This document includes a solicitation for ceiling mounted patient lift systems and the related federal contract opportunity. The solicitation specifies ceiling track systems made of extruded aluminum, lift units with 550 or 1100 pound lifting capacities, emergency lowering devices, batteries with 120 transfers at 200 pounds, and sling straps rated at 550 or 770 pounds. Submittals are due by February 21, 2023 and include shop drawings signed by a structural engineer, room layouts, and maintenance checklists. The related federal contract opportunity is for renovating the third floor of building B406 at the Tomah VA Medical Center in Wisconsin into a dementia unit. A pre-bid site visit is scheduled for February 7, 2023 with COVID-19 screening required, and bids are due on March 7, 2023 to the Department of Veterans Affairs contracting office in Milwaukee.

View the file

Other files

File Type Posted
S06 - 36C25223B0011 0014 ATT 3 - F7_minka-lavery-341-357-specification-sheet.pdf PDF
S06 - 36C25223B0011 014 ATT 2 - F6_PROG_P350110-020_spec.pdf PDF
36C25223B0011 0014.docx DOCX document
S06 - 36C25223B0011 0014 ATT 4 - F10_PROG_P3448-0930K9_spec.pdf PDF
S06 - 36C25223B0011 014 ATT 1 - F3_PROG_P300002-009_spec.pdf PDF
36C25223B0011 0013.docx DOCX document
36C25223B0011 0012.docx DOCX document
S06 0011 Att 2 The timeline located at the end of the SOW is hereby replaced with the following timeline.pdf PDF
36C25223B0011 0011.docx DOCX document
36C25223B0011 0010.docx DOCX document
S06 0010 ATT 1 AS103C - WALL TYPES.pdf PDF
S06 0010 Att 3 Pre-Bid RFI Clarifications Set 2 676-15-201 Renovate 3rd Fl .xlsx XLSX spreadsheet
S06 0010 ATT 2 Amico-aca-bed-bumpers-vertical-specs.pdf PDF
S06 0009 - ATT 6 Floor Infill detail.pdf PDF
36C25223B0011 0009.docx DOCX document
S06 0009 - ATT 3 033053 (Short-Form) Cast-In-Place Concrete.pdf PDF
S06 0009 - ATT 2 B406 Mechanical Attic Plans.pdf PDF
S06 0009 - ATT 5 090516 Subsurface Prep for Floor Finishes.pdf PDF
S06 0009 Attachment 7 All RFI Responses.xlsx XLSX spreadsheet
S06 0009 - ATT 4 MH101.pdf PDF
S06 0009 ATT 1 400-9 Sections Details.pdf PDF
36C25223B0011 0008.docx DOCX document
S06 - Amendment 7 attachment 1.pdf PDF
36C25223B0011 0007.docx DOCX document
36C25223B0011 0006.docx DOCX document
3rd Set of RFI Responses for posting.pdf PDF
36C25223B0011 0005.docx DOCX document
36C25223B0011 0004.docx DOCX document
Attachment 1 - RFI lighting Red markings.pdf PDF
36C25223B0011 0003.docx DOCX document
S06- site visit attendees.pdf PDF
36C25223B0011 0001.docx DOCX document
S02 - Att 2 676-15-201 Drawings_IFB - Final.pdf PDF
S02 - Att 5 Wage Rates.pdf PDF
S02 - Att 4 676-15-201 Specifications Vol 2_IFB REVISED 2023 01 23.pdf PDF
S02 - Att 3 676-15-201 Specifications Vol 1_IFB REVISED 2023 01 23.pdf PDF
S02 - Att 1 676-15-201 Renovate B406 3rd Floor - SOW - Const REVISED 2023 01 11 02.pdf PDF
36C25223B0011_1.docx DOCX document
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA MEDICAL CENTER DEPARTMENT OF VETERAN AFFAIRS

TOMAH, WI

RENOVATE B406 3RD FLOOR

VA PROJECT: 676-15-201 08-01-20

11 73 00 - 1

SECTION 11 73 00

CEILING MOUNTED PATIENT LIFT SYSTEM

PART 1 - GENERAL

1.1 DESCRIPTION

Ceiling Mounted Patient Lift Systems for the transfer of physically challenged patients are specified in this section.

1.2 RELATED WORK

A. Section 01 00 00, GENERAL REQUIREMENTS: Requirements for pre-test of equipment.

B. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS: General

Electrical Requirements and items, which are common to sections of

Division 26.

1.3 QUALITY ASSURANCE

A. Certification for compliance is required for Ceiling Mounted Patient

Lift Systems. Certifications shall be provided by the manufacturer who will conduct testing to ensure that the ceiling lift and charging system are safe and in compliance with ISO 10535 & UL 60601-1

B. Inspection of equipment after installation is required prior to use for patient movement. Inspection shall be in accordance with manufacturer’s installation checklist and the facilities installation checklist

(Patient Safety Alert AL14-07).

1.4 SUBMITTALS

A. Submit in accordance with specification Section 01 33 23, SHOP

DRAWINGS, PRODUCT DATA, AND SAMPLES.

1. Shop drawings shall show structural supports to the underside of structure. Structural calculations for the support of the track and its attachment to ceiling structure shall be submitted. Shop drawings used in the quoting phase shall be PDFs, and either 2D CAD files or 3D BIM files showing structural support to underside of structure. Shop drawings shall also provide general room layout with bed position and all obstructions to ceiling lift.

2. Once the purchase order is accepted by the vendor, a set of stamped drawings shall be provided by the vendor. Shop drawings and structural calculations shall be signed and stamped by a registered structural engineer and shall meet all code requirements in the jurisdiction having authority. Structural engineer shall ensure ceiling minimum structure capacity shall support the loads specified

RENOVATE B406 3RD FLOOR

VA PROJECT: 676-15-201 08-01-20

11 73 00 - 2 in the shop and installation drawings and comply with local structural and seismic codes.

3. Shop drawings shall show obstructions such as lights and sprinklers and coordinate their relocation.

4. Manufacturer shall provide BIM (Building Information Model) for clash detection on the request of the COR, VA Construction Agent, or

General Contractor.

B. Certificates of Compliance from Manufacturer

C. Manufacturer's Literature and Data:

1. Lifting Capacity

2. Lifting Speed

5. Vertical Axis Motor

6. Emergency Brake

7. Emergency Lowering Device

8. Emergency Stopping Device

9. Electronic Soft-Start and Soft-Stop Motor Control

10. Current Limiter for Circuit Protection

12. Strap Length

13. All equipment anchors and supports. Submittals shall include weights, dimensions, center of gravity, standard connections, manufacturer's recommendations and behavior problems (e.g., vibration, thermal expansion,) associated with equipment or piping so that the proposed installation can be properly reviewed.

D. Individual Room layouts showing location of lift system installation shall be approved before proceeding with installation of lifts.

E. Manufacturer’s Checklist for after installation inspection.

1.5 APPLICABLE PUBLICATIONS

A. The publications listed below form a part of this specification to the extent referenced. The publications are listed in the text by the basic designation only.

B. International Organization for Standardization (ISO):

10535-06................Hoist for the Transfer of Disabled Persons-

Requirements and Test Methods

C. Underwriters Laboratories (UL):

60601-1(2015)...........Medical Electrical Equipment: General

Requirements for Safety

RENOVATE B406 3RD FLOOR

VA PROJECT: 676-15-201 08-01-20

11 73 00 - 3

94-2013.................UL Standards for Safety Test for Flammability of Plastic Materials for Parts in Devices and

Appliances-Fifth Edition

D. International Electromagnetic Commission (IEC):

60601-1-2(2015).........Medical electrical equipment – Part 1-2:

General requirements for basic safety and essential performance – Collateral Standard:

Electromagnetic disturbances – Requirements and tests.

E. VA Patient Safety Alert AL14-07

PART 2 - PRODUCTS

2.1 GENERAL

A. The ceiling lift system shall be Guldmann GH3+ or equal manufacturer.

The ceiling lift system (motor/hanger assembly) shall be approved for use with Guldmann Repositioning, High Back, Twin Turner and Limb Lifter loop slings.

2.2 CEILING TRACK SYSTEM

A. The Ceiling Track shall be made from high strength extruded aluminum.

Provide anchor supports at ceiling substrate.

B. Installed rail shall be security tested for 1.5 times greater than the motor’s weight capacity and maximum allowable deflection of a horizontal rail is no more than 1/16th inch per 7.87 inch of track length per ISO 10535 standards.

2.3 LIFT UNIT

A. The Lift Unit shall be constructed of a steel frame system driven by a gear-reduced, high-torque, horizontal axis motor.

B. The Lift system shall have the following features.

1. The ceiling lift motor shall have an integrated Class III scale that allows users to read weights off the hand control.

2. Lifting capacity: 550 lbs (249.476 kg) for non-bariatric lifts; 1100 lbs (498.952 kg) for bariatric lifts

3. Electronic soft-start and soft-stop motor control.

4. Shall have an emergency manual lowering device. This emergency manual lowering device cord shall be red. Operation of the emergency manual lowering device shall be in such a way that users

RENOVATE B406 3RD FLOOR

VA PROJECT: 676-15-201 08-01-20

11 73 00 - 4 can apply continuous pull to the cord to facilitate slow descent of patient.

5. Emergency stopping device – when activated all vertical movement must cease at maximum load.

6. Current limiter for circuit protection in case of overload.

7. Safety device that stops the motor to lift when batteries are low.

8. Emergency brake (in case of mechanical failure).

9. Hanger bar shall be able to reach the floor.

10. Cab: VO plastic–fire retardant, UL 94.

11. Hand controller shall be able to be stored securely to the hanger bar.

12. The safe working load of the ceiling lift motor shall be clearly labeled on the outside of the ceiling lift motor.

2.4 MOTORS

A. Vertical Movement-DC Motor.

2.5 BATTERIES

A. The life cycle (number of charging cycles) for batteries shall comply with IEC 6100-1-2.

B. Provide rechargeable batteries with up to 120 transfers with a load of

200lbs (74kg) (for repositioning)

2.6 CHARGER

A. Charger shall be supplied.

2.7 STRAPS AND SLING

A. The straps shall meet ISO 10535. The straps shall ensure the patient’s safety by preventing the patient from falling out of the sling.

B. The sling shall meet ISO 10535. The sling shall cradle the body of the patient. Non-bariatric slings shall be rated to a minimum of 550 lbs and bariatric slings shall be rated to a minimum of 770 lbs.

2.8 HANGER BAR

A. The hanger bar style shall be the four (4) suspension point style compatible with the lift strap.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Install ceiling mounted patient lift system as per manufacturer's instruction and under the supervision of manufacturer's qualified representative and as shown on drawings.

RENOVATE B406 3RD FLOOR

VA PROJECT: 676-15-201 08-01-20

11 73 00 - 5

B. If the distance in between the suspended ceiling and anchors is more than 18” consult with manufacturer to determine if lateral braces will be required.

3.2 INSTRUCTION AND PERSONNEL TRAINING

A. Training shall be provided for the required personnel to educate them on proper operation and maintenance for the lift system equipment.

B. Biomedical staff will have the ability to be OEM trained and perform all preventative and corrective maintenance. To include but not limited to order OEM part and the ability clear maintenance reminders.

3.3 TEST

Conduct performance test, in the presence of the COR , Inspector of

Record (IOR), and a manufacturer's field representative, to show that the patient lift system equipment and control devices operate properly and in accordance with design, specification, and code requirements.

3.4 INSPECTION

1. Inspection of installed ceiling mounted patient lift systems shall be conducted in accordance with the manufacturer’s installation checklist and the VHA installation checklist (Patient Safety Alert

AL14-07) prior to use for patient movement.

2. Periodic Inspection shall be provided by the manufacturer on a yearly basis in compliance with ISO 10535.

- - - E N D - - -