This solicitation is for construction services to build a new Women's Clinic at the Clement J. Zablocki VA Medical Center in Milwaukee, Wisconsin. The project involves demolishing existing spaces and constructing new clinic and office areas totaling approximately 7,500 square feet. Key requirements include upgrading existing walls to one-hour fire rated construction; installing new finishes, casework, doors and hardware; and modifying mechanical, electrical and plumbing systems. The pre-bid meeting was held on January 11, 2023 and bids are due by February 28, 2023. The award is expected within 60 days thereafter with a notice to proceed to follow. The construction period is 270 calendar days. The solicitation was issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 12.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25223B0004 0006
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer) 695-19-132 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee WI 53214-1476 36C252 Department of Veterans Affairs Great Lakes Acquisition Center (GLAC) 115 S 84th Street, Suite 101 Milwaukee WI 53214-1476 To all Offerors/Bidders
36C25223B0004 02-10-2023
X X 2/28/2023 at 1:30PM Local Time
Please see Continuation Pages
CONTINUE TO MONITOR CONTRACT OPPORTUNITIES AT SAM.GOV FOR ANY AND ALL CHANGES TO THIS SOLICITATION.
Ryan McMillin Contracting Officer
CONTINUATION PAGES: CONSTRUCT WOMENS CLINIC PROJECT# 695-19-132
CLEMENT J. ZABLOCKI VA MEDICAL CENTER, MILWAUKEE, WI
I. The following changes are to be made to the solicitation:
a. Due to forthcoming VA responses to RFIs received to date, the Bid Due date/time is hereby extended to February 28, 2023, at 1:30pm Local Time.
II. The following changes are made on project specifications:
Specifications
1. The specifications include the following deletions. Eliminate the following Specification sections or eliminate the following paragraphs in Specification Section: None
2. The specifications include the following additional work. Provide the following in addition to the Specification Sections: See ATTACH 15 for the following: 07 21 13 Thermal Insulation, 21 08 00 Commissioning of Fire Protection System, 22 08 00 Commissioning of Plumbing System, 23 08 00 Commissioning of HVAC System, 26 08 00 Commissioning of Electrical System, 27 08 00 Commissioning of Communication System 28 08 00 Commissioning of Electronic Safety & Security System.
3. The following Specification Sections include clarifications: See ATTACH 15 for the following: 10 28 00 Toilet, Bath & Laundry Accessories, 14 92 00 Pneumatic Tube Systems, 21 13 13 Wet-pipe Sprinkler System.
III. The following changes are made on project drawings:
Architectural Drawings
1. The drawings include the following deletions. Eliminate the following Sheet: None
2. The drawings include the following clarifications. Revised information on Sheets: See ATTACH 16 for the following: GI101, GI102, GC101, AE002, AD100, AD 110, AE100, AE100.A, AE100.B, AE110, AE110.A, AE110.B, AE400, AE600, AI100, AI101, AI102, AI600, AI902, QH100.
3. The drawings include the Addition of the following Sheet: See ATTACH 16 for; AD 109
MEP Drawings
1. The drawings include the following deletions. Eliminate the following Sheet: None 2 The drawings include the following clarifications. Revised information on Sheets: See ATTACH 17 for the following; FX101, PD100, PD101, PP100, PP101, PP400, PP401, PP700, MH101, MP101, MM600, EDL101, EL101, EP101, EP400, EP601, EY101, 3 The drawings include addition of the following Sheet: None
PLEASE NOTE: Additional Documents See ATTACH 18 for the following.
| 1. Furniture Plan and Schedules | 10 pages | |
| 2. Photos of Dumbwaiter Shaft | 2 pages | |
| 3. Document “A” Question attachment from a bidder | 1 page |
IV. The following Questions and Answers / Clarifications are the result of bidders request(s) for information:
The following questions and answers provide clarification to the contract documents:
| Q2. | Ref specification 01 45 00 Part 3.4- It appears the project will require a full time QC manager with degree in construction management, architecture, or engineering. In addition to the full time QC manager a full time SSHO is also required onsite which must be separate from the QC manager. It appears the superintendent can fulfill only one role of the SSHO or the QC manager providing they can meet the education and experience requirement. Requirement. Please confirm if the superintendent can fulfill both roles of QC manager and SSHO. Also, is it acceptable for the superintendent to cover the role of the QC manager if the individual has 5 plus years of experience of successful projects similar in scope but does not hold a degree in architecture, engineering, or construction management? |
| A2. | No, as stated in 01 01 10SN.3.40. A – Site Superintendent is 100% dedicated to this project as the Site Superintendent only. |
| Q3. | Ref drawing PD100- Will a ceiling plan be provided for the basement areas with plumbing above the ceilings to determine hard and soft ceilings? Does furniture and equipment exist that will require removal/replacement. Are any of the basement areas considered sterile areas? What type of finishes exist that will require protection? |
| A3. | See ATTACH 16 added sheet AD109 |
| Q4. | Ref spec 14 92 00- Will the new pneumatic tube system be tied into an existing system and if so what manufacturer? Will a drawing be providing to show routing and tie in point of new tube and associated equipment? |
| A4. | Yes, the new pneumatic tube system is tied into the existing building system. See drawing Sheets PP 101 and PP 401 for location of the system. Specification Section 14 92 00 revised. ATTACH 15 |
The existing system manufacturer is Swisslog – Healthcare Contact Kyle Megna, Regional Sales Manager Office: 303-373-7847 Cell: 508-851-0551 Email: kyle.megna@swisslog-healthcare.com
| Q5. | Ref drawing AI102- Locker room 1453 is shown to received LVT-2 flooring. The room finish schedule on drawing AI600 indicates porcelain tile for the locker room. Which is correct? |
| A5. | AI102 – LOCKER ROOM 1453 is to have porcelain tile PT-1 flooring as indicated in Finish Schedule on AI600 in lieu of Luxury Vinyl Tile LVT-2 as indicated on the First Floor Finish Plan. See revised AI102. See ATTACH 16 |
| A6. | The current nurse call system is not capable of adding stations for the Women’s Clinic to it and the stations are no longer available. In addition, it is not compatible with the existing building wide CODE BLUE system. Recent clinic renovations have used the newer Jeron 790 system that has been installed on the campus for Nurse call and CODE BLUE. In addition, the current system in that area does not meet Specification section 27 52 23 that is included in the project documents. Can you provide direction for the system that should be included? |
| A6. | The Jeron 790 System should be used. See revised drawing EY101. See ATTACH 17 |
Q7. Please define the perimeter extents better than currently represented on AD100 - Demo Note 8 - REMOVE CERAMIC TILE FLOORING, ASSUME 2" THICK SET MORTAR BED AND PREPARE/ INFILL AND LEVEL FLUSH TO EXISTING CONCRETE SLAB FOR NEW FLOORING. COORDINATE WITH SHEET AE101.A FOR FLOOR DRAIN LOCATION.
Q7a. Please note that this crosses between phases, afterhours, and trades.
A7a. Yes, it does. This area connects the working kitchen with the main elevator bank that is used to transport food to the patient floors. This path MUST be kept open and dust free throughout the demolition and construction period. This is the reason for the phasing. Contractor to coordinate all work between phasing, after hours, and trades to complete work within phasing as indicated. Coordinate the phasing with the COR.
Q7b. See attached document for our interpretation. (Document “A” Drawing from Bidder is attached.)
A7b. See revised sheet AD100 for clarification. ATTACH 16
| Q8. | AD100 Note 16 wording "CONTRACTOR TO VERIFY FIRST AND SECOND FLOOR OPENING IS CLOSED OFF. IF NOT CLOSED, CONTRACTOR TO CLOSE FLOOR OPENING." The contractor is currently requesting this verification from the AE if these openings are in fact closed? |
| A8. | The original hospital plans show the dumbwaiter shaft starting on the first floor and up through the floors. See photo EP 1 & EP2 for the shaft condition. ATTACH 18 |
| Q9. | Please note that the plans indicate a double column n/s Column line AA and Z. Has AE thought about either dealing with void space or an expansion joint? |
| A9. | The hospital’s original construction documents show this as an expansion joint. The contractor is to provide and install expansion in this location in flooring and ceiling. See expansion joint detail on sheet AE110.B See ATTACH 16 |
| Q10. | Several Rooms with flooring removal have both an Abatement and Selective scope. For example, rooms 1457, 1450, 1408, 1406. Will the abatement contractor abate the entire floor, including mudset removal if any, in rooms where abatement occurs? |
| A10. | Yes, Abatement contractor must remove tile and mudset down to floor slab. |
| Q11. | Can all work be completed during normal (0700 – 1530) daytime work shifts? |
| A11. | NO. GC101: The sheet indicates specific phases for night work - Corridor work in Phase 1 and 3 will need to occur after hours. Additional after-hours work could be required, such as working in occupied spaces, for example. The GC is to coordinate the work schedule with the COR. |
| Q12. | Are there any noise restrictions for this project? If so, please define the hours. |
| A12. | Yes, GC101 – Infection Control General Notes letter “I” discusses vibration or loud work. |
| Q13. | Can the Site Superintendent fulfill the duties of the SSHO as well? |
| A13. | No, as stated in 01 01 10SN.3.40. A – Site Superintendent is 100% dedicated to this project as the Site Superintendent only |
| Q14. | Does the Superintendent have to be an employee of the general contractor? |
| A14. | Yes, as stated in 01 01 10SN.3.40. A. |
| Q15. | Are all subcontractors required to have an OSHA 30-hour competent person on site while performing work? |
| A15. | Yes, as stated in 01 01 10SN.3.11. B. |
| Q16. | What is the anticipated award date for this project, and how soon after award will the L-NTP be issued? |
| A16. | Award pending no issues should be within 60 days from bid due date. L-NTP will be determined after award. |
| Q17. | Will there be a duration of time between the end of the L-NTP and NTP, or should we assume the NTP will start 60 days after the L-NTP is issued? |
| A17. | Refer to the timeline outlined in the SOW. |
| Q18. | Will all materials be required to be on site prior to starting construction? |
| A18. | No, However the goal of Phase 0 is to avoid construction delays from long lead materials. The GC is to identify all these items, submit the shop drawings for approval, and purchase for timely delivery. Construction must flow uninterrupted. If this is not possible the GC must inform the COR before starting work. |
Q19. There are areas that will need to be completed and moved into by the VA staff prior to construction of the “next phase” of construction.
Q19a. How much time is needed for the VA to Occupy the completed space Phase 1?
A19a. The VA has two weeks to move the offices. Note that the VA will work with the GC to eliminate down time between phase 1 and phase 2. The contractor to provide the VA a minimum of 3 weeks’ notice of substantial completion/beneficial occupancy to coordinate the move.
Q19b. Will a substantial completion letter be issued for phase 1 as it is completed?
A19b. Yes, For this phase of work only, the completed VCS offices and corridor.
Q19c. Should the contractor plan for “down time” between Phase 1 and Phase 2? If so please advise the “down time” that should be planned for and is that time considered part of the construction period (phase 5 – 270 calendar days) A19c No, After the VCS offices are occupied, there is nothing that should cause a down time.
Q19d. How much time is needed for the VA to Occupy the completed space Phase 2?
| A19d. | There are no spaces that the VA needs to Occupy in Phase 2. |
| Q19e. | Will a substantial completion letter be issued for phase2 as it is completed? |
A19e. Only for the work completed, such as the public rest rooms,
| Q19f. | Should the contractor plan for “down time” between Phase 2 and Phase 3? If so, please advise the “down time” that should be planned for? |
| A19f. | No. |
Q19g. Will the contractor be required to mobilize and demobilize for each of the 3 phases of construction?
A19g. No. It is not planned at this point.
| Q20. | Is there a specific location for a site construction Trailer / Staging Area? If so, can you please advise where it is located? |
| A20. | TBD, As specified in 01 01 01.1.6.A – Contractor to coordinate with COR for storage and staging area. |
| Q21. | Is an interior staging area / storage area identified for this project? If so, can you please advise where it is located. |
| A21. | As specified in 01 01 01.1.6.A – Contractor to coordinate with COR for storage and staging area. |
| Q22. | Will a Construction Fence be required around the exterior staging area and trailer? |
| A22. | Yes, as specified in 01 01 10SN.3.35. B, the site is to be secured as specified. |
| Q23. | Can the “Kitchen Loading Dock” be used for deliveries throughout this project? And if so, are there any time constraints? |
| A23. | NO! This is a restricted clean area; the contractor does not have access to any of the active kitchen areas. |
| Q24. | In section 01 00 00 1.10.C, referring to delivering two electronic copies of complete As Builts within 15 calendar days after each completed phase. Is this required at each completed Phase or can the “As-Builts” be turned over at the end of the project? |
| A24. | Contractor to submit (2) forms of as-builts – (1) digital and (1) hard copy after each phase and at final acceptance. |
A24a. Does this also apply to approved shop drawings?
A24a. This applies for final close-out documents including, but not limited to shop drawings, as Builts drawings, and O&M manuals.
A24b. If electronic, does the VA require two.
A24b. See A24a. above.
| Q25. | Per section 01 00 00.1.18.A, how many hard copies of the completed / approved O&M Manuals does the VA require for this project? Do the manuals require delivery when the equipment arrives or at substantial completion? |
| A25. | This applies for final close-out documents including, but not limited to shop drawings, as-builts drawings, and O&M manuals. Two sets. |
| Q26. | Reference 01 32 16.15.1.2.C and 1.3, is an outside consultant required for CPM scheduling or can the General Contractor develop the schedule “In-House”? |
| A26. | Submit as specified – outside consultant. |
| Q27. | Reference 01 33 23 1.3.C, the VA provides the initial submittal register, will this be provided with the L-NTP? |
| A27. | Yes |
| Q28. | Reference 01 35 26.1.13, is Tuberculosis Screening required on this project? Can the Department of Health Services Wisconsin risk assessment TB questionnaire satisfy this requirement for this project? |
| A28. | Screening is not required at this time. |
| Q29. | Reference 01 81 13, is sustainable construction required on this project? |
| A29. | Yes, Sustainable construction practices are to be followed. However, the VA is not pursuing certification. |
Q30. There are (3) “Existing Dumbwaiters” that are to be removed and the floor / ceiling to be infilled. Since the “dumbwaiters” were not able to be viewed at the walk thru the scope of work associated with these needs to be more clearly identified.
Q30a. Do the dumbwaiters still exist?
A30a. The walls surrounding the shafts do exist. It is unknown if equipment exists in the west and center shaft. These two shafts are completely sealed. The East shaft does have some equipment in it. See Photos #1 and #2.
Q30b. Was the equipment removed from the shaft or is the equipment still in place? If the cars, rails and equipment still remain are we to remove them?
A30b. All three shafts are shown to be removed on sheet AD 100 Note 16.
Q30c. Are the shafts still intact? We can only assume they are still there and were “built around”. Please advise A30c. See A30b.
Q30d. Infill details for the floor and ceilings are not provided. Is this something that is to include steel angles and metal deck for infill? Please advise and provide details A30d. The infill detail is shown detail 5/AE110
Q30e. Are there any hazardous materials associated with the dumbwaiters that will need to be dealt with?
A30e. Unknown. There is nothing listed in the HM report. If demolition finds hazardous materials, notify the COR.
| Q31. | Is AISC Steel Certification required for BOTH the fabricator and installer on this project? The project appears to only involve Misc. Metal Fabrications, which should not require the AISC certifications. Please re-consider this requirement. |
| A31. | AISC Certification is not necessary for this project. |
| Q32. | Is the Third-Party Fire Penetration inspector hired by contractor or the VA? |
| A32. | Yes, Per Specification 07 84 00 Paragraph, the contractor is to engage a qualified |
inspector to perform inspections and final reports.
| Q33. | How will existing penetrations in Fire Rates Walls be remediated? Will the VA shops repair / remediate any existing penetrations that are not properly sealed but shown as existing rated walls? |
| A33. | Penetrations uncovered during construction that are not properly sealed and do not pertain to the work of this project would not be covered under the contract. If these penetrations are along the perimeter walls noted to be upgraded to 1 hour, then penetration sealing would be required. |
| Q34. | Are the door frames required to grouted? The Details on page AE600 do not show the frames being grouted. |
| A34. | Hollow metal frames are required to be grouted. |
| Q35. | Is Micro guard sealer required on all floor tile, Floor tile grout, wall tile and wall tile grout? |
| A35. | Yes, as specified in 09 30 12.3.13.A. |
| Q36. | Reference 09 91 00 Painting, are sample panels required or will draw down samples suffice? |
| A36. | Draw down samples provided to the VA is acceptable. |
| Q37. | Please confirm the Commissioning Agent (CxA) (Specification Section 01 91 00) will be engaged and paid for by the VA under a separate contract than this construction Contract. |
| A37. | Yes, The VA will be hiring the 3rd part Commissioning Agent. However, the contractor will be |
Responsible for completing prefunctional checklists, functional performance tests, addressing commissioning issues, etc., as outlined in Specifications.
Q38. There appears to be some confusion with specification Section 01 91 00 and the specification Sections referenced within 01 91 00. The Div 01 specification references Div 7, Div 21, Div 22, Div 23, Div 26, Div 27, Div 28, and Div 31.
Q38a. The individual Specification Sections for Div 7 does not contain a reference back to 01 91 00. Are the Div 7 systems to be included in commissioning activities?
A38a. Div 7, 8 & 31 are not included in commissioning.
Q38b. Section 08 71 13.11 does contain a reference to 01 91 00, But 01 91 00 does not reference Div 8 as part of commissioning. Are the 08 71 13.11 systems to be included in commissioning activities?
A38b. See A38a.
Q38c. Specification Sections for Div 21 do not contain any reference to 01 91 00, But 01 91 00 reference Div 21? Are the Div 21 systems to be included in commissioning activities?
A38c. Yes, Div 21 is included in commissioning. See updated Specification Section 21 13 13. ATTACH 15
Q38d. Specification Sections for Div 26, 27 and 28 do not contain any reference to 01 91 00, But 01 91 00 references Div 26, 27, and 28? Are the Div 26, 27, and 28 systems to be included in commissioning activities?
A38d. Yes, Div 26,27, and 28 are included in commissioning. The VA will be hiring the 3rd part Commissioning Agent, but the contractor is to be responsible for completing pre-functional checklists, functional performance tests, addressing commissioning issues, etc., as outlined in Specifications. See added Specification Sections 21 08 00, 22 08 00, 23 08 00, 26 08 00, 27 08 00, and 28 08 00. ATTACH 15
Q38e. Specification Sections for Div 31 are not contained in the contract documents, yet 01 91 00 references Div 31? Please confirm the 01 91 00 section will be revised to not include the reference to Div 31.
A38e. Ignore reference to Div 31.
| Q39. | Are Fire Dampers required in ductwork that penetrates 1 hour rated walls? It does not appear that any new fire dampers are being added to this project. Please advise if this is correct. |
| A39. | Fire dampers are not required in 1 hour, walls when adjacent areas are protected with a fire sprinkler system. |
| Q40. | Are Fire Dampers required in existing ductwork and/or ductwork that remains untouched that passes through the rated infection control walls? |
| A40. | Fire dampers are not required in 1 hour, walls when adjacent areas are protected with a fire sprinkler system. |
| Q41. | Are any of the “Clean” or “Dirty” rooms to be positively or negatively pressurized? Are they to be monitored? The drawings do not appear to show any room pressure monitors. Please confirm this is correct as drawn. |
| A41. | Permanently installed pressure monitors are not required. See revised MM600 for Room Cooling and Heating Loads Output Data Summary Schedule. |
| Q42. | 23 21 13, section 3.5 references section 23 25 00. There is no section 23 25 00 contained in the documents. Is there is a preferred water treatment vendor for cleaning piping systems? Is section 23 25 00 required? If so, please provide specification Section. |
| A42. | There is no water treatment required in this project. |
| Q43. | Specification Section 23 31 00, Section 3.1 “K”. Please clarify the expectations of ductwork cleaning. How far back do we clean when connecting new ductwork to existing. It would seem unreasonable to clean all the way back to the existing exhaust fan or air handling unit. |
| A43. | Contractor is responsible for cleaning of all existing and new ductwork in scope of work (project area) as well as any downstream ductwork. Contractor to clean existing ductwork 10 feet from the connection point with the new ductwork. It is not the expectation of the Contract Documents to clean any or all the ductwork to source located outside of project area. |
| Q44. | Specification Section 23 31 00, duct cleaning. During construction we have will the ends of all new ductwork wrapped in plastic to protect the integrity of the ductwork. Plastic will be removed just prior to system start up. Will machine cleaning of protected ductwork be a requirement of the project? |
| A44. | Yes |
| Q45. | Has the VA tested the ductwork and mechanical systems scheduled for demolition or relocation for biohazards? If the ductwork or equipment are contaminated, remediation will be required and due to insurance protocol, we cannot subcontract for the remediation. |
| A45. | No. The Area has never had biohazards. |
| Q46. | Specification Section 23 31 00, Section 3.2, items “B” thru “H”, will leak testing be required on ductwork down stream of air terminal units? |
| A46. | Per 23 31 00 3.2 B, all ductwork shall be tested. |
| Q47. | Do the MEPF contractors need to include any hours for training? Almost all systems are existing and being modified, there does not seem to be a need for “Training” on existing systems. Please advise what is required for training. |
| A47. | Any required training is indicated within each respective specification section as well as indicated in Section 01 91 00 “General Commissioning Requirements”. Include 3 hours for training. |
| Q48. | Will flexible conduit be allowed in areas where ridged would be difficult to install? (built-in millwork i.e. Nurses station) |
| A48. | All conduit to be installed in compliance with the requirements of the Contract Documents. Any special circumstances will be handled on a case-by-case basis during construction. “In accordance with the NEC, but not less than 0.75-inch unless otherwise shown. Where permitted by the NEC and the drawings, 0.575-inch hospital-grade flexible conduit (MC Cable) may be used for tap connections to individually-circuited below-cabinet lighting fixtures, or custom millwork." |
| Q49. | How will it be handled if MEPs are encountered above ceiling that were not shown on the plans, and we were not able to view during the walk through, site visit? |
| A49. | Not all existing conditions are shown nor purported to be shown on the Contract Documents. The Contractor is advised that they shall take reasonable care to ascertain existing conditions and make all accommodations necessary to complete with work indicated on the documents. |
| Q50. | Phase 1 – (detail 1/CG101) The existing wall is to remain as construction barrier for demo to occur behind the existing wall. Is this wall a 1 hour rated wall? Does it need to become 1 hour rated? What is the contractor responsible for on this existing wall? |
| A50. | If the wall is not currently 1-hour rated, it will need to be upgraded to meet the 1-hour fire rated smoke barrier wall construction NFPA 241 (detail 5/GC101). Construction barrier walls noted to remain after completion to have a paint finish. |
| Q51. | Once the demo “inside” Phase 1 is completed, behind the existing wall, are new IC barriers required to demo the existing wall and rebuild it? These are not indicated on the plans. Please advise. |
| A51. | There will need to be temporary construction barriers in place for the demolition and construction of the new corridor wall. This will require coordination with the VA. |
| Q52. | The Infection Control plans, and phasing plans do not show any ante rooms to be provided. Please confirm if this is correct. If ante rooms are required, please provide new IC plans indicating the Anteroom locations. |
| A52. | Infection control requirements are required per the ICRA level. Anterooms are required for this construction. This will be level 4 construction due to the proximity to the kitchen on the first floor. Infection control in the basement will be a different level depending on the level of work and duration and may not require an anteroom. |
| Q53. | Please provide an IC / Phasing plan for the work to be completed in the basement and provide direction on how that work is to be planned for. |
| A53. | Plumbing scope of work shall be coordinated with the phasing plan for the first floor. In occupied basement spaces the demolition of old and installation of the new work will occur at the same time. The GC will make every effort to minimizes the disruption of the users I the space. Infection control for 1-3 days is sealed plastic barriers. |
| Q54. | Plan Page MP101, in new room 1459 (Storage) there is some new piping that is called out to be a ¾” condensate from DSS-1461 to Mop Sink. We do not see any new equipment DSS-1461. Is this an existing piece of equipment? In the same area there is also a call out “refrigerant piping to DSS-1461” Please advise where this equipment is located and what we required to do with this incomplete ¾” condensate line and or piping. |
| A54. | Refrigerant and condensate piping scope shall be removed from the drawings in this area. See revised drawing MP101. ATTACH 17 |
| Q55. | On Plan Page AE600 there appears to be a OH door or counter shutter type door (labeled type SH) but there is no description of this door, secondly it is also not shown in the Door Schedule, and lastly there is no specification Section for a coiling type door. Please advise if this door type is required on this project. If it is required, can further description be provided and can it be added to the door schedule for clarity. |
| A55. | The SH door type is no longer a part of this project, omit. See revised AE600, ATTACH 16 |
| Q56. | On Sheet AE 600 in the door schedule a frame type of D2 is used at Door number C6A and C6C. There is no elevation of door frame D2 provide on the same sheet. Please provide more information on required door frames |
| A56. | Door frame D2 resembles type S2 but is for a double door not a single. See revised AE600, ATTACH 16 |
| Q57. | The Electrical Power Drawings do not show connections to the 4 Auto Operators. Are equipment connections needed at the (4) auto Operator locations? Can the connections be added to the electrical drawings? |
| A57. | Yes, power connections and circuits are required at the door operators. For bidding purposes, the contractor is advised to extend a separate 120V branch circuit from Life Safety Panel EPL-LS-16-1 and connect to 20A/1P circuit breakers available for each auto operator. See revised drawings EP101 & EP601 for the addition of circuits mentioned above. ATTACH 17 |
| Q58. | Per the door hardware schedule, door 1400 and C8A are to receive a Card reader, but it is not shown on the EY101 drawings. Please advise / correct. |
| A58. | These doors are to receive card readers. See revised drawing EY101 for addition of card readers. ATTACH 17 |
| Q59. | On Sheet EY101 Door 1465B shows a card reader to be installed, but the door hardware schedule on AE600 does not indicate this door to receive a carder reader. No Keynote 1 is indicated. Please advise what is correct, and revise drawings to reflect. |
| A59. | There is to be a card reader on door 1465B. See revised drawing AE100.A and AE100.B indicating CR locations. ATTACH 16 |
| Q60. | There are (4) doors that are indicated to have auto operators. Locations of Push Paddles / Handwave activation devices are not clearly shown. Please advise the locations of the activation buttons and what type of activation buttons are required. Push Paddles or Handwaves. Please revise drawings to indicate locations and type. |
| A60. | Enlarged Plan 1/AI200 note the locations of the automatic door actuators. These are all to be Handwaves. All handwaves devices are to be from a single manufacture and the same model. |
| Q61. | It appears some of the new Aluminum frames entrances / doors are to receive card readers. Where are these card readers to be placed? On the door itself? On the door frame? On an adjacent wall? Can card readers be placed on the actual door? |
| A61. | Card reader to be installed on adjacent walls for both doors. See revised plan AE100.A indicating CR locations. ATTACH 16 |
| Q62. | The “Finish Schedule” Call for all RWC-1 and RWC-2 to be installed to a height of 48” AFF. Please confirm this is corrected and that there are no rooms that require RWC-1 or RWC-2 to full height. |
| A62. | There is no full height wall protection a part of this project. 48” is correct height. |
| Q63. | The floor finish plan on page AI102 does not match the room finish schedule on AI600. Example: would be the locker room flooring. Please advise which is correct? |
| A63. | The floor pattern on the floor finish plan is incorrect. Please refer to the Room Finish Schedule on AI600 for the correct finish. |
| Q64. | If the wall protection is installed to 48” above the floor and electrical switches are also centered to 48” Aff, the switches will be half in the wall protection and half out. Should the switches be lowered or raised? Please advise / provide detail. |
| A64. | The wall protection shall be 48” AFF, and the switches are to remain at the same height in which they were designed. |
| Q65. | Please advise the height of the corner guards and End Guards. Are they to be 4’ High or 8’ high? |
| A65. | Guards are full 8 ft height unless noted otherwise. |
| Q66. | Are flex heads for the sprinkler system allowed for this project? |
| A66. | Yes. If using flexible connections to the sprinkler heads, the contract needs to ensure that ceiling tiles can be removed and the sprinkler main and elbows are not installed so low that ceiling access is prohibited to include but not limited to equipment maintenance, removal and replacement of ceiling tiles, filter replacement, etc. See revised specification section 21 13 13. ATTACH 15 |
| Q67. | Is any in wall blocking required for the sliding door hardware? None shown in the details. |
| A67. | Yes, Refer to manufacturer recommendations on required blocking. See revised sheet AE002 for blocking details and load tables. ATTACH 16 |
| Q68. | Is wood blocking required for the Auto Door Operators? None shown on the drawings. |
| A68. | Yes, Refer to manufacturer recommendations on required blocking. See revised sheet AE002 for blocking details and load tables. ATTACH 16 |
| Q69. | Door frame type ES (Sliding Doors) is called out as a HM frame in the door schedule. Detail 2/AE600 appears to be an Aluminum Frame detail for the sliding doors. Please advise what is correct and revise drawings as required. |
| A69. | The sliding doors will have an aluminum frame per the detail. See revised AE600, ATTACH 16 |
| Q70. | Specification Section 10 44 13 calls for recessed type FE Cabinets. Are these to be fully recessed or semi-recessed. Please advise where these are to be located as they are not shown on the floor plans. Has the wall type been reviewed to confirm the stud depth will accommodate a fully recessed cabinet? |
| A70. | Locations shown on GI102. Walls will accept semi-recessed fire extinguisher cabinets. |
| Q71. | There appears to be a pass thru cabinet between rooms 1438 and 1439. Please provide a specification for the pass thru cabinet as it does not appear to be included in section 10 28 00. |
| A71. | See revised 10 28 00 provided. ATTACH 15 See drawing 2/AE400. ATTACH 16 |
| Q72. | Plan Page QH100, General Note C indicate to refer to Furniture vendor Drawings and Schedule for final Placement, and General Note E has the VA reviewing and approving prior to order. There are no furniture plans included in the documents and there is no Modular Furniture Specification. Please confirm all reference “Furniture” (BSI) will be procured, coordinated, reviewed, approved, and installed under a separate contract held by the VA. If the furniture is to be part of this contract, please provide the furniture plans and a specification. |
| A72. | See basis of design attachment containing the desk and itemized list, attached Furniture Plan and Schedule. ATTACH 18 |
| Q73. | QH100 Equipment Schedule indicates the Cubical Curtain Track AND the Curtain are Contractor provided and installed, please confirm the VA is NOT furnishing the Cubical Curtains. |
| A73. | Refer to Finish Schedule on AI600 for additional information. Cubical Curtain Track and curtains are provided by the GC. |
| Q74. | There appears to be a number of TV’s being supplied and installed by the VA. Is blocking required for these? Please advise what needs to be installed in the walls for these items. |
| A74. | Blocking is required for wall mounted TVs. See revised sheet AE002 for blocking details and load tables. ATTACH 16 |
| Q75. | Plan Page AI200, Elevation 10 calls out patient toilet 17A and 21A. Please confirm they should be rooms 1452A and 1448A. |
| A75. | 1452A and 1448A are the correct room numbers. |
| Q76. | Will temporary plastic infection control barriers be required while building the 1 hr construction barriers? |
| A76. | Yes, any dust producing activity will need to be closed off from the hospital and kitchen areas. |
Q77. There appears to be conflicting information regarding the existing walls around the project. The Life Safety Plans GI101 and GI102 have a text box note on them that indicates “Existing wall upgraded to 1 hour fire rated construction”. This would indicate that this work has been completed. Likewise included in the “Wall Rating Legend” on pages AE100, AE100.A and AE100.B the existing wall shown in “grey” states “existing wall upgraded to 1 hour fire rated”. Drawing sheet AE100.A, Keynote 1, states the contractor is to upgrade the indicated wall to 1 hour construction and provides some details on what is needed. Keynote 1 conflicts with the notes on the Life safety Plans as well as the wall legend. Please provide clear direction on what has been completed, and what is expected from this contract.
Q77a. Around existing electrical room 1403EC – there is no keynote 1 around the majority of these walls, but by the wall legend these walls were upgraded already?
A77a. It is understood that this wall is already 1 Hour construction, if not, it will need to be upgraded. This pertains to the wall connecting the perimeter South wall to the new storefront as indicated by keynote 1.
Q77b. The south wall of the new space has keynote 1, but by the wall legend this has already been done.
A77b. AE100.A is showing the completed work of the project, if these walls do not meet 1 Hour construction they are to be upgraded by the contractor.
Q77c. The west wall of the space has keynote 1, but conflicts with the Life Safety plans as indicating this has been “Upgraded” A77c. AE100.A is showing the completed work of the project, if these walls do not meet 1 Hour construction they are to be upgraded by the contractor.
Q77d. Plan Page AE100.B does not have a similar keynote as AE100. A. Is anything required of this contract for existing walls shown on plan page AE100.B?
A77d. There is no 1 Hour fire upgrade requirement to the walls at this section of the project, however, there are requirements for security mesh in the office spaces noted on AE100. B. The Life Safety plans show the project as complete. The note, Existing wall upgraded to 1 Hour, refers to the work called out on sheet AE100. A. These existing walls will need to be upgraded to 1 Hour by the contractor if not already meeting this requirement
| Q78. | AE002 says we need to use 362S125-30 @ 16” o.c. The specs call out 0.036mil. Is a 19mil 20ga. Stud an acceptable alternate? |
| A78. | The specification calls for all metal studs to be 20 ga structural grade stud. At each door king studs must be 18 ga studs. |
| Q79. | The contract documents do not have a specification Section for Batt Insulation. Please advise if Mineral wool or fiberglass insulation can be used and where? The wall types call on AE002 out “i” or “t”. Please advise if the “i” is fiberglass and the “t” would be mineral wool. |
| A79. | Specification Section 07 21 13 Insulation has been added to the Bid Documents. As indicated on sheet AE002, the “i” represents sound insulation and the “t” represents thermal insulation. As indicated in notes on this sheet, mineral wool is acceptable as long as the fire rating or STC rating is accomplished. |
| Q80. | Many of the wall types shown on AE002 indicate “stud bracing at 4’0” OC (kickers). Are these truly necessary? This appears to be unnecessary, according to some of the trade professionals. |
| A80. | Install stud bracing as detailed. |
| Q81. | A number of the wall types on sheet AE002 call out the security mesh as welded at 6” OC. Can a mechanical fastener be used to make the connection? Most trade specific framers do not carry a welding technician to complete this. Please advise if a Mechanical Fastener system can be used. |
| A81. | No, the VA Physical Security Design Manual requires these walls to have |
| Q82. | 5. Ref drawing AI600- The finishes schedule comments #2 indicates the curtain tracks to be the CTRSS which is a wall mount type track. The specification section 10 21 23, 2.1 calls out Inpro Wisper Care tracks which mount to the ceiling grid. Which type of cubicle track is correct? Who is responsible for providing the curtains? If the contractor will a specification be provided for curtains? |
| A82. | CTRSS are the correct cubicle curtains, wall mounted. See question 73 answer. |
| Q83. | Ref drawing AD100- Sanitation Rm 1448 identifies the south wall with keynote 19. Based on site visit this wall is comprised of glazed block with upper portion of wall being clay tile and plaster. Stud framing and drywall do not appear to be present. This same condition exists on the west side of west wall of corridor C1B06. Can further clarification be provided? |
| A83. | There are no stud walls in front of the glazed block on the south wall of Rm 1448 or on the west side of the corridor wall C1B06. |
| Q84. | Ref drawing AD100 – Based on site visit the Trayline room 1446 appears to have stud framing and drywall in front of CMU wall on north side of this room. Notes do not indicate to remove the wall. Can further clarification be provided? |
| A84. | Drawing AD100 show ALL these walls being removed. |
| Q85. | Ref drawing AD100- Sanitation room 1448 illustrates keynote 16 for removal of dumbwaiter equipment removal. Can detail be provided for floor opening infill on 1st and 2nd floors? Is the 2nd floor opening accessible for infill work? Is the 2nd floor room occupied? Will the 2nd floor room require protection of surrounding? Will an infection control wall be required on 2nd floor? |
| A85. | The dumbwaiter was originally built to start on the first floor. If work is required on the Second-floor infection control is required, use infill Detail 5/AE110. See the attached Photos of Dumbwaiter Shaft for the existing condition. Note the steel deck at top of the shaft. |
| Q86. | Ref Drawing EP400 Panel Feeder - One-Line Diagram, per "Keyed Note" 1 - panels ELH-CR-16-1 and UH-16-1 are to "remove panel and all associated wire and conduit back to source". Drawing EP101, keyed note 20, same panels, "panels are existing to remain". Drawing EP300 keyed note 1 ", same panels, "existing panels to remain and be protected". Which drawing is correct? If these panels are to be removed the existing items downstream from these panels will not be energized. Should they stay in place? |
| A86. | Keyed Note #1 reference to Panels ELH-CR-16-1 and UH-16-1 on Sheet EP400 is incorrect and should be Keyed Note #15 that reads “Existing Electrical Panel to Remain”. See revised drawing EP400. ATTACH 17 |
| Q87. | Ref Drawing EP400 Electrical Feeder - One-Line Diagram, per "Keyed Note" 8 -States the following: "Disconnect and remove existing feeder conductor and conduit". This is in (2) locations, one from panel EPL-CR-16-1 to EPL-CR-16-2 and the other is from panel PL-16-1 to PL-16-2. Per "Keyed Note" 6 "Existing electrical panel to Remain.....". If these feeders are removed the two panels (EPL-CR-16-2 and PL-16-2) will not be energized. Will these feeders remain? Or are there going to be new feeders to these panels? |
| A87. | Keyed Note # 8 reference to Feeders to Panels EPL-CR-16-2 and 1 PL-16-2 on Sheet EP400 is incorrect and should be Keyed Note #9 that reads “Existing Feeder Conductors and Conduit to Remain”. See revised drawing EP400 ATTACH 17 |
| A88. | Ref Drawing EP400 Electrical Feeder - One-Line Diagram, per "Keyed Note" 8 -States the following: "Disconnect and remove existing feeder conductor and conduit". This is in (2) locations, one from panel EPL-CR-16-1 to EPL-CR-16-2 and the other is from panel PL-16-1 to PL-16-2. Per "Keyed Note" 6 "Existing electrical panel to Remain..". If these feeders are removed the two panels (EPL-CR-16-2 and PL-16-2) will not be energized. Will these feeders remain? Or are there going to be new feeders to these panels? |
| A88. | See Q 87 answer. |
| Q89. | As we were not able to access the space during the pre-bid walk thru, please provide pictures and/or as-builts of the credit union below the construction space as the project requires work to be done in the ceiling of the credit union. |
| A89. | Refer to sheet AD 109 RCP of the Basement Area. ATTACH 16 |
| Q90. | Per 28/A1902, please clarify what the identified letters mean for the G6 sign type. |
| A90. | See revised sheet AI 902. ATTACH 16. |
| Q91. | Ref drawing QH100 & AI202- Can elevations be provided for the manufactured casework required in the Chiefs Office 1465A? |
| A91. | These drawings can be found in the attached Furniture Plans and Schedule. ATTACH 18 |
| Q92. | Ref drawing AE002- It appears sound ratings are required on several new walls. The door schedule shown on drawing AE600 does not illustrate STC ratings for doors. Are doors required to be STC rated and if so, can a door schedule be provided with required ratings? |
| A92 | The specific solid wood interior doors and grouted HM frames will satisfy the VA’s sound requirements. |
V. General Information:
1. REMINDER: VAAR 852.219-77 VA Notice of Limitations on Subcontracting – Certificate of Compliance for Services and Construction is included in this solicitation (see SF1442 pages 53-55); signed certification must accompany bid to be considered for award.
2. NOTE: Change to the public bid opening.
NOTE: Ensure to include solicitation number on the bid envelope and all correspondence is mailed or hand-carried to the following address:
Department of Veterans Affairs Great Lakes Acquisition Center ATTN: Stacy Hoover and Kristine Sutton 115 S. 84th St., Suite 101 Milwaukee, WI 53214-1476
Vendor bids are due February 28 2023, at 1:30PM local time
ATTACHMENTS:
See attached document: ATTACH 15 Combined Spec Sections.
See attached document: ATTACH 16 Arch Drawings.
See attached document: ATTACH 17 MEP Drawings.
See attached document: ATTACH 18 Furniture Dwg Shaft Photos Doc A.