Attachment 6 - GC102 - PHASING PLAN.pdf

PDF 554 KB Posted

Attached to
Z1DA--Project 596A4-19-108 - Replace ED Flooring - 596-23-2-5821-0002
Solicitation number
36C24923R0046
Issued by

About this file

This document contains a phasing plan and related federal contract opportunity for replacing flooring and doors in an Emergency Department at a Veterans Affairs medical center. The scope of work involves completely preparing the site, demolishing and removing existing doors and flooring, and furnishing all labor, materials, and equipment to install new doors and flooring according to the drawings and specifications provided. The project is located at the Troy Bowling Campus of the Lexington Veterans Affairs Medical Center in Lexington, Kentucky. The justification for the project is that the current Emergency Department flooring has holes, cracks, and other damage throughout, and needs replacing to avoid injury to patients and staff. The federal agency issuing the solicitation is the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 9.

View the file

Other files

File Type Posted
36C24923R0046 0005.pdf PDF
36C24923R0046 - A0004.pdf PDF
36C24923R0046-A0003.pdf PDF
Attachment 1 - G000 - COVER SHEET.pdf PDF
Attachment 13 - AE501 - DETAILS.pdf PDF
Attachment 20 - 096519 Resilent Tile Flooring.pdf PDF
Attachment 18 - 090600 Schedule for Finishes.pdf PDF
Attachment 10 - AD101 - DEMOLITION PLAN.pdf PDF
Attachment 19 - 096516 RESILIENT SHEET FLOORING.pdf PDF
Attachment 14 - AE601 - DOOR DETAILS.pdf PDF
Attachment 12 - AE101 - ENLARGED FIRST FLOOR PLAN - NEW WORK.pdf PDF
Attachment 16 - 010000 General Requirements.pdf PDF
Attachment 7 - GC103 - PHASING PLAN.pdf PDF
Attachment 4 - G003 - FIRST FLOOR PLAN - OVERALL.pdf PDF
36C4923R0046-A0002.pdf PDF
Attachment 5 - GC101 - PHASING PLAN.pdf PDF
Attachment 9 - GC105 - PHASING PLAN.pdf PDF
Attachment 11 - AD102 - LOWER-LEVEL DEMOLITION PLAN.pdf PDF
Attachment 3 - G002 - CODE SHEET.pdf PDF
Attachment 8 - GC104 - PHASING PLAN.pdf PDF
Attachment 17 - 013526 Safety Requirements.pdf PDF
Attachment 2 - G001 - GENERAL NOTES.pdf PDF
Attachment 15 - AF101 - ENLARGED FIRST FLOOR PLAN - FINISHES.pdf PDF
36C4923R0046-A0001.pdf PDF
Attachment 3 - Wage Rates 01-13-2023.pdf PDF
Attachment 6 - Schedule-of-Values-Sample Template.xlsx XLSX spreadsheet
Attachment 7 - Past Performance Questionnaire.docx DOCX document
Attachment 2 - 596A4-19-108 Replace ED Flooring - Drawings.pdf PDF
Attachment 4 - Calc. of Self Performed Work General Contractor.xlsx XLSX spreadsheet
Attachment 1 - 596A4-19-108 Replace ED Flooring Specifications.pdf PDF
Attachment 5 - Contractor EMR Certification Form.docx DOCX document
36C24923R0046_1.docx DOCX document
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UP

UP

UP

UP

M

M

M

M

1B

1A

CONTRACTOR ACCESS

EGRESS

5' - 1 3/4"

EGRESS

PHASE 2

1300 SF

GC102

STAFF WORK

C130

TRIAGE 01

C121B

TRIAGE 02

C121A

EKG/LAB

C121C

TLT

C121D

PASSAGE

CH121A

SOILD UTIL

C122

EMS

C123

SPECIMEN

C124

SUB-WAITING

CH121B

PASSAGE

CH121

PASSAGE

CH125A

EXAM 11

C125A

EXAM 12

C125B

EXAM 13

C125C

EXAM 14

C125D

STORAGE

C125E

EXAM 15

C125F

EXAM 16

C125G

TOILET

C126A

PHYS WORK

C126C

ON CALL

C126D

PASSAGE

CH126

CART STORAGE

C125K

PASSAGE

CH125

STAFF WORK

C125

PASSAGE

CH125B

NOUR PREP

C125J

CLEAN UTILITY

C125HE CYL

C125I

MED RM

C129

STORAGE

C127

STAIR

CS104

MENTAL 17

C130A

OFFICE

C130B

EXAM 18

C130C

EXAM 19

C130D

EXAM 1

C130E

EXAM (NEG) 2

C130FVESTIBULE

CH130A

PASSAGE

CH132

TLT

C128TLT

C131

EXAM 6

C132A

STAFF / WORK RM

C133

TLT/SHOWER

C134

SOILD UTIL

C135

IT

C136

CLEAN UTIL

C137

EMS

C138

EXAM 7

C132B

EXAM 8

C132C

EXAM 5

C132D

OFFICE 3

C140

ER OFFICE 2

C141

STAFF TLT

C142

ER NURSE MGR

C143

EMPLOYEE TRAINING RM

C144

PASSAGE

CH140

PASSAGE

CH132A

EXAM (NEG) 3

C130H

EXAM (NEG) 4

C130I

EXAM (NEG) 9

C130J

EXAM 10

C130K

STAIRWELL

CS109

EC

CU100

ELEVATOR

P7

ELEVATOR

P6 IT

C121

PASSAGE

CH132

C130J C130K

SEAL AT TOP AND BOTTOM

OF BARRIER TO BE

AIRTIGHT

PROVIDE OPAQUE 10 MIL FIRE

RETARDANT POLYETHYLENE SHEET

PLASTIC FROM TOP OF WALL TO

CEILING TO AVOID EXISTING LIGHTS,

DIFFUSERS, AND SPRINKLER HEADS.

EXISTING WALL, COUNTER,

AND WORKSURFACE TO

REMAIN

G E N E R A L N O T E S

A. EACH PHASE INCLUDES OWNER MOVE OUT, TEMPORARY BARRIERS, CONSTRUCTION, PUNCH LIST, CLEANING, AND OWNER MOVE IN BEFORE NEXT PHASE STARTS. SEE DETAILED PHASING PLAN OUTLINED

IN SPECIFICATION SECTION 01 00 00.

B. CONTRACTOR TO PROVIDE FIRE EXTINGUISHER WITHIN CONSTRUCTION AREA PER SPEC 01 03 26.

C. SEE NO EXIT SIGN SHEET GC101 - TYPICAL ALL PHASES.

CURRENT PHASE

COMPLETED PHASE

FUTURE PHASE

OUTSIDE OF SCOPE

PHASE LEGEND

NO WORK

COMPLETED FLOORING

IN CURRENT PHASE

V A N O T E S

V2A. OFFICE C138B IS TEMPORARY MED ROOM C129. ALL ITEMS WILL BE RELOCATED BY VA.

V2B. OFFICE C138B SECURITY, IT AND CAMERA RELOCATION WILL BE BY VA.

EXISTING EXIT SIGN

TEMPORARY EXIT SIGN

MANUAL FIRE PULL

SYMBOL LEGEND

M

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

FULLY SPRINKLERED

U.S. Department of Veterans Affairs

B

C

D

E

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMP

321 4 5 6 7 8 9 10

12/31/2023

C U s e rs

\d u n n t\ D o c u m e n ts

\R e v it \2

\F F

E L e x in g to n

R e p la c e

E D

F lo o ri n g

(2 tj .d u n n

.r v t

/1

/2

:5

:4

A

M

GC102

PHASING PLAN

Owner

3/17/2023 PH TD

REPLACE FLOORING & EXAM ROOM

DOORS IN ED SUITE

596A4-19-108

LEXINGTON, KY

CONSTRUCTION

DOCUMENTS B-1A

TROY BOWLING

CAMPUS

EMERGENCY

ROOM

1/16" = 1'-0"

PHASING FIRST FLOOR PLAN - OVERALL

1/8" = 1'-0"

PHASING FIRST FLOOR PLAN - PHASE 2

D R A W I N G N O T E S

1 TEMPORARY CONSTRUCTION BARRIER AS REQUIRED TO ALLOW FOR CONTINUATION OF NEW FLOOR WHILE

MAINTAINING SEPARATION FOR ICRA REQUIREMENTS AND PHASING - OPAQUE 10 MIL FIRE RETARDANT

POLYETHYLENE SHEET PLASTIC PER SPECIFICATION 01 35 26.

2 TIE INTO FLOORING FROM PREVIOUS PHASE

3 REMOVE DOOR AT THE START OF PHASE 1 AND REPLACE AT THE END OF PHASE 5

4 PROVIDE "WARNING CONSTRUCTION AREA" SIGN ON DOOR

5 TEMPORARY SIGNAGE STATING "NO EXIT" ON DOOR - REMOVE UPON COMPLETION OF PHASE.

6 SEAL BOTH SIDES OF DOOR WITH 10 MIL FIRE RETARDANT POLYETHYLENE SHEET PLASTIC PER SPECIFICATION 01

35 26. THIS DOOR IS NOT TO BE USED IN THIS PHASE.

7 TEMPORARY CONSTRUCTION ZIPPER DOOR - OPAQUE 10 MIL FIRE RETARDANT POLYETHYLENE SHEET PLASTIC PER

SPECIFICATION 01 35 26.

1" = 1'-0"

TEMP. BARRIER AT NURSE STATION SECTION C

K E Y P L A N

No. Revisions: Date:

1 ADDENDUM 01 03/17/2023

Sheets
GC102 - PHASING PLAN