S06 0011 Att 2 The timeline located at the end of the SOW is hereby replaced with the following timeline.pdf
PDF 57 KB Posted
- Solicitation number
- 36C25223B0011
About this file
This document contains a federal contract solicitation and related files. The solicitation is for renovation work to convert space on the third floor of Building B406 at the Tomah VA Medical Center into a dementia unit. Offerors must submit responses by March 7, 2023. A non-mandatory site visit is scheduled for February 7, 2023 to view the existing space. The solicitation includes screening requirements for visitors to the patient floor due to COVID-19 protocols. The attached timeline file replaces and updates the schedule included in the original statement of work, outlining a 542-day performance period consisting of phases for submittals, review, construction, and closeout. The solicitation is issued by the Department of Veterans Affairs Veterans Health Administration VISN 12.
View the file
Other files
Show all 38
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The timeline located at the end of the SOW is hereby replaced with the following timeline:
TITLE Length in Days Activity
Limited Notice to Proceed 1 day LNTP
Phase 0: 30 days Contractor submit all product submittals.
Phase 1: 15 days VA review of Product Submittals
NTP/Pre‐Construction Meeting: 1 day NTP
Phase 2: 45 days Pre‐Construction Period Contractor to submit all other submittals.
Phase 3: 30 days VA review all other submittals.
Phase 4: 360 days Construction
Phase 5: 60 days Post‐Substantial Completion (Contractor to submit all closeout documents first 45 days, last 15 days are Vas)
542 days total