

B. Ability to meet the technical requirements of specification section 23 09 23, Direct-Digital Control system for HVAC.

C. Products or services of proposed manufacturer, suppliers and installers as follows:

1. Direct Digital Controls contractor is currently and regularly engaged in design, fabrication, and installation of HVAC control systems for hospital and/or medical centers usage.

2. Provide a list of two or more hospital and/or medical center installations where, service-related fabrication & installation of direct digital controls systems, within the past five years. Include the names and addresses of the hospital and/or medical center and the point of contact

3. Directs Digital Controls contractor has technical qualifications of at least five years of experience. Provide certifications and Company Resume/Bio of trained supervisory personnel, installation personnel, and facilities used to complete installation of control systems as required by contract documents.

4. Proposed Direct Digital Controls contractor shall submit a list of two or more prior hospital and/or medical center installations where all the contractor controls equipment they propose to furnish on this project has performed satisfactorily together under conditions of normal use. The list shall include projects that have been in operation for a period of not less than two years preceding the date of these specifications. Include the names and addresses of the hospital and/or medical center and the names of the hospital and/or medical center and the point of contact. Also included shall be project cost of direct digital control installation and project completion date.

5. Direct Digital Controls contractor shall submit proof of Tridium Niagara N4 and BACNET certifications by submitting training certification.

Special Note: When an offeror submits its proposal in response to this Request for Proposals, and the name and experience of a specific subcontractor is a required evaluation factor, then that subcontractor who is offered will be the same subcontractor who will actually perform the specified work on the project. If, during performance of the contract, it becomes necessary for the contractor to substitute a subcontractor for one of those whose qualifications were the basis for evaluation of the offer and award of the contract, the contractor shall submit to the Contracting Officer the same information that was required in the initial proposal regarding the proposed substitute subcontractor. The Contracting Officer shall have the right to review the qualifications of the proposed substitute subcontractor and to approve or disapprove its qualifications. If the proposed substitute subcontractor's qualifications are disapproved by the Contracting Officer, the contractor will propose another subcontractor who does possess equivalent qualifications.

FACTOR 4: TECHNICAL EXPERIENCE OF THE MECHANICAL SUBCONTRACTOR.

Offerors must provide evidence that the Mechanical subcontractor has the technical qualifications to self-perform and experience needed to meet the technical performance requirements of this project. To be evaluated as technical experience the information submitted by offerors must involve the following:

A. Work under the NAICS code 238220, Plumbing, Heating, and Air- Conditioning Contractor.

B. Ability to meet the technical requirements of specification Division 23 – Heating, Ventilating, and Air Conditioning (HVAC).

C. Products or services of proposed manufacturer, suppliers and installers as follows:

1. Mechanical contractor is currently and regularly engaged in design, fabrication, and installation of HVAC systems for hospital and/or medical centers usage.

2. Provide a list of two or more hospital and/or medical center installations where service-related fabrication & installation of mechanical systems, to include duct work, within the past five years. Include the names and addresses of the hospital and/or medical center and the point of contact.

3. Mechanical contractor has technical qualifications of at least five years of experience. Provide certifications and Company Resume/Bio of trained supervisory personnel, installation personnel, and facilities used to complete installation of mechanical works as required by contract documents.

4. Proposed Mechanical contractor shall submit a list of two or more prior hospital and/or medical center installations where all the equipment/material they propose to furnish on this project has performed satisfactorily together under conditions of normal use. The list shall include projects that have been in operation for a period of not less than two years preceding the date of these specifications. Include the names and addresses of the hospital and/or medical center and the names of the hospital and/or medical center and the point of contact. Also included shall be project cost of mechanical installation and project completion date.

Special Note: When an offeror submits its proposal in response to this Request for Proposals, and the name and experience of a specific subcontractor is a required evaluation factor, then that subcontractor who is offered will be the same subcontractor who will actually perform the specified work on the project. If, during performance of the contract, it becomes necessary for the contractor to substitute a subcontractor for one of those whose qualifications were the basis for evaluation of the offer and award of the contract, the contractor shall submit to the Contracting Officer the same information that was required in the initial proposal regarding the proposed substitute subcontractor. The Contracting Officer shall have the right to review the qualifications of the proposed substitute subcontractor and to approve or disapprove its qualifications. If the proposed substitute subcontractor's qualifications are disapproved by the Contracting Officer, the contractor will propose another subcontractor who does possess equivalent qualifications.

FACTOR 5. TECHNICAL QUALIFICATIONS OF PROPOSED KEY PERSONNEL.

To be Technically Acceptable, qualified offerors must submit a detailed resume of each key individual. This will be evaluated to determine if they have the appropriate technical training and or previous construction experience to meet the technical requirements directly related to demolition and renovation for an active hospital or medical facility, that includes HVAC installation or similar construction. Project Manager and Superintendent cannot be the same person No one individual can perform more than two of the staffing positions below:

(a.) Project Manager – Must have a minimum of 5 years’ experience as a project manager must provide a minimum of 3 projects with similar scope of this project. Provide the name of the construction contract, and the contract ID number; The name of the contracting agency or organization the contract was awarded by; The date of the construction contract award and the contract award amount in dollars; The date of the construction contract completion, and the final contract amount, in dollars; A brief description of the construction contract scope of work; Identification of at least one point-of-contact at the organization that awarded the submitted contract, including: the name of the point-of-contact; their current mailing address; phone number; and email address (if applicable). Note: Project Manager will be required to attend weekly project meetings in person at the station facilities office.

(b). Quality Control manager – Provide a minimum of 3 projects with similar scope of this project that they have acted as the QC manager. Provide the name of the construction contract, and the contract ID number; The name of the contracting agency or organization the contract was awarded by; and the date of the construction contract award. A brief description of the construction contract scope of work and the QC program that was implemented.; Identify at least one point-of-contact at the organization that awarded the submitted contract, including: the name of the point-of-contact; their current mailing address; phone number; and email address (if applicable). Note: Quality Control Manager will be required to be on site when work is being completed and sign off on all work prior to contractor leaving an area.

(c.) On Site Safety Officer(s); must have OSHA 30 training (must provide certificate) with a minimum of 5 years of experience as a safety officer.; provide a list of safety training, which includes at a minimum life safety, excavation safety, lock-out tag out, fall protection training, scaffold safety, crane/rigging safety. Provide a minimum of 3 projects with similar scope of this project. Provide the name of the construction contract, and the contract ID number; The name of the contracting agency or organization the contract was awarded by; Provide a brief description of the construction contract scope of work and how the safety program was implemented; Identify at least one point-of-contact at the organization that awarded the submitted contract, including: the name of the point-of-contact; their current mailing address; phone number; and email address (if applicable). Note: An on site Safety Officer must be on site when work is being completed.

(d) On Site Superintendent(s): Must have minimum of 5 years’ experience as a site superintendent and must have OSHA 30 training (must provide certificate).

Provide at least 3 projects as a site superintendent with similar scope of this project.

Provide the name of the construction contract, and the contract ID number.

The name of the contracting agency or organization the contract was awarded by.

The date of the construction contract award and the contract award amount in dollars.

The date of the construction contract completion, and the final contract amount, in dollars.

A brief description of the construction contract scope of work; Identification of at least one point-of-contact at the organization that awarded the submitted contract, including: the name of the point-of- contact; their current mailing address; phone number; and email address (if applicable). Note: On Site Superintendent will be required to attend weekly project meetings in person at the station facilities office and must be on site when work is being completed.

Special Note: When an offeror submits its proposal in response to this Request for Proposals, and key personnel who are proposed to work on the project are required to be submitted, those personnel who are offered will be the same personnel who will actually perform on the project. If, during performance of the contract, it becomes necessary for the contractor to substitute personnel for one of those whose qualifications were the basis for evaluation of the offer and award of the contract, the contractor shall submit to the Contracting Officer the same information that was required in the initial proposal regarding the proposed substitute employee. The Contracting Officer shall have the right to review the qualifications of the proposed substitute employee and to approve or disapprove his or her qualifications. If the proposed substitute employee's qualifications are disapproved by the Contracting Officer, the contractor will propose another employee who does possess equivalent qualifications.

FACTOR 6: PRIME CONTRACTOR SAFETY PLAN

Offerors must provide a construction safety plan:

A. The contractor's Safety Plan shall be evaluated for their compliance with local/State/Federal rules and regulations and the company's consideration of safety of its employees and the general public. The contractor's Safety Plan at the minimum shall address their safety policy, commitment to safety, detailed disciplinary action to be taken with respect to employees violating safety requirements, personnel safety responsibilities, personnel safety training, personal protective equipment, accident / incident reporting procedure and investigations, emergency procedures guidelines.

B. The contractor’s Safety Plan shall address their plan for completing all contract work on and around an active hospital without impact patient care and completing all work in accordance with all construction documents and all local/State/Federal rules and regulations.

FACTOR 7: PRIME CONTRACTOR INFECTION CONTROL PLAN

A. The contractor’s Infection Control plan shall demonstrate their knowledge and outline their plan to meet all ICRA requirements required for this work within an active hospital. ICRA 2.0 is the latest VA Infection Control guidance and is what the reviewers will evaluate proposed Infection Control plans. The Infection Control plans are to include who is responsible for the various aspects of these requirements. The plan shall also include how each level of ICRA requirement will be met.

d. PRICE PROPOSAL.

Price is to be submitted on page 5. Offerors must provide a price for each contract line item. In addition, offerors shall include a breakdown of material and labor costs, by specification division for each bid item. Overhead, profit and bond costs shall be added after a subtotal of materials and labor costs have been calculated see Appendix 1.

Note: It is intended that award will be made on contract line-item 1. If the price exceeds budget, then the award will be made to one of the deduct items item 2 or 3;

3. BASIS OF AWARD.

VA will make the award based on the lowest evaluated price of proposals meeting or exceeding the acceptability standards for non-cost factors. Note that offers that are not technically acceptable cannot be selected, regardless of price.

4. Special Contract Requirements

SUBSTITUTIONS OF SUBCONTRACTORS AND / OR KEY PERSONNEL

1. When an offeror submits its proposal in response to this Request for Proposals, and key personnel who are proposed to work on the project are required to be submitted, those personnel who are offered will be the same personnel who will actually perform on the project. If, during performance of the contract, it becomes necessary for the contractor to substitute personnel for one of those whose qualifications were the basis for evaluation of the offer and award of the contract, the contractor shall submit to the Contracting Officer the same information that was required in the initial proposal regarding the proposed substitute employee. The Contracting Officer shall have the right to review the qualifications of the proposed substitute employee and to approve or disapprove his or her qualifications. If the proposed substitute employee's qualifications are disapproved by the Contracting Officer, the contractor will propose another employee who does possess equivalent qualifications.

2. When an offeror submits its proposal in response to this Request for Proposals, and the name and experience of a specific subcontractor is a required evaluation factor, then that subcontractor who is offered will be the same subcontractor who will actually perform the specified work on the project. If, during performance of the contract, it becomes necessary for the contractor to substitute a subcontractor for one of those whose qualifications were the basis for evaluation of the offer and award of the contract, the contractor shall submit to the Contracting Officer the same information that was required in the initial proposal regarding the proposed substitute subcontractor. The Contracting Officer shall have the right to review the qualifications of the proposed substitute subcontractor and to approve or disapprove its qualifications. If the proposed substitute subcontractor's qualifications are disapproved by the Contracting Officer, the contractor will propose another subcontractor who does possess equivalent qualifications.

A Determination of Responsibility will be accomplished for the apparent awardee prior to processing the award. The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases, will be used to make the Determination of Responsibility. Failure to affirm being within the guidelines above or submit this information will result in a determination of “non-responsibility” for the bidder/offeror. NOTE: Any information received by the Government that would cause for a negative Determination of Responsibility will make the bidder/offeror ineligible for award.

This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.

(END OF INSTRUCTIONS TO OFFERORS)

1.2 APPENDIX 1 PRICE BREAKDOWN CALCULATION SELF PERFORMANCE AND SUB CONTRACT WORK

PRICE BREAKDOWN AND CALCULATION OF SELF-PERFORMED/SUBCONTRACTED WORK - Appendix 1

Provide a breakdown of material and personnel costs, by specification division listed for the project. Home Office overhead, profit/fee and bond costs shall be added after a subtotal of personnel and material/Equipment costs has been calculated. Clearly identify the personnel costs you will be performing, and the personnel costs of other eligible service disabled veteran-owned small business concerns. Below is the required format.

THIS DOCUMENT MUST BE COMPLETED FOR EACH BID ITEM.

Specification Division
SDVOB Vendor (Y or N)
Personnel Cost
Material/Equipment Costs
TOTAL COSTS

Division 01

$
$

Division 02

$
$

Division 03

$
$

Division 05

$
$

Division 06

$
$

Division 07

$
$

Division 08

$
$

Division 09

$
$

Division 10

$
$

Division 11

$
$

Division 14

$
$

Division 21

$
$

Division 22

$
$

Division 23

$
$

Division 26

$
$

Division 27

$
$

Division 28

$
$

l

$
$
Sub Total (Personnel Costs, Material/Equipment Costs)
$
$
Profit
$
Home Office Overhead
$
Bond
$
Grand Total
$

Calculation of self-performed personnel costs:

1. Total personnel costs * both prime and all subcontractors: $_________________

2. Subtract all subcontractor personnel costs* that are not SDVOSB companies that will perform work on this contract: $__________________

3. Remainder is ‘Total amount of work to be self-performed under the Contract’: $__________________

4. Self-performed work = Line 3/Line 1 x 100 = __________%

I certify the above representations are true and correct to the best of my knowledge.

___Signature____________________________________________
(Typed Name of Authorized Representative)Date

(Title of Authorized Representative)

INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS

2.1 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023)

(a) All actual and potential offerors are encouraged to provide feedback on the preaward and debriefing processes, as applicable. Feedback may be provided to agencies up to 45 days after award. The feedback is anonymous, unless the participant self-identifies in the survey. Actual and potential offerors can participate in the survey by selecting the following link: https:// www.acquisition.gov/360.

(b) The Contracting Officer will not review the information provided until after contract award and will not consider it in the award decision. The survey is voluntary and does not convey any protections, rights, or grounds for protest. It creates a way for actual and potential offerors to provide the Government constructive feedback about the preaward and debriefing processes, as applicable, used for a specific acquisition.

(End of Clause)

2.2 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.3 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014) (a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.4 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20% percent of the bid price or 3,000,000.00, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of Provision)

2.5 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) (FEB 2021)

(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee—

(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203–1; and

(2) Standard Form 28, Affidavit of Individual Surety.

(b) The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228–1, Bid Guarantee, or as otherwise established by the Contracting Officer.

(c) The Contracting Officer may release the security interest on the individual surety’s assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.

(End of Provision)

2.6 52.233-2 SERVICE OF PROTEST (SEP 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Jeanette Mathena James Petrik Hand-Carried Address:

Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway

Leavenworth KS 66048 Mailing Address:

Department of Veterans Affairs Network Contracting Office (NCO) 15 3450 S 4th Street Trafficway

Leavenworth KS 66048

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of Provision)

2.7 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for— July 11, 2025 at 10:00am

(c) Participants will meet at— Harry S Truman VAMC, Building 22 Facilities Trailer (End of Provision)

2.8 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.gov/browse/index/far https://www.va.gov/oal/library/vaar/

(End of Provision)

FAR Number
Title
Date
52.204-7
SYSTEM FOR AWARD MANAGEMENT
NOV 2024
52.204-16
COMMERCIAL AND GOVERNMENT ENTITY CODE REPORTING
AUG 2020
52.204-22
ALTERNATIVE LINE ITEM PROPOSAL
JAN 2017
52.211-6
BRAND NAME OR EQUAL
AUG 1999
52.215-1
INSTRUCTIONS TO OFFERORS—COMPETITIVE ACQUISITION
NOV 2021
52.236-28
PREPARATION OF PROPOSALS—CONSTRUCTION
OCT 1997

2.9 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009) Prime contractors are encouraged to assist service-disabled veteran-owned and veteran-owned small business potential subcontractors in obtaining bonding, when required. Mentor firms are encouraged to assist protégé firms under VA's Mentor-Protégé Program in obtaining acceptable bid, payment, and performance bonds, when required, as a prime contractor under a solicitation or contract and in obtaining any required bonds under subcontracts.

(End of Clause)

2.10 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)

(a) As an alternative to filing a protest with the Contracting Officer, an interested party may file a protest by mail or electronically with: Executive Director, Office of Acquisition and Logistics, Risk Management and Compliance Service (003A2C), Department of Veterans Affairs, 810 Vermont Avenue NW, Washington, DC 20420 or Email: EDProtests@va.gov.

(b) The protest will not be considered if the interested party has a protest on the same or similar issue(s) pending with the Contracting Officer.

(End of Provision) PLEASE NOTE: The correct mailing information for filing alternate protests is as follows:

Deputy Assistant Secretary for Acquisition and Logistics,
Risk Management Team, Department of Veterans Affairs
810 Vermont Avenue, N.W.
Washington, DC 20420

Or for solicitations issued by the Office of Construction and Facilities Management:

Director, Office of Construction and Facilities Management
811 Vermont Avenue, N.W.
Washington, DC 20420
FAR Number
Title
Date
852.223-70
INSTRUCTIONS TO OFFERORS—SUSTAINABLE ACQUISITION PLAN
SEP 2019
852.233-70
PROTEST CONTENT/ALTERNATIVE DISPUTE RESOLUTION
OCT 2018
852.236-92
NOTICE TO BIDDERS—ADDITIVE OR DEDUCTIVE BID LINE ITEMS

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .