S02 - ATTACH 6 - 695-19-132 Drawing Set_BidPart-4.pdf

PDF 2 MB Posted

Attached to
Y1AZ--Construction Women's Clinic, Project #695-19-132
Solicitation number
36C25223B0004
Issued by

About this file

This solicitation is for construction services for a Women's Clinic project at a Department of Veterans Affairs medical center. The solicitation seeks bids for renovations and upgrades to existing spaces to create new clinic areas, staff offices and support spaces. Work includes demolition, hazardous material abatement, and installation of new walls, floors, ceilings and building systems. Bids are due by mid-October 2022, with construction to be completed in phases to minimize disruptions to ongoing medical center operations. The award is a firm-fixed-price contract.

View the file

Other files

File Type Posted
36C25223B0004 0007.docx DOCX document
ATTACH 19 Amendment 0007 rev.pdf PDF
ATTACH 16 Arch Drawings.pdf PDF
ATTACH 17 MEP Drawings.pdf PDF
ATTACH 15 Combined Spec Sections.pdf PDF
ATTACH 18 Furniture Dwg Shaft Photos Doc A.pdf PDF
36C25223B0004 0006.docx DOCX document
36C25223B0004 0005.docx DOCX document
S04 - Sign In Sheet.FE.pdf PDF
36C25223B0004 0004.docx DOCX document
S02 - ATTACH 1 - Construct Womens Clinic Project 695-19-132 Manual V1 rev Oct 28.pdf PDF
36C25223B0004 0003.docx DOCX document
S02 - ATTACH 2 - Construct Womens Clinic Project 695-19-132 Manual V2 rev.pdf PDF
36C25223B0004 0002.docx DOCX document
S02 - ATTACH 7 - 695-19-132 Drawing Set_BidPart-5.pdf PDF
S02 - ATTACH 5 - 695-19-132 Drawing Set_BidPart-3.pdf PDF
S02 - ATTACH 4 - 695-19-132 Drawing Set_BidPart-2.pdf PDF
S02 - ATTACH 3 - 695-19-132 Drawing Set_BidPart-1.pdf PDF
36C25223B0004 0001.docx DOCX document
S02 - ATTACH 9 - SSJ Bldg Automation HVAC Cntrl System rev_Executed.pdf PDF
S02 - ATTACH 13 - SSJ Interior Signage rev_Executed.pdf PDF
S02 - ATTACH 14 - Wage Determination WI202100001.pdf PDF
S02 - ATTACH 10 - SSJ Door Hardware rev_Executed.pdf PDF
S02 - ATTACH 11 - SSJ Fire Alarm System rev_Executed.pdf PDF
S02 - ATTACH 8 - 695-19-132 Drawing Set_BidPart-6.pdf PDF
S02 - ATTACH 12 - SSJ HID MultiClass Readers rev_Executed.pdf PDF
36C25223B0004_1.docx DOCX document
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT LOCATION:

FIRST FLOOR

BUILDING 111 KEY PLAN

N

SHADE INDICATES

AREA NOT IN SCOPE,

TYP.

A. PROVIDE BLOCKING IN WALLS TO ACCOMMODATE EQUIPMENT,

FURNISHINGS, AND TECHNOLOGY, AND WALL MOUNTED ACCESSORIES AS

REQUIRED. REFER TO ARCHITECTURE SHEETS FOR MORE INFORMATION.

B. COORDINATE ALL EQUIPMENT LOCATIONS AND UTILITIES REQUIREMENTS

WITH EQUIPMENT PLANS, SCHEDULES, AND ENGINEERING DRAWINGS.

C. REFER TO FURNITURE VENDOR DRAWINGS AND DETAILED FURNITURE

SCHEDULE FOR FINAL FURNITURE PLACEMENT.

D. REFER TO THE VA ACQUISITION CODES FOR EACH PIECE OF EQUIPMENT

WITHIN THE PROJECT SCOPE TO DETERMINE THE PURCHASING AND

INSTALLATION RESPONSIBILITY REQUIRED.

E. FINAL FURNITURE AND EQUIPMENT SPECIFICATIONS TO BE REVIEWED AND

APPROVED BY THE VA PRIOR TO PLACEMENT OF ORDER.

F. ALL EQUIPMENT AND FURNITURE INDICATED IN THE DRAWINGS ARE DRAWN

TO SCALE FOR TEST FITTING UNLESS OTHERWISE NOTED.

EQUIPMENT GENERAL NOTES

CC CONTRACTOR FURNISHED / CONTRACTOR INSTALLED

VC VA FURNISHED / CONTRACTOR INSTALLED

VV VA FURNISHED / VA INSTALLED

VC(CF) VA FURNISHED WITH CONSTRUCTION FUNDS / CONTRACTOR INSTALLED

VV(CF) VA FURNISHED WITH CONSTRUCTION FUNDS / VA INSTALLED

R RELOCATE / REUSED EXISTING EQUIPMENT

RESPONSIBLE PARTY LEGEND

270 SF

VCS OFFICE

1465 81 SF

CASH OUT

1465B

121 SF

VCS CHIEF

OFFICE

1465A

52 SF

SOILED HOLDING

173 SF

PROCEDURE

67 SF

PATIENT TOILET

1452A

168 SF

PROCEDURE

57 SF

PATIENT TOILET

1448A

110 SF

CONSULT

208 SF

CHECK-IN

90 SF

INTAKE

30 SF

LINEN CLOSET

WHEELCHAIR

STORAGE

1400B

360 SF

RECEPTION /

WAITING

65 SF

PATIENT TOILET

129 SF

INTAKE

134 SF

LAB

112 SF

EXAM

105 SF

EXAM

106 SF

EXAM

68 SF

FAMILY TOILET

1400A

82 SF

LACTATION

141 SF

FAMILY WAITING

1400C

E L

E C

T R

IC

A

L

E

C

43 SF

INTAKE - ALCOVE

92 SF

CLEAN STORAGE

56 SF

EQUIPMENT

94 SF

CONSULT

305 SF

CORRIDOR

C1C03

118 SF

CORRIDOR

C1C01

293 SF

CORRIDOR

C1C02

5794 SF

CORRIDOR

C1C09

747 SF

CORRIDOR

C1B06

703 SF

CORRIDOR

C1C11

243 SF

WOMENS TOILET

209 SF

MENS TOILET

77 SF

ELECTRICAL

54 SF

HAC

143 SF

LOCKER ROOM

85 SF

STAFF TOILET

187 SF

RESIDENT

WORKROOM

259 SF

CONFERENCE /

BREAK

88 SF

CORRIDOR

C1C10

548 SF

OPEN

WORKSTATIONS

AI201

186 SF

SWING SPACE

25 SF

STORAGE

89 SF

INTAKE

61 SF

MEDS

125 SF

EXAM

1443 108 SF

EXAM

4'

97 SF

DRY STORAGE

30 SF

CANISTER

STORAGE

E0903E0903E0903E0903

M4020 F0206

F0206 F0305 F0740

M0515

F2017

E2000

F0740F0305

A1030

A5025

M1804

M1803

A1015

F0275

F4500

A1015

M1803 M1804

F4500

F0275

F2017

F2010

T7 R7000K4665

F4600

F0210

M0515

F3050

F0505

M

F2550

M1803M1804A1015

F0275

F4500

AI201

AI200

AI200

AI202

AI202

AI202

AI201

AI202

AI201

AI201

AI200

209 SF

WHEELCHAIR

WASH

AI202

NOTE:

ONLY NEW ARCHITECTURAL WORK TO TAKE

PLACE IN THIS AREA IS THE INSTALL OF THE

CONSTRUCTION BARRIER ACCESS

CORRIDOR FOR STAFF ACCESS. THE WORK

IS TO TAKE PLACE PRIOR TO DEMOLITION OF

PHASE 1.

REFER TO SHEETS GC100 AND GC101 FOR

MORE INFORMATION.

WHEELCHAIR

WASHER - CENTER

TO HOOD ABOVE

ARCHITECTURAL SYMBOLS LEGEND

NO NEW ARCHITECTURAL WORK TO TAKE PLACE IN

THIS AREA. REFER TO MEP DRAWINGS FOR

EXTENT OF WORK.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Consultant:

C

U s e rs \d c h ri s te n s e n \D o c u m e n ts \1

.1

.1

A v d c h ri s te n s e n M

N F

X

.r v t

/6 /2

:5

:2

P

M

QH100

FIRST FLOOR EQUIPMENT PLAN AND

SCHEDULE

GUIDON DESIGN, INC.

1221 N. PENNSYLVANIA STREET

SUITE 200

INDIANAPOLIS, INDIANA 46202

317.800.6388

CONSTRUCT WOMEN'S CLINIC

5000 W. NATIONAL AVE, MILWAUKEE, WI 53295

695-19-132

09/07/2022 JDF DMC

100% BID DOCUMENTS

FULLY SPRINKLERED

EQUIPMENT SCHEDULE

JSN DESCRIPTION

FFE

FURNISHED COMMENTS

CC

A1030 Locker, over under CC

A1200 Ceiling Mounted CC Patient Lift

A5025 Bench, Locker room, Floor mounted CC

A5180 Cubicle curtain and track CC

E0903 Locker, supply with shelves CC

F0240 Wall-mounted desk with upper storage bins -

HERMAN MILLER

CC

L1200 Pass-through specimen cabinet. CC

R

F3331 FLOOR SAFE, LARGE R

F3332 FLOOR SAFE, SMALL R

F3333 COIN COUNTER R

VV

A1014 Telephone, Wall mounted VV

A1015 Telephone, Desk VV

A5077 HAND SANITIZER DISPENSER VV

A5080 PAPER TOWEL DISPENSER VV

A5106 SHARPS w/ GLOVE DISPENSER VV

A5145 Hook, Garment VV

E2000 Check-in Kiosk VV

F0205 Chair, with arms VV

F0206 Chair, bariatric with arms VV

F0210 Chair, without arms VV

F0230 Chair, Drafting VV

F0255 Chair, easy VV

F0275 Chair, swivel VV

F0305 Chair, waiting VV

F0340 Stool, adjusting VV

F0420 Cabinet, Filing VV

F0505 Mop Bucket VV

F0740 Table, Lamp VV

F2000 Waste, paper VV

F2010 Waste, paper, step on VV

F2017 Waste Receptacle VV

F2310 Rack, Pamphlet VV

F2550 PAPER SHREDDER, HEAVY DUTY VV

F3050 Whiteboard, Dry erase VV

F3200 Clock, 12" Dia. VV

F4500 WORKSTABLE, 24x66 VV

F4600 TABLE, MOBILE FOLDABLE VV

K4665 MICROWAVE VV

L0100 Microscope VV

M0515 Television VV

M0750 Flowmeter, Air VV

M0755 Flowmeter, Oxygen VV

M0765 Regulator, Vacuum VV

M1000 Television VV

M1410 Chair,Lab, Blood draw VV

M1803 COMPUTER, 24" SCREEN w/UNDERCOUNTER

CPU MOUNT

VV

M1804 24" MONITOR VV

M1830 Copier, Printer VV

M2055 Shelving, storage VV

M3150 Distribution, Medication VV

M4020 Scale, Person weighing VV

M4200 Ophthalmoscope VV

M7401 Exam Light VV

M9025 Table, examination/treatment with cabinet. VV

M9066 Examination Table, Procedure VV

R6200 Refrigerator, Under counter, 5 CU FT VV

R7000 Refrigerator, 14 CU FT VV

N

SCALE: 1/8" = 1'-0"QH100

1 OVERALL EQUIPMENT PLAN

GENERAL NOTE:

ALL WORK TO BE COMPLETED SIMULTANEOUSLY (DEMOLITION - INCLUDING MEP, HAZMAT REMOVAL, NEW CONSTRUCTION - INCLUDING MEP) BY PHASE TO REDUCE DISRUPTION TO OCCUPIED SPACES. MULTIPLE MOBILIZATIONS ARE NOT PERMITTED WITHOUT COR APPROVAL. REFER TO SHEET GC101 AND MEP

DRAWINGS FOR PHASING PLAN.

Revisions: Date:

A/E ARCHITECT / ENGINEER

AAHX AIR TO AIR HEAT EXCHANGER

AAV AUTOMATIC AIR VENT

AB AIR BLENDER

ACC AIR COOLED CONDENSER

ACCH AIR COOLED CHILLER

ACCU AIR COOLED CONDENSING UNIT

ACD AUTOMATIC CONTROL DAMPER,

MODULATING

ACD-TP AUTOMATIC CONTROL DAMPER, TWO

POSITION

ACU AIR CONDITIONING UNIT

AD ACCESS DOOR

AF AFTER FILTER

AFCV AIR FLOW CONTROL VALVE

AFF ABOVE FINISHED FLOOR

AFMS AIR FLOW MEASURING STATION

AFW AIR FOIL WHEEL (FAN)

AHU AIR-HANDLING UNIT

AMP AMPERE

AP ACCESS PANEL

APD AIR PRESSURE DROP

AQST AQUASTAT

ARI AIR CONDITIONING AND REFRIGERATION

INSTITUTE

AS AIR SEPARATOR

ASHRAE AMERICAN SOCIETY OF HEATING

REFRIGERATION AIR

CONDITIONING ENGINEERS

ASME AMERICAN SOCIETY OF MECHANICAL

ENGINEERS

AW AIR WASHER

AXF AXIAL FLOW

B BOILER

BD BUTTERFLY DAMPER

BDD BACKDRAFT DAMPER

BDR BASE BOARD RADIATOR

BFP BACKFLOW PREVENTER

BFT BOILER PLANT FIRE TUBE

BG BOTTOM GRILLE

BHP BRAKE HORSEPOWER

BHW HOT WATER HEATING BOILER

BHX BOILER BLOWDOWN HEAT EXCHANGER

BIW BACKWARD INCLINED WHEEL (FAN)

BMT BONE MARROW TRANSPLANT

BR BOTTOM REGISTER

BSC BIOLOGICAL SAFETY CABINETS

BT BLOWOFF TANK

BTC BLOWOFF TANK CONTROL VALVE

BTU BRITISH THERMAL UNIT

BTUH BRITISH THERMAL UNIT PER HOUR

BWT BOILER PLANT WATER TUBE

C CENTIGRADE (CELSIUS)

CAV CONSTANT AIR VOLUME

CC COOLING COIL

CCD COOLING COIL CONDENSATE DRAIN

CD CEILING DIFFUSER

CD-1 CONSTRUCTION DOCUMENTS (SUBMISSION1)

CD-2 CONSTRUCTION DOCUMENTS (SUBMISSION2)

CENT CENTRIFICAL

CFH CUBIC FEET PER HOUR

CFM CUBIC FEET PER MINUTE

CFT CUBIC FEET

CFP CHEMICAL FEED PUMP

CG CEILING GRILLE

CH CHILLER

CHP CHILLED WATER PUMP

CHW CHILLER WATER

CHR CHILLED WATER RETURN

CHS CHILLED WATER SUPPLY

CI CAST IRON

CM CARBON MONOXIDE

CM CUBIC METER

CM/S CUBIC METER PER SECOND

CO CLEAN OUT

CO2 CARBON DIOXODE

COMP COMPRESSOR UNIT

COP COEFFICIENT OF PERFORMANCE

CP CONDENSATE PUMP

CR CEILING REGISTER

CS CONDENSATE STORAGE TANK

CSG CLEAN STEAM GENERATOR

CT COOLING TOWER

CU CONDENSING UNIT

CUH CABINET UNIT HEATER

CV CONSTANT VOLUME

CW COLD WATER (POTABLE)

CWCC CHILLED WATER COOLING COIL

CWP CONDENSER WATER PUMP

CWR CONDENSER WATER RETURN (TO COOLING

TOWER)

CWS CONDENSER WATER SUPPLY (FROM

COOLING TOWER)

D DAMPER - AUTOMATIC

Db DRY-BULB TEMPERATURE

DB DECIBELS

DCW DOMESTIC COLD WATER

DD-1 DESIGN DEVELOPMENT (SUBMISSION 1)

DD-2 DESIGN DEVELOPMENT (SUBMISSION 2)

DDC DIRECT DIGITAL CONTROLS

DEG DEGREE

DF DIFFUSER

DHW DOMESTIC HOT WATER

DHWR DOMESTIC HOT WATER RETURN

DIA DIAMETER

DIW DEIONIZED WATER

DP DEW POINT TEMPERATURE

DP DIFFUSER PLATE

DPA DIFFERENTIAL PRESSURE ASSEMBLY

DPS DIFFERENTIAL PRESSURE SENSOR

DX DIRECT EXPANSION

DXCC DIRECT EXPANSION COOLING COIL

EA EXHAUST AIR

EAT ENTERING AIR TEMPERATURE

EC EVAPORATIVE COOLER

ECC ENGINEERING CONTROL CENTER

ECU EVAPORATIVE CONDENSER UNIT

EDH ELECTRIC DUCT HEATER

EER ENERGY EFFICIENCY RATIO

EF EXHAUST FAN

EG EXHAUST GRILLE

EGS EMERGENCY GAS SHUTOFF

EGT ENTERING GLYCOL TEMPERATURE

EH EXHAUST HOOD

EJ EXPANSION JOINT

EMD END OF MAIN DRIP (STEAM)

ENT ENTERING

ER EXHAUST REGISTER

ERC ELECTRIC REHEAT COIL

ERP ELECTRIC RADIANT PANEL

ESP EXTERNAL STATIC PRESSURE

ET EXPANSION TANK

ETO ETHYLENE OXIDE

EUH ELECTRIC UNIT HEATER

EWC EVAPORATIVE WATER COOLER

EWT ENTERING WATER TEMPERATURE

EX EXISTING

FIRE SUPPRESSION ABBREVIATIONS

F FAHRENHEIT

F&T FLOAT AND THERMOSTATIC

F/SDPR COMBINATION FIRE SMOKE DAMPER

FA FREE AREA

FC FLEXIBLE CONNECTION

FCU FAN COIL UNIT (4 PIPE)

FCUC FAN COIL UNIT COOLING ONLY

FCUH FAN COIL UNIT HEATING ONLY

FCW FORWARD CURVED WHEEL (FAN)

FD FLOOR DRAIN

FD FIRE DAMPER

FF FINAL FILTER

FHX FLUE GAS/FEEDWATER HEAT EXCHANGER

FM FLOW METER

FOP FUEL OIL PUMP

FOT FUEL OIL TANK

FOHX FUEL OIL HEAT EXCHANGER

FPM FEET PER MINUTE

FPS FEET PER SECOND

FPTU FAN POWERED TERMINAL UNIT

FR FLOOR REGISTER

FRP FIBER REINFORCED POLYESTER

FS FLOW SWITCH

FSTAT FREEZESTAT

FT FEET

FT WC FEET OF WATER COLUMN

FT-LB FOOT-POUND

FTR FIN TUBE RADIATION

FV FACE VELOCITY

GA GAUGE

GAL GALLONS

GH GRAVITY HOOD

GPD GALLONS PER DAY

GPH GALLONS PER HOUR

GPM GALLONS PER MINUTE

GPR GAS PRESSURE REGULATOR

GS GALVANIZED STEEL

H HUMIDIFER

HAC HOUSEKEEPING AID CLOSET

HB HOSE BIBB

HC HEATING COIL

HD HOOD

HOA HAND/OFF/AUTOMATIC

HP HEAT PUMP

HP HORSEPOWER

HPDT HIGH PRESSURE DRIP TRAP

HPR HIGH PRESSURE RETURN (STEAM

CONDENSATE)

HPS HIGH PRESSURE SUPPLY (STEAM)

HRC HEAT RECOVERY COIL

HRD HEAT RECOVERY DEVICE

HRP HYDRONIC RADIANT (CEILING) PANEL

HRW HEAT RECOVERY WHEEL

HSTAT HUMIDISTAT

HTM HUMIDIFIER TERMINAL

HUM HUMIDIFIER UNIT MOUNTED

HVU HEATING AND VENTILATING UNIT

HW HOT WATER

HWC HOT WATER COIL

HWHC HOT WATER HEATING COIL

HWP HEATING HOT WATER PUMP

HWR HEATING HOT WATER RETURN

HWS HEATING HOT WATER SUPPLY

HWUH HOT WATER UNIT HEATER

HVD HOISTWAY VENT DAMPER

HX HEAT EXCHANGER

HZ HERTZ

I/O INPUT/OUTPUT

IAQ INDOOR AIR QUALITY

IBT INVERTED BUCKET TRAP

ICF IN-LINE CENTRIFUGAL FAN

ICU INTENSIVE CARE UNIT

ID INSIDE DIAMETER

IFB INTEGRAL FACE AND BYPASS

IN INCHES

IN HG INCHES OF MERCURY

IN WC INCH WATER COLUMN

IN WG INCH WATER GAUGE

IN-LB INCH-POUND

IPLV INTERGRATED PART LOAD VALUE

IRH INTRARED HEATER

IS INSECT SCREEN

IU INDUCTION UNIT

IV INLET VANES

J INTENTIALLY LEFT BLANK

KG KILOGRAM

KG/HR KILOGRAM PER HOUR

kPa KILOPASCAL

KW KILOWATT

KWH KILOWATT HOUR

L LITER

L/h LITERS PER HOUR (or LITERS/HOUR) L/m LITERS PER MINUTE (or LITERS/MINUTE) L/s LITERS PER SECOND (or LITERS/SECOND)

LAT LEAVING AIR TEMPERATURE

LBS/HR POUNDS PER HOUR

LF LINEAR FOOT (FEET)

LGT LEAVING GLYCOL TEMPERATURE

LH LATENT HEAT

LPG LIQUEFIED PETROLEUM GAS

LPR LOW PRESSURE RETURN (STEAM

CONDENSATE)

LPRC LOW PRESSURE STEAM RETURN (CLEAN)

LLHX LIQUID TO LIQUID HEAT EXCHANGER

LPS LOW PRESSURE STEAM

LPSC LOW PRESSURE STEAM (CLEAN)

LSD LINEAR SLOT DIFFUSER

LTCP LOCAL TEMPERATURE CONTROL PANEL

LVG LEAVING

LVR LOUVER

LWT LEAVING WATER TEMPERATURE

M METER, SI UNIT

M/S METERS PER SECOND (OR

METERS/SECOND)

MA MIXED AIR

MAT MIXED AIR TEMPERATURE

MAU MAKE-UP AIR UNIT

MAV MANUAL AIR VENT

MAX MAXIMUM

MB MIXING BOX

MBH 1,000 BTUH

MCA MINIMUM BRANCH CIRCUIT AMPACITY

MER MECHANICAL EQUIPMENT ROOM

MERV MINIMUM EFFICIENCY REPORTING VALUE

MH MANHOLE

MHP MOTOR HORSEPOWER

MIN MINIMUM

MM MILLIMETER

MOV MOTOR OPERATED VALVE

MPR MEDIUM PRESSURE RETURN (STEAM

CONDENSATE)

MPS MEDIUM PRESSURE STEAM

MRI MAGNETIC RESONANCE IMAGING

MTD MEAN TEMPERATURE DIFFERENCE

MVD MANUAL VOLUME DAMPER

MZ MULTI-ZONE

NA NOT APPLICABLE

NC NOISE CRITERIA

NC NORMALLY CLOSED

NG NATURAL GAS

NGFM NATURAL GAS FLOWMETER

Nm NEWTON METER

NO NORMALLY OPEN

NOAA NATIONAL OCEANIC & ATMOSPHERIC

ADMINISTRATION

NOM NOMINAL

NPLV NON-STANDARD PART LOAD VALUE

NPSH NET POSITIVE SUCTION HEAD

NPSHA NET POSITIVE SUCTION HEAD AVAILABLE

NPSHR NET POSITIVE SUCTION HEAD REQUIRED

NTS NOT TO SCALE

OA OUTSIDE AIR

OAD OUTDOOR AIR DAMPER

OAG OUTSIDE AIR GRILLE

OAI OUTSIDE AIR INTAKE

OD OUTSIDE DIAMETER

OFM OIL FLOWMETER

OR OPERATING ROOM

P PUMP

Pa PASCAL

PC PUMPED CONDENSATE

PCF POUNDS PER CUBIC FOOT (FEET)

PD PRESSURE DROP

PEF PROPELLER (TYPE) EXHAUST FAN

PF PRE-FILTER

PG PRESSURE GAGE

PGW PROPYLENE GLYCOL-WATER (SOLUTION)

PHC PREHEAT COIL

PPM PARTS PER MILLION

PRS PRESSURE REGULATING (VALVE) STATION

PRV PRESSURE REGULATING VALVE

PSI POUNDS PER SQUARE INCH

PSIA POUNDS PER SQUARE INCH – ABSOLUTE

PSIG POUNDS PER SQUARE INCH – GAGE

PSS PRIMARY SECONDARY SYSTEM

PSV PRESSURE SAFETY VALVE

PTAC PACKAGED TERMINAL AIR CONDITIONER

R/E RETURN OR EXHAUST

RA RETURN AIR

RAD RETURN AIR DAMPER

RAF RADIO FREQUENCY

RAHX ROTARY AIR HEAT EXCHANGER

RAT RETURN AIR TEMPERATURE

RCCH REMOTE CONDENSER CHILLER

RCU RECIPROCATING CHILLER UNIT

RD REFRIGERANT DISCHARGE

RDS ROOM DATA SHEETS

REA RELIEF AIR

RELAD RELIEF AIR DAMPER

RF RETURN FAN

RG RETURN GRILLE

RH RELATIVE HUMIDITY

RHC REHEAT COIL

RHG REFRIGERANT HOT GAS

RL REFRIGERANT LIQUID LINE

RLA RUN LOAD AMPERE

RO REVERSE OSMOSIS

RPM REVOLUTIONS PER MINUTE

RR RETURN REGISTER

RS REFRIGERANT SUCTION

RTU ROOF TOP UNIT

RV RELIEF VALVE

SA SUPPLY AIR

SAD SOUND ATTENUATING DEVICE

SAT SUPPLY AIR TEMPERATURE

SC SHADING COEFFICIENT

SCFM STANDARD CUBIC FEET PER MINUTE

SCI SPINAL CODE INJURY

SCR SILICON CONTROLLED RECTIFIER

SD SMOKE DETECTOR

SD SUPPLY AIR DIFFUSER

SD-1 SCHEMATIC DESIGN (SUBMISSION1)

SD-2 SCHEMATIC DESIGN (SUBMISSION2)

SDPR SMOKE DAMPER

SDR SMOKE DAMPER (RETURN)

SDS SMOKE DAMPER (SUPPLY)

SEN SENSIBLE HEAT

SF SUPPLY FAN

SG SUPPLY AIR GRILLE

SH STEAM HUMIDIFIER

SHC STEAM HEATING COIL

SI SQUARE INCHES

SP STATIC PRESSURE

SP GR SPECIFIC GRAVITY

SPD SUPPLY PROCESS AND DISTRIBUTION

SPRV STEAM PRESSURE REDUCING VALVE

SPS STATIC PRESSURE SENSOR

SQ FT SQUARE FOOT (FEET)

SR SUPPLY AIR REGISTER

SS STAINLESS STEEL

SSHX STEAM TO STEAM HEAT EXCHANGER

SSR SOLID SEPARATOR

ST STEAM TRAP

SUH STEAM UNIT HEATER

SV STEAM PRESSURE REDUCING VALVE

SVS STEAM VENT SILENCER

SW SOFTWATER

SWHX STEAM TO WATER HEAT EXCHANGER

T&PCV TEMPERATURE AND PRESSURE CONTROL

VALVE

TAB TESTING, ADJUSTING, BALANCE

TD TEMPERATURE DIFFERENCE

TDH TOTAL DYNAMIC HEAD

TDS TOTAL DISSOLVED SOLIDS

TG TRANSFER GRILLE

TP TRAP

TR TOP REGISTER

TSP TOTAL STATIC PRESSURE

TSTAT THERMOSTAT

TU TERMINAL UNIT

TWU THRU-WALL UNIT

UC UNDER CUT

UC UNIT COOLER

UH UNIT HEATER

U UNDERWRITERS LABORATORY

URV UPBLAST UNIT VENTILATOR

V VALVE

VAF VANE-AXIAL FAN

VAV VARIABLE AIR VOLUME

VD VOLUME DAMPER (MANUAL OPPOSED

BLADE)

VFD VARIABLE FREQUENCY DRIVE

VHA VETERANS HEALTH ADMINISTRATION

VI VIBRATION ISOLATOR

VP VACUUM PUMP

VPS VARIABLE PRIMARY SYSTEM

VR VACUUM (STEAM CONDENSATE) RETURN

VSD VARIABLE SPEED DRIVE

VUH VERTICAL UNIT HEATER

W WATTS

WAG WASTE ANETHESIA GAS

Wb WET-BULB (TEMPERATURE)

WC WATER COOLED

WCCH WATER COOLED CHILLER

WCCU WATER COOLED CONDENSING UNIT

WCHP WATER COOLED HEAT PUMPS

WCPU WATER COOLED PACKAGED UNIT

WEF WALL EXHAUST FAN

WF WATER FILTER

WFCV WATER FLOW CONTROL VALVE

WFM WATER FLOWMETER

WFMD WATER FLOW MEASURING DEVICE

WG WATER GAGE

WPD WATER SIDE PRESSURE DROP

YR YEAR

GENERAL PIPING SYMBOLS

VALVE SYMBOLS

FIRE SPRINKLER HEAD (CEILING)

FIRE SPRINKLER ZONE RISER VALVE

GENERAL NOTES

A. PROVIDE RECORD FLOW TEST PRIOR TO PREPARING SHOP

DRAWINGS AND HYDRAULIC CALCULATIONS. CONTRACTOR

SHALL PROVIDE THE FIRE SUPPRESSION DESIGN CRITERIA FORM

AS PART OF THEIR STATE SUBMITTAL.

B. COORDINATE INSTALLATION OF ALL SYSTEMS WITH MECHANICAL

(HVAC), PLUMBING, AND ELECTRICAL SYSTEMS. CEILING CAVITY

SPACE IS RESTRICTED AND INSTALLTION OF DUCTWORK SHALL

TAKE PRIORITY OVER ALL OTHER TRADES. NO EXTRA

COMPENSATION WILL BE ALLOWED TO COVER THE COST OF

RELOCATING SYSTEMS FOUND ENCROACHING ON SPACE

REQUIRED BY MECHANICAL, PLUMBING, OR ELECTRICAL

SYSTEMS.

C. PROVIDE SPRINKLERS ABOVE AND BELOW WIDE DUCTS (48" AND

WIDER INCLUDING INSULATION) PER NFPA 13 REQUIREMENTS.

REFER TO HVAC DRAWINGS FOR ADDITIONAL INFORMATION.

D. PIPING ARRANGEMENT AND SPRINKLER LOCATIONS ARE

DIAGRAMMATIC AND ARE PROVIDED FOR THE CONTRACTOR'S

INFORMATION. EXACT ROUTING OF PIPING AND FINAL SIZING

AND LOCATION OF SPRINKLERS SHALL BE SELECTED BY THE

CONTRACTOR TO ACCOUNT FOR ACTUAL FIELD CONDITIONS.

ALL AREAS SHALL BE PROTECTED UNLESS SPECIFICALLY

NOTED OTHERWISE. COORDINATE INSTALLATION WITH

CEILING HEIGHTS AND SOFFITS. REFER TO ARCHITECTURAL

DRAWINGS FOR ADDITIONAL INFORMATION.

E. EXTENDED COVERAGE SPRINKLERS MAY BE UTILIZED. THE USE

OF EXTENDED COVERAGE SHALL BE CONFIRMED BY HYDRAULIC

CALCULATIONS. PIPING SHALL BE CONCEALED IN ALL FINISHED

AREAS.

F. THIS BUILDING SHALL BE CONSIDERED LIGHT/ORDINARY HAZARD

OCCUPANCY WITH EXCEPTIONS PER NFPA 13, STATE, AND

LOCAL CODES. DESIGN DENSITIES SHALL BE IN ACCORDANCE

WITH GOVERNMENT/VA REQUIREMENTS.

G. SPRINKLER PIPING SHALL BE SCHEDULE 10 STEEL FOR PIPING

THAT IS 2-1/2" AND LARGER. PROVIDE SCHEDULE 40 STEEL

PIPING FOR 2" AND SMALLER UNLESS OTHERWISE NOTED.

THINWALL, LIGHTWALL, PRO-PRESS TYPE PIPING/FITTINGS WILL

NOT BE ALLOWED.

H. PROVIDE PIPE LABELS FOR ALL SPRINKLER PIPING & DEVICES.

LABELS SHALL READ "FIRE PROTECTION PIPING".

FIRE SPRINKLER HEAD (SIDEWALL)

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Consultant:

C U s e rs

\m p a q u in

\O n e

D ri v e

G u id o n

D e s ig n in c \D o c u m e n ts \1

.1

.1

M E

P v m p a q u in

G

E N

G .r v t

/6 /2

:2

:4

P

M

F000

FIRE SUPPRESSION SYMBOLS

AND ABBREVIATIONSGUIDON DESIGN, INC.

1221 N. PENNSYLVANIA STREET

SUITE 200

INDIANAPOLIS, INDIANA 46202

317.800.6388

CONSTRUCT WOMEN'S CLINIC

5000 W. NATIONAL AVE, MILWAUKEE, WI 53295

695-19-132

09/07/2022 CDH AJS

100% BID DOCUMENTS

FULLY SPRINKLERED

NOT TO SCALEF000

1 SPRINKLER WITH RETURN BEND

PHASE 1

TEMPORARY CONSTRUCTION

BARRIERS FOR ACCESS CORRIDOR

TO BE CONSTRUCTED PRIOR TO

START OF PHASE 1 DEMOLITION.

TEMPORARY CORRIDOR TO

REMAIN AFTER END OF PROJECT

CONSTRUCTION.

STAFF TO HAVE TRAVEL ACCESS

THRU SPACE THROUGHOUT PHASE

1.

PHASE 1 -

AFTER HOURS

ADJUST EXISTING FIRE SPRINKLER

HEAD LAYOUT AS REQUIRED TO

PROVIDE ADEQUATE FIRE

SPRINKLER COVERAGE FOR

TEMPORARY CORRIDOR. PROVIDE

ALL FIRE SPRINKLER HEADS AS

REQUIRED AND CONNECT TO

EXISTING FIRE SPRINKLER PIPING

SYSTEM. FIELD VERIFY ALL

CONNECTION LOCATIONS.

VA TO OCCUPY

VCS OFFICES

STAFF TO HAVE

TRAVEL ACCESS

THRU CORRIDOR

BUILT IN PHASE 1

THROUGHOUT PHASE

NOTE:

STAFF SPACES AND PUBLIC

RESTROOMS MUST BE

COMPLETE AND OCCUPIED

PRIOR TO BEGINNING WORK ON

PHASE 3.

PHASE 2

VA TO OCCUPY

STAFF AREA

PUBLIC RESTROOMS TO

BE OPEN TO PUBLIC

VA TO OCCUPY

VCS OFFICES

CORRIDOR IS OPEN.

STAFF TO TRAVEL

THRU NEW

CORRIDOR

THROUGHOUT

PHASE 3

PHASE 3-

AFTER HOURS

PHASE 3

PHASE 3-

AFTER HOURS

NO MORE THAN 50%

WIDTH OF MAIN

CORRIDOR TO BE

CLOSED AT ANY TIME

CONTRACTOR TO

COORDINATE WITH VA FOR

KITCHEN STAFF ACCESS TO

NEW CORRIDOR DURING

PHASE 3 - AFTER HOURS

WORK

PHASE 3

REFER TO MECHANCIAL

DRAWINGS FOR FULL

EXTEND OF WORK IN THIS

CORRIDOR.

TEMPORARY INFECTION CONTROL

BARRIER WALLS. SEE PLAN AND PLAN

NOTES

CONSTRUCTION ACCESS DOORS

BEYOND PROJECT

BOUNDARY

IC / PHASING LEGEND

PHASE 1

1. CONTRACTOR TO CONSTRUCT 1 HR RATED

CONSTRUCTION BARRIERS AS NOTED ON PLAN. VA

STAFF TO USE PATH THROUGH EXISTING KITCHEN

SPACE SEPARATED BY CONSTRUCTION BARRIER

WALLS THROUGHOUT DURATION OF PHASE 1 & 2.

2. CONTRACTOR TO DEMOLISH, INCLUDING HAZMAT

AND MEP REMOVAL, AND RENOVATE, INCLUDING

MEP, AREA OF VCS OFFICES. CONTRACTOR TO USE

EXISTING PERIMETER WALL AS CONTRUCTION

BARRIER SEPARATION FOR DEMOLITION. NEW

PERIMETER WALL TO BE CONSTRUCTED FIRST TO

ACT AS CONSTRUCTION BARRIER.

3. PHASE 1 WORK TO OCCUR IN JUNCTION WITH

PHASE 1 - AFTER HOURS.

4. VCS OFFICES AND ADJACENT CORRIDOR ARE OPEN

AND OCCUPIED AFTER COMPLETION OF PHASE 1

AND PHASE 1 - AFTER HOURS.

5. PHASE 2 TO BEGIN AFTER OFFICES AND CORRIDOR

ARE COMPLETE AND OPEN.

PHASE 2

1. CONTRACTOR TO CONSTRUCT INFECTION

CONTROL/CONSTRUCTION BARRIERS AS NOTED

ON PLAN. VA STAFF TO USE PATH THROUGH

EXISTING KITCHEN SPACE SEPARATED BY

CONSTRUCTION BARRIER WALLS THROUGHOUT

DURATION OF PHASE 2.

2. CONTRACTOR TO DEMOLISH, INCLUDING HAZMAT

AND MEP REMOVAL, AND RENOVATE, INCLUDING

MEP, AREAS OF THE STAFF SUPPORT SPACES AND

PUBLIC RESTROOMS AS INDICATED ON PLAN.

3. STAFF AREAS AND PUBLIC RESTROOMS ARE OPEN

AND OCCUPIED AFTER COMPLETION OF PHASE 2.

4. PHASE 3 TO BEGIN AFTER COMPLETION OF PHASE

2.

PHASE 3

1. CONTRACTOR TO CONSTRUCT INFECTION

CONTROL/CONSTRUCTION BARRIERS AS NOTED ON

PLAN. VA STAFF TO USE NEW CORRIDORS TO

TRAVEL THROUGH SPACE.

2. CONTRACTOR TO DEMOLISH, INCLUDING HAZMAT

AND MEP REMOVAL, AND RENOVATE, INCLUDING

MEP, AREAS FOR THE WOMEN'S CLINIC AND SWING

SPACE.

NOT IN PHASE BOUNDARY

PERMANENT INFECTION CONTROL BARRIER

WALLS AND/OR DOORS. SEE PLAN AND PLAN

NOTES

PHASE 3 - AFTER HOURS

1. CONTRACTOR TO DEMOLISH, INCLUDING MEP, AND

RENOVATE, INCLUDING MEP, THE CORRIDORS

DURING AFTER HOURS. CONTRACTOR TO

COORDINATE WITH THE VA FOR KITCHEN STAFF

ACCESS.

2. PHASE 3 - AFTERHOURS TO OCCUR IN JUNCTION

WITH PHASE 3.

PHASE 1 - AFTER HOURS

1. CONTRACTOR TO DEMOLISH, INCLUDING MEP, AND

RENOVATE, INCLUDING MEP, THE CORRIDOR DURING

AFTER HOURS. THE

2. CORRIDOR MUST BE OPEN DURING BUSINESS

HOURS. CONTRACTOR TO COORDINATE WITH THE

VA FOR KITCHEN STAFF ACCESS.

3. PHASE 1 - AFTERHOURS TO OCCUR IN JUNCTION

WITH PHASE 1.

PROJECT

LOCATION: FIRST

FLOOR

BUILDING 111 KEY PLAN

N

SHADE

INDICATES AREA

NOT IN SCOPE,

TYP.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Consultant:

REVISION 1 10-05-2022

C U s e rs

\m p a q u in

\O n e

D ri v e

G u id o n

D e s ig n in c \D o c u m e n ts \1

.1

.1

M E

P v m p a q u in

G

E N

G .r v t

/6 /2

:2

:4

P

M

F002

FIRE PROTECTION PHASING PLAN

GUIDON DESIGN, INC.

1221 N. PENNSYLVANIA STREET

SUITE 200

INDIANAPOLIS, INDIANA 46202

317.800.6388

CONSTRUCT WOMEN'S CLINIC

5000 W. NATIONAL AVE, MILWAUKEE, WI 53295

695-19-132

09/07/2022 CDH AJS

100% BID DOCUMENTS

FULLY SPRINKLERED

SCALE: 1/16" = 1'-0"F002

1 FIRE SUPPRESSION PHASING PLAN - PHASE 1 DEMOLITION

SCALE: 1/16" = 1'-0"F002

3 FIRE SUPPRESSION PHASING PLAN - PHASE 1 COMPLETE - PHASE 2 DEMOLITION

SCALE: 1/16" = 1'-0"F002

5 FIRE SUPPRESSION PHASING PLAN - PHASE 2 COMPLETE - PHASE 3 DEMOLITION

SCALE: 1/16" = 1'-0"F002

6 FIRE SUPPRESSION PHASING PLAN - CONTRUCTION COMPLETE

N N

N N

GENERAL NOTE:

ALL WORK TO BE COMPLETED SIMULTANEOUSLY (DEMOLITION - INCLUDING

MEP, HAZMAT REMOVAL, NEW CONSTRUCTION - INCLUDING MEP) BY PHASE

TO REDUCE DISRUPTION TO OCCUPIED SPACES. MULTIPLE MOBILIZATIONS

ARE NOT PERMITTED WITHOUT COR APPROVAL. REFER TO SHEET GC101 AND

MEP DRAWINGS FOR PHASING PLAN.

X U S RZAACCFFGG T

IIJJ HH

(TYP)

(TYP)

(TYP)

(TYP)

PROJECT

LOCATION: FIRST

FLOOR

BUILDING 111 KEY PLAN

N

SHADE

INDICATES AREA

NOT IN SCOPE,

TYP.

SANITATION

COMMUNICATION

CENTER

MAIL

DISTRIBUTION

CASH COUNT

1409A

CORRIDOR

C1B08

TOILET FEMALE

E L

E C

T R

IC

A

L

E C

WATER SOFTNER

TRAYLINE

KETTLE AREA

CANTEEN DRY

STORAGE

FOOD PREP

& SERVICE

CLASSROOM /

CONFERENCE

ADPAC /

TRAINING

CANTEEN ADMIN

OFFICE

OFFICE

1409B

STORAGE

1409C

TOILET MALE

A. REFER TO F000 FOR FIRE SUPPRESSION GENERAL NOTES.

B. REFER TO F002 FOR DEMO PHASING.

FIRE SUPPRESSION DEMOLITION GENERAL NOTES

FIRE SUPPRESSION DEMOLITION PLAN NOTES #

1. PROVIDE NEW FIRE SPRINKLER HEAD. MODIFY EXISTING BRANCH PIPING

AS REQUIRED FOR NEW FIRE SPRINKLER HEAD.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Consultant:

REVISION 1 10-05-2022

C U s e rs

\m p a q u in

\O n e

D ri v e

G u id o n

D e s ig n in c \D o c u m e n ts \1

.1

.1

M E

P v m p a q u in

G

E N

G .r v t

/6 /2

:2

:4

P

M

FDX101

FIRST FLOOR FIRE SUPPRESSION

DEMOLITION PLANGUIDON DESIGN, INC.

1221 N. PENNSYLVANIA STREET

SUITE 200

INDIANAPOLIS, INDIANA 46202

317.800.6388

CONSTRUCT WOMEN'S CLINIC

5000 W. NATIONAL AVE, MILWAUKEE, WI 53295

695-19-132

09/07/2022 CDH AJS

100% BID DOCUMENTS

FULLY SPRINKLERED

SCALE: 1/8" = 1'-0"FDX101

1 FIRST FLOOR FIRE SUPPRESSION DEMOLITION PLAN

N

GENERAL NOTE:

ALL WORK TO BE COMPLETED SIMULTANEOUSLY (DEMOLITION - INCLUDING

MEP, HAZMAT REMOVAL, NEW CONSTRUCTION - INCLUDING MEP) BY PHASE

TO REDUCE DISRUPTION TO OCCUPIED SPACES. MULTIPLE MOBILIZATIONS

ARE NOT PERMITTED WITHOUT COR APPROVAL. REFER TO SHEET GC101 AND

MEP DRAWINGS FOR PHASING PLAN.

A. REFER TO F000 FOR FIRE SUPPRESSION GENERAL NOTES.

B. REFER TO GC101 FOR CONSTRUCTION PHASING.

C. REFER TO AE110 FOR RCP.

1. PROVIDE NEW FIRE SPRINKLER HEAD. MODIFY EXISTING BRANCH PIPING AS

REQUIRED FOR NEW FIRE SPRINKLER HEAD.

FIRE SUPPRESSION GENERAL NOTES

FIRE SUPPRESSION PLAN NOTES #

PROJECT

LOCATION: FIRST

FLOOR

BUILDING 111 KEY PLAN

N

SHADE

INDICATES AREA

NOT IN SCOPE,

TYP.

X U S RZAACCFFGG T

VCS OFFICE

CASH OUT

1465B

VCS CHIEF OFFICE

1465A

CONSULT

PATIENT TOILET

1448A

PROCEDURE

PATIENT TOILET

1452A

SOILED HOLDING

PROCEDURE

EXAM

EXAM

EXAM

EXAM

EXAM

FAMILY TOILET

1400A

LACTATION

CHECK-IN

INTAKE

LINEN CLOSET

INTAKE

PATIENT TOILET

LAB

CONSULT

CLEAN STORAGE

EQUIPMENT

INTAKE - ALCOVE

MENS TOILET

RECEPTION /

WAITING

WOMENS TOILET

ELECTRICAL

HAC

WHEELCHAIR

STORAGE

1400B

FAMILY WAITING

1400C

CORRIDOR

C1C03

CORRIDOR

C1C01

CORRIDOR

C1C02

CORRIDOR

C1C09

CORRIDOR

C1B06

CORRIDOR

C1C11

LOCKER ROOM

STAFF TOILET

RESIDENT

WORKROOM

CONFERENCE /

BREAK

CORRIDOR

C1C10

OPEN

WORKSTATIONS

SWING SPACE

STORAGE

INTAKE

MEDS

DRY STORAGE

CANISTER STORAGE

(TYP)

(TYP)

(TYP)

(TYP)

IIJJ HH

WHEELCHAIR WASH

PROVIDE FIRE SPRINKLER

COVERAGE FOR HOOD, AREA

AROUND HOOD, AND

REMAINING ROOM.

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Consultant:

REVISION 1 10-05-2022

C U s e rs

\m p a q u in

\O n e

D ri v e

G u id o n

D e s ig n in c \D o c u m e n ts \1

.1

.1

M E

P v m p a q u in

G

E N

G .r v t

/6 /2

:4

:2

P

M

FX101

FIRST FLOOR FIRE SUPPRESSION

PLANGUIDON DESIGN, INC.

1221 N. PENNSYLVANIA STREET

SUITE 200

INDIANAPOLIS, INDIANA 46202

317.800.6388

CONSTRUCT WOMEN'S CLINIC

5000 W. NATIONAL AVE, MILWAUKEE, WI 53295

695-19-132

09/07/2022 CDH AJS

100% BID DOCUMENTS

FULLY SPRINKLERED

N

SCALE: 1/8" = 1'-0"FX101

1 FIRST FLOOR - FIRE SUPPRESSION PLAN

GENERAL NOTE:

ALL WORK TO BE COMPLETED SIMULTANEOUSLY (DEMOLITION - INCLUDING

MEP, HAZMAT REMOVAL, NEW CONSTRUCTION - INCLUDING MEP) BY PHASE

TO REDUCE DISRUPTION TO OCCUPIED SPACES. MULTIPLE MOBILIZATIONS

ARE NOT PERMITTED WITHOUT COR APPROVAL. REFER TO SHEET GC101 AND

MEP DRAWINGS FOR PHASING PLAN.

THE BASIS OF DESIGN OF SPACING AND SIZING FOR THE COMPLETE FIRE

SUPPRESSION SPRINKLER SYSTEM SHALL BE FOR A WET PIPE SYSTEM

HYDRAULICALLY CALCULATED FOR A:

1 LIGHT HAZARD AREA LIMITED TO A MAXIMUM OF 225 SQ. FT. PER SPRINKLER

WITH THE DENSITY OF 0.10 GPM/SQ. FT. OVER THE MOST REMOTE 1500 SQ. FT.

PROVIDE AN ADDITION OF 250 GPM HOSE ALLOWANCE.

2 ALL MECHANICAL, ELECTRICAL AND SIMILAR SPACE AREAS SHALL BE

ORDINARY HAZARD (GROUP 1) LIMITED TO A MAXIMUM OF 130 SQ. FT. PER

SPRINKLER WITH A DENSITY OF 0.15 GPM/SQ. FT. PROVIDE AN ADDITION OF

250 GPM HOSE ALLOWANCE.

3 ALL STORAGE, TRASH, FILE STORAGE AND SIMILAR SPACE AREAS SHALL BE

ORDINARY HAZARD (GROUP 2) LIMITED TO A MAXIMUM OF 130 SQ. FT. PER

SPRINKLER WITH A DENSITY OF 0.20 GPM/SQ. FT. PROVIDE AN ADDITION OF

250 GPM HOSE ALLOWANCE.

A/E ARCHITECT / ENGINEER

AD AREA DRAIN/ACCESS DOOR

AFF ABOVE FINISH FLOOR

AFG ABOVE FINISH GRADE

AG AIR GAP

AP ACCESS PANEL

AS AUTOMATIC SPRINKLER

ASD ADJUSTABLE SPEED DRIVES

ASD AUTOMATIC SPRINKLER DRAIN

ASHRAE AMERICAN SOCIETY OF HEATING,

REFRIGERATION, AIR CONDITIONING

ENGINEERS

ASME AMERICAN SOCIETY OF ECHANICAL

ENGINEERS

ASPE AMERICAN SOCIETY OF PLUMBING

ENGINEERS

ASR AUTOMATIC SPRINKLER RISER

AV ACID VENT

AW ACID WASTE

BFP REDUCED PRESSURE BACKFLOW

PREVENTER

BHP BREAK HORSEPOWER

BSP BLACK STEEL PIPE

BT BATHTUB

BTU BRITISH THERMAL UNIT

BTUH BRITISH THERMAL UNIT PER HOUR

C CELSIUS

CA COMPRESSED AIR

CGA COMPRESSED GAS ASSOCIATION

CFM CUBIC FEET PER MINUTE

CI CAST IRON

CO CLEANOUT

CS CLINICAL SINK

CV CONTROL VALVE

DCW DOMESTIC COLD WATER

DFU DRAINAGE FIXTURE UNITS

DHW DOMESTIC HOT WATER

DHWR DOMESTIC HOT WATER RETURN

DHWS DOMESTIC HOT WATER SUPPLY

DI DEIONIZED WATER

DN DOWN

DOE DEPARTMENT OF ENERGY

DS DOWNSPOUT

DW DISHWASHER

DWG DRAWING

DWH DOMESTIC WATER HEATER

DWR DRINKING WATER RETURN

DWS DRINKING WATER SUPPLY

DWV DRAIN WASTE VENT

EL ELEVATION

EMCS ENERGY MONOSERRAT AND CENTRAL

SYSTEM

EPA ENVIROMENTAL PROTECTION AGENCY

EPACT ENERGY POLICY ACT

ESC ESCUTCHEON

ESH EMERGENCY SHOWER

ET EXPANSION TANK

EWH ELECTRIC WATER HEATER

EWS EYE WASH STATION

EWS/SH EYE WASH/DRENCH SHOWER

EX EXISTING

F FAHRENHEIT

FCO FLOOR CLEANOUT

FCW FILTERED COLD WATER

FD FLOOR DRAIN

FDC FIRE DEPARTMENT (HOSE) CONNECTION

FM FLOW METER

FOP FUEL OIL PUMP

FOR FUEL OIL RETURN

FOS FUEL OIL SUPPLY

FOV FUEL OIL VENT

FS FLOOR SINK

FS FLOW SWITCH

FU FIXTURE UNITS

GAL GALLON

GCO GRADE CLEANOUTS

GPD GALLONS PER DAY

GPH GALLONS PER HOUR

GPM GALLONS PER MINUTE

GPR GAS PRESSURE REGULATOR

GRS GAS REGULATOR STATION

GT GREASE TRAP

GVTR GAS VENT THROUGH ROOF

GWH GAS FIRED WATER HEATER

H&CW HOT AND COLD WATER

HB HOSE BIBB

HD HUB DRAIN

HEX HEAT EXCHANGER

HP HORSEPOWER

HS HAND SINK

HST HOT WATER STORAGE TANK (DOMESTIC)

HWB HOT WATER BOILER

HWCP HOT WATER CIRCULATING PUMP

HWP HOT WATER PUMP

HYD HYDRANT

ID INSIDE DIAMETER

IE INVERT ELEVATION

ICW INDUSTRIAL COLD WATER

IHW INDUSTRIAL HOT WATER

INV INVERT

IPC INTERNATIONAL PLUMBING CODE

IRW IRRIGATION WATER

IW INDIRECT WASTE

IWH INSTANTANEOUS WATER HEATER

IWR INDUSTRIAL WATER RETURN

IWS INDUSTRIAL WATER SUPPLY

KW KILOWATT

KWH KILOWATT-HOUR

PLUMBING ABBREVIATIONS

L/S LITER PER SECOND

LA LABORATORY AIR

LAV LAVATORY

LBS/HR POUNDS PER HOUR

LCW LABORATORY COLD WATER

LHW LABORATORY HOT WATER

LNG LIQUID NATURAL GAS

LOX LIQUID OXYGEN

LV LABORATORY VACUUM

LW LOW WATER

M METER

MA MEDICAL AIR

MAV MANUAL AIR VENT

MBH 1000 BTUH

MED MEDICAL

MER MECHANICAL EQUIPMENT ROOM

MH MANHOLE

MOU MEMORANDUM OF UNDERSTADING

MSB MOP SERVICE BASIN

MV MEDICAL VACUUM

N2 NITROGEN

N20 NITROUS OXIDE

NC NORMALLY CLOSED

NG NATURAL GAS

NIC NOT IN CONTRACT

NO NORMALLY OPEN

NOM. NOMINAL

NPW NON POTABLE WATER

NTS NOT TO SCALE

O2 OXYGEN

OC ON CENTER

OD OUTSIDE DIAMETER

OFD OVERFLOW DRAIN

OR OPERATING ROOM

OVFL OVERFLOW

PA PASCAL

PD PRESSURE DROP OR DIFFERENCE

PDI PLUMBING AND DRAINAGE INSTITUTE

PG PRESSURE GAGE

PP PLUMBING PUMP

PPM PARTS PER MILLION

PRS PRESSURE REDUCING STATION

PRV PRESSURE REDUCING VALVE

PSI POUNDS PER SQUARE INCH

PSIA POUNDS PER SQUARE INCH ATMOSPHERE

PSIG POUNDS PER SQUARE INCH GAGE

PTRV PRESSURE TEMPERATURE RELIEF VALVE

PW POTABLE WATER

RD ROOF DRAIN

RDL ROOF DRAIN LEADER

RL ROOF LEADER

RP RECIRCULATION PUMP

RO REVERSE OSMOSIS WATER

RWL RAIN WATER LEADER

SAN SANITARY SEWER

SMACNA SHEET METAL AND AIR

CONDITIONING ONTRACTORS

NATIONAL ASSOCIATION

SCFM STANDARD CUBIC FOOT/MINUTE

SCW SOFTENED COLD WATER

SDMH STORM DRAIN MANHOLE

SMH SANITARY MANHOLE

SP SUMP PUMP

SPR SPRINKLER LINE

SQFT/SF SQUARE FEET

SS STAINLESS STEEL

ST STORAGE TANK

SW STORM WATER

TCV TEMPERATURE CONTROL VALVE

TD TEMPERATURE DIFFERENCE

TD TRENCH DRAIN

TDH TOTAL DYNAMIC HEAD

TEMP TEMPERATURE

TMV THERMOSTATIC MIXING VALVE

TP TRAP PRIMER

TSTAT THERMOSTAT

TWR TEMPERED WATER RETURN

TWS TEMPERED WATER SUPPLY

TYP TYPICAL

V VENT

VAC VACUUM

VB VACUUM BREAKER

VCO VACUUM CLEANER OUTLET

VP VACUUM PUMP

VS VENT STACK

VSD VARIABLE SPEED DRIVE

VTR VENT THROUGH ROOF

W WASTE

WC WATER CLOSET

WCO WALL CLEANOUT

WG WATER GAGE

WH WALL HYDRANT

WH WATER HEATER

WHA WATER HAMMER ARRESTER

WL WATER LINE

WM WATER METER

WPD WATER PRESSURE DROP

WS WASTE STACK

WSFU WATER SUPPLY FIXTURE UNITS

YCO YARD CLEANOUT

YH YARD HYDRANT

SECTION REFERENCE

DRAWING NUMBER

SHEET

LOCATION

DRAWING NUMBER

SHEET

LOCATION

DETAIL REFERENCE

OBJECT

REFERENCED

OBJECT

REFERENCED

X

XXXX

X

XXXX

SCALE: ??

VIEW TITLE

N NORTH ARROW

PROJECT BOUNDARY

BEYOND PROJECT BOUNDARY, NIC

DETAIL/DRAWING SCALE

TITLE OF DETAIL/DRAWING

DETAIL/DRAWING

NUMBER

SHEET NUMBER

X

X

XXXX

SHEET LOCATION

VIEW NUMBER

X X

X

SHEET LOCATION

VIEW NUMBER

XXXX

BUILDING SECTION REFERENCE

DRAWING NUMBER

SHEET

LOCATION

BUILDING X

XXXX

X

XXXX

ELEVATION REFERENCES

DRAWING SYMBOLS

XX-X X

EQUIPMENT

NUMBER

BUILDING NO. WHERE EQUIPMENT IS

LOCATED

EQUIPMENT ABBREVIATION

UNIT NUMBER TAG

CO

GENERAL PLUMBING SYMBOLS

TOP CONNECTION, 45o OR 90o

BOTTOM CONNECTION, 45o OR 90o

CAPPED OUTLET

RISE OR DROP IN PIPE

PIPE UP

PIPE DOWN

POINT OF CONNECTION BETWEEN NEW AND

EXISTING WORK

LIMIT OF DEMOLITION

CLEAN OUT

BALANCE VALVE

BALL/BUTTERFLY VALVE

PLUMBING VALVE SYMBOLS

A. COORDINATE INSTALLATION OF PLUMBING SYSTEMS WITH ALL OTHER SYSTEMS. ANY

COST DUE TO LACK OF COORDINATION OF THIS SYSTEM WITH OTHER SYSTEMS WILL BE

THE RESPONSIBILITY OF THE PLUMBING CONTRACTOR.

B. THE CONTRACTOR SHALL BE RESPONSIBLE FOR VISITING THE AREA TO BECOME

FAMILIAR WITH THE EXISTING CONDITIONS. VERIFY SIZE, LOCATION, AND USAGE OF

EXISTING UTILITIES PRIOR TO CONSTRUCTION. ROUTE PIPING AND CONNECT AS

REQUIRED.

C. DO NOT ROUTE ANY SYSTEMS OVER EXISTING AND/OR NEW ELECTRICAL AND/OR IT AND

TELECOMMUNCIATIONS ROOMS.

D. CUT, PATCH & REPAIR ALL OPENINGS IN WALLS, FLOORS, CEILING, ETC. WHERE

REQUIRED FOR NEW CONSTRUCTION. PATCHING SHALL MATCH EXISTING CONSTRUCTION

& FINISHES. COORDINATE ALL PATCHING AND FINISHES WITH ARCHITECT.

E. PROVIDE VALVE TAGS & PLASTIC LAMINATE IDENTIFICATION ON CEILING FOR ALL NEW

AND EXISTING VALVES AND EQUIPMENT LOCATED WITHIN THE CONSTRUCTION LIMITS AS

INDICATED IN THE SPECIFICATIONS.

F. IN THE CASE OF CONFLICTS OR DISCREPANCIES WITHIN OR AMONG THE CONTRACT

DRAWINGS, THE BETTER QUALITY, MORE STRINGENT REQUIREMENTS OR GREATER

QUANTITY OF WORK, AS DETERMINED BY THE GOVERNMENT, SHALL BE PROVIDED.

G. CONTRACTOR IS TO VERIFY THE PRESENCE OF EXISTING CONDUIT IN THE EXISTING

FLOOR SLABS PRIOR TO ANY WORK TAKING PLACE.

PLUMBING GENERAL NOTES

PLUMBING PIPING SYMBOLS

DOMESTIC COLD WATER (CW)

DOMESTIC HOT WATER (HW)

DOMESTIC HOT WATER RETURN (HWR)

VENT (SANITARY)

SOIL, WASTE, OR SANITARY SEWER

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Consultant:

REVISION 1 10-05-2022

C U s e rs

\m p a q u in

\O n e

D ri v e

G u id o n

D e s ig n in c \D o c u m e n ts \1

.1

.1

M E

P v m p a q u in

G

E N

G .r v t

/6 /2

:1

:4

P

M

P000

PLUMBING SYMBOLS AND

ABBREVIATIONSGUIDON DESIGN, INC.

1221 N. PENNSYLVANIA STREET

SUITE 200

INDIANAPOLIS, INDIANA 46202

317.800.6388

CONSTRUCT WOMEN'S CLINIC

5000 W. NATIONAL AVE, MILWAUKEE, WI 53295

695-19-132

09/07/2022 CDH AJS

100% BID DOCUMENTS

FULLY SPRINKLERED

TEMPORARY INFECTION CONTROL

BARRIER WALLS. SEE PLAN AND PLAN

NOTES

CONSTRUCTION ACCESS DOORS

BEYOND PROJECT

BOUNDARY

IC / PHASING LEGEND

PHASE 1

1. CONTRACTOR TO CONSTRUCT 1 HR RATED

CONSTRUCTION BARRIERS AS NOTED ON PLAN. VA

STAFF TO USE PATH THROUGH EXISTING KITCHEN

SPACE SEPARATED BY CONSTRUCTION BARRIER

WALLS THROUGHOUT DURATION OF PHASE 1 & 2.

2. CONTRACTOR TO DEMOLISH, INCLUDING HAZMAT

AND MEP REMOVAL, AND RENOVATE, INCLUDING

MEP, AREA OF VCS OFFICES. CONTRACTOR TO USE

EXISTING PERIMETER WALL AS CONTRUCTION

BARRIER SEPARATION FOR DEMOLITION. NEW

PERIMETER WALL TO BE CONSTRUCTED FIRST TO

ACT AS CONSTRUCTION BARRIER.

3. PHASE 1 WORK TO OCCUR IN JUNCTION WITH

PHASE 1 - AFTER HOURS.

4. VCS OFFICES AND ADJACENT CORRIDOR ARE OPEN

AND OCCUPIED AFTER COMPLETION OF PHASE 1

AND PHASE 1 - AFTER HOURS.

5. PHASE 2 TO BEGIN AFTER OFFICES AND CORRIDOR

ARE COMPLETE AND OPEN.

PHASE 2

1. CONTRACTOR TO CONSTRUCT INFECTION

CONTROL/CONSTRUCTION BARRIERS AS NOTED

ON PLAN. VA STAFF TO USE PATH THROUGH

EXISTING KITCHEN SPACE SEPARATED BY

CONSTRUCTION BARRIER WALLS THROUGHOUT

DURATION OF PHASE 2.

2. CONTRACTOR TO DEMOLISH, INCLUDING HAZMAT

AND MEP REMOVAL, AND RENOVATE, INCLUDING

MEP, AREAS OF THE STAFF SUPPORT SPACES AND

PUBLIC RESTROOMS AS INDICATED ON PLAN.

3. STAFF AREAS AND PUBLIC RESTROOMS ARE OPEN

AND OCCUPIED AFTER COMPLETION OF PHASE 2.

4. PHASE 3 TO BEGIN AFTER COMPLETION OF PHASE

2.

PHASE 3

1. CONTRACTOR TO CONSTRUCT INFECTION

CONTROL/CONSTRUCTION BARRIERS AS NOTED ON

PLAN. VA STAFF TO USE NEW CORRIDORS TO

TRAVEL THROUGH SPACE.

2. CONTRACTOR TO DEMOLISH, INCLUDING HAZMAT

AND MEP REMOVAL, AND RENOVATE, INCLUDING

MEP, AREAS FOR THE WOMEN'S CLINIC AND SWING

SPACE.

NOT IN PHASE BOUNDARY

PERMANENT INFECTION CONTROL BARRIER

WALLS AND/OR DOORS. SEE PLAN AND PLAN

NOTES

PHASE 3 - AFTER HOURS

1. CONTRACTOR TO DEMOLISH, INCLUDING MEP, AND

RENOVATE, INCLUDING MEP, THE CORRIDORS

DURING AFTER HOURS. CONTRACTOR TO

COORDINATE WITH THE VA FOR KITCHEN STAFF

ACCESS.

2. PHASE 3 - AFTERHOURS TO OCCUR IN JUNCTION

WITH PHASE 3.

PHASE 1 - AFTER HOURS

1. CONTRACTOR TO DEMOLISH, INCLUDING MEP, AND

RENOVATE, INCLUDING MEP, THE CORRIDOR DURING

AFTER HOURS. THE

2. CORRIDOR MUST BE OPEN DURING BUSINESS

HOURS. CONTRACTOR TO COORDINATE WITH THE

VA FOR KITCHEN STAFF ACCESS.

3. PHASE 1 - AFTERHOURS TO OCCUR IN JUNCTION

WITH PHASE 1.

PROJECT

LOCATION: FIRST

FLOOR

BUILDING 111 KEY PLAN

N

SHADE

INDICATES AREA

NOT IN SCOPE,

TYP.

PHASE 1

PHASE 1 -

AFTER HOURS

PHASE 2PHASE 2

VA TO OCCUPY

VCS OFFICES

(ABOVE)

PHASE 3

VA TO OCCUPY

STAFF AREA

(ABOVE)

PUBLIC RESTROOMS TO

BE OPEN TO PUBLIC

(ABOVE)

VA TO OCCUPY

VCS OFFICES

(ABOVE)

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

Consultant:

REVISION 1 10-05-2022

C U s e rs

\m p a q u in

\O n e

D ri v e

G u id o n

D e s ig n in c \D o c u m e n ts \1

.1

.1

M E

P v m p a q u in

G

E N

G .r v t

/6 /2

:1

:4

P

M

P002

BASEMENT PLUMBING PIPING

PHASING PLANGUIDON DESIGN, INC.

1221 N. PENNSYLVANIA STREET

SUITE 200

INDIANAPOLIS, INDIANA 46202

317.800.6388

CONSTRUCT WOMEN'S CLINIC

5000 W. NATIONAL AVE, MILWAUKEE, WI 53295

695-19-132

09/07/2022 CDH AJS

100% BID DOCUMENTS

FULLY SPRINKLERED

GENERAL NOTE:

ALL WORK TO BE COMPLETED SIMULTANEOUSLY (DEMOLITION - INCLUDING

MEP, HAZMAT REMOVAL, NEW CONSTRUCTION - INCLUDING MEP) BY PHASE

TO REDUCE DISRUPTION TO OCCUPIED SPACES. MULTIPLE MOBILIZATIONS

ARE NOT PERMITTED WITHOUT COR APPROVAL. REFER TO SHEET GC101 AND

MEP DRAWINGS FOR PHASING PLAN.

SCALE: 1/16" = 1'-0"P002

1 BASEMENT PLUMBING PIPING PHASING PLAN - PHASE 1 DEMOLITION

N

N

SCALE: 1/16" = 1'-0"P002

4 BASEMENT PLUMBING PIPING PHASING PLAN - NEW CONSTRUCTION

SCALE: 1/16" = 1'-0"P002

2 BASEMENT PLUMBING PIPING PHASING PLAN - PHASE 1 COMPLETE - PHASE 2 DEMOLITION

SCALE: 1/16" = 1'-0"P002

3 BASEMENT PLUMBING PIPING PHASING PLAN - PHASE 2 COMPLETE - PHASE 3 DEMOLITION

N

N